Professional Documents
Culture Documents
SPH FINAL QUANTITY KONTRAK PEMALANG BOQ Building
SPH FINAL QUANTITY KONTRAK PEMALANG BOQ Building
SPH FINAL QUANTITY KONTRAK PEMALANG BOQ Building
TOTAL PRICE
NO. DESCRIPTION
(IDR)
1 2 3
Signature of BIdder :
PEMALANG 500KV CONVENTIONAL SUBSTATION
DAFTAR ISIAN 1 : DAFTAR KUANTITAS DAN HARGA (BOQ)
4. BILL NO 4 : CONTROL BUILDING, PERIMETER FENCE AND GATE
7.1c Steel fire door W1000xH2100 complete with panic bar. unit 1.00 1.00 13,954,000.00 13,954,000.00
7.1d Aluminium door W800xH2100 unit 1.00 1.00 3,183,689.79 3,183,689.79
TOTAL 3,138,973,042.62
Signature of BIdder :
PEMALANG 500KV CONVENTIONAL SUBSTATION
DAFTAR ISIAN 1 : DAFTAR KUANTITAS DAN HARGA (BOQ)
4. BILL NO 4 : CONTROL BUILDING, PERIMETER FENCE AND GATE
116,940,461.36
(RUPIAH) (RUPIAH)
1 2 3 4 5 6
8 Ceiling work
8.1 Accoustic ceiling 600x600x12 mm m2 808.00 912.49 234,731.00 189,662,648.00
8.2 GRC panel ceiling 600x600x4.5 mm m2 186.00 271.66 309,095.00 57,491,670.00
9 Pipe works
9.1 Piping and water supply Ls 1.00 1.00 42,278,209.00 42,278,209.00
9.2 Piping and water waste Ls 1.00 1.00 113,153,500.00 113,153,500.00
10 Sanitary work
10.1 Bath basin complete accessories unit 1.00 3.00 1,243,008.00 1,243,008.00
10.2 Water closed complete accessories unit 2.00 3.00 5,141,413.00 10,282,826.00
10.3 Urinal complete accessories unit 4.00 4.00 4,737,523.00 18,950,092.00
10.4 Wash basin complete accessories unit 2.00 2.00 2,928,071.00 5,856,142.00
10.5 Ceramic wall and floor m2 60.00 62.00 204,742.00 12,284,520.00
11 Septic tank works (3m2) complete unit 1.00 1.00 19,630,657.00 19,630,657.00
12 CABLE DUCT
12.1 Common Excavation m3 - -
12.2 Sand Layer m3 - -
12.3 Lean concrete m3 - -
12.4 Reinforced concrete m3 - -
13 Metal Works
13.1 Chequer Plate 5 mm thick kg 990.00 650.00 18,547.00 18,361,530.00
13.2 Steel angle / UNP kg 660.00 2,725.80 22,256.00 14,688,960.00
13.3 Galvanized Cable tray kg -
14 Painting works
14.1 External Wall and Ceiling painting m2 1,224.00 1,224.00 54,388.00 66,570,912.00
Signature of BIdder :
PEMALANG 500KV CONVENTIONAL SUBSTATION
DAFTAR ISIAN 1 : DAFTAR KUANTITAS DAN HARGA (BOQ)
4. BILL NO 4 : CONTROL BUILDING, PERIMETER FENCE AND GATE
14.2 Internal Wall and Ceiling painting m2 2,406.00 2,406.00 43,398.00 104,415,588.00
TOTAL 696,885,597.00
(RUPIAH) (RUPIAH)
1 2 3 4 5 6
15 Miscellaneous work
Ditch size W300xD500, made of reinforced concrete K.175 thick of
15.1 wall and slab 100 mm, including excavation, sandfill, lean concrete m 127.00 127.00 570,114.00 72,404,478.00
etc to complete works.
15.2 PVC 4 inc dia m 5.00 5.00 150,660.00 753,300.00
15.3 PVC 3 inc dia m 5.00 5.00 102,380.00 511,900.00
15.4 Water tank and jet pump complete unit 1.00 1.00 91,385,032.00 91,385,032.00
with tower piping and installation pipe
16 Electrical
16.1 Entrance
1. Decorative luminaires ceiling mounted NO -
incandescent fitting (down light type)
including installation wiring, lamp 2 x 60 W
and single pole switch
2. Hologen Lamps ceiling mounted NO -
incandescent fitting (square type)
including installation wiring, lamp 3 x 60 W
and triple pole switch
5. Stop contact AC and Fan including installation wiring NO 25.00 25.00 462,142.00 11,553,550.00
Signature of BIdder :
PEMALANG 500KV CONVENTIONAL SUBSTATION
DAFTAR ISIAN 1 : DAFTAR KUANTITAS DAN HARGA (BOQ)
4. BILL NO 4 : CONTROL BUILDING, PERIMETER FENCE AND GATE
6. Emergency lighting including installation NO 13.00 13.00 945,569.00 12,292,397.00
wiring and lamp 20W.
TOTAL 330,688,598.00
(RUPIAH) (RUPIAH)
1 2 3 4 5 6
16.4 Kitchen, Urinoir, Toilet and Pray Room
1. Indoor Luminaires type flourescent fitting NO -
2x40W inculding installation wiring and
single pole switch.
2. Indoor Luminaires type flourescent fitting NO -
2x20W inculding installation wiring and
double pole switch.
3. Clear lamp ceiling mounted in candescent NO 18.00 18.00 936,270.00 16,852,860.00
fitting (squre type) including installation
wiring lamp 60W and single pole switch
4. Stop contact including wiring NO 4.00 4.00 428,791.00 1,715,164.00
16.5 20 KV Switchgear
1. Indoor Luminaires type flourescent fitting NO 40.00 40.00 966,704.00 38,668,160.00
2x40W inculding installation wiring and
double pole switch.
2. Indoor Luminaires type flourescent fitting 2x20W NO - - -
inculding installation wiring and triple pole switch
3. Stop contact including installation wiring NO 10.00 10.00 428,791.00 4,287,910.00
4. Emergency lighting including wiring and NO 3.00 3.00 945,569.00 2,836,707.00
lamp 20W.
5. SP including installation fuse, switch, MCB, NO 1.00 1.00 10,881,410.00 10,881,410.00
wiring pipe indicator lamp and grounding system
18 Lightning Protection
Cable BC 70 mm including all accessories Lot 1.00 1.00 42,278,209.00 42,278,209.00
clamps steel plate, material support and
spole, grounding system for control building
19 Fire Alarm
1. Alarm bell 6" (150 mm) diameter including NO 2.00 2.00 655,414.00 1,310,828.00
installation wiring
2. Smoke detector including installation wiring NO 34.00 34.00 782,224.00 26,595,616.00
3. Fixed and rate of rise temperature detector NO 9.00 9.00 503,242.00 4,529,178.00
including installation wiring
4. MCFA (Master Control Fire Almr) NO 1.00 1.00 11,638,340.00 11,638,340.00
Including indication lamp, batttery rectifier
and all accessories
21 Crane Manual
Crane Manual complete with accessories NO 1.00 1.00 65,828,877.00 65,828,877.00
capacity 1,0 ton
22 Auxiliary Building for genset 300 kW (6m x 12m) NO 1.00 1.00 304,344,000.00 304,344,000.00
23 Post security (4m x 4 m) included toilet 1,5m x 1,5m unit 1.00 1.00 78,904,000.00 78,904,000.00
24 Fence
Signature of BIdder :
PEMALANG 500KV CONVENTIONAL SUBSTATION
DAFTAR ISIAN 1 : DAFTAR KUANTITAS DAN HARGA (BOQ)
4. BILL NO 4 : CONTROL BUILDING, PERIMETER FENCE AND GATE
- Boundary fence type-1, Fabricated concrete 2.00 m height m' 1,688.00 1,688.00 1,262,811.00 2,131,624,968.00
- Boundary fence type-2, Plastered brickwall 2.00 m height m' 12.00 12.00 2,527,897.00 30,334,764.00
26 Road (new) -
a. Preparation and compacted subgrade. m2 11,090.00 10,508.65 38,888.00 431,267,920.00
b. Sub base course m3 3,327.00 3,152.60 407,351.90 1,355,259,764.04
c. Base course m3 2,773.00 2,627.16 482,438.17 1,337,801,034.01
d. Penetration macadam 5 cm m2 -
e. Wearing course Hotmix 5 cm m2 11,090.00 10,508.65 108,028.00 1,198,030,520.00
f. Reinforced Concrete road 20 cm thick, including lean concrete 5
cm, sand 10 cm, 2 layer wire mesh M8, dowel 25 mm, surface m2 1,200.00 1,408.00 1,412,692.33 1,695,230,796.00
finishing, and curing
28 Drainage
28.1 Excavation of soil m3 2,222.00 2,357.20 48,773.00 108,373,606.00
28.1 Backfilling with selected material. m3 515.00 942.88 133,273.00 68,635,595.00
28.1 Compacted sand layer t : 0.10 m m3 115.00 115.00 328,297.00 37,754,155.00
28.1 Lean concrete K.100 t : 0.05 m m3 57.00 57.00 893,907.00 50,952,699.00
28.1 Concrete grade K.175 m3 574.00 574.00 1,008,901.00 579,109,174.00
28.1 Reinforcement BJTP24 kg 71,710.00 71,710.00 11,305.00 810,681,550.00
28.1 Formworks m2 9,525.00 9,525.00 114,572.00 1,091,298,300.00
28.1 Soil disposal m3 1,707.00 1,707.00 100,057.00 170,797,299.00
2. Switchyard flood lighting 400 W complete with NO 64.00 64.00 3,557,725.00 227,694,400.00
bracket, fuse box, grounding system and
installation of cable conduit and wiring and
all accessories.
4. Lighting panel outdoor complete with folo cell Set 1.00 1.00 4,338,200.00 4,338,200.00
switch fuse, mcb, grouding system -
indicator wiring and all accessories (foto cell)
and foundation of panel
TOTAL 14,103,383,034.65
Total Bill No. 4 18,269,930,272.27
Signature of BIdder :
AL SUBSTATION
DAN HARGA (BOQ)
ETER FENCE AND GATE
LUAS BANGUNAN
( RUPIAH )
7 18,269,930,272.27
38,747,500.00 Tidak
Untuk termasuk setting
penyimpanan out
dan benchmark
fabrikasi utama
material
141,173,796.88 subcontractor, penyimpanan alat, lokasi dekat dengan
42,270,000.00 area
Biayapekerjaan.
bulanan konsumsi listrik di site office and security.
Penyediaan air minum, internet, sewa photocopy A3
126,810,000.00
scan, ATK, office boy/girl 1 orang.
N/A
N/A
N/A
Signature of BIdder :
AL SUBSTATION
DAN HARGA (BOQ)
ETER FENCE AND GATE
Micro concrete 50 mm thk including wiremesh 20x20
19,946,025.00 mm, bonding agent, persiapan permukaan beton,
troweling, curing
Setara Roman, serta memperhitungkan penggunaan
214,152,320.00
anti acid untuk battery room.
6,997,732.50 5 kg / m2 warna
16,440,461.36
22,500,000.00
13,954,000.00
3,183,689.79
988,400.00
1,878,000.00
4,556,877,562.66
Signature of BIdder :
AL SUBSTATION
DAN HARGA (BOQ)
ETER FENCE AND GATE
-
12,055,550.00
60,665,404.80
-
-
-
2 lapis Setara Dulux weather shield, complete dengan 2
66,570,912.00
lapis wall sealer.
Signature of BIdder :
AL SUBSTATION
DAN HARGA (BOQ)
ETER FENCE AND GATE
2 lapis Setara Dulux interior, complete dengan 2 lapis
104,415,588.00
wall sealer.
2 lapis Setara Dulux weather shield, complete dengan 2
8,242,360.00
lapis primer
811,801,064.15
72,404,478.00
-
-
-
-
-
-
-
-
-
-
-
-
-
Philips TBS 2x36 dengan kabel NYM 3x2,5 mm + switch
29,001,120.00
setara panasonic.
-
-
-
-
-
-
-
-
stop kontak setara panasonic dengan kabel NYM 3x2,5
6,431,865.00
mm
1,891,138.00 Exit lamp
-
11,201,550.00
-
-
11,201,550.00
-
-
-
-
Philips TBS 2x36 dengan kabel NYM 3x2,5 mm + switch
69,602,688.00
setara panasonic.
-
-
Philips TBS 2x36 + NiCad battery dengan kabel NYM
11,600,448.00
3x2,5 mm + switch setara panasonic.
-
-
-
-
-
stop kontak setara panasonic dengan kabel NYM 3x2,5
5,574,283.00
mm
stop kontak setara panasonic dengan kabel NYM 3x2,5
11,553,550.00
mm
Signature of BIdder :
AL SUBSTATION
DAN HARGA (BOQ)
ETER FENCE AND GATE
12,292,397.00
-
-
335,405,299.00
Signature of BIdder :
AL SUBSTATION
DAN HARGA (BOQ)
ETER FENCE AND GATE
BRC 7 mm hotdip galvanise dan tiang pipa galvanised
994,585,760.00 50 mm, complete dengan pondasi 50x50x75 cm , slope
15x20 cm dll
Tiang pipa galvanised 50 mm, Termasuk pondasi
50x50x75cm dan slope 15x20 cm
Precast concrete panel 2 m H complete with pondasi,
2,567,228,749.04
slope, strut dan barbed wire.
