Professional Documents
Culture Documents
20191007-Procare Remaining - Cost Plan Report-Rev0 PDF
20191007-Procare Remaining - Cost Plan Report-Rev0 PDF
20191007-Procare Remaining - Cost Plan Report-Rev0 PDF
AL – KHOBAR, K.S.A.
Prepared by:
Table of Contents
Table of Contents ......................................................................................................................................... 2
1 Foreword .............................................................................................................................................. 4
1.1 Synopsis........................................................................................................................................ 4
1 Introduction ......................................................................................................................................... 5
1.1 About the Project ......................................................................................................................... 5
1.1.1 The Project ........................................................................................................................... 5
1.2 Chronological Major Events of the Project ................................................................................ 6
2 Executive Summary ............................................................................................................................. 7
2.1 Project Description ...................................................................................................................... 7
2.2 Key Stakeholders ......................................................................................................................... 8
2.2.1 Employer (First Party); ....................................................................................................... 8
2.2.2 Contractor (Second Party);.................................................................................................. 8
2.2.3 Project Manager Consultant (the Project Manager) ......................................................... 8
2.2.4 Design Consultant (the Designer) ...................................................................................... 8
2.2.5 Supervision Consultant (the Engineer); ............................................................................ 8
2.2.6 Interior Design Consultant; ................................................................................................ 8
3 Scope of Service (C/o Ihab) ................................................................................................................ 9
3.1 Contracts Review and Recommendations ................................................................................. 9
3.2 Completed and Balance of Works Technical Evaluation .......................................................... 9
3.3 Financial Evaluation .................................................................................................................... 9
3.4 Outstanding due payment & Cost of Balance of Work Budget ................................................. 9
4 Project Current Status ....................................................................................................................... 10
4.1 Site Observation......................................................................................................................... 10
4.1.1 Architectural Works .......................................................................................................... 10
4.1.2 Structural Works ............................................................................................................... 15
4.1.3 Electrical Works................................................................................................................. 19
4.1.4 Mechanical Works ............................................................................................................. 25
4.2 Signed Contract Status .............................................................................................................. 30
4.2.1 The Project Management Contract (PMC): ...................................................................... 30
4.2.2 The Supervision Consultant Contract; ............................................................................. 31
4.2.3 Main Contractor ................................................................................................................. 32
4.2.4 Nominated MEP Subcontractor Contractor ..................................................................... 34
4.2.5 The Design Service Contract: ............................................................................................ 35
5 Projection to Completion .................................................................................................................. 36
5.1 Technical Valuation ................................................................................................................... 36
5.1.1 Architectural Valuation ..................................................................................................... 36
5.1.2 Structural Valuation .......................................................................................................... 36
5.1.3 Electrical Valuation ........................................................................................................... 36
5.1.4 Mechanical Valuation ........................................................................................................ 36
5.2 Commercial Valuation ............................................................................................................... 37
5.2.1 Closure of Existing Contracts ............................................................................................ 37
1 Foreword
1.1 Synopsis
RICHMOND ENGINEERING AND MANAGEMENT has been appointed by PROCARE RIAYA HOSPITAL
(Employer) as the Cost & Technical Consultant (CTC) an aimed to advise contractually, financially and
technicality the Employer for the project to complete from its current state which was stop of construction
activities last xx Nov. 2016.
The major part of Richmond assignments is to a prepare Cost Plan Report based on the on site
verifications, documets and outstanding contracts, financial and techincal of the project as its current
state.
This Cost Report is intended to put in record the current project’s status in terms of;
i. Technical Aspect (current state work done and future plans)
ii. Contractual Aspect
iii. Financial Outstanding & Commercial Evaluation
iv. Recommendations
All the above aspects have been taken and attended properly as to the professional way and means with
the analytical studies and careful assessment of the project.
For any queries on this report, please contact the undersigned.
Ihab Z. Abbas
Chief Executive Officer
1 Introduction
1.1 About the Project
2 Executive Summary
2.1 Project Description
Project Name: Procare Riaya Hospital Expansion Project
Al Khobar, Kingdom of Saudi Arabia
Project Description: The Expansion of the Procare Riaya Hospital is to be develop in
Al-Khobar. The Hospital expansion building consist of the
following;
• Basement level, Ground Floor and seven (7) above ground
floors.
• Total Build-up=17,887m2
• 75 hospital beds (1 Royal Suite, 4 VIP Suite, 70 beds)
• 36 Clinics
• Administration offices, maintenance, IT and security
departments.
• 144 Parking Slot
Employer: Procare Riaya Hospital
Project Manager: Fuad AI-Salah & Associates Consulting Engineering Co.
Design Consultant: (Projacs)
Supervision Consultant: Suhaimi Design
Main Contractor: Otaishan Consulting Engineers
Nom. MEP Sub-contractor: Project Build General Contracting Co, Ltd.
Saudi Taab Construction
Type of Contract: Fixed Lump Sum –FIDIC based
Initial Construction Cost: SAR 100,761,459.00(Cast in-situ Beams & Columns w/ Precast Slab)
(Alternative Structural System SAR 99,500,000- Flat Slab in
lieu of Precast Slab.)
