PRADHAN MANTRI GRAM SADAK YOJANA FOR THE YEAR 2016-17

Ministry of Rural Development Government of India, New Delhi

Name of Road :

Name of District :

Name of Blcok :

Package No. :

Road Length :

ABSTRACT OF COST

Amount Rs. In
Sl No. Item of Works
Lacs.
Road Works
1 Pavement Works
A Cost of Earth work for ebmankment Rs. 11.12
B Cost of Pavement (excluding embankment) Rs. 70.92
Total Rs. 82.04
2 Total Cost of CD Works Rs. 9.73
3 Total Cost of Protection Works Rs. 0.00
4 Total Cost of Road Logo & Road Furniture Rs. 2.53
5 Total Cost of Drain works Rs. 0.00
Total Rs. 12.26
6 Cost of preparation of DPR @ Rs. 16,500/km Rs. 0.25
7 Shifting of Utilities Rs. 0.50
Grand Total = Rs. 95.05
Maintenance
Maintenance of road for five years Rs. 8.73