Brick wall fence 2 m H complete with pondasi, kolom,
30,334,764.00
slope, plaster and painting.
1,989,070,800.64 K.225
2,039,230,800.00
599,108,525.50 1,695,230,796.00
344,000,004.00
Signature of BIdder :
ANALISA HARGA SATUAN PEKERJAAN
A MATERIAL
Portland Cement (PC) 2.5000 kg 1,260.00 3,150.00
Seng Gelombang 3" - 5" 1.2000 lbr 48,000.00 57,600.00
Pasir Beton (PB) 0.0050 m³ 225,000.00 1,125.00
Koral Beton (maksimum 30 mm) 0.0090 m³ 200,000.00 1,800.00
Kayu Meranti Batu 5/7 (ikat) 0.0895 m³ 2,650,000.00 237,175.00
Paku Biasa 2" - 5" 0.0600 kg 15,000.00 900.00
Meni Besi 0.4000 Kg 35,000.00 14,000.00
B UPAH
Pekerja 0.3250 Oh 60,000.00 19,500.00
Tukang Kayu 0.1300 Oh 70,000.00 9,100.00
Kepala Tukang 0.0130 Oh 80,000.00 1,040.00
Mandor 0.0130 Oh 100,000.00 1,300.00
ALISA 30,940.00
C PERALATAN
Alat Bantu 1.0000 Ls 31,575.00 31,575.00
B Tenaga
Pekerja 0.6000 Oh 60,000.00 36,000.00
Tukang Batu 0.3000 Oh 70,000.00 21,000.00
Tukang Kayu 0.6000 Oh 70,000.00 42,000.00
Kepala Tukang 0.0900 Oh 80,000.00 7,200.00
Mandor 0.0150 Oh 100,000.00 1,500.00
Jumlah Biaya Upah 107,700.00
C Peralatan
Alat Bantu 1.0000 Ls 69,595.50 69,595.50
Jumlah Biaya Peralatan 69,595.50
B Tenaga
Pekerja 0.3000 Oh 60,000.00 18,000.00
Tukang Kayu 0.6000 Oh 70,000.00 42,000.00
Kepala Tukang 0.0600 Oh 80,000.00 4,800.00
Mandor 0.0150 Oh 100,000.00 1,500.00
Jumlah Biaya Upah 66,300.00
C Peralatan
Alat Bantu 1.0000 Ls 74,780.00 74,780.00
Jumlah Biaya Peralatan 74,780.00
B Tenaga
Pekerja 0.0500 Oh 60,000.00 3,000.00
Tukang Kayu 0.0500 Oh 70,000.00 3,500.00
Kepala Tukang 0.0050 Oh 80,000.00 400.00
Mandor 0.0025 Oh 100,000.00 250.00
Jumlah Biaya Upah 7,150.00
C Peralatan
Alat Bantu 1.0000 Ls 715.00 715.00
Jumlah Biaya Peralatan 715.00
B Tenaga
Pekerja 0.4600 Oh 60,000.00 27,600.00
Mandor 0.0250 Oh 100,000.00 2,500.00
Jumlah Biaya Upah 30,100.00
C Peralatan
Alat Bantu 1.0000 Ls 4,515.00 4,515.00
Jumlah Biaya Peralatan 4,515.00
B Tenaga
Pekerja 0.9000 Oh 60,000.00 54,000.00
Mandor #VALUE! Oh 100,000.00 #VALUE!
Jumlah Biaya Upah #VALUE!
C Peralatan
Alat Bantu 1.0000 Ls #VALUE! #VALUE!
Jumlah Biaya Peralatan #VALUE!
B Tenaga
Pekerja 1.0000 Oh 60,000.00 60,000.00
Mandor 0.1250 Oh 100,000.00 12,500.00
Jumlah Biaya Upah 72,500.00
C Peralatan
Alat Bantu 1.0000 Ls 10,875.00 10,875.00
Jumlah Biaya Peralatan 10,875.00
B Tenaga
Pekerja 0.2500 Oh 60,000.00 15,000.00
Mandor 0.0083 Oh 100,000.00 833.33
Jumlah Biaya Upah 15,833.33
C Peralatan
Alat Bantu 1.0000 Ls 2,375.00 2,375.00
Jumlah Biaya Peralatan 2,375.00
B Tenaga
Pekerja 0.9500 Oh 60,000.00 57,000.00
Mandor 0.0475 Oh 100,000.00 4,750.00
Jumlah Biaya Upah 61,750.00
C Peralatan
Alat Bantu 1.0000 Ls 9,262.50 9,262.50
Jumlah Biaya Peralatan 9,262.50
B Tenaga
Pekerja 0.3000 Oh 60,000.00 18,000.00
Mandor 0.0300 Oh 100,000.00 3,000.00
Jumlah Biaya Upah 21,000.00
C Peralatan
Alat Bantu 1.0000 Ls 3,150.00 3,150.00
Jumlah Biaya Peralatan 3,150.00
11 Pembersihan lahan
A Bahan
B Tenaga
Pekerja 0.0273 Oh 60,000.00 1,636.20
Mandor 0.0136 Oh 100,000.00 1,363.50
Jumlah Biaya Upah 2,999.70
C Peralatan
Alat Bantu 1.0000 Ls 449.96 449.96
Jumlah Biaya Peralatan 449.96
B Tenaga
Pekerja 0.1000 Oh 60,000.00 6,000.00
Mandor 0.0313 Oh 100,000.00 3,134.08
Jumlah Biaya Upah 9,134.08
C Peralatan
Excavator 0.0034 Jam 145,000.00 486.90
Dump Truck 0.0500 Jam 165,000.00 8,250.00
Motor Grader 0.0350 Jam 338,000.00 11,830.00
Vibro Roller 0.0049 Jam 335,000.00 1,636.27
Alat Bantu - Ls - -
B Tenaga
Sopir Truck 1.0000 Oh 70,000.00 70,000.00
C Peralatan
Biaya Angkat Tanah ke Dump Truck(Excavator) 0.1975 Jam 145,000.00 28,638.74
Sewa Dump Truck + BBM 0.1000 Hr 1,000,000.00 100,000.00
B Tenaga
Pekerja 0.3000 Oh 60,000.00 18,000.00
Mandor 0.0325 Oh 100,000.00 3,250.00
Jumlah Biaya Upah 21,250.00
B Peralatan
Alat Bantu 1.0000 Ls 19,250.00 19,250.00
Jumlah Biaya Peralatan 19,250.00
B Tenaga
Pekerja 0.6600 Oh 60,000.00 39,600.00
Tukang Batu 0.2640 Oh 70,000.00 18,480.00
Kepala Tukang 0.0264 Oh 80,000.00 2,112.00
Mandor 0.0330 Oh 100,000.00 3,300.00
B Peralatan
Alat Bantu 1.0000 Ls 52,978.00 52,978.00
Jumlah Biaya Peralatan 52,978.00
JUMLAH BIAYA UPAH, MATERIAL dan PERALATAN ( A + B + C ) 640,838.00
OVERHEAD & PROFIT 0.00% -
HARGA SATUAN PEKERJAAN 640,838.00
B Tenaga
Pekerja 2.1000 Oh 60,000.00 126,000.00
Tukang Batu 0.7000 Oh 70,000.00 49,000.00
Kepala Tukang 0.0700 Oh 80,000.00 5,600.00
Mandor 0.1050 Oh 100,000.00 10,500.00
B Peralatan
Alat Bantu 1.0000 Lot 48,100.00 48,100.00
Jumlah Biaya Peralatan 48,100.00
B Tenaga
Pekerja 0.1300 Oh 60,000.00 7,800.00
Tukang Batu 0.0975 Oh 70,000.00 6,825.00
Kepala Tukang 0.0098 Oh 80,000.00 780.00
Mandor 0.0065 Oh 100,000.00 650.00
Jumlah Biaya Upah 16,055.00
B Peralatan
Alat Bantu 1.0000 Lot 1,314.24 1,314.24
Jumlah Biaya Peralatan 1,314.24
18 Memasang 1 m² Acian
A Bahan
Portland Cement (PC) 3.2500 kg 1,260.00 4,095.00
B Tenaga
Pekerja 0.1020 Oh 60,000.00 6,120.00
Tukang Batu 0.0680 Oh 70,000.00 4,760.00
Kepala Tukang 0.0068 Oh 80,000.00 544.00
Mandor 0.0054 Oh 100,000.00 544.00
B Peralatan
Alat Bantu 1.0000 Lot 409.50 409.50
Jumlah Biaya Peralatan 409.50
B Tenaga
Pekerja 0.0600 Oh 60,000.00 3,600.00
Tukang Batu 0.0100 Oh 70,000.00 700.00
Kepala Tukang 0.0010 Oh 80,000.00 80.00
Mandor 0.0030 Oh 100,000.00 300.00
B Peralatan
Alat Bantu 1.0000 Lot 15,174.17 15,174.17
Jumlah Biaya Peralatan 15,174.17
20 Membuat 1 m³ beton mutu f'c=7,4 Mpa (K 100); slump (3-6) cm; w/c = 0,87 Lantai Kerja
A Bahan
Portland Cement (PC) 200.0000 kg 1,260.00 252,000.00
Pasir Beton (PB) 0.5000 m³ 225,000.00 112,500.00
Koral Beton (maksimum 30 mm) 0.7000 m³ 200,000.00 140,000.00
Air 200.0000 liter 50.00 10,000.00
B Tenaga
Pekerja 0.9000 Oh 60,000.00 54,000.00
Tukang Batu 0.1000 Oh 70,000.00 7,000.00
Kepala Tukang 0.0200 Oh 80,000.00 1,600.00
Mandor 0.0600 Oh 100,000.00 6,000.00
B Peralatan
Alat Bantu 1.0000 Lot 51,450.00 51,450.00
Jumlah Biaya Peralatan 51,450.00
JUMLAH BIAYA UPAH, MATERIAL dan PERALATAN ( A + B + C ) 634,550.00
OVERHEAD & PROFIT 0.00% -
HARGA SATUAN PEKERJAAN 634,550.00
21 Membuat 1 m³ beton mutu f'c=14,5 Mpa (K 175); slump (12 ± 2) cm; w/c = 0,66
A Bahan
Portland Cement (PC) 250.0000 kg 1,260.00 315,000.00
Pasir Beton (PB) 0.5000 m³ 225,000.00 112,500.00
Koral Beton (maksimum 30 mm) 0.7000 m³ 200,000.00 140,000.00
Air 215.0000 liter 50.00 10,750.00
B Tenaga
Pekerja 1.0263 Oh 60,000.00 61,578.00
Tukang Batu 0.1711 Oh 70,000.00 11,973.50
Kepala Tukang 0.0174 Oh 80,000.00 1,393.28
Mandor 0.0516 Oh 100,000.00 5,162.60
B Peralatan
Alat Bantu 1.0000 Lot 57,825.00 57,825.00
Jumlah Biaya Peralatan 57,825.00
22 Membuat 1 m³ beton mutu f'c=19,3 Mpa (K 225); slump (12 ± 2) cm; w/c = 0,58
A Bahan
Portland Cement (PC) 371.0000 kg 1,260.00 467,460.00
Pasir Beton (PB) 0.4986 m³ 225,000.00 112,178.57
Koral Beton (maksimum 30 mm) 0.7756 m³ 200,000.00 155,111.11
Air 215.0000 liter 50.00 10,750.00
B Tenaga
Pekerja 1.0263 Oh 60,000.00 61,578.00
Tukang Batu 0.1711 Oh 70,000.00 11,973.50
Kepala Tukang 0.0174 Oh 80,000.00 1,393.28
Mandor 0.0516 Oh 100,000.00 5,162.60
B Peralatan
Alat Bantu 1.0000 Lot 74,549.97 74,549.97
Jumlah Biaya Peralatan 74,549.97
23 Membuat 1 m³ beton mutu f'c=21,7 Mpa (K 250); slump (12 ± 2) cm; w/c = 0,56
A Bahan
Portland Cement (PC) 384.0000 kg 1,260.00 483,840.00
Pasir Beton (PB) 0.4943 m³ 225,000.00 111,214.29
Koral Beton (maksimum 30 mm) 0.7696 m³ 200,000.00 153,925.93
Air 215.0000 liter 50.00 10,750.00
B Tenaga
Pekerja 1.0263 Oh 60,000.00 61,578.00
Tukang Batu 0.1711 Oh 70,000.00 11,973.50
Kepala Tukang 0.0174 Oh 80,000.00 1,393.28
Mandor 0.0516 Oh 100,000.00 5,162.60
B Peralatan
Alat Bantu 1.0000 Lot 75,973.02 75,973.02
Jumlah Biaya Peralatan 75,973.02
24 Membuat 1 m³ beton mutu f'c=26,4 Mpa (K 300); slump (12 ± 2) cm; w/c = 0,52
A Bahan
Portland Cement (PC) 413.0000 kg 1,260.00 520,380.00
Pasir Beton (PB) 0.4864 m³ 225,000.00 109,446.43
Koral Beton (maksimum 30 mm) 0.7563 m³ 200,000.00 151,259.26
Air 215.0000 liter 50.00 10,750.00
B Tenaga
Pekerja 1.0263 Oh 60,000.00 61,578.00
Tukang Batu 0.1711 Oh 70,000.00 11,973.50
Kepala Tukang 0.0174 Oh 80,000.00 1,393.28
Mandor 0.0516 Oh 100,000.00 5,162.60
B Peralatan
Alat Bantu 1.0000 Lot 79,183.57 79,183.57
Jumlah Biaya Peralatan 79,183.57
25 Membuat 1 m³ beton mutu f'c=31,2 Mpa (K 350); slump (12 ± 2) cm; w/c = 0,48
A Bahan
Portland Cement (PC) 448.0000 kg 1,260.00 564,480.00
Pasir Beton (PB) 0.4764 m³ 225,000.00 107,196.43
Koral Beton (maksimum 30 mm) 0.7407 m³ 200,000.00 148,148.15
Air 215.0000 liter 50.00 10,750.00
B Tenaga
Pekerja 1.0263 Oh 60,000.00 61,578.00
Tukang Batu 0.1711 Oh 70,000.00 11,973.50