Contract Sum: SAR 115,948,959.00 (Excl. VAT)
Approved Variation Orders: SAR 420,119.35
Revised Contract Sum SAR 116,369,078.35
Original Contract Period : 490 Calendar days
Start Date: 27 February 2014
Original Completion Date: 01-July 2015
Provisional EOT: 70 Calendar Days
Revised Completion Date: 09 September 2015
Current Construction Status: Work Suspended by the Contractor
Contract Status Contract Terminated as per Sub-clause 16.1[ Contractor’s
Entitlement to Suspend Work ] & 16.2 [Termination by
Contractor]
Note: The Contractual Completion Period data was taken from the last PMC Monthly Report on November
2016.
To perform the review the contracts of all the parties involved in the project and recommends to
Procare Riaya Hospital the suitable approach and action for the smooth continuation of the Project.
3.2 Completed and Balance of Works Technical Evaluation
To evaluate the completed works in terms of Technical integrity of the completed systems for the
incorporation and performance of the balance of works with due consideration on the more than three
(3) years of exposure of the completed works of harsh environment
3.3 Financial Evaluation
To evaluate and allocate budget for the financial closure of all the parties involved in the project
3.4 Outstanding due payment & Cost of Balance of Work Budget
To prepare the detailed cost estimate for budgetary purposes for the continuation of the construction.
CURRENT BALANCEE
S.N LEVEL WORK DESCRIPTION REMARKS
WORK % WORK %
Floor screed 10% 90%
Masonry works 80% 20%
DECK Gypsum partition 10% 90% Bad condition
9
FLOOR Plastering works 15% 85%
Floor screed 10% 90%
UPPER Masonry works 90% 10%
10 ROOF
FLOOR Plastering works 25% 75%
EXTERNAL Pre-cast Conc. Cladding 85% 15%
11
FINSISH
Note:
o The site are very dirty, full of rubbished materials, dusty and dead animals, the gypsum
partitions are damaged due to prolong exposure of harsh environment condition.
o All other works are not yet started.
Note:
o Some exposed and unprotected water proofing are damage. Exposed reinforcing steel are very
rusty.
o All other works are not yet started.
CURRENT BALANCEE
S.N LEVEL WORK DESCRIPTION REMARKS
WORK % WORK %
Fire Alarm Systems 35% 65%
CATV System 35% 65%
Centralized Clock Systems 35% 65%
CCTV system 35% 65%
Security Access Control 35% 65%
Voice & Data Internet Protocol 15% 85%
Perforated Cable tray system 100% 0%
Public Address system 15% 85%
Grounding system & Lightning
90% 10%
protection system
Lighting & power installation 100% 0%
Fire Alarm Systems 35% 65%
CATV System 35% 65%
Centralized Clock Systems 35% 65%
CCTV system 35% 65%
6 4TH FLOOR Security Access Control 35% 65%
Voice & Data Internet Protocol 15% 85%
Perforated Cable tray system 100% 0%
Public Address system 15% 85%
Grounding system & Lightning
90% 10%
protection system
Lighting & power installation 100% 0%
Fire Alarm Systems 35% 65%
CATV System 35% 65%
Centralized Clock Systems 35% 65%
CCTV system 12% 88%
7 5TH FLOOR Security Access Control 35% 65%
Voice & Data Internet Protocol 15% 85%
Perforated Cable tray system 65% 35%
Public Address system 15% 85%
Grounding system & Lightning
90% 10%
protection system
Lighting & power installation 100% 0%
Fire Alarm Systems 35% 65%
CATV System 35% 65%
Centralized Clock Systems 15% 85%
CCTV system 0% 100%
8 6TH FLOOR Security Access Control 35% 65%
Voice & Data Internet Protocol 15% 85%
Perforated Cable tray system
Public Address system 15% 85%
Grounding system & Lightning
90% 10%
protection system
Lighting & power installation 100% 0%
Fire Alarm Systems 35% 65%
DECK
9 CATV System
FLOOR
Centralized Clock Systems 15% 85%
CCTV system 0% 100%
Procare Hospital Expansion Project
Cost Plan for Remaining Works to Complete October 2019 Page 20 of 64
PROCARE RIAYA HOSPITAL EXPANSION
AL – KHOBAR, Kingdom of Saudi Arabia
CURRENT BALANCEE
S.N LEVEL WORK DESCRIPTION REMARKS
WORK % WORK %
Security Access Control 35% 65%
Voice & Data Internet Protocol 15% 85%
Perforated Cable tray system
Public Address system 15% 85%
Grounding system & Lightning
90% 10%
protection system
Lighting & power installation 100% 0%
Fire Alarm Systems
CATV System
Centralized Clock Systems
UPPER CCTV system 0% 100%
10 ROOF Security Access Control
FLOOR Voice & Data Internet Protocol
Perforated Cable tray system
Public Address system
Grounding system & Lightning
0% 100%
protection system
Note:
o Installed Electrical works are exposed to prolong period, thus develop thickly dust condition and
some bird’s nest are scattered in the work.
o Some cable trays are not properly coordinated. Installed wiring are not properly protected.
o All other works are not yet started.
