Professional Documents
Culture Documents
Nde Procedure Magnetic Particle Testing
Nde Procedure Magnetic Particle Testing
:CSB/SD/QAQC/003
WORKING PROCEDURE
Page 1 of 19 Rev. 0
NDE PROCEDURE – MAGNETIC PARTICLE
Date: 30/3/2010
TESTING
NDE PROCEDURE -
MAGNETIC PARTICLE TESTING
TABLE OF CONTENTS
1.0 PURPOSE
2.0 SCOPE
This procedure establishes the method and process for Magnetic Particle
Inspection using a magnetic yoke for detection of discontinuities on surface or
sub surface of ferromagnetic material. Magnetic Particle Examination shall be
carried out after Visual Examination of the joint has been accepted.
3.0 REFERENCE
4.0 DEFINITIONS
5.0 PROCEDURES
Performance check shall be carried out every week by use castrol strip
and lifting block, result of the performance check shall be recorded.
Refer to Appendix I of this section for the procedure to check the
magnetizing force of yokes. Use of permanent magnet shall be limited
to as where the use of AC Yoke is not practical. Weight stenciled
with the applicable nominal weight prior to first use .A weight of this
type shall be made available upon request by PCSB at all sites where
MPI is performed.
5.3.3 Dry iron powder red or yellow colour may be used where
temperature of parts to be tested is higher than 130°F
(54°C) but lower than 600°F/315°C (not recommended for
overhead position).
5.5.4 Switch on the current flow and apply black magnetic ink on the Castrol
Strip.
5.5.5 If the three lines are clearly visible, then the conclusion that can be
made is the AC Yoke has sufficient magnetic field to meet the
requirements.
5.5.6 The MPI Technician shall carry the field intensity indicator with him
at all times while carrying out MPI.
The use of the magnetic Yoke favours the detection of flaws where
the major axis lies transverse to the line joining the pole pieces of
the yoke. As such, two magnetizing application, each being at right
angle to the other, should be applied over the same area. When an
indication is found, a third application should be made at an axis
where maximum indication is obtained.
5.9.1
Wet Method
5.9.1.1 Clean and dry area of test free from rust, oil,
grease or any· other material that may obstruct
movement o f iron particles or impair result
interpretation. Grind lightly if necessary.
5.2.9.1 Clean and dry area of test free from rust, oil, grease
or any other material that may obstruct movement
of iron particles or impair result interpretation. Grind
lightly if necessary.
Not applicable
7.0 Records
7.1 Reporting
All tests carried out shall be reported in a format that contains the
f o l l o w i n g information:
i. Job Identification.
ii. Date of Test.
iii. Type of Equipment Used.
iv. Type of Technique Applied
v. Identification of weld/ Component
vi. Type of magnetizing Current
vii. Result Interpretation
viii. Name and signature of tester.
APPENDICES
TABLE 6.1
Inspection Acceptance Criteria
Discontinuity Category and Statically Cyclically Tubular
inspection Criteria Loaded Loaded Connectio
Non-Tabular Non-Tabular ns (All
Connection Connection Loads)
(1) Crack Prohibition
Any crack shall be unacceptable,
regardless of size or location
(2) Weld/Base Metal Fusion
Through fusion shall exist between
adjacent layers of weld and
between weld and base metal
(3) Porosity & linear indication
(A) CJP groove welds in butt joints
transverse to the direction of
computed tensile stress shall
have no visible piping porosity.
For all other groove welds and
or fillet welds, the sum of the x x
visible piping porosity 1 mm or
greater in diameter shall not
exceed 100 in any linear inch of
weld and shall not exceed
20mm in any 300mm length of
weld
(B) The frequency of piping
porosity in fillet welds shall not
exceed one in each 100mm of
weld length and the maximum
diameter shall not exceed
2.5mm. exception: for filler
welds connection stifeners to x
web, the sum of the diameters
of piping porosity shall not
exceed 10mm in any linear inch
of weld and shall not exceed
20mm in any 300mm length of
weld
(C) CJP Groove welds in butt joints
transverse to the direction of
computed tensile stress shall
have no piping porosity. For all
other groove welds, the
x
frequency of piping porosity
shall not exceed on in 100mm
of length and the maximum
diameter shall not exceed
2.5mm
(4) Undercut
(a) For material less than 1 in. [25
mm] thick, undercut shall not
exceed 1/32 in. [1 mm], with
the following exception: x x
undercut shall not exceed 1/16
in. [2mm ] for any length of
weld