DOCUMENT REGISTER - QAPCO - Joel
DOCUMENT REGISTER - QAPCO - Joel
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
8 T-DANM-QAP-0008 QV-00-VEN-E19-14400917-0001 ELECTRICAL LOAD LIST 0 Electrical 3-Mar-19 7-Mar-19 T-QAP-DANM-0006 Commented
9 T-DANM-QAP-0008 QV-00-VEN-E50-14400917-0002 SPECIFICATION FOR ELECTRICAL BULK MATERIALS 0 Electrical 3-Mar-19 7-Mar-19 T-QAP-DANM-0006 Commented
10 T-DANM-QAP-0008 QV-00-VEN-E50-14400917-0001 SPECIFICATION FOR LV CABLE 0 Electrical 3-Mar-19 7-Mar-19 T-QAP-DANM-0006 Commented
14 T-DANM-QAP-0010 QV-1S-VEN-Y15-14400917-0005 L-SHAPED WALL DESIGN REPORT 0 Civil 3-Mar-19 7-Mar-19 T-QAP-DANM-0004 Commented
15 T-DANM-QAP-0010 QV-1S-VEN-Y60-14400917-0005 FOAM PUMP FOUNDATION DETAILS 0 Civil 3-Mar-19 7-Mar-19 T-QAP-DANM-0004 Commented
16 T-DANM-QAP-0010 QV-1S-VEN-Y60-14400917-0006 L-SHAPED WALL DETAILS 0 Civil 3-Mar-19 7-Mar-19 T-QAP-DANM-0004 Commented
Meeting
arranged on
18 T-DANM-QAP-0012 00009 PROJECT HSE PLAN 0 HSE 4-Mar-19 14-Mar-19
18/03/19 to
discuss
Page 2 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
20 T-DANM-QAP-0014 QV-1S-VEN-P58-14400917-0001 EQUIPMENT LOCATION PLAN 0 Piping 6-Mar-19 16-Apr-19 T-QAP-DANM-0044 Commented
21 T-DANM-QAP-0015 QV-1S-VEN-Y15-14400917-0006 STUDY REPORT FOR PILE FOUNDATION OPTIMIZATION 1 Civil 7-Mar-19 12-Mar-19 T-QAP-DANM-0008 Commented
T-QAP-DANM-0008
22 T-DANM-QAP-0015 QV-00-VEN-C02-14400917-0001 DESIGN BASIS 0 Process 7-Mar-19 12-Mar-19 Commented
T-QAP-DANM-0062
23 T-DANM-QAP-0016 00011 METHOD STATEMENT FOR EXCAVATION AND BACKFILLING 0 Civil 9-Mar-19 22-Apr-19 T-QAP-DANM-0048 Commented
Commented
24 T-DANM-QAP-0016 00012 METHOD STATEMENT FOR PILING WORKS 0 Civil 9-Mar-19 21-Mar-19 T-QAP-DANM-0048 via email on
21/03/19
PREQUALIFICATION AND MIX DESIGN DOCUMENT FROM
25 T-DANM-QAP-0017 00013 0 Civil 9-Mar-19 11-Mar-19 T-QAP-DANM-0007 Commented
M/S. UNIBETON READY MIX
26 T-DANM-QAP-0018 00014 TECHNICAL QUERIES FOR ELECTRICAL FROM DANEM 0 Electrical 11-Mar-19 14-Mar-19 T-QAP-DANM-0010 Commented
28 T-DANM-QAP-0019 QV-1S-VEN-E81-14400917-0001 HAZARDOUS AREA CLASSIFICATION 0 Electrical 11-Mar-19 14-Mar-19 T-QAP-DANM-0009 Commented
29 T-DANM-QAP-0019 QV-1S-VEN-E60-14400917-0001 CABLE TRENCH SECTION DETAILS 0 Electrical 11-Mar-19 14-Mar-19 T-QAP-DANM-0009 Commented
31 T-DANM-QAP-0019 QV-1S-VEN-E71-14400917-0002 SINGLE LINE DIAGRAM MODIFICATION LIGHTING DB 0 Electrical 11-Mar-19 27-Jun-19 T-QAP-DANM-0009 Commented
32 T-DANM-QAP-0019 QV-1S-VEN-E71-14400917-0001 SINGLE LINE DIAGRAM MODIFICATION MCC 0 Electrical 11-Mar-19 27-Jun-19 T-QAP-DANM-0009 Commented
34 T-DANM-QAP-0020 QVC-2V-UD-C72-00005 PROCESS FLOW DIAGRAM NO. 3901 SALES EDC-STORAGE 0 Process 11-Mar-19 29-Apr-19 T-QAP-DANM-0063 Commented
37 T-DANM-QAP-0022 93092-PIP-TQ-0001 TECHNICAL QUERIES FOR PIPING 0 Piping 14-Mar-19 25-Mar-19 T-QAP-DANM-0018 Commented
38 T-DANM-QAP-0023 QV-1S-VEN-Y60-14400917-0003 BLOWER FOUNDATION DETAILS 0 Civil 11-Mar-19 21-Mar-19 T-QAP-DANM-0014 Commented
39 T-DANM-QAP-0023 QV-1S-VEN-Y15-14400917-0002 FOUNDATION DESIGN REPORT FOR BLOWER 0 Civil 11-Mar-19 21-Mar-19 T-QAP-DANM-0014 Commented
40 T-DANM-QAP-0024 93092-INS-TQ-0003 TECHNICAL QUERIES FOR E&I NEED LIST 0 Instrument 14-Mar-19 30-Jun-19 T-QAP-DANM-0146 Commented
41 T-DANM-QAP-0025 93092-HSE-TQ-0001 TECHNICAL QUERIES FOR HSE 0 HSE 14-Mar-19 25-Mar-19 T-QAP-DANM-0018 Commented
Page 3 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
43 T-DANM-QAP-0027 QV-00-VEN-M58-14400917-0001 GA DRAWING FOR NEW SALES EDC TANK 0 Mech 17-Mar-19 26-Mar-19 T-QAP-DANM-0020 Commented
46 T-DANM-QAP-0030 QV-1S-VEN-C16-14400917-0001 DYKE VOLUME CALCULATION REPORT 0 Process 19-Mar-19 27-Mar-19 T-QAP-DANM-0022 Approved
48 T-DANM-QAP-0032 QV-1S-VEN-Y66-14400917-0001 GENERAL DRAWING NOTES 0 Civil 19-Mar-19 23-Jun-19 T-QAP-DANM-0139 Approved
51 T-DANM-QAP-0035 QV-1S-TPI-C78-03906-0001 PID FOR EDC STORAGE & LOADING FACILITIES STORAGE 0 Process 21-Mar-19 9-Apr-19 T-QAP-DANM-0036 Commented
52 T-DANM-QAP-0035 QV-1S-TPI-C78-03906-0002 PID FOR EDC STORAGE & LOADING FACILITIES STORAGE 0 Process 21-Mar-19 9-Apr-19 T-QAP-DANM-0036 Commented
53 T-DANM-QAP-0035 QVC-2V-UD-C78-00026 PID FOR BATTERY LIMIT SALES EDC STORAGE 0 Process 21-Mar-19 9-Apr-19 T-QAP-DANM-0036 Commented
54 T-DANM-QAP-0035 QVC-2V-UD-C78-00027 PID FOR INTER-CONNECTION CAUSTIC STORAGE 0 Process 21-Mar-19 9-Apr-19 T-QAP-DANM-0036 Commented
55 T-DANM-QAP-0035 QVC-2V-UD-C78-00019 PID FOR SALES GRADE EDC STORAGE TANK 0 Process 21-Mar-19 9-Apr-19 T-QAP-DANM-0036 Commented
56 T-DANM-QAP-0035 QVC-1U-VEN-C78-00001 PID FOR INSTRUMENT AIR HEADER 0 Process 21-Mar-19 9-Apr-19 T-QAP-DANM-0036 Commented
57 T-DANM-QAP-0036 QV-1S-VEN-Y02-14400917-0001 STRUCTURAL DESIGN BASIS FOR TANK FOUNDATION 0 Civil 21-Mar-19 27-Mar-19 T-QAP-DANM-0021 Commented
58 T-DANM-QAP-0037 00018 PROJECT EXECUTION SCHEDULE 0 General 23-Mar-19 28-Mar-19 T-QAP-DANM-0025 Commented
60 T-DANM-QAP-0039 QV-1S-VEN-E81-14400917-0001 HAZARDOUS AREA CLASSIFICATION 0 Electrical 23-Mar-19 2-Apr-19 T-QAP-DANM-0027 Commented
61 T-DANM-QAP-0040 QV-1S-VEN-I19-14400917-0002 ALARM & TRIP SET POINT LIST 0 Instrument 23-Mar-19 9-Apr-19 T-QAP-DANM-0038 Commented
62 T-DANM-QAP-0041 QV-1S-VEN-I54-14400917-0010 DATASHEET FOR RESTRICTION ORIFICE 0 Instrument 24-Mar-19 6-Apr-19 T-QAP-DANM-0035 Commented
63 T-DANM-QAP-0042 QV-00-VEN-I54-14400917-0012 DATASHEET FOR FLOW INDICATOR 0 Instrument 24-Mar-19 10-Apr-19 T-QAP-DANM-0039 Commented
