No. Description Crew No.

Start Finish

I Mobilization 1 2-Sep-19 6-Sep-19


II Site Development (Access road development and Clearing of site) 1 3-Sep-19 10-Sep-19
III Temfacil
a Barracks 1 2 6-Sep-19 19-Sep-19
b Barracks 2 2 20-Sep-19 3-Oct-19
c Barracks 3 3 24-Sep-19 7-Oct-19
d Barracks 4 2 4-Oct-19 17-Oct-19
e Common Comfort Room 1 4 6-Sep-19 15-Sep-19
f Common Comfort Room 2 4 3-Oct-19 12-Oct-19
g Common Comfort Room 3 4 13-Oct-19 22-Oct-19
h Field Office 5 6-Sep-19 22-Sep-19
i Canteen 4 16-Sep-19 26-Sep-19
j Water Elevated Tank 4 27-Sep-19 2-Oct-19
k Engineers Quarter 5 4-Oct-19 19-Oct-19
l Construction Warehouse 3 6-Sep-19 11-Sep-19
m Maintenance Warehouse 3 6-Sep-19 11-Sep-19
n Motorpool 5 23-Sep-19 3-Oct-19
o Diesel Compartment 3 12-Sep-19 15-Sep-19
p Oil Section 3 16-Sep-19 19-Sep-19
q Oil and Water Separator 3 12-Sep-19 19-Sep-19
r Materials Laboratory 3 8-Oct-19 24-Oct-19
s Guard House 3 20-Sep-19 23-Sep-19
t Perimeter Fence (200m ribbed type with barbed wire, 850m barbed wire) 1 11-Sep-19 1-Oct-19
u Pantry/Laundry Area 5 20-Oct-19 23-Oct-19
v Laundry Area for Workers 5 20-Oct-19 23-Oct-19
w Locker Room / Charger Area 3 20-Sep-19 23-Sep-19
x Materials Recovery Facility 2 18-Oct-19 21-Oct-19
y Fabrication Area 5 24-Oct-19 27-Oct-19
z Carpentry Area 5 24-Oct-19 27-Oct-19
IV Others
a Drainage 1 2-Oct-19 11-Oct-19
b Batching Plant 6 15-Sep-19 5-Oct-19
c Crusher Plant 6 1-Oct-19 21-Oct-19

MANPOW
1 - FIeld Engineer
1 - Welder Field Engin
1 - Pipefitter
Crew 1 Crew 2
1 - Foreman 1 - Foreman
2 - M/Carp 4 - M/Carp
10 - Laborer 8 - Laborer
------------------------------------------------------------------------------
1 - Field Engineer
2 - Welder
2 - Pipefitter
Crew 3 Crew 4
1 - Foreman 1 - Foreman
4 - M/Carp 4 - M/Carp
8 - Laborer 8 - Laborer
--------------------------------------------------------------- EQUIPME
1 - Field Engineer Bagger Mi
2 - Welder
2 - Pipefitter Genset 45k
Crew 5 Crew 6 Concrete Vibra
1 - Foreman 1 - Foreman
4 - M/Carp 4 - M/Carp
8 - Laborer 8 - Laborer Portable Welding Mach

Tower Light (LE

Prepared by: Checked by:

Kenneth Christopher R. Gabriel Roland G. Cruz


Office Engineer Head Office Engineer
C.M. PANCHO CONSTRUCTION, INC.
Construction of Airport to NCC Access Road Pha
No. of
Days
October
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

5 gggggg
gggggg
gggggg
gggggg
gggggg
8 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

14 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
14 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
14 gggggg
gggggg
14
10 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
10
10
17 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
11 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
6
16
6 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
6 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
11 gggggg
gggggg
gggggg
4 gggggg
gggggg
gggggg
gggggg
4 gggggg
gggggg
gggggg
gggggg
8 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
17
4 gggggg
gggggg
gggggg
gggggg
21 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
4
4
4 gggggg
gggggg
gggggg
gggggg
4
4
4

10
21 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
21

MANPOWER
Field Engineer 1 1 1 1 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Foreman 1 1 1 1 1 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
M/Carp 2 2 2 2 2 18 18 18 18 18 18 18 18 18 22 22 22 22 22 22 22 22 22 22 22
Laborer 10 10 10 10 10 42 42 42 42 42 42 42 42 42 50 50 50 50 50 50 50 50 50 50 50
Pipefitter 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Welder 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Mechanic 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Electrician 1 1 1 1 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