CURRENT BALANCEE
S.N LEVEL WORK DESCRIPTION REMARKS
WORK % WORK %
Plumbing Installation 0% 100%
UPPER Medical Gas
10 ROOF Fire Protection 0% 100%
FLOOR HVAC pipe work 33% 67%
Duct & air distribution system 10% 90%
Note:
o Installed Mechanical works are exposed to prolong period, thus develop thickly dust condition
and some bird’s nest are scattered in the work.
o Some all HVAC duct are not properly protected, insulations are damage & dust are entered into
the duct.
o Chilled water piping are very rusty condition, proper treatment & flushing has to be done prior
to resume of any works.
o Medical gas pipe are not protected.
o All other works has not been started.
The Project Manager Consultancy Service for Procare Raiya Hospital Expansion project was entered
into agreement between each of the Procare Riaya Hospital, referred to as “the Employer” and Fuad
AI-Salah & Associates Consulting Engineering Co. (Projacs) referred to as “the Project Manager” to
provide Project Management Consultancy Services for the Procare Riaya Hospital Expansion Project, Al
Khobar, Kingdom of Saudi Arabia, hereinafter referred to as the "Project" on 16th April 2013. Project
Management Consultancy Service contract of a) Value Engineering and Design Review with 2 months
period, b) Tender Management Service with 4 months period and c) Construction Management
Consultancy Service with 18 months Construction phase duration.
A. Advantage of Option 1
1- The PMC familiar the project and advantage of being aware of the project’s conditions.
2- M/s PRH will be spare of contractual dispute (if any).
3- M/s PRH will be spare in taking re-Tender of PMC.
4- Avert any delay due to re-appointment of new PMC.
5- M/s Projacs has been familiar with the design of the project.
B. Dis-advantage of Option 1
1- The PMC staff who engage in the project will not be available, thus new staff will be
expected to be deploy.
2- Extension of the PMC (M/s Projacs) associated cost may be charge to Contractor or
Employer.
4.2.1.2.2 Option 2- Terminate PMC (M/s Projacs) & appoint new PMC
A. Advantage of Option 2
1- Fresh start of the project and will eliminate the previous problems in project
management.
2- If any new changes in the design will be reviewed thoroughly as per new requirements.
3- M/s PRH will select new PMC through Tender a capable contractor to complete the
project.
B. Dis-advantage of Option 2
1- The PMC (M/s Projacs) may resort to Contractual dispute.
2- The project will be high risk of resumption delay, due to tedious progress of re-Tendering
and appointment of new PMC for the project.
The supervision of the works was entered into agreement on 18th August 2013 between each of the
Procare Riaya Hospital, referred to as “the Employer” (“the First party”) and Otaishan Consulting
Engineers referred to as “the Supervision Consultant” for the Consultancy Supervision Services for
Procare Riaya Hospital Expansion referred as “the Project.” The Supervision Consultant shall perform
as the Engineer in the Main Contractor’s Contract. Supervision Consultant contract commence on 18th
August 2013 for a duration of 16 months. Contractual Supervision Start on 22 October 2013.
A. Advantage of Option 1
1- The Supervision Consultant has familiarized the project and taking advantage of the
available resources and aware of the project’s conditions.
2- M/s PRH will be spare of any contractual dispute (if any).
3- M/s PRH will be spare in taking re-Tender of Supervision Consultant.
4- Avert any delay due to re-appointment of new Consultant.
5- Status of technical submittals will be remain as approved.
B. Dis-advantage of Option 1
1- The previous Supervision Consultant staff might not be available, thus deployment of new
staff.
2- M/s PRH will face same fate of the project as the Consultant performance in the project.
3- Extension of the Supervision Consultant (M/s OCE).
4.2.2.2.2 Option 2- Terminate Supervision Consultant (M/s OSE) & appoint new Engineer
A. Advantage of Option 2
1- Fresh start of the project and will eliminate the previous problems.
2- M/s PRH will select Supervision Consultant through Tender with capability to supervise
the works to the completion of the project.
B. Dis-advantage of Option 2
1- The Supervision Consultant (M/s OCE) may resort to Contractual dispute (if any).
2- The project will be high risk of resumption delay, due to tedious progress of re-Tendering
and appointment of new Supervision Consultant for the project.
The construction of Procare Raiya Hospital Expansion project entered into agreement between
Procare Riaya Hospital, referred to as the Employer (“the First party”) and Project Build General
Contracting Co, Ltd. referred to as Contractor (“the Second party”) on 23 October 2013 with a Fixed
Lump Sum Contract in accordance with the Contract conditions, specifications, plans and documents as
well General Conditions of Contract shall be the "Conditions of Contract for Construction for Building
and Engineering Works Designed by the Employer", First Edition 1999 published by the Fédération
Internationale des Ingénieurs-Conseils (FIDIC). The project site handing-over was done and accepted
by the Contractor on 27 February 2014 for a Contract Term of 490 calendar days.
B. Dis-advantage of Option 1
1- The Contractor has been known to have been at blink of Bankruptcy, thus the project at
risk of catastrophic effect if does happened.
2- The Contractor will open its claims of associated cost due to delays.
3- The project will be high risk of delay, if Contractor will maintain its rate of progress due to
lack of effective management, technical staff, financing and resources.
4- M/S PRH will face same fate of the project as the Contractor has no capability to continue
the project, mainly as it has not enough financial resources to procure materials and
deploy manpower, to hire suppliers as well.