Kepala Tukang 0.0174 Oh 80,000.00 1,393.28
Mandor 0.0516 Oh 100,000.00 5,162.60
B Peralatan
Alat Bantu 1.0000 Lot 83,057.46 83,057.46
Jumlah Biaya Peralatan 83,057.46
B Tenaga
Pekerja 0.1118 Oh 60,000.00 6,710.40
Tukang Batu 0.1398 Oh 70,000.00 9,786.00
Kepala Tukang 0.1398 Oh 80,000.00 11,184.00
Mandor 0.0466 Oh 100,000.00 4,660.00
Pekerja (bongkar cetakan) 0.1118 Oh 60,000.00 6,710.40
B Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.1000 Oh 60,000.00 6,000.00
Tukang Batu 0.1100 Oh 70,000.00 7,700.00
Kepala Tukang 0.1200 Oh 80,000.00 9,600.00
Mandor 0.0300 Oh 100,000.00 3,000.00
Pekerja (bongkar cetakan) 0.1118 Oh 60,000.00 6,710.40
B Tenaga
Pekerja 0.1680 Oh 60,000.00 10,080.00
Tukang Batu 0.0840 Oh 70,000.00 5,880.00
Kepala Tukang 0.0840 Oh 80,000.00 6,720.00
Mandor 0.0280 Oh 100,000.00 2,800.00
Pekerja (bongkar cetakan) 0.0840 Oh 60,000.00 5,040.00
B Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.0080 Oh 60,000.00 480.00
Tukang Besi 0.0030 Oh 70,000.00 210.00
Kepala Tukang 0.0030 Oh 80,000.00 240.00
Mandor 0.0015 Oh 100,000.00 150.00
B Tenaga
Pekerja 0.0080 Oh 60,000.00 480.00
Tukang Besi 0.0030 Oh 70,000.00 210.00
Kepala Tukang 0.0030 Oh 80,000.00 240.00
Mandor 0.0015 Oh 100,000.00 150.00
B Peralatan
Alat Bantu - Lot - -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.0600 Oh 60,000.00 3,600.00
Tukang Besi 0.0040 Oh 70,000.00 280.00
Kepala Tukang 0.0010 Oh 80,000.00 80.00
Mandor 0.0002 Oh 100,000.00 20.00
B Peralatan
Peralatan (Oxigen,solar,Elpiji,kawat las dll ) 0.1250 Lot 15,000.00 1,875.00
Besi IWF ex DN SII 1,875.00
B Tenaga
Pekerja 0.0600 Oh 60,000.00 3,600.00
Tukang Besi 0.0040 Oh 70,000.00 280.00
Kepala Tukang 0.0010 Oh 80,000.00 80.00
Mandor 0.0002 Oh 100,000.00 20.00
B Peralatan
Peralatan (Oxigen,solar,Elpiji,kawat las dll ) 0.1250 Lot 15,000.00 1,875.00
Jumlah Biaya Peralatan 1,875.00
B Peralatan
Peralatan (Oxigen,solar,Elpiji,kawat las dll ) 0.1250 Lot 15,000.00 1,875.00
Jumlah Biaya Peralatan 1,875.00
B Tenaga
Pekerja 0.0600 Oh 60,000.00 3,600.00
Tukang Besi 0.0040 Oh 70,000.00 280.00
Kepala Tukang 0.0010 Oh 80,000.00 80.00
Mandor 0.0002 Oh 100,000.00 20.00
B Peralatan
Peralatan (Oxigen,solar,Elpiji,kawat las dll ) 0.1250 Lot 15,000.00 1,875.00
Jumlah Biaya Peralatan 1,875.00
B Tenaga
Pekerja 0.0600 Oh 60,000.00 3,600.00
Tukang Besi 0.0040 Oh 70,000.00 280.00
Kepala Tukang 0.0010 Oh 80,000.00 80.00
Mandor 0.0002 Oh 100,000.00 20.00
B Peralatan
Peralatan (Oxigen,solar,Elpiji,kawat las dll ) 0.1250 Lot 15,000.00 1,875.00
Jumlah Biaya Peralatan 1,875.00
B Tenaga
Pekerja 0.0600 Oh 60,000.00 3,600.00
Tukang Besi 0.0040 Oh 70,000.00 280.00
Kepala Tukang 0.0010 Oh 80,000.00 80.00
Mandor 0.0002 Oh 100,000.00 20.00
B Peralatan
Peralatan (Oxigen,solar,Elpiji,kawat las dll ) 0.1250 Lot 15,000.00 1,875.00
Jumlah Biaya Peralatan 1,875.00
B Tenaga
Pekerja 0.0220 Oh 60,000.00 1,320.00
Tukang 0.0693 Oh 70,000.00 4,851.00
Kepala Tukang 0.0069 Oh 80,000.00 554.40
Mandor 0.0028 Oh 100,000.00 275.00
B Peralatan
Steger werk 0.0250 Ls 20,000.00 500.00
B Tenaga
Pekerja 0.0220 Oh 60,000.00 1,320.00
Tukang 0.0693 Oh 70,000.00 4,851.00
Kepala Tukang 0.0069 Oh 80,000.00 554.40
Mandor 0.0028 Oh 100,000.00 275.00
B Peralatan
Steger werk 0.0250 Ls 20,000.00 500.00
40 1 M2 Pengecatan Besi
A Bahan
Cat Meni 0.2000 Kg 35,000.00 7,000.00
Plamir 0.1500 Kg 19,900.00 2,985.00
Cat Dasar 0.1700 Bh 34,500.00 5,865.00
Cat Penutup 0.2600 Bh 58,000.00 15,080.00
Kuas 0.0100 Bh 12,000.00 120.00
Ampelas 0.5000 Lbr 3,500.00 1,750.00
B Tenaga
Pekerja 0.0490 Oh 60,000.00 2,940.00
Tukang 0.0735 Oh 70,000.00 5,145.00
Kepala Tukang 0.0028 Oh 80,000.00 224.00
Mandor 0.0018 Oh 100,000.00 175.00
B Peralatan
Steger werk 0.0250 Ls 20,000.00 500.00
B Tenaga
Pekerja 0.8688 Jam 8,571.43 7,446.86
Tukang 0.2172 Jam 10,000.00 2,172.00
Mandor 0.1086 Jam 14,285.71 1,551.43
C Peralatan
Alat Bantu 0.0000 Ls - -
B Tenaga
Pekerja 0.2500 Oh 60,000.00 15,000.00
Tukang 0.5000 Oh 70,000.00 35,000.00
Kepala Tukang 0.0500 Oh 80,000.00 4,000.00
Mandor 0.0250 Oh 100,000.00 2,500.00
C Peralatan
Alat Bantu 0.0000 Ls -
B Tenaga
Pekerja 0.2250 Oh 60,000.00 13,500.00
Tukang Batu 0.0750 Oh 70,000.00 5,250.00
Kepala Tukang 0.0075 Oh 80,000.00 600.00
Mandor 0.0113 Oh 100,000.00 1,125.00
C Peralatan
Alat Bantu 0.0000 Ls -
C Peralatan
Alat Bantu 0.0000 Ls - -
B Tenaga
Pekerja 0.2000 Oh 60,000.00 12,000.00
Tukang Batu 0.0500 Oh 70,000.00 3,500.00
Mandor 0.0500 Oh 100,000.00 5,000.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.2000 Oh 60,000.00 12,000.00
Tukang Batu 0.0500 Oh 70,000.00 3,500.00
Mandor 0.0500 Oh 100,000.00 5,000.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.1500 Oh 60,000.00 9,000.00
Mandor 0.0150 Oh 100,000.00 1,500.00
C Peralatan
-
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.0810 Oh 60,000.00 4,860.00
Tukang 0.2700 Oh 70,000.00 18,900.00
Kepala Tukang 0.0270 Oh 80,000.00 2,160.00
Mandor 0.0432 Oh 100,000.00 4,320.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.0400 Oh 60,000.00 2,400.00
Tukang 0.0945 Oh 70,000.00 6,615.00
Kepala Tukang 0.0069 Oh 80,000.00 554.40
Mandor 0.0028 Oh 100,000.00 275.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.0400 Oh 60,000.00 2,400.00
Tukang 0.0945 Oh 70,000.00 6,615.00
Kepala Tukang 0.0069 Oh 80,000.00 554.40
Mandor 0.0028 Oh 100,000.00 275.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
C Peralatan
Alat Bantu 1.0000 Lot 159,900.00 159,900.00
Jumlah Biaya Peralatan 159,900.00
B Tenaga
Pekerja 3.3000 Oh 60,000.00 198,000.00
Tukang 1.1000 Oh 70,000.00 77,000.00
Kepala Tukang 0.0010 Oh 80,000.00 80.00
Mandor 0.1600 Oh 100,000.00 16,000.00
C Peralatan
Alat Bantu 1.0000 Lot 146,250.00 146,250.00
Jumlah Biaya Peralatan 146,250.00
B Tenaga
Pekerja 0.0616 Oh 60,000.00 3,696.00
Tukang 0.0528 Oh 70,000.00 3,696.00
Kepala Tukang 0.0528 Oh 80,000.00 4,224.00
Mandor 0.0176 Oh 100,000.00 1,760.00
C Peralatan
Alat Bantu Lot - -
Jumlah Biaya Peralatan -
JUMLAH BIAYA UPAH, MATERIAL dan PERALATAN ( A + B + C ) 272,828.00
OVERHEAD & PROFIT 0.00% -
HARGA SATUAN PEKERJAAN 272,828.00
B Tenaga
Pekerja 0.1500 Oh 60,000.00 9,000.00
Tukang 0.4000 Oh 70,000.00 28,000.00
Kepala Tukang 0.0250 Oh 80,000.00 2,000.00
Mandor 0.0013 Oh 100,000.00 125.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.1920 Oh 60,000.00 11,520.00
Tukang 0.0960 Oh 70,000.00 6,720.00
Kepala Tukang 0.0096 Oh 80,000.00 768.00
Mandor 0.0010 Oh 100,000.00 96.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
57 1 M2 Lisplang Zincalum t = 50 cm
A Bahan
Lisplang zincalume t=0.4 mm 0.5000 M2 117,000.00 58,500.00
Rangka Lisplang 0.5000 M2 150,000.00 75,000.00
Nail (Screw) 6.0000 Bh 300.00 1,800.00
B Tenaga
Pekerja 0.1100 Oh 60,000.00 6,600.00
Tukang 0.0550 Oh 70,000.00 3,850.00
Kepala Tukang 0.0055 Oh 80,000.00 440.00
Mandor 0.0006 Oh 100,000.00 55.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
58 AC Split 2 pk, tipe : Inverter dengan COP minimum 10 % dari standard SNI (termasuk pemasangan)
A Bahan
AC Split 2 pk, tipe : Inverter dengan COP 1.0000 Bh 6,000,000.00 6,000,000.00
B Tenaga
Pekerja 1.0000 Oh 60,000.00 60,000.00
Tukang 1.5800 Oh 70,000.00 110,600.00
Kepala Tukang 0.3500 Oh 80,000.00 28,000.00
Mandor 0.0200 Oh 100,000.00 2,000.00
59 AC Split 1 pk, tipe : Inverter dengan COP minimum 10 % dari standard SNI (termasuk pemasangan)
A Bahan
AC Split 1 pk, tipe : Inverter dengan COP 1.0000 Bh 3,400,000.00 3,400,000.00
Perlengkapan 1.0000 Ls 750,000.00 750,000.00
B Tenaga
Pekerja 1.0000 Oh 60,000.00 60,000.00
Tukang 1.5800 Oh 70,000.00 110,600.00
Kepala Tukang 0.3500 Oh 80,000.00 28,000.00
Mandor 0.0400 Oh 100,000.00 4,000.00
60 1 M2 FOOR HARDENER
A Bahan
Floor Hardener Sika Chapdur 5 Kg/m2 (Warna) 5.0000 Kg 8,800.00 44,000.00
B Tenaga
Pekerja 0.1000 Oh 60,000.00 6,000.00
Tukang 0.0200 Oh 70,000.00 1,400.00
Kepala Tukang 0.0100 Oh 80,000.00 800.00
Mandor 0.0060 Oh 100,000.00 600.00
Jumlah Biaya Upah 8,800.00
C Peralatan
Mesin Trowel 1.0000 M2 3,000.00 3,000.00
Alat Bantu 1.0000 Lot 4,400.00 4,400.00
Jumlah Biaya Peralatan 7,400.00
B Tenaga
Pekerja Oh 60,000.00 -
Tukang Oh 70,000.00 -
Kepala Tukang Oh 80,000.00 -
Mandor Oh 100,000.00 -
63 1 M2 KERAMIK Dinding
A Bahan
Keramik dinding ex Roman 1.0500 M2 90,000.00 94,500.00
Semen PC 10.0000 Kg 1,260.00 12,600.00
Pasir pasang 0.0450 M3 220,000.00 9,900.00
Semen Cor Nat 0.3000 Kg 10,000.00 3,000.00
Jumlah Biaya Material 120,000.00
B Tenaga
Pekerja 0.2325 Oh 60,000.00 13,950.00
Tukang 0.1313 Oh 70,000.00 9,187.50
Kepala Tukang 0.0131 Oh 80,000.00 1,050.00
Mandor 0.0113 Oh 100,000.00 1,125.00
B Tenaga