Page 4 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
68 T-DANM-QAP-0043 QV-00-VEN-M60-14400917-0013 1ST SHELL COURSE NOZZLE MARKING-SHT 01 OF 01 0 Mech 24-Mar-19 Cancelled Commented
71 T-DANM-QAP-0045 00013 CONCRETE MIX DESIGN 1 Civil 27-Mar-19 27-Mar-19 T-QAP-DANM-0024 Approved
73 T-DANM-QAP-0047 93092-PIP-TQ-0002 PIPING TECHNICAL QUERY 0 Piping 30-Mar-19 6-Apr-19 T-QAP-DANM-0034 Commented
74 T-DANM-QAP-0048 93092-HSE-TQ-0002 FPC REVIEW REPORT-TECHNICAL QUERIES 0 Process 31-Mar-19 9-Apr-19 T-QAP-DANM-0037 Commented
75 T-DANM-QAP-0049 00013 CONCRETE MIX DESIGN 2 Civil 2-Apr-19 3-Apr-19 T-QAP-DANM-0031 Approved
76 T-DANM-QAP-0050 DEW-QAPCO-LYD-001 DANEM LAYDOWN AREA IN QAPCO FOR EDC TANK 0 General 2-Apr-19 3-Apr-19 T-QAP-DANM-0032 Commented
78 T-DANM-QAP-0051 QV-1S-VEN-C16-14400917-0001 DYKE VOLUME CALCULATION REPORT A Process 2-Apr-19 3-Apr-19 T-QAP-DANM-0033 Commented
78 T-DANM-QAP-0052 QV-1S-VEN-C16-14400917-0001 DYKE VOLUME CALCULATION REPORT A Process 4-Apr-19 11-Apr-19 T-QAP-DANM-0042 Commented
81 T-DANM-QAP-0054 QV-1S-VEN-Y56-14400917-0002 PILE LAYOUT AND DETAILS OF TEST PILE-SHT 01 TO 02 0 Civil 4-Apr-19 Resub Rev 1 Commented
Page 5 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
90 T-DANM-QAP-0061 QV-1S-VEN-Y60-14400917-0005 FOAM PUMP FOUNDATION DETAILS 1 Civil 16-Apr-19 23-Apr-19 T-QAP-DANM-0050 Approved
92 T-DANM-QAP-0062 QV-1S-VEN-C02-14400917-0002 CONTROL AND SAFEGUARDING PHILOSOPHY 0 Process 16-Apr-19 13-Jun-19 T-QAP-DANM-0119 commented
93 T-DANM-QAP-0063 QV-1S-VEN-C19-14400917-0002 UTILITY CONSUMPTION LIST 0 Process 16-Apr-19 23-Apr-19 T-QAP-DANM-0051 Commented
95 T-DANM-QAP-0065 QV-1S-VEN-C16-14400917-0002 PVV SIZING CALCULATION 0 Process 16-Apr-19 22-Apr-19 T-QAP-DANM-0047 Commented
96 T-DANM-QAP-0066 QV-1S-VEN-P50-14400917-0001 PIPING MATERIAL SPECIFICATION 0 Piping 16-Apr-19 1-May-19 T-QAP-DANM-0071 Approved
98 T-DANM-QAP-0068 QV-1S-VEN-P54-14400917-0004 DATA SHEET FOR BALL VALVE 0 Piping 16-Apr-19 24-Apr-19 T-QAP-DANM-0054 Approved
99 T-DANM-QAP-0069 QV-1S-VEN-P54-14400917-0005 DATA SHEET FOR BUTTERFLY VALVE 0 Piping 16-Apr-19 24-Apr-19 T-QAP-DANM-0055 Approved
100 T-DANM-QAP-0070 QV-1S-VEN-P54-14400917-0003 DATA SHEET FOR CHECK VALVE 0 Piping 16-Apr-19 24-Apr-19 T-QAP-DANM-0056 Approved
101 T-DANM-QAP-0071 QV-1S-VEN-P54-14400917-0002 DATA SHEET FOR GATE VALVE 0 Piping 16-Apr-19 24-Apr-19 T-QAP-DANM-0057 Approved
102 T-DANM-QAP-0072 QV-1S-VEN-P54-14400917-0006 DATA SHEET FOR PLUG VALVE 0 Piping 16-Apr-19 24-Apr-19 T-QAP-DANM-0058 Approved
103 T-DANM-QAP-0073 QV-1S-VEN-P56-14400917-0002 PIPING KEY PLAN 0 Piping 16-Apr-19 13-Jun-19 T-QAP-DANM-0122 Commented
104 T-DANM-QAP-0074 00009 PROJECT HSE PLAN A HSE 17-Apr-19 Resub Rev B Email from Eldrin
105 T-DANM-QAP-0074 00022 EMERGENCY RESPONSE PROCEDURE 0 HSE 17-Apr-19 22-Apr-19 Approved
106 T-DANM-QAP-0075 QV-00-VEN-C15-14400917-0001 CONTROL VALVE SIZING 0 Process 18-Apr-19 24-Apr-19 T-QAP-DANM-0060 Commented
Page 6 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
113 T-DANM-QAP-0082 00012 METHOD STATEMENT FOR PILING WORKS 1 Civil 22-Apr-19 30-Apr-19 T-QAP-DANM-0065 Commented
114 T-DANM-QAP-0083 QV-1S-VEN-I71-14400917-0004 INSTRUMENT CABLE BLOCK DIAGRAM 0 Instrument 23-Apr-19 26-May-19 T-QAP-DANM-0096 Commented
115 T-DANM-QAP-0084 QV-1S-VEN-I54-14400917-0005 DATASHEET FOR PRESSURE VACUUM RELIEF VALVE 0 Instrument 23-Apr-19 1-May-19 T-QAP-DANM-0070 Commented
116 T-DANM-QAP-0084 QV-1S-VEN-I54-14400917-0009 DATASHEET FOR CONTROL VALVE 0 Instrument 23-Apr-19 1-May-19 T-QAP-DANM-0070 Commented
118 T-DANM-QAP-0086 00009 PROJECT HSE PLAN B HSE 23-Apr-19 Commented commented
119 T-DANM-QAP-0087 QV-1S-VEN-I18-14400917-0002 INSTRUMENT JUNCTION BOX SCHEDULE 0 Instrument 24-Apr-19 5-May-19 T-QAP-DANM-0072 Commented
120 T-DANM-QAP-0088 QV-1S-VEN-I71-14400917-0003 INSTRUMENT INTERCONNECTION DIAGRAM-SHT 01 TO 21 0 Instrument 24-Apr-19 9-May-19 T-QAP-DANM-0076 Commented
121 T-DANM-QAP-0089 93092-PRS-CRS-0004 CRS-PVV SIZING CALCULATION 0 Process 24-Apr-19 30-Apr-19 T-QAP-DANM-0064 Commented
122 T-DANM-QAP-0090 93092-PRS-CRS-0003 CRS-PIPING & INSTRUMENTATION DIAGRAM 0 Process 24-Apr-19 13-Jun-19 T-QAP-DANM-0123 Commented
124 T-DANM-QAP-0092 00018 PROJECT EXECUTION SCHEDULE 1 General 25-Apr-19 25-Apr-19 T-QAP-DANM-0061 Commented
125 T-DANM-QAP-0093 QV-1S-VEN-I54-14400917-0003 DATASHEET FOR RELIEF VALVE 0 Instrument 25-Apr-19 1-May-19 T-QAP-DANM-0069 Commented
126 T-DANM-QAP-0094 QV-1S-VEN-I54-14400917-0008 DATASHEET FOR ESD VALVE 0 Instrument 25-Apr-19 26-May-19 T-QAP-DANM-0097 Commented
127 T-DANM-QAP-0095 QV-1S-VEN-Y15-14400917-0005 L-SHAPED WALL DESIGN REPORT 1 Civil 27-Apr-19 30-Apr-19 T-QAP-DANM-0067 Commented
128 T-DANM-QAP-0095 QV-1S-VEN-Y60-14400917-0006 L-SHAPED WALL DETAILS 1 Civil 27-Apr-19 30-Apr-19 T-QAP-DANM-0067 Commented
129 T-DANM-QAP-0096 QV-1S-VEN-I71-14400917-0001 INSTRUMENT HOOK-UP DIAGRAM 0 Instrument 30-Apr-19 5-May-19 T-QAP-DANM-0073 Commented
130 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-01 PIPING GA TANKFARM AREA SHT 1 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
131 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-02 PIPING GA TANKFARM AREA SHT 2 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
132 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-03 PIPING GA TANKFARM AREA SHT 3 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