4.2.3.2.2 Option 2- Terminate Contractor (M/s PBC) & appoint new Contractor
A. Advantage of Option 2
1- Fresh start of the project and will eliminate the previous problems.
2- M/s PRH will select through Tender a capable Contractor to complete the project.
B. Dis-advantage of Option 2
1- The Contractor (M/s PBC) may resort to Contractual dispute resulting to litigation and
will claim loss of profit.
2- The project will be high risk of more delay, due to tedious progress of re-Tendering and
appointment of new Contractor for the project.
3- Completed work has to be undertaken by the new Contractor.
4- Resubmission of all Technical submissions (shop drawings, material & sample submittals,
and sub-contractor/supplier.
5- Audit of the work done will be tedious prior the start of the new Contractor.
The Procare Raiya Hospital nominated on 09 August 2014 as sub-contractor for the agreement
between Project Build General Contracting Co, Ltd, referred to as the Employer (“the Main
Contractor”) and Saudi Taab Contracting Co. Ltd. referred to as Contractor (“the nominated sub-
contractor”) on 10 August 2014 with a Fixed Lump Sum Contract in accordance with the Contract
conditions, specifications, plans and documents as well General Conditions of Contract shall be the
"Conditions of Contract for Construction for Building and Engineering Works Designed by the
Employer", First Edition 1999 published by the Fédération Internationale des Ingénieurs-Conseils
(FIDIC). M/s STC mobilized at the site on 15 August 2014.
A. Advantage of Option 1
1- The MEP sub-contractor has already mobilized on site taking advantage of the available
resources and aware of the project’s conditions.
2- M/s PRH will be spare of any contractual dispute (if any).
3- M/s PRH will be spare in taking re-appointment MEP sub-contractor of the project.
4- Avert any delay due to re-appointment of new MEP sub-contractor.
5- Status of technical submittals will be remain as approved.
6- Liability of the completed work will not be complicated.
B. Dis-advantage of Option 1
1- The sub-contractor will open the previous claims of associated delays (if any).
2- Previous staff might not be available, thus deploying fresh staff.
3- The project will be high risk of delay, if Contractor will maintain its rate of progress.
4.2.4.2.2 Option 2- Terminate Contractor (M/s STC) & appoint new MEP Contractor
A. Advantage of Option 2
1- Fresh start of the project and will eliminate the previous problems.
2- M/s PRH will select through Tender a capable MEP sub-contractor to complete the
project.
B. Dis-advantage of Option 2
1- The MEP sub-contractor (M/s STC) may resort to Contractual dispute.
2- The project will be high risk of more delay, due to tedious progress of re-Tendering and
appointment of new MEP Sub-contractor for the project.
3- The liability of the completed MEP works will be complicated.
4- Audit of the work done will be tedious prior the start of the new MEP sub-contractor.
The Design Consult Contract Agreement was entered into agreement on 11th September 2011 between
the Procare Riaya Hospital referred to as “the Owner” and Sahaimi Design referred as the “the
Design Consultant to perform the design and prepare Tender Documents for the Proposed Procare
Raiya Hospital Expansion.
Note:
5 Projection to Completion
5.1 Technical Valuation
5.1.1 Architectural Valuation
Note:
A. The above valuation amount excluding the following:
1. Completed Variations or Claims Submitted by the Contractor pending or yet to be approved.
2. Work done not certified beyond 15th March 2016.
B. The release of retention money shall be done upon the Contractor submitted an undertaking letter
acknowledging the work done.
C. Retention is recommended to be release in six (6) equal installment payments.
D. The value of work done shall be verified by a third party (duly registered QS Company).
E. Work done shall be supported by the Engineer’s approved ITR’s.
F. Value of Materials shall be supported by the Engineer’s approved DTR’s.
G. Temporary facilities shall be remain on site for the new Contractor utilization, however the value of the
facilities shall be agreed upon with the M/s PBC.
Note:
A. The above valuation amount excluding the following:
1. Completed Variations or Claims Submitted by the sub-contractor pending or yet to be approved.
2. Work done not certified beyond 15th March 2016.
B. The release of retention money shall be done upon the Contractor submitted an undertaking letter
acknowledging the work done.
C. The value of work done shall be verified by a third party (duly registered QS Company).
D. Work done shall be supported by the Engineer’s approved ITR’s.
E. Value of Materials shall be supported by the Engineer’s approved DTR’s.
Note:
A. The release of retention money shall be done upon the new Project Management Consultant submitted an
undertaking letter with full responsibility of the project management.
B. Retention is recommended to be release in four (4) equal installment payments.
Note:
A. The release of retention money shall be done upon the new Supervision Consultant submitted an
undertaking letter full responsibility of the work done and balance of work.
B. Retention is recommended to be release in four (4) equal installment payments.
5.2.2.2 Assumptions
Relevant in
S.N. Elements /Descriptions Assumption
Estimate
1. The existing temporary facilities Asummed free of charge General
will be utilized by the New Preliminaries
Contractor.