Pekerja 0.2500 Oh 60,000.00 15,000.00
Tukang 0.1500 Oh 70,000.00 10,500.00
Kepala Tukang 0.0300 Oh 80,000.00 2,400.00
Mandor 0.0480 Oh 100,000.00 4,800.00
Ditch size W300xD500, made of reinforced concrete K.175 thick of wall and
66 slab 100 mm, including excavation, sandfill, lean concrete etc to complete
works. Cast insitu
A Bahan
Galian tanah 0.4550 M3 34,615.00 15,749.83
Pasir urug t = 10 cm 0.0455 M3 233,000.00 10,601.50
Lantai kerja t = 5 cm 0.0228 M3 634,550.00 14,436.01
Beton t = 10 cm K- 175 0.1300 M3 716,182.00 93,103.66
Pembesian dia. 8 - 15 cm (1 lapis) 8.6900 Kg 9,628.00 83,667.32
Bekisting 2.3000 m2 94,832.00 218,113.60
Jumlah Biaya Material 435,671.92
B Tenaga
-
Jumlah Biaya Upah -
C Peralatan
Alat Bantu 1.0000 Lot 21,783.60 21,783.60
Jumlah Biaya Peralatan 21,783.60
A Bahan
Galian tanah 0.4550 M3 34,615.00 15,749.83
Pasir urug t = 10 cm 0.0455 M3 233,000.00 10,601.50
U Ditch ukuran 300x500x1200 mm 1.0000 M' 334,583.33 334,583.33
B Tenaga
Upah Pasang 1.0000 M' 83,646.00 83,646.00
-
Jumlah Biaya Upah -
C Peralatan
Alat Bantu 1.0000 Lot 16,729.00 16,729.00
Jumlah Biaya Peralatan 16,729.00
JUMLAH BIAYA UPAH, MATERIAL dan PERALATAN ( A + B + C ) 377,663.66
OVERHEAD & PROFIT -
HARGA SATUAN PEKERJAAN 377,664.00
A Bahan
Batu Split 5-7 cm t = 10 cm 1.0000 m3 175,000.00 175,000.00
Jumlah Biaya Material 175,000.00
B Tenaga Penghamparan batu
Pekerja 0.3750 Oh 60,000.00 22,500.00
Mandor 0.0375 Oh 100,000.00 3,750.00
A Bahan
Batu Split 3-5 cm t = 10 cm 0.1200 m3 200,000.00 24,000.00
Pemadatan Tanah 1.0000 m2 24,150.00 24,150.00
Obat Pembunuh Rumput Round Up 486 SL 0.0067 Ltr 90,000.00 600.00
A Bahan
Galian tanah septic tank 6.2250 m3 #VALUE! #VALUE!
Septic Tank Biotech volume 3 m3 uk. 2000x1160x1270 mm RC 03 1.0000 bh 11,500,000.00 11,500,000.00
Urugan Pasir t = 10 cm 0.2320 m3 233,000.00 54,056.00
Beton Tumbuk, Bawah = 10 cm K- 175 0.2320 m3 716,182.00 166,154.22
Beton Tumbuk, Tutup atas = 12 cm K- 175 0.2784 m3 716,182.00 199,385.07
Urugan Kembali bekas galian dengan Pasir 3.2786 m3 233,000.00 763,913.80
Jumlah Biaya Material #VALUE!
B Tenaga
Pekerja 2.5000 Oh 60,000.00 150,000.00
Mandor 0.2500 Oh 100,000.00 25,000.00
Jumlah Biaya Upah 175,000.00
C Peralatan
1.0000 Lot #VALUE! #VALUE!
Jumlah Biaya Peralatan #VALUE!
B Tenaga
Pekerja 0.2750 Oh 60,000.00 16,500.00
Tukang 0.1800 Oh 70,000.00 12,600.00
Kepala Tukang 0.0175 Oh 80,000.00 1,400.00
Mandor 0.0018 Oh 100,000.00 180.00
B Tenaga
Pekerja 0.2750 Oh 60,000.00 16,500.00
Tukang 0.1800 Oh 70,000.00 12,600.00
Kepala Tukang 0.0175 Oh 80,000.00 1,400.00
Mandor 0.0018 Oh 100,000.00 180.00
Jumlah Biaya Upah 30,680.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.2750 Oh 60,000.00 16,500.00
Tukang 0.1800 Oh 70,000.00 12,600.00
Kepala Tukang 0.0175 Oh 80,000.00 1,400.00
Mandor 0.0018 Oh 100,000.00 180.00
B Tenaga
Pekerja 0.2750 Oh 60,000.00 16,500.00
Tukang 0.1800 Oh 70,000.00 12,600.00
Kepala Tukang 0.0175 Oh 80,000.00 1,400.00
Mandor 0.0018 Oh 100,000.00 180.00
B Tenaga
Pekerja 0.5500 Oh 60,000.00 33,000.00
Tukang 0.3600 Oh 70,000.00 25,200.00
Kepala Tukang 0.0350 Oh 80,000.00 2,800.00
Mandor 0.0036 Oh 100,000.00 360.00
Jumlah Biaya Upah 61,360.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.5500 Oh 60,000.00 33,000.00
Tukang 0.3600 Oh 70,000.00 25,200.00
Kepala Tukang 0.0350 Oh 80,000.00 2,800.00
Mandor 0.0036 Oh 100,000.00 360.00
B Tenaga
Pekerja 0.3438 Oh 60,000.00 20,625.00
Tukang 0.2250 Oh 70,000.00 15,750.00
Kepala Tukang 0.0219 Oh 80,000.00 1,750.00
Mandor 0.0023 Oh 100,000.00 225.00
B Tenaga
Pekerja 0.3438 Oh 60,000.00 20,625.00
Tukang 0.2250 Oh 70,000.00 15,750.00
Kepala Tukang 0.0219 Oh 80,000.00 1,750.00
Mandor 0.0023 Oh 100,000.00 225.00
Jumlah Biaya Upah 38,350.00
C Peralatan
Alat Bantu - Lot -
Jumlah Biaya Peralatan -
B Tenaga
Pekerja 0.3438 Oh 60,000.00 20,625.00
Tukang 0.2250 Oh 70,000.00 15,750.00
Kepala Tukang 0.0219 Oh 80,000.00 1,750.00
Mandor 0.0023 Oh 100,000.00 225.00
B Tenaga
Pasang Pagar BRC 1.0000 m' 15,000.00 15,000.00
B Tenaga
Upah Pasang Wire mesh 1.0000 m' 13,200.00 13,200.00
81 Boundary fence type-1, Fabricated concrete Panel 2.00 m height 1.00 m'
A Bahan
Pekerjaan Galian tanah 0.0625 m3 34,615.00 2,163.44
Urugan Pasir t 5 cm 0.0090 m3 233,000.00 2,097.00
Lantai kerja t = 5 cm 0.0090 m3 634,550.00 5,710.95
Pagar Panel 40 x 240 x 5 cm, t = 200 cm 1.0000 M' 375,000.00 375,000.00
Beton Pondasi Tiang 50 x 50 cm x 70 cm K 225 0.2150 m3 2,673,996.00 574,909.14
Skoor Kolom Beton 15 x 15 cm 0.0225 m3 2,673,996.00 60,164.91
Kawat Duri 4 Jalur 1.0000 m' 68,000.00 68,000.00
83 Main Gate 2,1 m height x opening 10 m wide. 1.00 unit pjg 10 meter
A Bahan
Galian tanah 3.67 m3 34,615.00 127,106.28
Urugan Pasir t = 5 cm 0.61 m3 233,000.00 141,198.00
Lantai Kerja t = 5 cm 0.61 m3 634,550.00 384,537.30
Beton Dudukan Rel Pintu K-225 2.40 m3 2,627,302.00 6,305,524.80
Square Tube 50x50 t = 2,5 mm 52.60 m' 32,500.00 1,709,500.00
Square Tube 20x40 t =3 mm 360.00 m' 15,333.33 5,520,000.00
Square Tube 25x25 28.00 m' 7,750.00 217,000.00
Steel Plate t = 2 mm 9.00 m2 138,333.00 1,244,997.00
Roda Pintu 6.00 bh 150,000.00 900,000.00
Besi beton dia 16 mm 18.96 kg 9,628.00 182,546.88
Anchor bolt dia 10 -12 cm 10.00 bh 12,500.00 125,000.00
Finishing cat besi 42.00 m2 50,141.00 2,105,922.00
Handel Pintu 1.00 psg 250,000.00 250,000.00
Kunci 1.00 bh 150,000.00 150,000.00
-
Jumlah Biaya Material 5.1500 15,649,863.38
B Tenaga
Pasang 1.0000 unit 3,912,465.85 3,912,465.85
Jumlah Biaya Upah 3,912,465.85
C Peralatan
Alat Bantu - Lot - -
Jumlah Biaya Peralatan -
84 Switchyard Gate 1.20 m height x opening 3 m wide. 1.00 unit pjg 3 meter
A Bahan
Galian tanah 1.15 m3 34,615.00 39,876.48
Urugan Pasir t = 5 cm 0.19 m3 233,000.00 43,338.00
Lantai Kerja t = 5 cm 0.19 m3 634,550.00 121,833.60
Beton Dudukan Rel Pintu K-225 0.72 m3 2,627,302.00 1,891,657.44
Square Tube 50x50 t = 2,5 mm 18.60 m' 32,500.00 604,500.00
Square Tube 20x40 t =3 mm 48.00 m' 15,333.33 736,000.00
Square Tube 25x25 8.40 m' 7,750.00 65,100.00
Steel Plate t = 2 mm 2.70 m2 138,333.00 373,499.10
Roda Pintu 3.00 bh 150,000.00 450,000.00
Besi beton dia 16 mm 6.32 kg 9,628.00 60,848.96
Anchor bolt dia 10 -12 cm 3.00 bh 12,500.00 37,500.00
Finishing cat besi 12.60 m2 50,141.00 631,776.60
Handel Pintu 1.00 psg 250,000.00 250,000.00
Kunci 1.00 bh 150,000.00 150,000.00
Jumlah Biaya Material 3,875,804.62
B Tenaga
Pasang 1.0000 unit 968,951.16 968,951.16
85 - Main personal Gate 2,1 m height x opening 1,2 m wide. 1.00 unit pjg 1,2 meter
A Bahan
Galian tanah 0.43 m3 34,615.00 14,953.68
Urugan Pasir t = 5 cm 0.07 m3 233,000.00 16,776.00
Lantai Kerja t = 5 cm 0.07 m3 634,550.00 45,687.60
Beton Dudukan Rel Pintu K-225 0.29 m3 2,627,302.00 756,662.98
Square Tube 50x50 t = 2,5 mm 11.80 m' 32,500.00 383,500.00
Square Tube 20x40 t =3 mm 43.20 m' 15,333.33 662,400.00
Square Tube 25x25 10.40 m' 7,750.00 80,600.00
Steel Plate t = 2 mm 1.08 m2 138,333.00 149,399.64
Roda Pintu 2.00 bh 150,000.00 300,000.00
Besi beton dia 16 mm 1.90 kg 9,628.00 18,254.69
Anchor bolt dia 10 -12 cm 3.00 bh 12,500.00 37,500.00
Finishing cat besi 5.04 m2 50,141.00 252,710.64
Handel Pintu 1.00 psg 250,000.00 250,000.00
Kunci 1.00 bh 150,000.00 150,000.00
Jumlah Biaya Material 2,109,979.90
B Tenaga
Pasang 1.0000 unit 527,494.97 527,494.97
Tenaga
Pekerja 0.0595 jam 8,571.43 510.00
Mandor 0.0085 jam 14,285.71 121.43
Tenaga
Pekerja 0.0416 jam 8,571.43 356.80
Mandor 0.0059 jam 14,285.71 84.95
Peralatan
WHEEL LOADER 0.0059 jam 482,500.00 2,869.26
DUMP TRUCK 0.3530 jam 165,000.00 58,244.78
MOTOR GRADER 0.0016 jam 338,000.00 554.28
TANDEM ROLLER 0.0150 jam 205,000.00 3,073.63
WATER TANK TRUCK 0.0098 jam 225,000.00 2,213.86
Alat Bantu 1.0000 Lot - -
Jumlah Biaya Peralatan 66,955.81
Dump Truck
JUMLAH BIAYA UPAH, MATERIAL dan PERALATAN ( A + B + C ) 342,397.56
OVERHEAD & PROFIT 0.00% -
HARGA SATUAN PEKERJAAN Harga Per M3 342,397.56
HARGA SATUAN PEKERJAAN t = 25 cm Harga Per M2 -
Tenaga
Pekerja 0.0595 jam 8,571.43 509.71
Mandor 0.0085 jam 14,285.71 121.36
Peralatan
WHEEL LOADER 0.0008 jam 482,500.00 394.52
ASPHALT MIXING PLANT (AMP) 0.0026 jam 1,900,000.00 4,978.92
GENERATORSET ( GENSET ) 0.0026 jam 402,088.00 1,053.66
DUMP TRUCK (DT) 0.0322 jam 165,000.00 5,308.36
ASPHALT FINISHER 0.0010 jam 856,725.00 819.21
TANDEM ROLLER 0.0024 jam 205,000.00 500.65
PNEUMATIC TIRE ROLLER 0.0011 jam 250,000.00 272.45
Alat Bantu 1.0000 Lot - -
Jumlah Biaya Peralatan 13,327.77
Tenaga
Pekerja 4.7143 jam 8,571.43 40,408.16
Mandor 0.1429 jam 14,285.71 2,040.82
Peralatan
THREE WHEEL ROLLER 0.0457 jam 205,000.00 9,359.54