133 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-04 PIPING GA TANKFARM AREA SHT 4 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
134 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-06 PIPING GA TANKFARM DYKE WALL AREA SHT 6 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
135 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-05 PIPING GA TANKFARM DYKE WALL AREA SHT 5 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
Page 7 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
136 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-08 PIPING GA EXISTING TIE-IN AREA SHT 8 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
137 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-07 PIPING GA EXISTING TIE-IN AREA SHT 7 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
138 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-09 PIPING GA BLOWER AREA SHT 9 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
139 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-10 PIPING GA FIRE FIGHTING TIE-IN SHT 10 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
140 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-11 PIPING GA FIRE FIGHTING TIE IN FOAM PUMP SHT 11 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
141 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-12 PIPING GA- SECTION TANKFARM AREA SHT 12 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
142 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-13 PIPING GA- SECTION VIEW OVERALL SHT 13 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
143 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-14 PIPING GA SECTION VIEW TIE IN AREA SHT 14 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
144 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-15 PIPING GA SECTION VIEW OVERALL SHT 15 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
145 T-DANM-QAP-0097 QV-1S-VEN-P58-14400917-0002-16 PIPING GA SECTION VIEW OVERALL SHT 16 OF 16 0 Piping 30-Apr-19 23-Jun-19 T-QAP-DANM-0140 AWC
147 T-DANM-QAP-0099 QV-00-VEN-M60-14400917-0008 NAME PLATE DETAILS-SHT 01 OF 01 0 Mech 30-Apr-19 13-Jun-19 T-QAP-DANM-0124 Commented
148 T-DANM-QAP-0100 QV-00-VEN-M60-14400917-0011 SUPPORT DETAILS & MISC-SHT 01 OF 01 0 Mech 30-Apr-19 13-Jun-19 T-QAP-DANM-0126 Commented
149 T-DANM-QAP-0101 QV-00-VEN-M60-14400917-0009 SPIRAL STAIRWAY DETAILS-SHT 01 TO 04 0 Mech 30-Apr-19 15-Jun-19 T-QAP-DANM-0134 Commented
150 T-DANM-QAP-0102 QV-00-VEN-M60-14400917-0010 PERIPHERAL HANDRAIL DETAILS-SHT 01 OF 01 0 Mech 30-Apr-19 24-Jun-19 T-QAP-DANM-0145 Approved
152 T-DANM-QAP-0104 QV-00-VEN-M60-14400917-0013 1ST SHELL COURSE NOZZLE MARKING-SHT 01 OF 01 0 Mech 30-Apr-19 24-Jun-19 T-QAP-DANM-0145 Approved
153 T-DANM-QAP-0105 QV-1S-VEN-M30-14400917-0001 MECHANICAL BULK MTO 0 Mech 30-Apr-19 24-Jun-19 T-QAP-DANM-0145 Approved
155 T-DANM-QAP-0107 QV-00-VEN-M60-14400917-0002 BOTTOM PLATE DETAILS-SHT 01 OF 01 0 Mech 1-May-19 24-Jun-19 T-QAP-DANM-0145 Approved
157 T-DANM-QAP-0109 QV-00-VEN-M60-14400917-0004 ROOF STRUCTURAL DETAILS-SHT 01 OF 01 0 Mech 1-May-19 24-Jun-19 T-QAP-DANM-0145 Approved
158 T-DANM-QAP-0110 QV-00-VEN-M60-14400917-0005 SHELL NOZZLE DETAILS-SHT 01 OF 01 0 Mech 1-May-19 24-Jun-19 T-QAP-DANM-0145 Approved
Page 8 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
161 T-DANM-QAP-0113 00028 CV OF CONSTRUCTION MANAGER-MECHANICAL 0 General 1-May-19 13-Jun-19 T-QAP-DANM-0127 Approved
163 T-DANM-QAP-0115 QV-00-VEN-I54-14400917-0012 DATASHEET FOR FLOW INDICATOR 1 Instrument 1-May-19 26-May-19 T-QAP-DANM-0095 Commented
164 T-DANM-QAP-0116 QV-1S-VEN-I54-14400917-0010 DATASHEET FOR RESTRICTION ORIFICE 1 Instrument 1-May-19 30-Jun-19 T-QAP-DANM-0035 Commented
165 T-DANM-QAP-0117 00009 PROJECT HSE PLAN C HSE 2-May-19 6-May-19 T-QAP-DANM-0074 Approved
169 T-DANM-QAP-0121 QV-1S-VEN-P54-14400917-0002 DATA SHEET FOR GATE VALVE A Piping 5-May-19 9-May-19 T-QAP-DANM-0077 Approved
170 T-DANM-QAP-0121 QV-1S-VEN-P54-14400917-0003 DATA SHEET FOR CHECK VALVE A Piping 5-May-19 9-May-19 T-QAP-DANM-0077 Approved
171 T-DANM-QAP-0121 QV-1S-VEN-P54-14400917-0004 DATA SHEET FOR BALL VALVE A Piping 5-May-19 9-May-19 T-QAP-DANM-0077 Approved
172 T-DANM-QAP-0121 QV-1S-VEN-P54-14400917-0005 DATA SHEET FOR BUTTERFLY VALVE A Piping 5-May-19 9-May-19 T-QAP-DANM-0077 Approved
173 T-DANM-QAP-0121 QV-1S-VEN-P54-14400917-0006 DATA SHEET FOR PLUG VALVE A Piping 5-May-19 9-May-19 T-QAP-DANM-0077 Approved
169 T-DANM-QAP-0124 QV-1S-VEN-P54-14400917-0009 DATA SHEET FOR FLAME ARRESTOR 0 Piping 8-May-19 26-May-19 T-QAP-DANM-0093 Commented
170 T-DANM-QAP-0125 QV-1S-VEN-Y60-14400917-0005 FOAM PUMP FOUNDATION DETAILS A Civil 8-May-19 9-May-19 T-QAP-DANM-0075 Approved
171 T-DANM-QAP-0126 QV-1S-VEN-154-14400917-0011 DATASHEET FOR PUSH BUTTON STATION 0 Instrument 8-May-19 19-May-19 T-QAP-DANM-0089 Commented
172 T-DANM-QAP-0127 QV-1S-VEN-I54-14400917-0004 DATASHEET FOR TEMPERATURE GAUGE 0 Instrument 8-May-19 26-May-19 T-QAP-DANM-0094 Commented
173 T-DANM-QAP-0128 QV-1S-VEN-I54-14400917-0007 DATASHEET FOR TEMPERATURE TRANSMITTER 0 Instrument 8-May-19 23-May-19 T-QAP-DANM-0091 Commented
174 T-DANM-QAP-0129 QV-1S-VEN-E60-14400917-0002 EARTHING LAYOUT-SHT 01 OF 01 0 Electrical 8-May-19 15-Jul-19 T-QAP-DANM-0155 commented