2. No unpaid utility bills from the Asummed no hidden General
previus Contractor charges Preliminaries
3. Rerouting of existing utiliy lines Assumption that no re- Site Works
routing works
4. Pre-cast Concrete Cladding Assumption only balance Concrete Works
fabrication of work is the installation
5. Treatment of cracks on installed Included in the cost of Masonry Works
masonry. repair
6. Defective and delafidated exposed Assumption to be Thermal &
waterproofing membrane included in the repair. moisture
protection works
7. Removal & replacement of Installed Assumption 80% of the Finishings
Gypsum Boards & insulations for completed works
Partions
8. Unprotected Gypsum board Assumption not to be Finishings
material on site which are exposed used
to extrem weather.
9. Installed Aluminum profile to be Assumption included in Windows
removed and replaced the repair and balance of
works.
10. Repairs of al installed HVAC ducts, Assumption only , actual Mechanical works
pipes & devices cost of repair will be done
by Technical evaluation
11. Repairs of al installed conduits, Assumption only , actual Electrical works
cables trays, wiring & etc. cost of repair will be done
by Technical evaluation
12. All completed works are accepted Assumption no rejected All completed
by the Engineer works works
13. All protected materials on site could Assumed to be in good Materials on site
be used in the project conditions
14. All unprotected materials on site Assumed no in good Materials on site
shall be removed. condition
15. All recorded work completed are Assumption no rejected All completed
accepted by the Engineer works works
5.2.2.3 Exclusions
Relevant in
S.N. Elements /Descriptions Exclusions
Estimate
1. Demolition of existing Utility Demolition works Site Works
Building area concrete structure as
per demarcated line
2. Backfilling & compaction on the No backilling on demolish Site Works
demolished concrete structure. area
3. Exposed reinforcing steel & inserts Cleaning or rush Concrete Works
corrosion cleaning converssion excluded
4. Pouring lift, bonding of new concrete Concrete bonding agent Concrete Works
to old concrete. work
5. Replace of embedded water stop if New water stops Concrete works
found defective.
6. Wood & Plastic works(e.g. kitchen Exlcuded in main works, Division 6
cabinets, nurse stations, receiption however included in the ID
counters, build-in closet, serving works
counter & etc.)
7. Cubicle curtain track & curtains Excluded, part of Owner’s Specialty works
Furnished Materials (OFM)
8. Identification devices & signages: Excluded in the estimate Specialty works
9. Laboratory benches & caseworks: Excluded , part of Owner’s Specialty works
Furnished Materials (OFM)
10. Kitchen equipment: Excluded , part of Owner’s Equipment
Furnished Materials (OFM)
11. Cold/ freezer storage room: Excluded , part of Owner’s Equipment
Furnished Materials (OFM)
12. Energy recovery units & pipe Excluded HVAC works
jacketing
13. Ecterior Signage, Bollard & Floor Excluded Electrical Works
mounted lightings
TOTAL FOR I 11.74% 14,133,139.28 2,639,623.02 2,510,119.89 2,510,119.89 2,510,119.89 1,981,578.30 1,981,578.30 - - - - - - - - -
I MAIN WORKS
* ADVANCE PAYMENT 2.88% 3,463,181.50 10% 3,463,181.50 100.0
DIV.8 DOORS AND WINDOWS 6.24% 7,517,175.00 12 501,145.00 501,145.00 501,145.00 501,145.00 501,145.00 501,145.00 501,145.00 501,145.00 501,145.00 501,145.00 501,145.00 501,145.00
77.84%
DIV.9 FINISHES 9.56% 11,512,075.00 12 767,471.67 767,471.67 767,471.67 767,471.67 767,471.67 767,471.67 767,471.67 767,471.67 767,471.67 767,471.67 767,471.67 767,471.67
TOTAL FOR MAIN WORK 28.76% 34,631,815.00 3,463,181.50 2,642,969.00 2,642,969.00 2,447,603.00 1,803,727.00 2,162,343.00 2,314,129.00 2,314,129.00 2,314,129.00 2,433,811.00
6.86%