Alat Bantu 1.0000 Lot - -
Jumlah Biaya Peralatan 9,359.54
Wheel Loader
JUMLAH BIAYA UPAH, MATERIAL dan PERALATAN ( A + B + C ) 1,083,901.97
OVERHEAD & PROFIT 0.00% -
HARGA SATUAN PEKERJAAN PER M3 1,083,901.97
HARGA SATUAN PEKERJAAN Harga Per M2 54,195.00
B Tenaga
B Tenaga
B Tenaga
B Tenaga
Pekerja 2.5000 Oh 60,000.00 150,000.00
Tukang 0.5000 Oh 70,000.00 35,000.00
Mandor 0.2500 Oh 100,000.00 25,000.00
1.000 1 Pembuatan Pagar Sementara (Kayu 5/7 - Seng Gelombang Tinggi 2.00m)
2.50 1.000
1.20 1.000
0.01 1.000
0.01 1.000
0.07 1.000
0.06 1.000
0.40 1.000
0.50 0.650
0.20 0.650
0.02 0.650
0.02 0.650
1.000
1.000
1.000
1.000
2.00 0.300
1.00 0.300
2.00 0.300
0.30 0.300
0.05 0.300
69,860,080.00
0.23 1.000
0.30 1.000
10.50 1.000
0.03 1.000
0.05 1.000
1.50 1.000
1.000
1.000
1.00 0.300
2.00 0.300
0.20 0.300
0.05 0.300
1.000
1.000
0.0120 1.000
0.0200 1.000
0.0070 1.000
0.1000 0.500
0.1000 0.500
0.0100 0.500
0.0050 0.500
1.000
1.000
71,092.49
0.4575
1.000
60,000.00
0.90 1.000
0,0450 1.000
1.000
1.000
1.00 1.000
0.13 1.000
1.000
1.000
0.25 1.000
0.01 1.000
1.000
1.000
0.6000 100.00
0.0600
1.000
0.50 0.600
0.05 0.600
1.000
1.000
0.10 0.273
0.05 0.273
1.000
1.000
3,000.00
0.01 0.450
0.43 0.450
0.12 0.450
0.01 0.450
0.01 1.000
0.43
0.12
0.01
12 Pembuangan tanah Keluar area
1.00 1.00
560,000.00
1.000
11.52
8.00 0.20 1.000
2.40 0.14 1.000
1,000,000.00
18.72
0.50 0.650
0.05 0.650
1.000
1.000
14
1.20 1.000
163.00 1.000
0.52 1.000
3.26 ZAK/M3
1.50 0.440
0.60 0.440
0.06 0.440
0.08 0.440
1.000
1.000
17,500.00
1.000
70,410.00
0.3700 0.667
0.1570 0.667
0.0070 0.667
0.0164 0.667
0.0185 0.667
- 1.000
-
1.000
8.33
4.00
-
0.3700 0.667
0.1570 0.667
0.0070 0.667
0.0164 0.667
0.0185 0.667
2,212.67 1.000
2,212.67
1.000
130,268.00
6.24 1.000
0.02 1.000
0.12 ZAK/M3
0.20 0.650
0.15 0.650
0.02 0.650
0.01 0.650
1.000
1.000
3.25 1.000
0.07 ZAK/M3
0.15 0.680
0.10 0.680
0.01 0.680
0.01 0.680
1.000
1.000
0.06 1.000
0.01 1.000
0.00 1.000
0.00 1.000
1.000
1.000
200.0000 1.000
0.5000 1.000
0.7000 1.000
200.00 1.000
4.00 ZAK/M3
0.9000 1.000
0.1000 1.000
0.0200 1.000
0.0600 1.000
1.000
1.000
250.0000 1.000
0.5000 1.000
0.7000 1.000
215.00 1.000
5.00 ZAK/M3
1.000
1.000
371.00 1.000
0.50 1.000
0.78 1.000
215.00 1.000
1.65 0.622
0.28 0.622
0.03 0.622
0.08 0.622
1.000
1.000
384.00 1.000
0.49 1.000
0.77 1.000
215.00 1.000
1.65 0.622
0.28 0.622
0.03 0.622
0.08 0.622
1.000
1.000
413.00 1.000
0.49 1.000
0.76 1.000
215.00 1.000
1.65 0.622
0.28 0.622
0.03 0.622
0.08 0.622
1.000
1.000
448.00 1.000
0.48 1.000
0.74 1.000
215.00 1.000
1.65 0.622
0.28 0.622
0.03 0.622
0.08 0.622
1.000
1.000
#REF!
0.35 0.300
0.40 1.000
0.02 0.500
0.12 0.932
0.15 0.932
0.15 0.932
0.05 0.932
0.12 0.932
1.000
1.000
#REF!
25,317,988,575.09
0.35 0.500
0.40 1.000
0.02 0.500
0.12 0.932
0.15 0.932
0.15 0.932
0.05 0.932
0.12 0.932
1.000
1.000
0.3470 0.300
0.4000 1.000
0.0170 0.500
0.12 0.932
0.15 0.932
0.15 0.932
0.05 0.932
0.12 0.932
1.000
1.000
0.02 0.500
0.30 1.000
0.10 1.000
0.02 0.500
0.30 0.560
0.15 0.560
0.15 0.560
0.05 0.560
0.15 0.560
1.000
1.000
0.04 0.200
0.02 0.200
0.02 0.200
0.01 0.200
1,500.00 1.000
72.00
1.000
0.04 0.200
0.02 0.200
0.02 0.200
0.01 0.200
1.000
1.000
1.05 1.000
0.06 1.000
0.00 1.000
0.00 1.000
0.00 1.000
1.000
0.13 1.000
1.000
1.05 1.000
0.06 1.000
0.00 1.000
0.00 1.000
0.00 1.000
1.000
0.13 1.000
1.000
1.05 1.000
0.06 1.000
0.00 1.000
0.00 1.000
0.00 1.000
1.000
0.13 1.000
5,855.00
1.000
1.05 1.000
0.06 1.000
0.00 1.000
0.00 1.000
0.00 1.000
1.000
0.13 1.000
1.000
1.05 1.000
0.06 1.000
0.00 1.000
0.00 1.000
0.00 1.000
1.000
0.13 1.000
1.000
1.05 1.000
0.06 1.000
0.00 1.000
0.00 1.000
0.00 1.000
1.000
0.13 1.000
1.000
0.13 1.000
0.25 1.000
0.01 1.000
0.50 1.000
0.02 1.000
0.07 1.000
0.01 1.000
0.00 1.000
1.000
0.03 1.000
1.000
57,552.60
0.02 1.000
0.07 1.000
0.01 1.000
0.00 1.000
1.000
0.03 1.000
1.000
45,922.80
0.2000 1.000 0
0.1500 1.000 0
0.1700 1.000 0
0.2600 1.000 0
0.0100 1.000
0.5000 1.000 0
40,754.00
0.0700 0.700
0.1050 0.700
0.0040 0.700
0.0025 0.700
1.000
0.0250 1.000
1.000
1.67 1.000
1.000
0.25 1.000
0.04 1.000
1.16 0.750 1
0.29 0.750 0
0.14 0.750
1.000
- 1.000
1.000
1.000
1.000
0.25 1.000 1
0.50 1.000 0
0.05 1.000
0.03 1.000
1.000
- 1.000
1.000
73.00 1.000
11.50 1.000
0.04 1.000
69,975.00
0.30 0.750
0.10 0.750
0.01 0.750
0.02 0.750
1.000
- 1.000
1.000
1.000
1.000
236,249.60
0.2000 1.000
0.0200 1.000
0.0100 1.000
55,462.40 1.000
- 1.000
1.000
1.00 1.000
0.20 1.000
0.05 1.000
0.05 1.000
9,603.00 1.000
1.000
1.000
1.00 1.000
0.20 1.000
0.05 1.000
0.05 1.000
5,795.70 1.000
1.000
1.000
1.00 1.000
0.15 1.000
0.02 1.000
3,375.00 1.000
- 1.000
1.000
1.000
4.17 1.000
4.17 1.000
0.35 1.000
28.00 1.000
0.09 0.900
0.30 0.900
0.03 0.900
0.05 0.900
6,862.50 1.000
1.000
1.000
0.10 1.000
0.10 1.000
0.26 1.000
0.04 1.000
0.09 1.000
0.01 1.000
0.00 1.000
2,550.00 1.000
1.000
1.000
0.10 1.000
0.10 1.000
0.26 1.000
0.04 1.000
0.09 1.000
0.01 1.000
0.00 1.000
2,550.00 1.000
1.000
1.000
1.00 1.000
30% harga kloset 1.000
3.3000 1.000
1.1000 1.000
0.0010 1.000
0.1600 1.000
369,000.00 1.000
1.000
1.000
1.00 1.000
10% harga kloset 1.000
3.30 1.000
1.10 1.000
0.00 1.000
0.16 1.000
337,500.00 1.000
1.000
1.000
1.00 1.000
12% harga kloset 1.000
1.50 1.000
0.15 1.000
0.01 1.000
0.00 1.000
244,650.00 1.000
1.000
1.000
1.00 1.000
10% harga kloset 1.000
0.08 0.800 0
0.07 0.800 0
0.07 0.800 0
0.02 0.800
17,550.00 1.000
1.000
1.000
1.00 1.000
10% harga kloset 1.000
0.15 1.000 0
0.40 1.000 0
0.03 1.000 0
0.00 1.000 0
15,600.00 1.000
1.000
1.000
1.00 1.000
1.000
0.24 0.800 0
0.12 0.800 0
0.01 0.800 0
0.00 0.800 0
8,370.00 1.000 0
0
0
1.000 0
1.000
1.00 1.000
0.20 0.550
0.10 0.550
0.01 0.550
0.00 0.550
17,550.00 1.000
1.000
1.000
1.000
1.000
1.70 1.000
2.00 1.000
0.35 1.000
0.04 1.000
900,000.00 1.000
1.000
1.000
1.70 1.000
2.00 1.000
0.35 1.000
0.04 1.000
510,000.00
0.12 1.000
0.02 1.000
0.01 1.000
0.01 1.000
1,320.00
16,200.00
64,500.00 1 m2 Warna
150,000.00
0.12 1.000
0.02 1.000
0.01 1.000
0.01 1.000
-
1.05
10.00
0.05
0.15
0.62 0.375 1
0.35 0.375 0
0.04 0.375 0
0.03 0.375 0
13,500.00
1.05
10.00
0.05
0.15
0.62 0.375 1
0.35 0.375 0
0.04 0.375 0
0.03 0.375 0
19,500.00
1.05
10.00
0.05
0.15
0.62 0.375
0.35 0.375
0.04 0.375
0.03 0.375
13,500.00
0.36
3.60
0.11
0.15
0.25 1.000 0 - Carpenter
0.15 1.000 0 - Carpenter leader
0.03 1.000 0 - Worker
0.05 1.000 0 - Supervisor
6,750.00
0.36
3.60
0.11
0.15
9,600.00
0.36
3.60
0.11
0.15
0.09 1.0000
5,192.25
0.36
3.60
0.11
0.09 1.0000
5,192.25
Water tank 2 m3, 2 unit jet pump 250 watt,
steel water tower tinggi 10 m + deep well 20 m
6,000,000.00
776,666.67
7,362,000.00
350,000.00 6.50
3,242,904.55
54,078,750.00
1.2000
1.5000 0.25
0.1500 0.25
0.0027 0.25
0.1500 1.00
0.0150 1.00
0.0003 1.00
3.00
2.5000 1.00
0.2500 1.00
0.0003 1.00
585,000.00
1.05
10.00
0.28 1.000 0
0.18 1.000 0
0.02 1.000 0
0.00 1.000 0
57,750.00
10.00
0.28 1.000
0.18 1.000
0.02 1.000
0.00 1.000
1.05
10.00
0.28 1.000
0.18 1.000
0.02 1.000
0.00 1.000
55,500.00
1.05
10.00
0.28 1.000
0.18 1.000
0.02 1.000
0.00 1.000
58,500.00
10.00
0.28 1.000
0.18 1.000
0.02 1.000
0.00 1.000
1.05
10.00
0.55 1.000
0.36 1.000
0.04 1.000
0.00 1.000
100,500.00
0.55 1.000
0.36 1.000
0.04 1.000
0.00 1.000
1.05
10.00
0.34 1.000
0.23 1.000
0.02 1.000
0.00 1.000
28,500.00
1.05
10.00
0.34 1.000
0.23 1.000
0.02 1.000
0.00 1.000
42,000.00
1.05
10.00
0.34 1.000
0.23 1.000
0.02 1.000
0.00 1.000
12,300.00
0.03
- 0.42
0.18
20,625.00
141.00
Terpasang 1.00
574,909.14 0.12
0.42
56,250.00
330.00
25.00
1,513,108.76
75,655.00
1,588,764.00
141.00
3.67
0.61
0.61
2.40
180.00
0.42
0.18
5,192.25
141.00
1.00
1.17
0.12
80.00 0.03
160.00
0.42
0.18
5,192.25
141.00
1.00
1.17
0.12
80.00 0.03
160.00
0.42
0.18
5,192.25
0.0595 1.00
0.0085 1.00
0.0085 0.70
0.0500 0.70
0.0029 0.70
0.0134 0.70
0.0141 0.70
1.0000 1.00
RABP
Target
0.0595 0.70
0.0085 0.70
0.0085 0.70
0.5043 0.70
0.0023 0.70
0.0214 0.70
0.0141 0.70
0.0383 0.95
0.0372 0.95
2.3142 0.95
6.4519 0.95
0.0011 0.75
0.0035 0.75
0.0035 0.75
0.0429 0.75
0.0013 0.75
0.0033 0.75
0.0015 0.75
1.9225 0.75
0.2070 0.75
107.1200 0.75
4.5918 0.75
4.7143 1.00
0.1429 1.00
0.0609 0.75
0.18 1.00
1.00 1.00
1.00 1.00
1.00 1.00
1.00 1.00
1.00 1.00
0.18 1.00
19.36 1.00
1.20 1.00
5,192.25
9,000,000.00
1.00 1.00
1.00 1.00
1.00 1.00
1.00 1.00
1.00 1.00
1.00 1.00
1.00 1.00
1.00 1.00
2,624,500.00 1.00 1.00
1.00 1.00
1.00 1.00
775,000.00 1.00 1.00
3,399,500.00
2.50 1.00
0.50 1.00
0.25 1.00
120,000,000.00
55.00
4,270,948.75
129.60 1.00
12.96 1.00
4.32 1.00
1.00
3.52
120,000,000.00
80,000,000.00
374.20
296.37 1.00
74.84 1.00
18.71 1.00
1.00
AIR HUJAN
10.00 #VALUE!