Page 9 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
175 T-DANM-QAP-0129 QV-1S-VEN-E57-14400917-0001 ELECTRICAL EQUIPMENT LAYOUT-SHT 01 OF 01 0 Electrical 8-May-19 15-Jul-19 T-QAP-DANM-0155 Approved
176 T-DANM-QAP-0129 QV-1S-VEN-E56-14400917-0001 LIGHTING LAYOUT-SHT 01 OF 01 0 Electrical 8-May-19 15-Jul-19 T-QAP-DANM-0155 Approved
177 T-DANM-QAP-0130 QV-1S-VEN-I54-14400917-0001 DATASHEET FOR LEVEL TRANSMITTER 0 Instrument 8-May-19 26-May-19 T-QAP-DANM-0100 Commented
178 T-DANM-QAP-0131 QV-1S-VEN-I54-14400917-0002 DATASHEET FOR PRESSURE GAUGE 0 Instrument 8-May-19 18-May-19 T-QAP-DANM-0087 Commented
179 T-DANM-QAP-0132 QV-1S-VEN-I54-14400917-0006 DATASHEET FOR PRESSURE TRANSMITTER 0 Instrument 8-May-19 18-May-19 T-QAP-DANM-0086 Commented
180 T-DANM-QAP-0133 00031 CV OF PLANNING ENGINEER-MECHANICAL 0 General 12-May-19 15-May-19 T-QAP-DANM-0080 Approved
181 T-DANM-QAP-0134 QV-1S-VEN-P56-14400917-0001 PLOT PLAN 3 Piping 12-May-19 27-May-19 T-QAP-DANM-0105 Commented
182 T-DANM-QAP-0135 QV-1S-VEN-P58-14400917-0001 EQUIPMENT LOCATION PLAN-SHT 01 TO 02 1 Piping 12-May-19 16-May-19 T-QAP-DANM-0084 Commented
183 T-DANM-QAP-0136 QV-1S-VEN-C16-14400917-0001 DYKE VOLUME CALCULATION REPORT B Process 12-May-19 26-May-19 T-QAP-DANM-0092 Commented
188 T-DANM-QAP-0141 00012 METHOD STATEMENT FOR PILING WORKS 2 Civil 13-May-19 18-May-19 T-QAP-DANM-0085 Commented
189 T-DANM-QAP-0142 93092-PIP-TQ-0001 TECHNICAL QUERIES FOR PIPING 1 Piping 13-May-19 15-May-19 T-QAP-DANM-0081 Approved
193 T-DANM-QAP-0146 00037 CV OF QA/QC ENGINEER-CIVIL 0 General 14-May-19 20-May-19 T-QAP-DANM-0090 Approved
194 T-DANM-QAP-0147 QV-1S-VEN-Y56-14400917-0003 PILE & PILE CAP DETAILS 0 Civil 15-May-19
Page 10 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
198 T-DANM-QAP-0151 QV-1S-VEN-C16-14400917-0002 PVV SIZING CALCULATION 1 Process 21-May-19 26-May-19 T-QAP-DANM-0098 Commented
199 T-DANM-QAP-0152 00038 TEST CERTIFICATE OF REBAR 0 Civil 22-May-19 26-May-19 T-QAP-DANM-0101 Approved
200 T-DANM-QAP-0153 00039 WELDER SUMMARY AND WELDER CERTIFICATES 0 QA/QC 23-May-19 13-Jun-19 T-QAP-DANM-0120 Commented
202 T-DANM-QAP-0155 QV-1S-VEN-Y56-14400917-0002 PILE LAYOUT AND DETAILS OF TEST PILE-SHT 01 TO 04 1 Civil 25-May-19 Resub Rev 2 Commented
206 T-DANM-QAP-0159 QV-1S-VEN-Y02-14400917-0001 STRUCTURAL DESIGN BASIS FOR TANK FOUNDATION 1 Civil 28-May-19
213 T-DANM-QAP-0165 QV-1S-VEN-C19-14400917-0001 EQUIPMENT LIST & LINE LIST 0 Process 4-Jun-19 11-Jun-19 T-QAP-DANM-0115 Approved
214 T-DANM-QAP-0166 QV-1S-VEN-C19-14400917-0002 UTILITY CONSUMPTION LIST 1 Process 4-Jun-19 13-Jun-19 T-QAP-DANM-0129 Commented
215 T-DANM-QAP-0167 QV-1S-VEN-Y56-14400917-0002 PILE LAYOUT AND DETAILS OF TEST PILE-SHT 01 TO 04 2 Civil 8-Jun-19 Commented
217 T-DANM-QAP-0169 QV-1S-VEN-C16-14400917-0002 PVV SIZING CALCULATION 2 Process 8-Jun-19 30-Jun-19 T-QAP-DANM-0098 Commented
219 T-DANM-QAP-0171 QVC-2V-UD-C72-00005 PROCESS FLOW DIAGRAM NO. 3901 SALES EDC-STORAGE 1 Process 8-Jun-19 13-Jun-19 T-QAP-DANM-0130 Commented
220 T-DANM-QAP-0172 93092-PRS-CRS-0007 COMMENT RESOLUTION SHEET (CRS) FOR DESIGN BASIS 0 Civil 8-Jun-19 15-Jun-19 T-QAP-DANM-0136 Commented
Page 11 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
222 T-DANM-QAP-0174 QV-1S-VEN-C79-14400917-0001 CAUSE & EFFECT DIAGRAM 0 Process 8-Jun-19 16-Jul-19 T-QAP-DANM-0156 Commented
224 T-DANM-QAP-0176 QV-1S-VEN-Y58-14400917-0002 EDC TANK FOUNDATION DRAWING AND DETAIL 0 Civil 8-Jun-19 13-Jun-19 T-QAP-DANM-0133 Commented
225 T-DANM-QAP-0177 QV-1S-VEN-P54-14400917-0001 DATA SHEET FOR GLOBE VALVE 0 Piping 8-Jun-19 11-Jun-19 T-QAP-DANM-0113 Approved
226 T-DANM-QAP-0177 QV-1S-VEN-P54-14400917-0011 DATA SHEET FOR REGULATING VALVE 0 Piping 8-Jun-19 11-Jun-19 T-QAP-DANM-0113 Approved
227 T-DANM-QAP-0178 00012 METHOD STATEMENT FOR PILING WORKS 3 Civil 9-Jun-19 11-Jun-19 Approved
INSPECTION AND TEST PLAN FOR PILING WORKS ALONG
228 T-DANM-QAP-0179 00036 WITH CHECK LIST FOR PILING WORKS, PILE RECORD 1 QA/QC 9-Jun-19 11-Jun-19 Approved
FORMAT AND SURVEY REPORT FORMAT
234 T-DANM-QAP-0185 QV-1S-VEN-P50-14400917-0001 PIPING MATERIAL SPECIFICATION A Piping 12-Jun-19 13-Jun-19 T-QAP-DANM-0132 Approved
235 T-DANM-QAP-0186 00012 METHOD STATEMENT FOR PILING WORKS A Civil 12-Jun-19 Approved
237 T-DANM-QAP-0054 QV-1S-VEN-Y56-14400917-0002 PILE LAYOUT AND DETAILS OF TEST PILE-SHT 01 TO 04 A Civil 17-Jun-19 17-Jun-19 T-QAP-DANM-0138 Approved
238 T-DANM-QAP-0177 QV-1S-VEN-P54-14400917-0001 DATA SHEET FOR GLOBE VALVE A Piping 17-Jun-19 19-Jun-19 T-QAP-DANM-0113 Approved
239 T-DANM-QAP-0177 QV-1S-VEN-P54-14400917-0011 DATA SHEET FOR REGULATING VALVE A Piping 17-Jun-19 19-Jun-19 T-QAP-DANM-0113 Approved
T-QAP-DANM-0075
240 T-DANM-QAP-0125 QV-1S-VEN-Y60-14400917-0005 FOAM PUMP FOUNDATION DETAILS B Civil 17-Jun-19 23-Jun-19 Commented
(Rev B)
241 T-DANM-QAP-0188 93092-PIP-TQ-0004 PIPING TECHNICAL QUERY 0 Piping 17-Jun-19 23-Jun-19 T-QAP-DANM-0141 Commented
Page 12 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
INSPECTION AND TEST PLAN FOR FABRICATION AND
244 T-DANM-QAP-0137 00032 1 QA/QC 19-Jun-19 4-Jul-19 T-QAP-DANM-0102 commented
INSTALLATION OF TANK AS PER API 650
T-DANM-QAP-0191
245 00046 CV OF PROJECT ENGINEER--CIVIL (Mr. SUMESH) 0 General 19-Jun-19
(Rev 0)
T-DANM-QAP-0160 MECHANICAL DESIGN CALCULATION FOR NEW EDC SALES T-QAP-DANM-0112
246 QV-00-VEN-M16-14400917-0001 2 Mech 20-Jun-19 6-Jul-19 Commented