2,209,881.00 2,209,881.00 2,209,881.00 1,731,590.75 1,731,590.75
58.07%
II MEP WORKS 6.67% 6.67% 6.67%
** MEP ADVANCE PAYMENT 3.37% 4,064,280.50 10% 4,064,280.50 6.32% 6.24% 6.24%
* RELEASE OF RETENTION 3.37% 4,064,280.50 10% 51.83% 2,032,140.25 2,032,140.25
5.84%
*** MEP PRELIMINARY 0.33% 399,445.00 12 26,629.67 26,629.67 26,629.67 26,629.67 26,629.67 26,629.67 26,629.67 26,629.67 26,629.67 26,629.67 26,629.67 26,629.67
DIV.15 A MECHANICAL - PLUMBING 7.15% 8,608,205.00 12 573,880.33 573,880.33 573,880.33 573,880.33 573,880.33
45.99%
573,880.33 573,880.33 573,880.33 573,880.33 573,880.33 573,880.33 573,880.33
DIV.15B MECHANICAL - FIRE PROTECTION 1.31% 1,578,425.00 12 105,228.33 105,228.33 105,228.33 105,228.33 105,228.33 105,228.33 105,228.33 105,228.33 105,228.33 105,228.33 105,228.33 105,228.33
DIV.15C MECHANICAL - HVAC 9.30% 11,199,795.00 12 746,653.00 746,653.00 746,653.00 746,653.00 746,653.00 746,653.00 746,653.00 746,653.00 746,653.00 746,653.00 746,653.00 746,653.00
PIII # 03 FURNITURE AND PARTITIONS WORKS 2.87% 3,459,985.00 6 461,331.33 461,331.33 461,331.33 461,331.33 461,331.33 461,331.33
OTR.1 ALLOW BUDGET FOR CHANGE IN PROGRAM 1.87% 2,249,710.75 12 168,728.31 168,728.31 168,728.31 168,728.31 168,728.31 168,728.31 168,728.31 168,728.31 168,728.31 168,728.31 168,728.31 168,728.31
OTR.2 ALLOW CONTENGENCY 7.47% 8,998,843.00 12 674,913.23 674,913.23 674,913.23 674,913.23 674,913.23 674,913.23 674,913.23 674,913.23 674,913.23 674,913.23 674,913.23 674,913.23
TOTAL FOR OTHER 13.54% 16,310,402.94 449,942.15 1,153,448.07 1,153,448.07 1,143,679.77 1,111,485.97 1,170,788.15 1,178,377.45 1,201,444.02 1,201,444.02 1,237,223.62 1,226,027.12 1,226,027.12 1,226,027.12 815,520.15 815,520.15
TOTAL CONSTRUCTION COST TO COMPLETE 100% 120,431,972.22 12,088,408.17 9,016,057.30 9,016,057.30 8,810,923.00 7,606,311.61 8,851,657.28 7,029,454.28 7,513,852.18 7,513,852.18 8,265,223.78 8,030,097.28 8,030,097.28 8,030,097.28 5,314,941.65 5,314,941.65
Commutative Monthly Schedule of Works 12,088,408.17 21,104,465.46 30,120,522.76 38,931,445.75 46,537,757.36 55,389,414.65 62,418,868.93 69,932,721.11 77,446,573.29 85,711,797.08 93,741,894.36 101,771,991.64 109,802,088.93 115,117,030.57 120,431,972.22
Projected Monthly Schedule of Works % 10.04% 7.49% 7.49% 7.32% 6.32% 7.35% 5.84% 6.24% 6.24% 6.86% 6.67% 6.67% 6.67% 4.41% 4.41%
Commutative Monthly Schedule of Works % 10.04% 17.52% 25.01% 32.33% 38.64% 45.99% 51.83% 58.07% 64.31% 71.17% 77.84% 84.51% 91.17% 95.59% 100.00%
Projected Monthly Cash Flow Amount 12,088,408.17 9,016,057.30 9,016,057.30 8,810,923.00 7,606,311.61 8,851,657.28 7,029,454.28 7,513,852.18 7,513,852.18 8,265,223.78 8,030,097.28 8,030,097.28 8,030,097.28 5,314,941.65 5,314,941.65
Commutative Monthly Cash Flow Amount 12,088,408.17 21,104,465.46 30,120,522.76 38,931,445.75 46,537,757.36 55,389,414.65 62,418,868.93 69,932,721.11 77,446,573.29 85,711,797.08 93,741,894.36 101,771,991.64 109,802,088.93 115,117,030.57 120,431,972.22
6 Annexes
6.1 Annex I- Signed Contracts
(I~J
30·li:rl)v·n
.31·Der.·B 26·l,;n-l~
' 3'530.l)l)j
73,792.29 If}-Feb·lt:l 2S·Fe!)·14 See- nQ-te.1-oo~',·
:n·lan·14 21J·AIH-14 7G, B0.71 7~}~23. 1)1·M:w-14 7l'324'23.,t 28-MtlY·14 6 AJleod
28-Fel>·14 28·Ap r ·l~ ( 1,500,00) 61)lI)l),OO 3 710.1)1) 1)1·tII.itji-14 5$,710.1)0 2B·May·14
31·Mar·ll:l 28·Aj)f·14 Wf»oor 61,800.00 58,111).01) 1)7-tJ1,1<'{ -14 53. 710.00 23-M ,~y·lt1
8
7 "'''fd
AfteCld
01·Apr-14 30·AI)r-14 30·At>r· l~ 118,646.15 71.14G.15 G.7'588i84 l1Hftw-lt:1 137,5-88.84 30-M<'IV-18 ~Sl.:n ~ A/re(1d
1)1~M<lY-14 31-May,·14 IRJun·14
125'500'OO ~
,Ifl.OO,IIj 78,OOO.t)l) r 74,101).1)1) 11~J lJn.lt:1 74,100.00 01l·JI)I·14 · O!t.'j()(),G<) 10 AllI~""
OHm·'· 1
01·M·14
31)·Juo·14
J.l ·hll·}q
03-Jul-101
lO·Aua.-l~
125,500.QO
120,7~
78.,000.1)1)
73, 24.!1.00
74 , 1~ _~l·Jul .tQ
11l:-r\ll~'lQ !