EQUIPMENT
Bagger Mixer 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Genset 45kVa 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Concrete Vibrator 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Genset 5kVa 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
ble Welding Machine 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Miller 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Tower Light 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Tower Light (LED) 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Checked by: Approved by:

Janica May M. Aguilar Norman M. Syguia


Head Office Engineer Vice President for Operations
d Phase 2
2019
OCTOBER
26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4 4 4 4 4 4 4 4 4 4 2 2
22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 20 20 20 20 20 20 20 20 20 20 12 8
50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 40 40 40 40 40 40 40 40 40 40 24 16
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 3 3
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2

Noted by: Noted by:

Clemente V. Pancho Gerardo V. Pancho


Vice President President and General Manager
OCTOBER
24 25 26 27 28 29 30 31

gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
2 1 1 1
2 1 1 1
8 4 4 4
16 8 8 8
3 2 2 2
4 3 2 2
1 1 1 1
2 1 1 1

3 3 3 3
1 1 1 1
3 3 3 3
2 2 2 2
4 3 2 2
1 1 1 1
1 1 1 1
2 1 1 1
No. Description Crew No. Start Finish

I Mobilization 1 14-Oct-19 18-Oct-19


II Site Development (Access road development and Clearing of site) 1 16-Oct-19 23-Oct-19
III Temfacil
a Barracks 1 2 19-Oct-19 1-Nov-19
b Barracks 2 2 2-Nov-19 15-Nov-19
c Barracks 3 3 6-Nov-19 19-Nov-19
d Barracks 4 2 16-Nov-19 29-Nov-19
e Common Comfort Room 1 4 19-Oct-19 28-Oct-19
f Common Comfort Room 2 4 15-Nov-19 24-Nov-19
g Common Comfort Room 3 4 25-Nov-19 4-Dec-19
h Field Office 5 19-Oct-19 4-Nov-19
i Canteen 4 29-Oct-19 8-Nov-19
j Water Elevated Tank 4 9-Nov-19 14-Nov-19
k Engineers Quarter 5 16-Nov-19 1-Dec-19
l Construction Warehouse 3 19-Oct-19 24-Oct-19
m Maintenance Warehouse 3 19-Oct-19 24-Oct-19
n Motorpool 5 5-Nov-19 15-Nov-19
o Diesel Compartment 3 25-Oct-19 28-Oct-19
p Oil Section 3 29-Oct-19 1-Nov-19
q Oil and Water Separator 3 25-Oct-19 1-Nov-19
r Materials Laboratory 3 20-Nov-19 6-Dec-19
s Guard House 3 2-Nov-19 5-Nov-19
t Perimeter Fence (200m ribbed type with barbed wire, 850m barbed wire) 1 24-Oct-19 13-Nov-19
u Pantry/Laundry Area 5 2-Dec-19 5-Dec-19
v Laundry Area for Workers 5 2-Dec-19 5-Dec-19
w Locker Room / Charger Area 3 2-Nov-19 5-Nov-19
x Materials Recovery Facility 2 29-Nov-19 2-Dec-19
y Fabrication Area 5 6-Dec-19 9-Dec-19
z Carpentry Area 5 6-Dec-19 9-Dec-19
IV Others
a Drainage 1 14-Nov-19 23-Nov-19
b Batching Plant 6 15-Sep-19 5-Oct-19
c Crusher Plant 6 1-Oct-19 21-Oct-19

MANPOW
Field Engin

1 - FIeld Engineer
1 - Welder
1 - Pipefitter
Crew 1 Crew 2
1 - Foreman 1 - Foreman
2 - M/Carp 4 - M/Carp
10 - Laborer 8 - Laborer
------------------------------------------------------------------------------
1 - Field Engineer
2 - Welder
2 - Pipefitter
Crew 3 Crew 4
1 - Foreman 1 - Foreman EQUIPME
4 - M/Carp 4 - M/Carp Bagger Mi
8 - Laborer 8 - Laborer
--------------------------------------------------------------- Genset 45k
1 - Field Engineer Concrete Vibra
2 - Welder
2 - Pipefitter
Crew 5 Crew 6 Portable Welding Mach
1 - Foreman 1 - Foreman
4 - M/Carp 4 - M/Carp
8 - Laborer 8 - Laborer
Tower Light (LE

Prepared by: Checked by:

Kenneth Christopher R. Gabriel Roland G. Cruz


Office Engineer Head Office Engineer
C.M. PANCHO CONSTRUCTION, INC.
Construction of Airport to NCC Access Road Pha
No. of
Days
October
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07