(Rev 2) TANK (Rev 2)
T-DANM-QAP-0166 T-QAP-DANM-0129
247 QV-1S-VEN-C19-14400917-0002 UTILITY CONSUMPTION LIST 2 Process 20-Jun-19 27-Jun-19 Commented
(Rev 2) (Rev 2)
T-DANM-QAP-0166
93092-PRS-CRS-0006 CRS-UTILITY CONSUMPTION LIST 1 Process 20-Jun-19
(Rev 2)
T-DANM-QAP-0100 T-QAP-DANM-0126
248 QV-00-VEN-M60-14400917-0011 SUPPORT DETAILS & MISC-SHT 01 OF 01 1 Mech 20-Jun-19 23-Jun-19 Commented
(Rev 1) (Rev 1)
T-DANM-QAP-0100 CRS FOR SUPPORT AND MISC DETAILS FOR NEW SALES T-QAP-DANM-0126
93092-MEC-CRS-0003 0 Mech 20-Jun-19 23-Jun-19 Commented
(Rev 1) EDC TANK (Rev 1)
T-DANM-QAP-0112
249 QV-00-VEN-M60-14400917-0007 ROOF NOZZLE DETAILS-SHT 01 OF 01 1 Mech 22-Jun-19 30-Jun-19 T-QAP-DANM-0145 Approved
(Rev 1)
T-DANM-QAP-0108
250 QV-00-VEN-M60-14400917-0003 ROOF PLATE DETAILS-SHT 01 OF 01 1 Mech 22-Jun-19 23-Jun-19 T-QAP-DANM-0142 Approved
(Rev 1)
T-DANM-QAP-0111
251 QV-00-VEN-M60-14400917-0006 SHELL MANWAY DETAILS-SHT 01 OF 01 1 Mech 22-Jun-19 23-Jun-19 T-QAP-DANM-0144 Approved
(Rev 1)
T-DANM-QAP-0106
252 QV-00-VEN-M60-14400917-0001 SHELL PLATE DETAILS-SHT 01 OF 01 1 Mech 22-Jun-19 23-Jun-19 T-QAP-DANM-0143 Approved
(Rev 1)
T-DANM-QAP-0157 PILE DESIGN REPORT FOR EDC SALES TANK WITH
253 QV-00-VEN-Y15-14400917-0001 4 Civil 22-Jun-19
(Rev 4) ATTACHMENTS
T-DANM-QAP-0193 DESIGN BASIS FOR WATER BASED FIRE PROTECTION
254 QV-1S-VEN-F02-14400917-0001 0 Process 23-Jun-19 4-Jul-19 T-QAP-DANM-0149 Commented
(Rev 0) SYSTEM
T-DANM-QAP-0194 TECHNICAL SPECIFICATION OF INTERNATIONAL PAINT
255 00047 0 QA/QC 23-Jun-19
(Rev 0) MATERIALS – FOR PAINTING SYSTEM “GA” AND “C”
T-DANM-QAP-0176 T-QAP-DANM-0133
256 QV-1S-VEN-Y58-14400917-0002 EDC TANK FOUNDATION DRAWING AND DETAIL 1 Civil 23-Jun-19 24-Jun-19 Commented
(Rev 1) (Rev 1)
T-DANM-QAP-0032
257 QV-1S-VEN-Y66-14400917-0001 GENERAL DRAWING NOTES A Civil 23-Jun-19 23-Jun-19 T-QAP-DANM-0139 Approved
(Rev A)
T-DANM-QAP-0195
258 00048 CV OF E&I ENGINEER 0 General 23-Jun-19
(Rev 0)
T-DANM-QAP-0125 T-QAP-DANM-0075
259 QV-1S-VEN-Y60-14400917-0005 FOAM PUMP FOUNDATION DETAILS B Civil 23-Jun-19 25-Jun-19 Approved
(Rev B) (Rev B)
T-DANM-QAP-0138 INSPECTION AND TEST PLAN FOR PIPING FABRICATION T-QAP-DANM-00104
260 00033 1 QA/QC 25-Jun-19 2-Jul-19 Commented
(Rev 1) AND INSTALLATION (Rev 1)
T-DANM-QAP-0192 PILE CAP DESIGN REPORT FOR EDC SALES TANK WITH
261 QV-00-VEN-Y15-14400917-0007 0 Civil 26-Jun-19 2-Jul-19 T-QAP-DANM-0148 Commented
(Rev 0) ATTACHMENT
T-DANM-QAP-0159
262 QV-1S-VEN-Y02-14400917-0001 STRUCTURAL DESIGN BASIS FOR TANK FOUNDATION 2 Civil 26-Jun-19
(Rev 2)
T-DANM-QAP-0027
263 QV-00-VEN-M58-14400917-0001 GA DRAWING FOR NEW SALES EDC TANK 1 Mech 26-Jun-19 6-Jul-19 T-QAP-DANM-0020 Approved
(Rev 1)
Page 13 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
T-DANM-QAP-0101
265 QV-00-VEN-M60-14400917-0009 SPIRAL STAIRWAY DETAILS-SHT 01 TO 04 1 Mech 2-Jul-19
(Rev 1)
T-DANM-QAP-0198 QV-00-VEN-Y15-14400917-
272 CRS - PILE CAP DESIGN REPORT FOR EDC SALES TANK 0 Civil 9-Jul-19
Rev 0 0007_CRS
T-DANM-QAP-0148
195 00018 PROJECT EXECUTION SCHEDULE 3 General 9-Jul-19
Rev 3
T-DANM-QAP-0008
274 QV-00-VEN-E54-14400917-0001 DATASHEET FOR LV CABLE 1 Electrical 13-Jul-19
Rev 1
T-DANM-QAP-0008
275 QV-1S-VEN-E16-14400917-0001 CABLE SIZING CALCULATION 1 Electrical 13-Jul-19
Rev 1
T-DANM-QAP-0166
276 QV-1S-VEN-C19-14400917-0002 UTILITY CONSUMPTION LIST 3 Process 13-Jul-19 14-Jul-19 T-QAP-DANM-0129 Approved
(Rev 3)
Page 14 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
286 T-DANM-QAP-0134 QV-1S-VEN-P56-14400917-0001 PLOT PLAN 4 Piping 15-Jul-19 16-Jul-19 T-QAP-DANM-0105 Commented
287 T-DANM-QAP-0084 QV-1S-VEN-I54-14400917-0005 DATASHEET FOR PRESSURE VACUUM RELIEF VALVE 1 Instrument 15-Jul-19
T-DANM-QAP-0202
288 93092-PEC-MOM-0004 MINUTES OF MEETING 0 General 15-Jul-19
Rev 0
T-DANM-QAP-0201
289 QV-1S-VEN-P16-14400917-0003 STRESS ANALYSIS REPORT SYTEM 3 0 Piping 15-Jul-19
Rev 0
T-DANM-QAP-0166
290 QV-1S-VEN-C19-14400917-0002 UTILITY CONSUMPTION LIST A Process 17-Jul-19 Approved
(Rev A)
METHOD STATEMENT FOR LATERAL LOAD TEST FOR T-QAP-DANM-0157
267 T-DANM-QAP-0183 00026 2 Civil 17-Jul-19 20-Jul-19 Approved
PRELIMINARY TEST PILE dated 20/07/19
T-DANM-QAP-0203 TECHNICAL DATA SHEET OF 2MM HDPE LINER ALONG WITH
268 00053 0 Civil 17-Jul-19
Rev 0 METHOD STATEMENT AND ITP
269 T-DANM-QAP-0008 QV-00-VEN-E50-14400917-0002 SPECIFICATION FOR ELECTRICAL BULK MATERIALS 1 Electrical 17-Jul-19
T-DANM-QAP-0129
270 QV-1S-VEN-E57-14400917-0001 ELECTRICAL EQUIPMENT LAYOUT-SHT 01 OF 01 A Electrical 18-Jul-19 Approved
Rev A
T-DANM-QAP-0039
271 QV-1S-VEN-E81-14400917-0001 HAZARDOUS AREA CLASSIFICATION 1 Electrical 17-Jul-19
Rev 1
272 T-DANM-QAP-0035 QV-1S-TPI-C78-03906-0001 PID FOR EDC STORAGE & LOADING FACILITIES STORAGE 1 Process 17-Jul-19
273 T-DANM-QAP-0035 QV-1S-TPI-C78-03906-0002 PID FOR EDC STORAGE & LOADING FACILITIES STORAGE 1 Process 17-Jul-19
274 T-DANM-QAP-0035 QVC-2V-UD-C78-00026 PID FOR BATTERY LIMIT SALES EDC STORAGE 1 Process 17-Jul-19
275 T-DANM-QAP-0035 QVC-2V-UD-C78-00027 PID FOR INTER-CONNECTION CAUSTIC STORAGE 1 Process 17-Jul-19
276 T-DANM-QAP-0035 QVC-2V-UD-C78-00019 PID FOR SALES GRADE EDC STORAGE TANK 1 Process 17-Jul-19
277 T-DANM-QAP-0035 QVC-1U-VEN-C78-00001 PID FOR INSTRUMENT AIR HEADER 1 Process 17-Jul-19
T-DANM-QAP-0192 PILE CAP DESIGN REPORT FOR EDC SALES TANK WITH
283 QV-00-VEN-Y15-14400917-0007 1 Civil 20-Jul-19
(Rev 1) ATTACHMENT
