Professional Documents
Culture Documents
Critical Equipment
Critical Equipment
Identification of Depot
Marquer tout
Critical HSSE &
Operational equipment les Equipment
Equipment Breakdown
Work order
Maintenance Depot
generated
Engineer operator
Depot Depot
Engineer / Manager
Specialised Depot Technician
Contactor Maint.
Sign-
Tech
Sign-off off
responding to an alarm,
following a procedure, or
activating emergency response equipment.
To ensure that barriers will continue to work the way they were designed, critical activities
are assigned to individuals.
Critical activities
• Critical activities ensure that the holes (of the Swiss cheese) will not align
• Each critical activity must be assigned to one position and only one
Electrical system
Earthing system Protect the equipment, ‘= or < 10 Ω for all equipment
including strips, instrumentation, tanks,....& the 2 & buildings except for clean
cables, earthing personal from static electricity earth required for electronic
rods,.... equipment where it should be
< 2 Ω or as recommended by
supplier.
Switch boards To switch off electricity when there is 1 √
(circuit breakers, short circuit / load induced failure
overloads....) ranging from simple overload of the
motor
Phase sequence To protect equipment when there is a
source induced failure ranging from 1
voltage unbalance, phase failure or
√
phase reversal.
Stabilizer Protect electrical equipment from
sudden fluctuation of the electrical 1
current
√
(Generic for standalone JB or
Junction
integrated in the equipment).
boxes
All electrical circuits are enclosed in a 1
house strong enough to contain any √
spark / fire that may take place on
the inside.
Cable gland Ensure tightness of the cable / JB 1 √
connection and does not allow
vapours’ entry into JB.
Cable conduits / Protect cables from dynamic loads 3
trenches
Loading Gantry
Interlock system Protection from static electricity
(over fill & generated during product loading as 1
earthing system) well avoiding accidental overfill.
√
Containment To contain accidental spill and 3
area prevent it to spread all over the
installation
Drainage system
Oil Interceptor Treating effluent water to reduce the 2 HC content should be equal <
HC content to equal < 15ppm. 15ppm.
Interceptor Valve Ensure that the treated water from
oil interceptor will not be drained to
the public sewer or water streams
prior been analysed and that HC
content is within the acceptable
limits.
Security
CCTV To provide adequate internal (loading
gantry,..)& external (boundaries , 2
gate, external
surroundings,..)security controls.
Badge Allowing only authorized drivers / 3
Identification personal to enter the depots
Fire Fighting
Fire Alarm The system detects smoke / heat and 1 √
system activate siren to alert operators that
a fire is starting.
Fire water tank Tank to store water needed to 1 √
combat a worst case scenario fire for
a certain period of time.
Fire pumps Provide required water flow & 1 √
pressure needed for cooling & foam.
Tank cooling Provide water needed for cooling the 2 Min spray orifice = 6mm
rings tank shell & roof Pressure = 10.5 bar gauge
Ap rate (roof)= 1.7 Ap rate
(roof)= 1.7 lit/min/m2
Ap rate (Shell)= 17 lit/min/m
Fire water Network providing water under 1 √ 7 – 10.5 bar gauge
hydrant pressure
Tank foam Device to inject foam in the tank 1 √ Fixed roof (class 1)=4 lit/min/m2
chamber Fixed roof (class 2)=4 lit/min/m2
Base foam Device to inject foam in the tank 1 √ for 45 min application
injection (Gasoil tanks located in class 1 bund
should be treated as class1 tanks
Foam tank Tank to store foam concentrate 2
Foam To mix the foam concentrate with 1 √
proportions water to produce the foam
Foam manifold To direct the foam to the location 1 √
including valves where the foam application is
required.
Foam canons Equipment which direct the foam to 2 Fixed roof (class 1)=6 lit/min/m2
location where fire took place Fixed roof (class 2)=6 lit/min/m2
Criticality
Operation Function Level
Critical
Equipment
Pumps & pipes
Product pumps & In case of breakdown the operation will stop 1
motors
Loading Gantry
Loading arm The criticality level increase / decrease according to the 2
number of loading arm(s) / product.
Meter & Preset Ensure the required product quantity (volume) is 1
loaded in the road tank compartments.
Electrical system
Transformer Breakdown of the transformer will seize the operation 1
of the installation
IT System
Server & JDE System malfunction / down will seize the loading 1
process
The Asset Manager (Depot/ Bitumen / LPG filling plant& LOBP manager) is Accountable
for Creating, making available and maintaining the documentation for HSSE Critical
Equipment, including data and drawings that are critical to managing Process Safety.
Installations Drawings
Drawings:
Engineering Procedures
2. Relief Valves
Pressure / Vacuum Valve Technical Inspection
Pressure Relief valves Technical Inspection
5. Hoses
Dry-Break Coupler Inspection
Marine & Terminal Hoses Visual test
Marine & Terminal Hoses annual Inspection
6. Electrical
Detailed Inspection of Motors
Detailed Inspection of Earthing and Bonding
Inspection - Electrical HV and LV Switchboards and MCCs
Test Emergency Shutdown Device (ESD)
Visual and Close Inspection of Electrical Equipment in Hazardous Areas
Close Inspection of Electrical Standby and Battery Supply Systems
Inspection of Portable Electric Equipment
Visual Inspection of Power Transformers
7. Bund Wall
Bund Walls & Compound Technical Inspection
8. Storage Tanks
External routine inspection
External detailed inspection
Internal detailed inspection
Tanks calibration
9. Additive System
Blender Technical Inspection
13. Drainage
Inspect Monitoring Wells
Technical Inspection Interceptors, Drainage & Pollution Control Systems
Sample and Test Interceptor Effluent
B) Inspection & testing procedure
Fire Pump - Flow Test Annual Tests recommended for each Fire Pump Set
(electric motor and diesel powered) and Jockey Pumps.
should be tested by a certified testing laboratory, in
The foam concentrate accordance with regulatory requirements and
manufacturer’s recommendations.
Low pressure steam boilers are inspected, at minimum:
Boiler Inspection (a) Internally -- every two years, when physical
construction of the boiler allows; and
(b) Externally -- every two years, while under pressure.
C) Calibration procedure
1. Tanks calibration
2. PVV vent calibration
3. Meter calibration
4. Weighing scales calibration (Weighbridge)