0.79 1.00
0.20 1.00
0.05 1.00
18,269,930,272.27
8.33
25.0000 1.000
0.50 ZAK/M3
0.3000 0.650
0.2000 0.650
0.0200 0.650
0.0130 0.650
1.000
1.000
8.33
0.50 ZAK/M3
0.2500 0.600
0.0250 0.600
0.0125 0.600
0.0050 0.600
1.000
1.000
-
Terbuat dari bata di plaster,
steel grating cover termasuk galian, lantai kerja, pasir dll.
0.79 1.00
0.20 1.00
0.05 1.00
0.79 1.00
ng Tinggi 2.00m)
DAFTAR HARGA MATERIAL
TAHUN ANGGARAN 2016
HARGA SATUAN
NO. JENIS BAHAN BANGUNAN SATUAN
Rp.
BAHAN MATERIAL
6 Steel fire door W1000xH2100 complete with panic bar. unit 1.0000
Harga Daun Pintu Fire door unit 1.0000 6,000,000.00 6,000,000.00
Accesories ls 1.0000 2,000,000.00 2,000,000.00
Kusen unit 1.0000 2,000,000.00 2,000,000.00
Finishing bh 1.0000 500,000.00 500,000.00
Transfortasi ls 1.0000 1,000,000.00 1,000,000.00
Harga 1 Unit 11,500,000.00
ANALISA HARGA SATUAN PEKERJAAN PAGAR BATA RINGAN
No Description / Sketc
II FOUNDATION WORK
No Description / Sketc
II FOUNDATION WORK
2.2 0
No. Design Drawing: S - UAC - E - AG - 0015
No Description / Sketc
II FOUNDATION WORK
2.3 0
No. Design Drawing: S - UAC - E - AG - 0015
cription / Sketc As
Common Excavati
Depth Excavation
Vol
1 P.1
2 P.2
3. Tie-Beam + Cable g
TOTAL EXCAVATION
cription / Sketc As
Depth Excavation
Vol
1 P.1
2 P.2
3 P.1
4 P.2
5 A.S A/C ( 1 - 5 )
TOTAL EXCAVATION
cription / Sketc As
BACK FILL
Depth Excavation
Vol
1 P.1
2 P.2
3 P.1
4 P.2
5 A.S A/C ( 1 - 5 )
6 CABLE TRAY
TOTAL EXCAVATION
I. Foundation
Vol
1 P.1
2 P.2
3 Tie-Beam + Cable g
TB. 1
TB. 2
TB. 3
TB. 4
TB. 5
4 Tie-Beam (+0,45 a
TB. 1
TB. 2
TB. 3
TB. 4
5 A.S A/C ( 1 - 5 )
6 AS B/C ( 1 - 3 ) CT
CT.1
CT.1'
CT.2
CT.3
CT.4
7AS B - C ( 1 - 3 )
L1
L2
L3
L4
L5
L6
L7
CABLE TRAY
TOTAL SAND LAYER
I. Foundation
Vol
1 P.1
2 P.2
3 Tie-Beam + Cable g
TB. 1
TB. 2
TB. 3
TB. 4
TB. 5
4 Tie-Beam (+0,45 a
TB. 1
TB. 2
TB. 3
TB. 4
6 AS B/C ( 1 - 3 ) CT
CT.1
CT.1'
CT.2
CT.3
CT.4
7AS B - C ( 1 - 3 )
L1
L2
L3
L4
L5
L6
L7
Concrete Reinforce
a. Concrete K 225
Vol
1 P.1
area 1
area 2
Vol. P. 1
P.2
3 Stump column
4 PHT
5 Tie-Beam + Cable g
TB. 1
TB. 2
TB. 3
TB. 4
TB. 5
6 Tie-Beam (+0,45 a
TB. 1
TB. 2
TB. 3
TB. 4
7 AS B - C ( 1 - 3 ) ( C
L1
L2
L3
L4
L5
L6
L7
Concrete Reinforce
d. Formwork for f
Vol
1 P.1
a.
b.
c.
2 P.2
3 Stump column
CT 1
CT 2
CT 2
CT 3
CT 4
5 SLAB BRED
SB 1
SB 2
SB 3
SB 4
d. TOTAL Formwor
CT Type 2
CT Type 4
5 Dinding CT
CT Type 1
CT Type 2
CT Type 4
6 SLAB BRED
SB 1
SB 2
SB 3
SB 4
SB 5
SF 2
SF 3
SF 4
SF 5
SF 6
10 Dinding CT
CT Type 1
CT Type 2
CT Type 4
11 SLAB BRED
SB 1
SB 2
SB 3
SB 4
B3
B1
B2
B4
EL+ 4.95
B1
B3
B5
B1
B4
B2
B4
B5
15 TANGGA 1
16 KANOPI
Concrete Reinforc
d. Formwork for s
Vol
1 Tie-Beam + Cable g
TB. 1
TB. 2
TB. 3
TB. 4
TB. 5
2 Tie-Beam (+0,45 a
TB. 1
TB. 2
TB. 3
TB. 4
3 Column
4 Kepalaan Kolom
5 Column
6 Column SECOND
TOTAL Formwork f
EAM POWER PLANT 2x1000 MW
uilding, Perimeter fence and Gate
0
Calculation
pth Excavation = B - A
= -1.95 - -0.30
= 1.65 m
= P x L x T x Σ
Calculation
pth Excavation = B - A
= -1.80 - -1.10
= 0.70 m
= P x L x T x Σ
S A/C ( 1 - 5 )
==> 6.65 x 6.30 x 0.50 x 4.00
==> 83.79 m3
Calculation
Existing (A) = -1.10 m
Bottom Design Drawing (B) = -1.80 m
pth Excavation = B - A
= -1.80 - -1.10
= 0.70 m
= P x L x T x Σ
S A/C ( 1 - 5 )
==> 6.65 x 6.30 x 0.50 x 4.00
==> 83.79 m3
==> 6.65 x 6.30 x 0.50 x 1.00
==> 20.95 m3
BLE TRAY
==> 9.00 x 1.30 x 0.80 x 4.00
==> 37.44 m3
nd Layers (m3)
undation
= P x L x T x Σ
S A/C ( 1 - 5 )
==> 6.65 x 6.30 x 0.05 x 4.00
==> 8.38 m3
B/C ( 1 - 3 ) CT
==> 9.07 x 0.80 x 0.05 x 3.00
==> 1.09 m3
BLE TRAY
==> 9.00 x 1.30 x 0.05 x 4.00
==> 2.34 m3
TAL SAND LAYERS
undation
= P x L x T x Σ
= P x L x T x Σ
mp column
==> 0.50 x 0.50 x 0.80 x 9.00
==> 1.80 m3
==> ∏ x r2 x T x Σ
==> 3.14 x 0.13 x 0.95 x 48.00
==> 2.24 m3
B - C ( 1 - 3 ) ( Cable tray - 45 )
==> 10.15 x 1.38 x 0.15 x 2.00
==> 4.24 m3
= K x T x Σ x Σ. Found
AB BRED
==> 15.00 x 0.75 x 2.00
==> 22.50 m2
==> 13.90 x 0.75 x 1.00
==> 10.43 m2
==> 13.90 x 0.90 x 1.00
==> 12.51 m2
==> 4.20 x 0.75 x 1.00
==> 3.15 m2
==> 4.20 x 0.90 x 1.00
==> 3.78 m2
b First Floor + 0. 45
==> 30.50 x 7.75 x 0.15 x 1.00
==> 35.46 m3
umm First Floor + 0. 45
==> 0.50 x 0.50 x 3.35 x 6.00
==> 5.03 m3
ding CT
==> 29.61 x 0.15 x 0.75 x 1.00
==> 3.38 m3
==> 36.28 x 0.15 x 0.75 x 1.00
==> 4.13 m3
ding CT
==> 33.71 x 0.15 x 0.75 x 2.00
==> 7.63 m3
AB BRED
==> 15.00 x 0.75 x 0.25
==> 2.81 m3
b First Floor + 0. 45
==> 5.25 x 0.87 x 0.15 x 1.00
==> 0.74 m3
NGGA 1 ==> 5 m3
==> 4 m3
palaan Kolom
==> 0.50 x 0.70 x 4.00 x 15.00
==> 21.00 m2
umn SECOND
==> 0.50 x 4.50 x 4.00 x 7.00
==> 63.00 m2
Progress in
Period: Week
03
315.98 m3 15.00 Unit
Progress in
Period: Week
03
Progress in
Period: Week
03
Progress in
Period: Week
12
Progress in
Period: Week
13
Progress in
Period: Week
12
Progress in
Period: Week
13
Progress in
Period: Week
13
Progress in
Period: Week
24
Progress in
Period: Week
07
Progress in
Period: Week
07
Progress in
Period: Week
11
Progress in
Period: Week
13
Progress in
Period: Week
19
4.448
Progress in
Period: Week
24
Progress in
Period: Week
2.340 24
44.33 m3
Progress in
Period: Week
07
Progress in
Period: Week
11
Progress in
Period: Week
11
Progress in
Period: Week
19
4.448
35.59 m3
141.639
Progress in
Period: Week
08
Progress in
Period: Week
19
204.405
289.011
439.61 m2
BAR B
PEKERJAA: BUILDING CONTROL
ITEM PEK : PILE CAP P1 (12 Unit)
RENCANA : TGL........