Page 15 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
T-DANM-QAP-0206
285 93092-PRS-CRS-0009 CRS FOR CAUSE AND EFFECT DIAGRAM 0 Process 20-Jul-19
Rev 0
T-DANM-QAP-0207
286 QV-1S-TPI-C78-03908-001 PID FOR EDC STORAGE & LOADING FACILITIES DRAINAGE 0 Process 20-Jul-19
Rev 0
288 T-DANM-QAP-0162 QV-1S-VEN-Y15-14400917-0005 L-SHAPED WALL DESIGN REPORT A Civil 20-Jul-19 Approved
289 T-DANM-QAP-0171 QVC-2V-UD-C72-00005 PFD FOR SALES EDC- STORAGE 2 Process 20-Jul-19
T-DANM-QAP-0136
290 QV-1S-VEN-C16-14400917-0001 DYKE VOLUME CALCULATION REPORT C Process 20-Jul-19
Rev C
T-DANM-QAP-0169
291 QV-1S-VEN-C16-14400917-0002 PVV SIZING CALCULATION A Process 20-Jul-19
Rev A
T-DANM-QAP-0176
QV-1S-VEN-Y58-14400917-0002 EDC TANK FOUNDATION DRAWING AND DETAIL 2 Civil
(Rev 1)
Page 16 of 51
DOCUMENT REGISTER
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Commented via
email on 14/02/19
Resub Rev 1
For Record
Resub Rev 1
PEC to reply
PEC to reply
Resub Rev 1
Resub Rev 1
Resub Rev 1
Resub Rev 1
Resub Rev 1
Resub Rev 1
Resub Rev A
Page 17 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Resub Rev 1
Resub Rev 1
Resub Rev 2
Resub Rev 1
Resub Rev 1
PEC to reply
PEC to reply
Supereseded
PEC to reply
PEC to reply
PEC to reply
PEC to reply
Resub change to
0043
Resub Rev 1
Resub Rev 1
Resub Rev 1
Page 18 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Resub Rev 2
Resub Rev 1
Resub Rev 1
Commented via
email on 20/03/19
Sub Rev A
Resub Rev 1
PEC to reply
PEC to reply
Resub Rev 1
Resub Rev 1
Cancelled
Cancelled
Page 19 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Cancelled
Cancelled
Cancelled
Cancelled
Resub Rev 2
Resub Rev 1
Resub Rev A
Resub Rev B
Resub Rev 1
Resub Rev 1
Resub Rev 3
Resub Rev 2
Mail reply
Page 20 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Mail reply
Resub Rev A
Resub Rev 1
PEC to reply
Resub Rev 1
Resub Rev 1
Resub Rev 1
Resub Rev A
PEC to reply
Resub Rev A
Resub Rev A
Resub Rev A
Resub Rev A
Resub Rev A
PEC to reply
Resub Rev B
Resub Rev 1
Resub Rev 1
Page 21 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Resub Rev 2
Resub Rev 1
Resub Rev C
Resub Rev 2
Resub Rev 2
Resub Rev 2
Page 22 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Resub Rev 1
AWC, Conditional w/
3rd party
AWC, Conditional w/
3rd party
AWC, Conditional w/
3rd party
AWC, Conditional w/
3rd party
Resub Rev 1
AWC, Conditional w/
3rd party
Resub Rev 1
AWC, Conditional w/
3rd party
AWC, Conditional w/
3rd party
Page 23 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Resub Rev 1
Resub Rev 1
PEC to reply
Resub Rev 2
PEC to reply
Resub Rev B
Page 24 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Resub Rev A
Resub Rev A
Resub Rev 4
Resub Rev 2
Comments Email on
27May19
Resub Rev 1
QAPCO to comment
No need to submit to
QAPCO
PEC to reply
Resub Rev 3
Page 25 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Resub Rev 2
Resub Rev 2
Resub Rev 2
Resub Rev 2
QAPCO to comment
Resub Rev 2
Resub Rev A
QAPCO to comment
PEC to reply
CODE 5
CODE 5
CODE 5
AWC
Page 26 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
PEC to reply
CODE 5
Resub Rev 1
Resub Rev A
Resub Rev A
CODE 5
Resub Rev 2
AWC
AWC/ Qapco to
approved
CODE 5
CODE 5
Page 27 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
CODE 5
Resub Rev 3
CODE 5
PEC to reply
AWC, Conditional w/
3rd party
AWC, Conditional w/
3rd party
AWC, Conditional w/
3rd party
AWC, Conditional w/
3rd party
QAPCO to comment
PEC to reply
Resub Rev 2
Resub Rev 2
AWC, Conditional w/
3rd party
Page 28 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
QAPCO to comment
QAPCO to comment
QAPCO to comment
QAPCO to comment
QAPCO to comment
QAPCO to comment
Approved
Approved
Page 29 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
Resub Rev 5
QAPCO to comment
QAPCO to comment
QAPCO to comment
QAPCO to Approved
QAPCO to comment
QAPCO to comment
QAPCO to comment
QAPCO to reply
QAPCO to comment
QAPCO to comment
QAPCO to comment
QAPCO to comment
QAPCO to comment
QAPCO to comment
QAPCO to Approved
ABSG to reply
QAPCO /
PEC to reply ABS
QAPCO to reply
QAPCO to reply
QAPCO to reply
QAPCO to comment
QAPCO to comment
Page 30 of 51
STRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
QAPCO to comment
QAPCO to comment
QAPCO to Approved
QAPCO to Approved
QAPCO to comment
QAPCO to comment
QAPCO to Approved
Ramachandran to
confirm submission
Prem confirm
submission
Page 31 of 51
DOCUMENT REGISTER
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status Remarks
Date Reply Date
BASIC CALCULATION DETAILS FOR PILE SELECTION
Email from Aly dated
6 T-DANM-QAP-0006 00006 (SUPPORTING DOCUMENT FOR STUDY REPORT FOR PILE 0 Civil 27-Feb-19 28-Feb-19 Commented
28/02/19
FOUNDATION OPTIMIZATION)
21 T-DANM-QAP-0015 QV-1S-VEN-Y15-14400917-0006 STUDY REPORT FOR PILE FOUNDATION OPTIMIZATION 1 Civil 7-Mar-19 12-Mar-19 T-QAP-DANM-0008 Commented Resub Rev 2
23 T-DANM-QAP-0016 00011 METHOD STATEMENT FOR EXCAVATION AND BACKFILLING 0 Civil 9-Mar-19 22-Apr-19 T-QAP-DANM-0048 Commented
Commented
JSA FOR SITE CLEARANCE, REBAR DISMANTLING AND
45 T-DANM-QAP-0029 00017 0 Civil 18-Mar-19 20-Mar-19 Commented via email on
HOUSE KEEPING WORK
20/03/19
COMMENT RESOLUTION SHEET (CRS) FOR STUDY
47 T-DANM-QAP-0031 CRS_QAP-DANM-0002 0 Civil 19-Mar-19 24-Mar-19 T-QAP-DANM-0017 Commented
REPORT FOR PILE FOUNDATION OPTIMIZATION