5 gggggg
gggggg
gggggg
gggggg
gggggg
8 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

14 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
14 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
14 gggggg
gggggg
14
10 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
10
10
17 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
11 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
6 ggg
16
6 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
6 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
11 gggggg
gggggg
gggggg
4 gggggg
gggggg
gggggg
gggggg
4 gggggg
gggggg
gggggg
gggggg
8 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
17
4 gggggg
gggggg
gggggg
gggggg
21 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
4
4
4 gggggg
gggggg
gggggg
gggggg
4
4
4

10
21 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
21

MANPOWER
Field Engineer 1 1 1 1 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Foreman 1 1 1 1 1 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
M/Carp 2 2 2 2 2 18 18 18 18 18 18 18 18 18 22 22 22 22 22 22 22 22 22 22 22
Laborer 10 10 10 10 10 42 42 42 42 42 42 42 42 42 50 50 50 50 50 50 50 50 50 50 50
Pipefitter 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Welder 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Mechanic 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Electrician 1 1 1 1 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

EQUIPMENT
Bagger Mixer 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Genset 45kVa 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Concrete Vibrator 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Genset 5kVa 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
ble Welding Machine 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Miller 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Tower Light 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Tower Light (LED) 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Checked by: Approved by:

Janica May M. Aguilar Norman M. Syguia


Head Office Engineer Vice President for Operations
d Phase 2
2019
November Dec
08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggg
gggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4 4 4 4 4 4 4 4 4 4 2 2
22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 20 20 20 20 20 20 20 20 20 20 12 8
50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 50 40 40 40 40 40 40 40 40 40 40 24 16
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 3 3
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2

Noted by: Noted by:

Clemente V. Pancho Gerardo V. Pancho


Vice President President and General Manager
December
06 07 08 09 10 11 12 13

gggggg

gggggg

gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
2 1 1 1
2 1 1 1
8 4 4 4
16 8 8 8
3 2 2 2
4 3 2 2
1 1 1 1
2 1 1 1

3 3 3 3
1 1 1 1
3 3 3 3
2 2 2 2
4 3 2 2
1 1 1 1
1 1 1 1
2 1 1 1
Project Name : Construction of Airport to NCC Access Road Phase 2
Location : New Clark City
Subject : Construction of Campsite Schedule

No. Description Crew No. Start Finish

I Mobilization 1 14-Oct-19 18-Oct-19


II Site Development (Access road development and Clearing of site) 1 15-Oct-19 22-Oct-19
III Temfacil
a Barracks 1 2 18-Oct-19 4-Nov-19
b Barracks 2 2 5-Nov-19 18-Nov-19
c Barracks 3 3 9-Nov-19 22-Nov-19
d Barracks 4 2 19-Nov-19 2-Dec-19
e Common Comfort Room 1 4 18-Oct-19 27-Oct-19
f Common Comfort Room 2 4 18-Nov-19 27-Nov-19
g Common Comfort Room 3 4 28-Nov-19 7-Dec-19
h Field Office 5 18-Oct-19 7-Nov-19
i Canteen 4 28-Oct-19 11-Nov-19
j Elevated Water Tank (3 units) 4 12-Nov-19 17-Nov-19
k Engineers Quarter 5 19-Nov-19 4-Dec-19
l Construction Warehouse 3 18-Oct-19 23-Oct-19
m Maintenance Warehouse 3 18-Oct-19 23-Oct-19
n Motorpool 5 8-Nov-19 18-Nov-19
o Diesel Compartment 3 24-Oct-19 27-Oct-19
p Oil Section 3 28-Oct-19 30-Oct-19
q Oil and Water Separator 3 24-Oct-19 30-Oct-19
r Materials Laboratory (with curing tank and troxler house) 3 23-Nov-19 11-Dec-19
s Guard post (3 units) and Checker's Tower (1 unit) 3 4-Nov-19 8-Nov-19
t Perimeter Fence (200m ribbed type with barbed wire, 850m barbed wire) 1 23-Oct-19 16-Nov-19
u Pantry/Laundry Area 5 5-Dec-19 8-Dec-19
v Laundry Area for Workers 1 3-Dec-19 6-Dec-19
w Locker Room / Charger Area 2 3-Dec-19 7-Dec-19
x Materials Recovery Facility 2 8-Dec-19 11-Dec-19
y Guards' Sleeping Area 6 24-Oct-19 26-Oct-19
z RSB and Formworks Fabrication Area 1 7-Dec-19 10-Dec-19
IV Others
a Drainage (RCP and Catch Basin) 1 17-Nov-19 26-Nov-19
b Casting Area (3 locations) 1 27-Nov-19 2-Dec-19
c Batching Plant 6 27-Oct-19 20-Nov-19
d Crusher Plant 6 21-Nov-19 11-Dec-19