2 No.6 Ha D 16
No.6 Hb D 16
3 No.7 Ha D 16
No.7 Hb D 16
4 No.8 Ha D 16
No.8 Hb D 16
5 No.9 Ha D 16
No.9 Hb D 16
6 No.10 Ha D 16
No.10 Hb D 16
7 No.11 Ha D 16
No.11 Hb D 16
8 No.12 Ha D 16
No.12 Hb D 16
9 No.13 Ha D 16
No.13 Hb D 16
10 No.14 Ha D 16
No.14 Hb D 16
11 No.15 Ha D 16
No.15 Hb D 16
12 No.16 Ha D 16
No.16 Hb D 16
13 No.17 Ha D 16
No.17 Hb D 16
14 No. a&r V1 D 16
No.a&r V2 D 16
15 No. b&q V1 D 16
No. b&q V2 D 16
16 No. c&p V1 D 16
No. c&p V2 D 16
17 No. d&o V1 D 16
No. d&o V2 D 16
18 No. e&n V1 D 16
No. e&n V2 D 16
19 No. f&m V1 D 16
No. f&m V2 D 16
20 D13
D13
BAR B
PEKERJA : BUILDING CONTROL
ITEM PEK : PILE CAP P2 (3 Unit)
RENCANA: TGL........
D 16
D 16
D 16
D 16
PEMINGGANG D13
BAR BENDING SC
PEKERJAA: BUILDING CONTROL
ITEM PEK : KOLOM STRUKTUR
RENCANA I: TGL........
SKET
NO VOLUME/LUASAN DIAMETER BERAT
PROFIL
TULANGAN JENIS
PXL TYPE M3 DETAIL POT.
mm Kg/m'
1 2 3 4 5 6 7
KOLOM 50 X 50 = 15 B
2500
BAWAH 3.00
Tulangan kolom Stump Pondasi 16 D.19 D.19 2.2256
Sengkang Ø 10 - 15 cm D.10 - 15 0.6165
3.00
2.24
BA
PEKERJ : BUILDING CONTROL
ITEM PE : TIE BEAM - 0. 45
RENCANA : TGL........
SKET DIAMET
NO VOLUME/LUASAN GAMBA
R PROFIL ER BERAT
(MODUL TULANG JENIS
PXL SEGME TYPE M3 DETAIL POT. AN
N) mm Kg/m'
1 2 3 4 5 6 7.00
TIE BEAM + Support Slab (-0,45 area)
1 As B/ 1-3,TB 3, 500x650 cm = 15,40 m
Tulangan Pokok atas 5 D,22 D.22 2.98
Tulangan Pokok sambungan atas 5 D.22 D.22 2.23
Tulangan extraTumpuan ujung atas 4 D.22 D.22 2.98
Tulangan extraTumpuan tengah atas 4 D.22 D.22 2.98
Tulangan extraTumpuan tengah bawah 2 D.22 D.22 2.98
Tulangan tengah 4 D.13 D.13 1.04
Tulangan sambungan tengah 4 D.13 D.13 1.04
Tulangan Pokok bawah 5 D.22 D.22 2.98
Tulangan Pokok sambungan bawah 5 D.22 D.22 2.98
Sengkang D 10 - 12,5 cm D.10 0.62
Sengkang D 10 - 20 cm D.10 0.62
Tul Extra support D.13-50 D.13 1.04
Tul Extra support D.10-50 D.10 0.62
BAR BE
PEKERJ : BUILDING CONTROL
ITEM PE : Pondasi Kabel Tray
RENCANA : TGL........
1 CT Type 1 D 10
- P = 10,10 m' x 3 Un D 10
- P = 5,00 m' x 1 Uni D 10
D 10
2 CT Type 2 ( 1600 ) D 10
- P = 7,50 m' x 1 Uni D 10
- P = 4,5 m' x 1 Unit D 10
D 10
3 CT Type 3 ( 4500 ) D 10
- P = 4,83 m' x 1 Uni D 10
D 10
D 10
4 CT Type 4 ( 4500 ) D 10
- P = 1,27 m' x 1 Unit D 10
- P = 4,83 m' x 1 Unit D 10
D 10
440.00 -
8,454.08
18.96
BAR BENDING SCHEDULE
REKAPITULASI
CATATAN
TOTAL
KETERANGAN
WASTE
D.13 d.16 BERAT
NOTE
Kg Kg
14 15 16
TULASI
CATATAN
TAL KETERANGAN
BERAT WASTE NOTE
Kg Kg
14 15 16
1,869.47 106.83
221.94 64.73
2,091.41 171.56
221.94 47.35
1,335.34 10.68
1,557.28 58.03
REKAPITULASI CATATA
TOTAL N
KETERANGAN
WASTE
D.16 D.19 D.22 BERAT
NOTE
Kg Kg
14 15 16
REKAPITULASI
CATATAN
TOTAL
KETERANGAN
WASTE
D.16 BERAT
NOTE
Kg Kg
14 15 16
2,883.82 761.71
2,883.82 26.41%
36,751.73
SKET
NO VOLUME/LUASAN
GAMBAR PROFIL DIAMETER
(MODUL TULANGAN
PXL SEGMEN) TYPE M3 DETAIL POT.
mm
1 2 3 4 5 6
TIE BEAM CONTROL BUILDING
TIE BEAM (+0,45 area)
1 As A/1-5,TB 1, 500x650 mm = 30,40 m
BA
PEKERJAAN : BUILDING CONTROL
ITEM PEKER : PLAT Second Floor
RENCANA IN : TGL........
SKET
NO VOLUME/LUASAN
GAMBAR PROFIL DIAMETER
(MODUL TULANGAN
PXL SEGMEN) TYPE M3 DETAIL POT.
mm
1 2 3 4 5 6
SECOND FLOOR CONTROL BUILDING
ARAH PANJANG
1 AS A - C / AS 1 - 4, Arah Panjang = 22,90 ( EV + 4.50 )
Tulangan Pokok atas D. 13 - 20 cm D.13
Tulangan Pokok atas sambungan D.13-20 D.13
D.13
D.13
D.13
D.13
A. SUB TOTAL PERHITUNGAN KUANTITAS PER BAGIAN
B. TOTAL REKAPITULASI KUANTITAS SELURUHNYA
SKET DIAMETE
NO VOLUME/LUASAN
PROFIL R
TULANG
PXL TYPE M3 DETAIL POT. AN
mm
1 2 3 4 5 6
KOLOM 50 X 50 = 15 BH 1.80
2500
BAWAH
Tulangan Kolom Stump Pondasi 16 D.19 D.19
Sengkang D 10 - 15 cm D.10 - 15
Tice D. 13mm - 50 cm D.13 - 50
BA
PEKERJAAN : BUILDING CONTROL
ITEM PEKER : FIRST FLOOR SLAB
RENCANA IN : TGL........
SKET
NO VOLUME/LUASAN
GAMBAR PROFIL DIAMETER
(MODUL TULANGAN
PXL SEGMEN) TYPE M3 DETAIL POT.
mm
1 2 3 4 5 6
FIRST FLOOR CONTROL BUILDING
ARAH PANJANG
1 AS A-B / 1 - 5 ARAH PANJANG 30 M
Tulangan Pokok atas D. 13 - 20 cm D.13
Tulangan Pokok atas sambungan D.13-20 D.13
Tulangan Pokok bawah D.13
Tulangan Pokok bawah sambungan D.13
SKET
NO VOLUME/LUASAN
GAMBAR PROFIL DIAMETER
(MODUL TULANGAN
PXL SEGMEN) TYPE M3 DETAIL POT.
mm
1 2 3 4 5 6
BEAM CONTROL BUILDING
BEAM CONCRETE SECOND FLOOR El. + 4,50
13 TB 6, P = 7,40
Tulangan Atas D.16
Tulangan Bawah D.16
Tulangan Atas D.16
Tulangan Bawah D.16
Sengkang Ø.10
Tice Ø.10
38.96
A. SUB TOTAL PERHITUNGAN KUANTITAS PER BAGIAN
1 As B/ 1-3,T= 25 cm = 15,40 m
Tul Dinding Rib D.13-15 Tegak D.13
Tul Dinding Rib D.10-15 Datar 12 m D.10
Tul Dinding Rib D.10-15 Datar samb, D.10
3 As C/ 1-3,T= 25 cm = 15 m
Tul Dinding Rib D.13-15 Tegak D.13
Tul Dinding Rib D.10-15 Datar 12 m D.10
Tul Dinding Rib D.10-15 Datar 12 m D.10
4 As 1/ B-C,T= 25 cm = 7,80 m
Tul Dinding Rib D.13-15 Tegak D.13
Tul Dinding Rib D.10-15 Datar 12 m D.10
DIAMETER
NO VOLUME/LUASAN SKET
TULANGAN
PROFIL
PXL TYPE M3 DETAIL POT.
mm
1 2 3 4 5 6
KOLOM 50 X 50 = 15 BH 1.80
2500
BAWAH
Tulangan Kolom Stump Pondasi 16 D.19 D.19
Sengkang D 10 - 15 cm D.10 - 15
Tice D. 13mm - 50 cm D.13 - 50
DIAMETER
NO VOLUME/LUASAN SKET
GAMBAR TULANGAN
(MODUL PROFIL
SEGMEN)
PXL TYPE M3 DETAIL POT.
mm
1 2 3 4 5 6
mm
1 2 3 4 5 6
1 D.13
D.13
2 D.13
3 D.13
D.13
4
PERHITUNGAN / KALKULASI REKAPITULASI
PANJANG POTONGAN TOTAL
BERAT JENIS
JUMLAH SUB TOTAL SUB TOTAL
RENCANA DIGUNAKAN BATANG D. 10 D.13
POTONGAN PANJANG BERAT
Kg/m' m m buah m Kg batang
7 8 9 10 11 12 13
8,385.98
-
1.0414 4.00 4.00 50 200.00 208.28 20.00 20.00
120.00 10.00
3,921.68
-
1.0414 2.12 8.02 138 292.56 304.67 30.00 -
- -
-
-
1.0414 6.52 6.52 80 521.60 543.18 50.00 50.00
-
850.00 - 450.00
- -
1.5775 12.00 12.00 3 36.00 56.79 10.00
1.5775 4.92 5.00 3 15.00 23.66 10.00
0.6162 12.00 12.00 2 24.00 14.79 10.00 10.00
0.6162 4.92 5.00 2 10.00 6.16 10.00 10.00
0.6162 2.03 2.03 60.00 121.80 75.05 20.00 20.00
0.6162 2.03 2.03 38 76.13 46.91 10.00 10.00
1.5775 12.00 12.00 4 48.00 75.72 10.00
1.5775 4.92 5.00 4 20.00 31.55 10.00
0.6162 0.62 0.62 31.00 19.22 11.84 10.00 10.00
2,590.00 1,250.00 -
660.00
BERAT JENIS
PERHITUNGAN / KALKULASI REKAPITULASI
JUMLAH SUB TOTAL SUB TOTAL
PANJANG POTONGAN TOTAL
POTONGAN PANJANG BERAT
RENCANA DIGUNAKAN BATANG D.19 D.13
1.57824 12 12 3 36 56.81664 3
1.57824 5.5 5.5 3 16.5 26.04096 2
0.6165 1.1 1.1 56.66666667 62.33333333 38.4285 6 6
0.6165 1.1 1.1 30 33 20.3445 3 3
1.57824 12 12 3 36 56.81664 3
1.57824 5.5 5.5 3 16.5 26.04096 2
0 0 0
1.57824 12 12 3 36 56.81664 3
1.57824 5.5 5.5 3 16.5 26.04096 2
0.6165 1.1 1.1 46.66666667 51.33333333 31.647 5 5
0.6165 1.1 1.1 30 33 20.3445 3 3
1.57824 12 12 3 36 56.81664 3
1.57824 5.5 5.5 3 16.5 26.04096 2
1.57824 12 12 6 72 113.63328 6
1.57824 8.5 8.5 3 25.5 40.24512 3
0.6165 1.1 1.1 93.33333333 102.6666667 63.294 9 9
0.6165 1.1 1.1 60 66 40.689 6 6
1.57824 12 12 6 72 113.63328 6
1.57824 8.18 8.18 3 24.54 38.7300096 3
1.577472 12 12 6 72 113.577984 6
1.577472 8.5 8.5 3 25.5 40.225536 3
0.6162 1.1 1.1 93.33333333 102.6666667 63.2632 9 9
0.6162 1.1 1.1 60 66 40.6692 6 6
1.577472 12 12 6 72 113.577984 6
1.577472 8.18 8.18 3 24.54 38.71116288 3
0.6162 12 12 2 24 14.7888 2 2
0.6162 4.3 4.3 2 8.6 5.29932 1 1
0.6162 0.53 0.53 40 21.2 13.06344 2 2
0.6162 0.53 0.53 32 16.96 10.450752 2 2
0.6162 12 12 2 24 14.7888 2 2
0.6162 4.3 4.3 2 8.6 5.29932 1 1
0.6162 8 8 2 16 9.8592 2 2
0.6162 0.53 0.53 40 21.2 13.06344 2 2
0.6162 0.53 0.53 32 16.96 10.450752 2 2
0.6162 8 8 2 16 9.8592 2 2
0.6162 8 8 2 16 9.8592 2 2
0.6162 0.53 0.53 40 21.2 13.06344 2 2