48 T-DANM-QAP-0032 QV-1S-VEN-Y66-14400917-0001 GENERAL DRAWING NOTES 0 Civil 19-Mar-19 23-Jun-19 T-QAP-DANM-0139 Approved
75 T-DANM-QAP-0049 00013 CONCRETE MIX DESIGN 2 Civil 2-Apr-19 3-Apr-19 T-QAP-DANM-0031 Approved
194 T-DANM-QAP-0147 QV-1S-VEN-Y56-14400917-0003 PILE & PILE CAP DETAILS 0 Civil 15-May-19
Page 32 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status Remarks
Date Reply Date
199 T-DANM-QAP-0152 00038 TEST CERTIFICATE OF REBAR 0 Civil 22-May-19 26-May-19 T-QAP-DANM-0101 Approved
236 T-DANM-QAP-0054 QV-1S-VEN-Y56-14400917-0002 PILE LAYOUT AND DETAILS OF TEST PILE-SHT 01 TO 04 A Civil 17-Jun-19 17-Jun-19 T-QAP-DANM-0138 Approved AWC
220 T-DANM-QAP-0172 93092-PRS-CRS-0007 COMMENT RESOLUTION SHEET (CRS) FOR DESIGN BASIS 0 Civil 8-Jun-19 15-Jun-19 T-QAP-DANM-0136 Commented CODE 5
T-DANM-QAP-0176 T-QAP-DANM-0133
256 QV-1S-VEN-Y58-14400917-0002 EDC TANK FOUNDATION DRAWING AND DETAIL 1 Civil 23-Jun-19 24-Jun-19 Commented Rejected
(Rev 1) (Rev 1)
METHOD STATEMENT OF STATIC LOAD TEST FOR
230 T-DANM-QAP-0181 00024 1 Civil 11-Jun-19 4-Jul-19 T-QAP-DANM-0150 Approved CODE 5
WORKING TEST PILE (COMPRESSION)
METHOD STATEMENT OF STATIC LOAD TEST FOR 6/13/2019 / Ranju to
231 T-DANM-QAP-0182 00025 1 Civil 11-Jun-19 T-QAP-DANM-0118 Approved
PRELIMINARY TEST PILE (COMPRESSION) 04/07/19 Resub Rev A
METHOD STATEMENT FOR LATERAL LOAD TEST FOR T-QAP-DANM-0157
267 T-DANM-QAP-0183 00026 2 Civil 17-Jul-19 20-Jul-19 Approved
PRELIMINARY TEST PILE dated 20/07/19
AWC/ Qapco
235 T-DANM-QAP-0186 00012 METHOD STATEMENT FOR PILING WORKS A Civil 12-Jun-19 Approved
to approved
SAMPLE FOR PVC SPACER COVER BLOCKS 75MM FOR
242 T-DANM-QAP-0190 00045 0 Civil 17-Jun-19 CODE 5
PILING
T-DANM-QAP-0125 T-QAP-DANM-0075
259 QV-1S-VEN-Y60-14400917-0005 FOAM PUMP FOUNDATION DETAILS B Civil 23-Jun-19 25-Jun-19 Approved
(Rev B) (Rev B)
T-DANM-QAP-0159 QAPCO to
263 QV-1S-VEN-Y02-14400917-0001 STRUCTURAL DESIGN BASIS FOR TANK FOUNDATION 2 Civil 26-Jun-19
(Rev 2) comment
T-DANM-QAP-0197 TECHNICAL DATA SHEET OF CONCRETE UNDERGROUND QAPCO to
269 00050 0 Civil 8-Jul-19
Rev 0 PROTECTION MATERIAL (BITUMEN PRIMER) comment
T-DANM-QAP-0197 TECHNICAL DATA SHEET OF CONCRETE UNDERGROUND
270 00051 0 Civil 8-Jul-19 17-Jul-19 T-QAP-DANM-0153 Approved
Rev 0 PROTECTION MATERIAL (BITUMEN MEMBRANE)
T-DANM-QAP-0203 TECHNICAL DATA SHEET OF 2MM HDPE LINER ALONG WITH QAPCO to
268 00053 0 Civil 17-Jul-19
Rev 0 METHOD STATEMENT AND ITP comment
T-DANM-QAP-0204 QAPCO to
280 00054 STATIC LOAD TEST REPORT FOR WORKING PILE 0 Civil 18-Jul-19
Rev 0 reply
Page 33 of 51
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status Remarks
Date Reply Date
T-DANM-QAP-0192 PILE CAP DESIGN REPORT FOR EDC SALES TANK WITH QAPCO to
283 QV-00-VEN-Y15-14400917-0007 1 Civil 20-Jul-19
(Rev 0) ATTACHMENT comment
Page 34 of 51
DOCUMENT REGISTER
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status Remarks
Date Reply Date
QV-00-VEN-E19-14400917- QAPCO to
285 T-DANM-QAP-0008 ELECTRICAL LOAD LIST 1 Electrical 13-Jul-19
0001 comment
QV-00-VEN-E50-14400917- QAPCO to
269 T-DANM-QAP-0008 SPECIFICATION FOR ELECTRICAL BULK MATERIALS 1 Electrical 17-Jul-19
0002 comment
QV-00-VEN-E50-14400917- QAPCO to
282 T-DANM-QAP-0008 SPECIFICATION FOR LV CABLE 1 Electrical 13-Jul-19
0001 comment
Page 35 of 51
DOCUMENT REGISTER
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status Remarks
Date Reply Date
T-DANM-QAP-0202 QAPCO to
288 93092-PEC-MOM-0004 MINUTES OF MEETING 0 General 15-Jul-19
Rev 0 comment
Page 36 of 51
DOCUMENT REGISTER
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status Remarks
Date Reply Date
41 T-DANM-QAP-0025 93092-HSE-TQ-0001 TECHNICAL QUERIES FOR HSE 0 HSE 14-Mar-19 25-Mar-19 T-QAP-DANM-0018 Commented
Approval Email
105 T-DANM-QAP-0074 00022 EMERGENCY RESPONSE PROCEDURE 0 HSE 17-Apr-19 Approved from Eldrin dated
22.4.19
165 T-DANM-QAP-0117 00009 PROJECT HSE PLAN C HSE 2-May-19 6-May-19 T-QAP-DANM-0074 Approved
Page 37 of 51
DOCUMENT REGISTER
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status Remarks
Date Reply Date
SPECIFICATION FOR INSTRUMENT CABLES AND JUNCTION
165 T-DANM-QAP-0173 QV-1S-VEN-I50-14400917-0001 A Instrument 13-Jul-19 14-Jul-19 T-QAP-DANM-0028 Approved
BOXES
CRS-SPECIFICATION FOR INSTRUMENT CABLES AND
166 T-DANM-QAP-0173 93092-INS-CRS-0003 A Instrument 13-Jul-19 14-Jul-19 T-QAP-DANM-0028 Approved
JUNCTION BOXES
QAPCO to
287 T-DANM-QAP-0084 QV-1S-VEN-I54-14400917-0005 DATASHEET FOR PRESSURE VACUUM RELIEF VALVE 1 Instrument 15-Jul-19
comment
T-DANM-QAP-0205 QAPCO to
281 QV-1S-VEN-I56-14400917-0002 F&G DETECTOR LAYOUT 0 Instrument 18-Jul-19
Rev 0 reply
Page 38 of 51
DOCUMENT REGISTER
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status Remarks
Date Reply Date
T-DANM-QAP-0200
282 QV-1S-VEN-S60-14400917-0001 PLATFORM & STAIR DETAILS-SHT 6 TO 9 OF 13 0 Mech 14-Jul-19 15-Jul T-QAP-DANM-0154 Approved
Rev 1
T-DANM-QAP-0200 TYPICAL HANDRAIL & MISC DETAILS FOR PLATFORM &
283 QV-1S-VEN-S60-14400917-0002 0 Mech 14-Jul-19 15-Jul T-QAP-DANM-0154 Approved
Rev 1 STAIR-SHT 1 OF 1
Page 39 of 51
DOCUMENT REGISTER
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status
Date Reply Date
285 T-DANM-QAP-0135 QV-1S-VEN-P58-14400917-0001 EQUIPMENT LOCATION PLAN-SHT 01 TO 02 2 Piping 13-Jul-19
T-DANM-QAP-0201
289 QV-1S-VEN-P16-14400917-0003 STRESS ANALYSIS REPORT SYTEM 3 0 Piping 15-Jul-19
Rev 0
Page 40 of 51
OCUMENT REGISTER
RUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Remarks