MANPOW
Field Engin

1 - FIeld Engineer
1 - Welder
1 - Pipefitter
Crew 1 Crew 2
1 - Foreman 1 - Foreman
2 - M/Carp 4 - M/Carp
10 - Laborer 10 - Laborer
------------------------------------------------------------------------------
1 - Field Engineer
2 - Welder
2 - Pipefitter
Crew 3 Crew 4
1 - Foreman 1 - Foreman EQUIPME
4 - M/Carp 4 - M/Carp Bagger Mi
10 - Laborer 10 - Laborer
--------------------------------------------------------------- Genset 45k
1 - Field Engineer Concrete Vibra
2 - Welder
2 - Pipefitter
Crew 5 Crew 6 Portable Welding Mach
1 - Foreman 1 - Foreman
4 - M/Carp 4 - M/Carp
10 - Laborer 10 - Laborer
Tower Light (LE

Prepared by: Checked by:

Kenneth Christopher R. Gabriel Chris Nebran


Office Engineer Project Engineer
No. of
Days
October
14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03 04 05 06 07

gggggg
5 gggggg
gggggg
gggggg
gggggg
8 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

14 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
14 gggggg
gggggg
gggggg
14
14
10 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
10
10
17 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
11 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
6
16
6 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
6 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
11
4 gggggg
gggggg
gggggg
gggggg
3 gggggg
gggggg
gggggg
7 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
19
5 gggggg
gggggg
gggggg
gggggg
21 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
4
4
5
4
3 gggggg
gggggg
gggggg
4

10
6
21 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
21

MANPOWER
Field Engineer 1 1 1 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Foreman 1 1 1 1 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
M/Carp 2 2 2 2 18 18 18 18 18 18 18 22 22 22 22 22 22 22 22 22 22 22 22 22 22
Laborer 10 10 10 10 50 50 50 50 50 50 50 60 60 60 60 60 60 60 60 60 60 60 60 60 60
Pipefitter 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5
Welder 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Mechanic 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Electrician 1 1 1 1 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

EQUIPMENT
Bagger Mixer 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Genset 45kVa 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Concrete Vibrator 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Genset 5kVa 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
ble Welding Machine 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Miller 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Tower Light 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Tower Light (LED) 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Checked by: Approved by:

Janica May M. Aguilar Norman M. Syguia


Head Office Engineer Vice President for Operations
2019
November Dec
08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 01 02 03 04 05

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4 4 4 4 4 4 4 4 4 4 4 2
22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 22 20 20 20 20 20 12
60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 60 50 50 50 50 50 30
5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 3
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2

Noted by:

Gerardo V. Pancho
President and General Manager
December
06 07 08 09 10 11 12 13

gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

2 2 2 2
2 2 2 2
12 12 12 12
30 30 30 30
3 3 3 3
4 4 4 4
1 1 1 1
2 2 2 2

3 3 3 3
1 1 1 1
3 3 3 3
2 2 2 2
4 3 2 2
1 1 1 1
1 1 1 1
2 1 1 1
Project Name : Construction of Airport to NCC Access Road Phase 2
Location : New Clark City
Subject : Construction of Campsite Schedule