1)9,S8:1.l3f)
14,!i)I).I)1)
69..58:1.80 t 02.A~g.14
09-Sep·14
:~,11(4). m
.~,.,..:. ..:::-
(.fgjIkMIId-SI.!t!II'O'tl!$bq/OW·
(SJ Bahind· Srre llo-II!-~ ffflto-I't'
t.>l~7 I 18:-$1: 1)·14
j
Ol·Aug·14 31·Allg-14 Ol·Sep-N ,130.60)
1!3,976.92 65,7~.n 62.45-9.57 oroct· 14 ( 1 (J~ftiftrJ. Si!e notp.s f1.P.k>tY· 1
Ol·Sep·14
01·O~t·14
.3D·Sel)·ll1
31 ·0ct·14
Ol-O(t-14
OG·Nov·14,
125,500.00
129,519.00
125,500.00
129, 519.00
11').225.00
123,i)~3.05
1~·!j,:~·1~
1li.. N\)v-14
119.22.,>.1)1) QH.lov·lt1 "'' ' ' > f
3:,281i..5i!.
1),2:75.1)1). (Jeflimt· Sep. llorf.!S lil1fQW '
::~~
118,069.00 118,OG9:Q1) ill,165o.S5 1 Allend 1
OI-Oec-14 31·Dec·14 21·J3n-15 142,9-U.~ 142,943.:50 135, 79S.6:S f)')·F\O-[:.·15 13S'795'85 ~ (uT ·Sehilld.$;a- notes bl!1O'w'
1)t-Jan·IS 3].)3n·15 Heb·15 167,473.00 iJ,B7S.00J 15'?~l;Q 1£17,618..10 W·Mar-l5' 147,Sl8.10 OO-Mar·15 147,818-.11) 05.A I}f·1~ 1).00 {l71 BtJllllId.Soo.;"Q-tas fMlow'
OI-Feb·IS 27'Feb'1 5 ~1.-;:~ar'15 197/l50.00 (1l,875(i(J)
r_l5 1
J
~~~OO ~.l9G. 25 11-M~r-l5 176,2%,25 O.,)-A I)r.~S 1).00
5~
176. 295.25 lO.AP
Me.d
31· M;)r-lS DB-Apr-IS 187,4S4.OO (11,87> ~ .OO llj.f3.,!~OO.05 f l'l-Apr:15 166,301}05 08-M,J~ 166,~OS 01·Jul-15 1).1)0 ;"', 8e!!!.nd. Sal! M!I!s...I!e~IV· -
:sIkA'pr·lS IM-M;tY-15 166,13~.~ ~,n4 . 00 157,$.2:1.31) l'}:-IA;)y-15 157.82:7.30 IB-JI)~'15 -- 157.82:7.31} 16')1)1·15 0.1)0 (43, lJelillld· SeeflQI(l$ balow'
3l-!\~;>y·lS (16) Beflind·SfJa~1Q-tQ.S IJ1Jtow'
r ~~;J
31·Mi.W·15 J 172,427.00 172,42.7.00 lG$.Sf)5 .r~5 11-!lJn-15 163,805.65 30-)un-15 1f)3.,805.G.5 1/;'.JI),I ·IS
01·Jon-1S 30·Jun-1.'> J 02-Jul-lS 183,7134.00 183,7114.00 174, 594.60 .£G-)ul-15 *594'S~ 1)1-AI)S-15 ' 1711,.S94.80 B·AOij:·1S (?!~j lkflind· ~tq$ befow'
01·Jul-1S '3.1-11,11-1'> j 30.JUI.15 162,534.00 161,072..69 153,019.1)6 U-A.M~l? 15$,019,01) ~9-Aug-15 153,1)19.1)(;'
~'4g'-'ss'lj
14·Se l)-15 , noroSbefOW' j
('0,1 8l!hi/idoSee-
01·Al)g·1S 31-Al)g-15 01-S~!}-15 163,669.00 163.669.00 lS5.4ij5.55 07-S",£-15 1S5.1I8~.5~ Ol-Oct·15 f (r1.10) -440d()Y$ to dUf] date
COI\sulta nt I),oer Time _ 14-Set)·15 17.747.50 H J47.50 16,813D.13 . ~ 1)-15 0".,5 \ (IG,86M" '0" -411 d~ystQ dua-datrJ
Dl-Sel)·15
Ol-Oct-15
I
ili
30·.) e1)015
31·I)r.HS
01·0ct-15
. OHJov-15
152,535.00
163,819.00
I I,
111[
152,535.00
136,829.81
144,9OS ~5
129,988.12
....!!:.Nl)y-15
21)-()I"t-15
15,1!6O 13
~15
129,988 32:
1.
~ct· 1 5
1)3. Dec-lS
{144lJOiL2';
(11~Nj ,3/)1
(1101 . ~10dayst~do(fl
(377J 0311 dClYS to !lue do!(J'
I
Ol-Nl)v-14
01-Dec·lS
31)·Nov·14
31-Dec-15
08-Dec-l5
03')3n-16
15B,SS:!:..OO
136,249.00
'W.8S}
:,39i5~"
92,347.12 87,72!!.:!.6 20-Dec· 15- 8 7,729.7*; 07-Jal)-16 f i8!,!}' 16
( ',1!4 . 5~·)
lj (34:>' -34Z d~iio ~V;dc,ra
122,857.41 116.114.54 IT·feb-16 116,71454 02·fel> 16 1 ( . ) -316 days to' due da(l~ I
Consultant Over Time J. 13'),)1)-16 ~49G.00 3,496.00 3,321.2.0 28·Mar-16 3,32120 12 Feb·lG 'J,1I1,'01 ) -3OGdoYs!O'delP.datl? /.