QAPCO to
comment
QAPCO to
comment
QAPCO to
comment
Page 41 of 51
DOCUMENT REGISTER
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status Remarks
Date Reply Date
T-DANM-QAP-0169 QAPCO to
291 QV-1S-VEN-C16-14400917-0002 PVV SIZING CALCULATION A Process 20-Jul-19
Rev A Approved
Page 42 of 51
DOCUMENT REGISTER
Contract: 7000010671 – ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING OF NEW SALES EDC TANK IN QAPCO VINYL PLANT
Subm. QAPCO
Sl. No. Transmittal No. Document / Drawing No. Description Rev Discipline QAPCO Trans Status Remarks
Date Reply Date
PROCEDURE FOR SURFACE PREPARATION & PAINTING AT
50 T-DANM-QAP-0034 00010 1 QA/QC 19-Mar-19 23-Mar-19 T-QAP-DANM-0016 Approved
SITE
200 T-DANM-QAP-0153 00039 WELDER SUMMARY AND WELDER CERTIFICATES 0 QA/QC 23-May-19 12-Jun-19 T-QAP-DANM-0120 Commented
Page 43 of 51
SL No Document Description
1 DESIGN BASIS
2 CONTROL AND SAFE GUARDING PHILOSPOHY
3 CONTROL VALVE SIZING
4 ELECTRICAL LOAD LIST
5 SPECIFICATION FOR LV CABLE
6 SPECIFICATION FOR ELECTRICAL BULK MATERIALS
7 DATA SHEETS FOR LV CABLE
8 FIRE FIGHTING DEVELOPMENT VIEWS 5 sheets
9 COORDINATES LAYOUT & PILE LAYOUT (GEOTECHNICAL & TOPOGRAP
10 INSTRUMENTATION INDEX
11 DATA SHEET FLOW INDICATOR
12 MECHANICAL DESIGN CALCULATION (TPI CERTIFICATE)
13 GENERAL ASSEMBLY AND NOZZLE ORIENTATION
14 1st SHELL COURSE NOZZLE MARKING
15 SHELL PLATE DETAIL
16 BOTTOM PLATE DETAIL
17 ROOF PLATE DETAIL
18 ROOF STRUCTURAL DETAIL
19 SHELL NOZZLE DETAIL
20 SHELL MANWAY DETAIL
21 ROOF NOZZLE DETAIL
22 NAME PLATE DETAIL-
23 SPIRAL STAIR WAY DETAIL (3 Sheets)
24 PERIPHERAL HAND RAIL DETAIL DETAIL
25 SUPPORT DETAIL AND MISC
26 INTERNALS
27 PIPE SUPPORT DESIGN (With CRS)
28 DESIGN REPORT / DESIGN CALCULATION FOR BLOWER FOUNDATIO
29 DYKE WALL DESIGN REPORT
30 DESIGN CALCULATION OF FOAM PUMP FOUNDATION
31 DESIGN CALCULATIONS FOR TEMPORARY ACCESS RAMP
32 SCOPE OF WORK FOR PILING / SOIL IMPROVEMENT WORKS / SOW F
33 DYKE WALL EXTENTION DETAIL
34 P&ID EDC STORAGE TANK & LOADING FACILITIES / EXISTING TANK T-3921
35 P&ID EDC STORAGE TANK & LOADING FACILITIES / EXISTING TANK T-3921
36 EQUIPMENT LIST AND LINE LIST
37 UTILITY CONSUMPTION LIST
38 CAUSE AND EFFECT DIAGRAM
39 F&G Cause & Effect Diagram
40 CABLE SIZING CALCULATION
41 ELECTRICAL CABLE SCHEDULE
42 ELECTRIC MATTERIAL TAKE OFF (MTO)
43 LIGHTING LAYOUT / EXISTING LAYOUT
44 ELECTRIC EQUIPMENT LAYOUT
45 CABLE TRENCH SECTION DETAILS
46 EARTHING & GROUNDING LAYOUT DETAIL / EXISTING EARTHING LAY
47 ELECTRIC INSTALLATION DETAILS
48 SINGLE LINE DIAGRAM MODIFICATON MCC
49 SINGLE LINE DIAGRAM MODIFICATON LIGHTING JUNCTION BOX
50 SINGLE LINE DIAGRAM MODIFICATON FOR EMERGENCY LIGHTING
51 CABLE ROUTING DIAGRAMS
52 HAZARDOUS AREA CLASSIFICATION
53 INSTRUMENT CABLE SCHEDULE
54 QV-00-VEN-I18-14400917-0002
55 Fire & Gas Cable Schedule
56 ALARM & TRIP SET POINT LIST
57 IO LIST
58 Fire & Gas IO List
59 INSTRUMENTATION BULK MTO
60 SPECIFICATION FOR INSTRUMENT CABLES AND JUNCTION BOXES
61 DATA SHEET FOR LEVEL TRANSMITTERS
62 DATA SHEET FOR PRESSURE GAUGE
63 DATA SHEET FOR PRESSURE RELIEF VALVE
64 DATA SHEET FOR TEMPERATURE GAUGE
65 DATA SHEET FOR PRESSURE VACUUM RELIEF VALVE
66 DATA SHEET FOR PRESSURE TRANSMITTER
67 DATA SHEET FOR TEMPERATURE TRANSMITTER
68 DATA SHEET FOR ESD VALVE
69 DATA SHEET FOR CONTROL VALVE
70 DATA SHEET FOR RESTRICTION ORIFICE
71 DATA SHEET FOR PUSH BUTTON STATION
72 F&G Interconnection Diagram
73 INSTRUMENT HOOKUP DIAGRAM
74 INSTRUMENT LOCATION PLAN & CABLE LAYOUT DIAGRAM
75 INSTRUMENT INTERCONNECTION DIAGRAM
76 INSTRUMENT CABLE BLOCK DIAGRAM
77 F&G Cable Block Diagram
78 F&G DETECTOR & CABLE ROUTING LAYOUT
79 MECHANICAL BULK MTO
80 STRESS ANALYSIS
81 PIPE SUPPORT SCHEDULE
82 TIE-IN LIST
83 PIPING MATERIAL TAKE-OFF PIPING (MTO)
84 PIPING MATERIAL SPECIFICATION
85 DATA SHEET FOR GLOBE VALVE
86 DATA SHEET FOR GATE VALVE
87 DATA SHEET FOR CHECK VALVE
88 DATA SHEET FOR BALL VALVE
89 DATA SHEET FOR BUTTERFLY VALVE
90 DATA SHEET FOR PLUG VALVE
91 DATA SHEET FOR STRAINER
92 DATA SHEET FOR EXPANSION BELLOW
93 DATA SHEET FOR FLAME ARRESTOR
94 DATASHEET FOR DELUGE VALVE
95 DATASHEET FOR DELUGE VALVE
96 DATASHEET FOR FOAM POURER
97 DATASHEET FOR FOAM POURER WITH CHAMBER
98 DATASHEET FOR FOAM INLINE MIXER
99 PIPING PLOT PLAN
100 PIPING KEY PLAN
101 L-SHAPED WALL DETAIL
102 EQUIPMENT LOCATION / LAYOUT PLAN ( 2 Sheet)
103 PIPING GENERAL ARRANGEMENT DRAWING 12 Sheets
104 PLATFORM AND STAIR DETAILS( 5 Sheet)
105 TYPICAL HAND RAIL AND STAIR DETAILS( 2 Sheet)
106 PIPE SUPPORT DETAILS (With CRS)
107 ACESS PLATFORM DETAILS (3 Sheets)
108 L-SHAPED WALL DESIGN REPORT
109 BAR BENDING SCHEDULE
110 BAR BENDING LAY OUT
111 MATERIAL TAKE-OFF (CIVIL)
112 FOUNDATION PLAN
113 Design Report for Tank Foundation
114 PILE MARKING LAYOUT DRAWINGS
115 TEMPORARY ACESS RAMP DESIGN AND DETAILS
116 BLOWER FOUNDATION, SUCTION PIT AND DETAILS Sht 2 & 3( suction pit
117 FOAM PUMP FOUNDATION DETAIL
118 ISOMETRIC DRAWINGS
119 SCHEMATIC DIAGRAM SALES GRADE EDC STORAGE TANK
120 PROCESS FLOW DIAGRAM
121 P&ID OF NEW SALES EDC TANK 2-3901
122 P&ID NO: 2-0015 BATTERY LIMIT SALES EDC STORAGE
123 P&ID NO: 2-0016 INTER-CONNECTION PID SALES EDC /CAUSTIC STO
124 P&ID EDS OF EXISTING TANK T-39210 FIRE FIGHTING FOAM SYSTEMS
125 P&ID EDS OF EXISTING TANK T-39210 FIRE FIGHTING WATER SPRAY
126 P&ID OF NEW SALES EDC TANK FIRE FIGHTING UNDERGROUND TIE-I