0.6162 0.53 0.53 32 16.96 10.450752 2 2
0.6162 8 8 2 16 9.8592 2 2
1412.600272 129 73 0
PERHITUNG TANGGA
BERAT JENIS
PERHITUNGAN / KALKULASI REKAPITULASI
JUMLAH SUB TOTAL SUB TOTAL
PANJANG POTONGAN TOTAL
POTONGAN PANJANG BERAT
RENCANA DIGUNAKAN BATANG dia. 10 D.13
PERHITUNGAN KANOPI
BERAT JENIS
PERHITUNGAN / KALKULASI REKAPITULASI
1,133.99
116,939.21
REKAPITULASI
CATATAN
TOTAL
KETERANGAN
WASTE
D.16 D.19 D.22 BERAT
NOTE
Kg Kg
14 15 16
33,436.37 25,050.39
REKAPITULASI
CATATAN
TOTAL
KETERANGAN
WASTE
D.16 D.19 D.22 BERAT
NOTE
Kg Kg
14 15 16
1,999.45 49.99
1,999.45 49.99
-
2,999.17 112.47
1,124.69 54.20
1,374.62 27.49
374.90 39.68
249.93 88.10
249.93 41.66
249.93 50.00
- - - 10,372.12 463.57
10,372.12 4.47%
EKAPITULASI
CATATAN
TOTAL
KETERANGAN
WASTE
D.10 BERAT
NOTE
Kg Kg
14 15 16
3,204.81 85.46
80.00 591.84 50.86
125.03 40.63
REKAPITULASI
CATATAN
TOTAL
KETERANGAN
WASTE
D.16 D.19 D.22 BERAT
NOTE
Kg Kg
14 15 16
999.72 99.97
374.90 58.32
999.72 99.97
374.90 58.32
- -
499.86 24.99
249.93 71.86
749.79 112.47
249.93 101.75
374.90 108.72
- -
- -
- -
124.97 44.40
- - - 3,374.06 33.32
- -
- -
- - - 1,249.65 97.10
- - - 374.90 70.23
- -
624.83 81.64
- - - 10,622.06 1,063.07
10,622.06 10.01%
REKAPITULASI
CATATAN
TOTAL
WASTE
D.16 D.19 D.22 BERAT
NOTE
Kg Kg
14 15
- - -
10.00 189.30 132.51
10.00 189.30 165.63
73.94 59.16
73.94 67.78
147.89 72.83
73.94 27.04
10.00 189.30 113.58
10.00 189.30 157.75
73.94 62.10
-
10.00 357.89 214.73
10.00 357.89 298.24
10.00 357.89 276.77
10.00 357.89 286.31
147.89 29.58
73.94 60.04
147.89 5.55
73.94 27.73
10.00 357.89 214.73
10.00 357.89 298.24
10.00 357.89 286.31
73.94 57.90
73.94 64.01
500.10 112.73
147.96 54.25
73.98 40.40
125.03 9.72
73.98 33.37
500.10 102.80
147.96 54.25
73.98 40.40
250.05 51.40
73.98 9.95
250.05 51.40
73.98 9.95
2,291.16 570.63
2,291.16 570.63
2,291.16 24.91%
CATATAN KETERANGAN
WASTE
D.10 BERAT
NOTE
Kg Kg
14 15 16
2,403.61 89.02
80.00 591.84 70.90
125.03 43.76
CATATAN
3 56.81664 0 0
2 37.87776 11.8368 11.8368
44.388 5.9595 5.9595
22.194 1.8495 1.8495
3 56.81664 0 0
2 37.87776 11.8368 11.8368
0 0
3 56.81664 0 0
2 37.87776 11.8368 11.8368
36.99 5.343 5.343
22.194 1.8495 1.8495
3 56.81664 0 0
2 37.87776 11.8368 11.8368
6 113.63328 0 0
3 56.81664 16.57152 16.57152
66.582 3.288 3.288
44.388 3.699 3.699
6 113.63328 0 0
3 56.81664 18.0866304 18.0866304
6 113.577984 0 0
3 56.788992 16.563456 16.563456
66.5496 3.2864 3.2864
44.3664 3.6972 3.6972
6 113.577984 0 0
3 56.788992 18.07782912 18.07782912
14.7888 0 0
7.3944 2.09508 2.09508
14.7888 1.72536 1.72536
14.7888 4.338048 4.338048
14.7888 0 0
7.3944 2.09508 2.09508
56 0 0
###
CATATAN KETERANGAN
WASTE
D.16 D.19 D.22 BERAT
NOTE
Kg Kg
14 15 16
125.03 83.35
125.03 83.35
125.03 37.51
2,625.55 46.88
3,500.73 62.51
147.89 49.30
6,286.35
CATATAN KETERANGAN
WASTE
D.16 D.19 D.22 BERAT
NOTE
Kg Kg
14 15 16
625.13 56.26
375.08 60.01
250.05 83.35
125.03 41.68
- -
(1,133.99)
PERHITUNGAN BEGESTING BALOK PERHITUNGAN BEGESTING BALOK
EV = +45 EV = +45
As 1-4/ As A As A-C /As 1
B1 B1
NO P L V SAT NO P L V
1 21.1 0.4 21.5 m2 1 13.5 0.4 13.9
2 21.1 0.7 21.8 m2 2 13.5 0.7 14.2
3 21.1 0.7 21.8 m2 3 13.5 0.7 14.2
65.1 42.3
Begesting Lantai
Elevasi + 45.00
No P L Z V sat
1 3.35 3.35 24 269.34 M2
2 1.2 3.35 2 8.04 M2
277.38 M2
Elevasi + 4,95
No P L Z V sat
1 2.1 3.275 8 55.02 M2
2 1.6 3.275 2 10.48 M2
65.5 M2
As 1-5/ As C
RB1
NO P L V SAT
1 28 0.25 7 m2
2 28 0.4 11.2 m2
3 28 0.4 11.2 m2
29.4
As A - C/ As 1
RB1
NO P L V SAT
1 6.5 0.25 1.625 m2
2 6.5 0.4 2.6 m2
3 6.5 0.4 2.6 m2
6.825
As A - C/ As 5
RB1
NO P L V SAT
1 6.5 0.25 1.625 m2
2 6.5 0.4 2.6 m2
3 6.5 0.4 2.6 m2
6.825
As A - C/ As 4
RB2
NO P L V SAT
1 6.5 0.15 0.975 m2
2 6.5 0.2 1.3 m2
3 6.5 0.2 1.3 m2
3.575
As 1 - 4/ As B
RB2
NO P L V SAT
1 7 0.15 1.05 m2
2 7 0.2 1.4 m2
3 7 0.2 1.4 m2
3.85
As A - B/ As 4'
RB2
NO P L V SAT
1 7.5 0.15 1.125 m2
2 7.5 0.2 1.5 m2
3 7.5 0.2 1.5 m2
4.125
GRAND TOTAL 84 M2
ING BALOK As A-C /As 4 As 4 - 5/ As B'
B2 B4
NO P L V SAT 6.45
1 13.5 0.4 13.9 m2 6.45
SAT 2 13.5 0.7 14.2 m2
m2 3 13.5 0.7 14.2 m2 6.45
m2 42.3
m2 As A-C /As 4 As 4 - 5/ As B''
B6 B4
NO P L V SAT 6.45
' 1 13.5 0.3 13.8 m2 6.45
2 13.5 0.4 13.9 m2 6.45
SAT 3 13.5 0.4 13.9 m2
m2
m2 41.6 As 4 - 5/ As C
m2 B1
6.45
6.45
6.45
EV = +4,95
SAT As 4 - 5/ As A
m2 B1
m2 NO P L V SAT
m2 1 6.45 0.4 6.85 m2 As A - C / As 4
2 6.45 0.7 7.15 m2 B5
3 6.45 0.7 7.15 m2 1 13.5
' 21.15 2 13.5
As 4 - 5/ As A' 3 13.5
SAT B1
m2 NO P L V SAT
m2 1 2.6 0.4 3 m2 As A - C / As 4'
m2 2 2.6 0.55 3.15 m2 B3
3 2.6 0.55 3.15 m2 1 13.5
9.3 2 13.5
As 4 - 5/ As A'' 3 13.5
B1
SAT NO P L V SAT
m2 1 2.6 0.4 3 m2 As A - C / As 5
m2 2 2.6 0.55 3.15 m2 B1
m2 3 2.6 0.55 3.15 m2 1 13.5
9.3 2 13.5
' As 4 - 5/ As B 3 13.5
B2
SAT NO P L V SAT
m2 1 6.45 0.4 6.85 m2
m2 2 6.45 0.7 7.15 m2 FORMWORK BALO
m2 3 6.45 0.7 7.15 m2 931.65
21.15
82
GRAND TOTAL 1219.51
84
439.6103
1825.12
As 4 - 5/ As B'
B4
0.4 6.85
0.55 7
0.55 7
20.85
As 4 - 5/ As B''
B4
0.4 6.85
0.55 7
0.55 7
20.85
As 4 - 5/ As C
B1
0.4 6.85
0.7 7.15
0.7 7.15
21.15
As A - C / As 4
B5
0.35 13.85
0.5 14
0.5 14
41.85
As A - C / As 4'
B3
0.4 13.9
0.55 14.05
0.55 14.05
42
As A - C / As 5
B1
0.4 13.9
0.55 14.05
0.55 14.05
42
FORMWORK BALOK
931.65 M2
BRICKDOWN BOUNDREY
Diketahui Oleh
Slamet
Y
Dibuat Oleh
Balmer
No Description / Sketc As
26 PREPATION
KERBS
294 x 2 588
291 x 2 582
294 x 2 588
294 x 2 588
274.85 x 2 549.7
274.85 x 2 549.7
274.85 x 2 549.7
34.00 x 2 68
45.50 x 2 91
176 x 2 352
4506.1
Calculation
Vol = P x L
274.85 x 3 = 824.55
274.85 x 3 = 824.55
274.85 x 3 = 824.55
m2
m2
m2
m2
m2
PROGRESS
WEEK 22
10,508.65 m2
SALURAN JALAN
1 GALIAN
294 x 0.60 x 0.80 = 295
1179 2357.2
2
BACK FILL
294 x 0.10 x = 294
1173 2346.8
2
CABLE TRENCH TYPE A
I GALIAN BETON
SECTION 1 SECTION 1
P L T P L T
6.4 6.7 1.6 68.608 6.4 1.2 0.15
6.4 1.2 0.2
SECTION 2
P L T SECTION 2
5.6 1.8 1.95 19.656 P L T
5.2 1.4 0.15
SECTION 3 5.2 1.4 0.2
P L T
5.6 1.8 1.95 19.656 SECTION 3
P L T
SECTION 4 5.2 1.4 0.15
P L T 5.2 1.4 0.2
5.6 1.8 1.95 19.656
SECTION 4
127.576 P L T
5.2 1.4 0.15
BACK FILL 5.2 1.4 0.2
SECTION 1 DINDING
P L T SECTION 2
6.4 0.4 1.6 4.096 P L T
6.4 0.2 1.5
SECTION 2 6.4 0.2 1.5
P L T 6.4 0.3 1.5
5.6 0.4 1.95 4.368 6.4 0.3 1.5
SECTION 3
SECTION 3 P L T
P L T 6.4 0.15 1.5
5.6 0.4 1.95 4.368 6.4 0.15 1.5
6.4 0.3 1.5
SECTION 4 6.4 0.3 1.5
P L T SECTION 4
5.6 0.4 1.95 4.368 P L T
6.4 0.15 1.5
17.2 6.4 0.15 1.5
6.4 0.3 1.5
SOIL DISPOSAL 6.4 0.3 1.5
110.376
SAND LAYER
P L T
6.4 1.5 0.05 0.48
SECTION 2
P L T
5.6 1.6 0.05 0.448
SECTION 3
P L T
5.6 1.6 0.05 0.448
SECTION 4
P L T
5.6 1.6 0.05 0.448
1.824
LC
1.824
N1
1.152
1.536
N2
1.092
1.456
N3
1.092
1.456
N4
1.092
1.456
G
1.92
1.92
2.88
2.88
1.44
1.44
2.88
2.88
1.44
1.44
2.88
2.88
31.976
PERHITUNGAN KANOPI
DIAMETER BERAT
NO VOLUME/LU SKET PERHITUNGAN / KALKULASI REKAPITULASI
TULANGAN JENIS
GAMBA
R
JUMLAH SUB TOTAL SUB TOTAL
(MODUL PROFIL PANJANG POTONGAN TOTAL
POTONGAN PANJANG BERAT
SEGME
N)
1 BAWAH D.13 1.0419 5.50 5.50 126 693.00 722.03 60.00 60.00
D.10 0.6162 2.00 2.00 216 432.00 266.20 40.00 40.00
2 ATAS D.13 1.0419 5.50 5.50 126 693.00 722.03 60.00 60.00
D.13 1.0419 2.00 2.00 216 432.00 450.09 40.00 40.00
3 DINDING D.13 1.0419 2.00 2.00 216 432.00 450.09 40.00 40.00
D.13 1.0419 2.00 2.00 126 252.00 262.56 30.00 30.00
4 2,872.99
CATATAN KETERANGAN
WASTE
D.16 D.19 D.22 BERAT
NOTE
Kg Kg
14 15 16
750.16 28.13
295.78 29.58
750.16 28.13
500.10 50.01
500.10 50.01
375.08 112.52
(2,872.99)
PERHITUNGAN KEBUTUHUAN BAJA
NO
233.3 233.3 KG
280 560 KG
187 187 KG
140 140
3 204 KG