No. Description Crew No. Start Finish

II Site Development (Access road development and Clearing of site) 8 4-Nov-19 21-Nov-19
III Temfacil
a Barracks 1 2 4-Nov-19 17-Nov-19
b Barracks 2 2 18-Nov-19 1-Dec-19
c Barracks 3 3 4-Nov-19 17-Nov-19
d Barracks 4 2 2-Dec-19 15-Dec-19
e Common Comfort Room 1 4 4-Nov-19 13-Nov-19
f Common Comfort Room 2 4 5-Dec-19 14-Dec-19
g Common Comfort Room 3 3 18-Nov-19 27-Nov-19
h Field Office 5 4-Nov-19 20-Nov-19
i Canteen 4 14-Nov-19 28-Nov-19
j Elevated Water Tank (3 units) 4 29-Nov-19 4-Dec-19
k Engineers Quarter 7 4-Nov-19 19-Nov-19
l Construction Warehouse 3 4-Nov-19 9-Nov-19
m Maintenance Warehouse 3 4-Nov-19 9-Nov-19
n Motorpool 5 21-Nov-19 1-Dec-19
o Diesel Compartment 3 10-Nov-19 13-Nov-19
p Oil Section 3 14-Nov-19 16-Nov-19
q Oil and Water Separator 3 10-Nov-19 16-Nov-19
r Materials Laboratory (with curing tank and troxler house) 7 20-Nov-19 8-Dec-19
s Guard post (3 units) and Checker's Tower (1 unit) 3 28-Nov-19 2-Dec-19
t Perimeter Fence (200m ribbed type with barbed wire, 850m barbed wire) 1 7-Nov-19 27-Nov-19
u Pantry/Laundry Area 5 2-Dec-19 5-Dec-19
v Laundry Area for Workers 1 6-Dec-19 9-Dec-19
w Locker Room / Charger Area 2 8-Dec-19 12-Dec-19
x Materials Recovery Facility 3 3-Dec-19 6-Dec-19
y Guards' Sleeping Area 1 4-Nov-19 6-Nov-19
z RSB and Formworks Fabrication Area 1 10-Dec-19 13-Dec-19
IV Others
a Drainage (RCP and Catch Basin) 1 4-Dec-19 13-Dec-19
b Casting Area (3 locations) 1 28-Nov-19 3-Dec-19
c Batching Plant 6 11-Nov-19 1-Dec-19
d Crusher Plant 6 30-Nov-19 20-Dec-19

1 - FIeld Engineer MANPO


2 - Welder Field En
2 - Pipefitter
Crew 1 Crew 2
1 - Foreman 1 - Foreman
2 - M/Carp 4 - M/Carp
10 - Laborer 10 - Laborer
------------------------------------------------------------------------------
1 - Field Engineer
2 - Welder
2 - Pipefitter
Crew 3 Crew 4 Crew 8
1 - Foreman 1 - Foreman 1 - Foreman
4 - M/Carp 4 - M/Carp 4 - Laborer
10 - Laborer 10 - Laborer
---------------------------------------------------------------
EQUIP
1 - Field Engineer
2 - Welder Bagge
2 - Pipefitter Genset
Crew 5 Crew 6 Crew 7
1 - Foreman 1 - Foreman 1 - Foreman Concrete V
4 - M/Carp 4 - M/Carp 4 - M/Carp
10 - Laborer 10 - Laborer 10 - Laborer
Portable Welding M

Tower Ligh

Prepared by: Checked by:

Kristopher Revilla Roland Cruz


Project Engineer Project Engineer
No. of
2019
Days
November
04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27

gggggg
18 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
10 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
14 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
14 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
14
gggggg
10 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
10
10 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
13 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
11 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
6
gggggg
16 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
6 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
6 gggggg
gggggg
gggggg
gggggg
gggggg
11 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
4 gggggg
gggggg
gggggg
gggggg
3 gggggg
gggggg
gggggg
7 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
19 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
5
21 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
4
4
5
4
3gggggg
gggggg
gggggg
4
10
6
21 gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
21

MANPOWER
Field Engineer 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Foreman 8 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 6 6 6 6 6 6 6
M/Carp 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26 26
Laborer 74 74 74 74 74 74 74 74 74 74 74 74 74 74 74 74 74 70 70 70 70 70 70 70
Pipefitter 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Welder 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Mechanic 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Electrician 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

EQUIPMENT
Bagger Mixer 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Genset 45kVa 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Concrete Vibrator 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Genset 5kVa 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
able Welding Machine 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Miller 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Tower Light 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Tower Light (LED) 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3

Checked by: Checked by: Approved by:

Reynaldo B. Janica May M. Aguilar Norman M. Syguia


Project Mana Head Office Engineer - MO Vice President for Operations
2019
December
28 29 30 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20

gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg

gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gggggg
gg

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1 1 1
6 6 6 6 6 6 6 6 6 5 5 5 5 5 5 4 3 2 1 1 1 1 1
26 26 26 26 26 26 26 26 26 22 22 22 22 22 22 18 12 8 4 4 4 4 4
70 70 70 70 70 70 70 70 70 60 60 60 60 60 60 50 30 20 10 10 10 10 10
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 2 2 2 2 2 2
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 2 2 2 2 2 2
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1 1 1

3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1 1 1
2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 4 4 2 2 2 2 2 2
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2 2 1 1 1 1 1

Noted by:

Gerardo V. Pancho
President and General Manager