01·Jan·16 31')311-16 iL OG·Feb-16 122,496.00 {11A 33,005.35 78,931.03 31-Mar·lG ~8,'Hl.03 07-Mar- ~6 1 <17,U5.00 (Ji,Sdii( ~i (11, .Seh~ld·Sel1nO'tes:b~I" Vlrect!'VlIS/I!1" 01 SQ{arr
Ol-Fel)·16 29-Fel)-lG -/ 13-M ar-16 125,477.00 I.m 9S,328.00 90,5/Jl.r;.o 2.:j·AI>r-16 90.561.60 12.-Alir-1G 117,125.00 (43,411, I ' (9) GeMM· Sl!rr /lOWS below' DIrect rrrJai{tJ r 01 fo./rnr
( BI
- - I1
01·Mar-16 3~-Mar.16 02-Ayr-16 79,OOO. OO~ 73,7~.G7 70,076.34 16-API'-16 70,078.311 02:-May-16 <12,637.01) (1/,141 'II (481 8t!hlnc/· Se(J'n~,-e;t;;;o ,v' Diro(t Tn.ms{-c/· Qf SO{~fY
OI·Apr·I6
.
01-MaY-16 76~ 76,481100 72,663.60 ~-M;'1'V'-16 72,663 ..?O_ 3l-May-16 42.8.37/00 ilM''; ,ul (111 Beflirrd· Sf?f1noff1$ berow' Direct rrum[ru' ofSQ(ary
79,000.00 79,000.00 75,05Q.0I? 02-Jun-16 75,050.00 01-1u l-16 47,125.00 ( 17,~;~ , OOI (69) Befl/lld- Sea nQ-tes befow ' f Tmnrfi!r of Sarl1.ry
..'-
, ~.
DIrect
7S,377.00 (0,071 75,376.93 71,608.03 03-JIJI1-16 71,606.08: 01-Aug-16 45,111.00 I 27-Nov-16 11..,491,081 (i t~~l l setdnd. mnO't~s bl?loy,' DIrect TronsJar QfSflfaljf
""'[ ~"'to
43,707.70 (507.701 43,200.00 41,040.00 07-Au~16 41,040.00 05-Se l~ 141,040,00;
7~200.0£1 74,200.00 70,490.00 04·SeQ.16 70,490.00 03·0ct-16 (m:49(),IJilI ~12 days to due dote
- -- (72)
07-0ec-16
77,430.00
~ > ,~ "
73,5S8.50
73:905,19 1
67,592.50 1
3,93'J,83S.42
10·0ct·16
06-Nov-16
10·Dec-16
73,S53.~0
67,59250
3,930,838.42
31·0ct-16
73,945.19. 01-0ec-16
t
06·Ja n·17
l:il:mijfjJ
- t- (13,558,\ U)
j7:,~
(6/,>91.501
. "(IWkiN)
(44)
(13)
23
-44 days dull' dart!
-13 doys to dUl?date
23 d(JYs to- dWl dare
2.4.2 All paymenls we to the Coowllant in tonMcli<ln wilh his services h9loof shall be made in
Sa.udi Riyals in Saudi Arabia wilhin 30 IThifly) days of Ihe date of Ina Pfoject "'iMager's
Gp,rtificati..-m 01 thiJ "\f()ioo. Certified Paymp.nts 3,930,838..:42
Actual Payment Madp. 2,.330,~
~~d ill~y
, cm
".",I.::
't,,-
' __________ -1.!90,~
1.17.4 In lhs evanl lhat lhe Emp:Oyer r~1s Ii,) pay lha SUPQrvis-ion Consullant 1M Fees in
a.ccordance with SchedulQ ' (f of S GC~on 3 of Ih~ Request for Pmposal, the Supervision
ConsuJlN11 may feserve wrillan notice on Ihe Employer gfvir;g the Employer (60) days
hom reCQipt 01such notica 10 maka IhGdJ.J:(J payment.
1.17.5 In lha event of lIon~paymij(lt by Ula Employer rollowing the (;xpoifam QI such notice
refelfl~ d \0 in 1.1"7.4 above, Ule :illpervisioo Consultant rnay telmmato the Agreement \\~Ih
immediale ellacl by wriUen notice to trIG Empto~e(. In Ih9 event of such termination. th9
SuperVision Consulli¥11shall be paid his ice!; a,; calculated lip to Ihe date ol lennv,alion
plus all approved reimbwsabla costs Md (1xponses incurred up 10 the date of termination.
PROCARE RIAYA HOSPITAL EXPANSION
AL – KHOBAR, Kingdom of Saudi Arabia
1.2 SPECIFICATIONS
The contractor shall price the items listed below which are described in
the specifications. In addition, the contractor shall list below, describe
and price any obligations contained in the specifications or in any other
document for which has not allowed elsewhere and which wishes to price
separately, such as:
1.2.1 The required Shop Drawings.
1.2.2 As- Built Drawings.
1.2.3 Maintenance Manuals.
1.2.4 All required Testing Works .
1.2.5 Third party inspection ,testing and certificates for works and Equipments LS 1 150,771.00 150,771.00 0.38 37.81% 57,006.52 0.62 62.19% 93,764.48
according to the Employer/Consultant(s) requirement and instruction.
1.3 MEASUREMENTS:
This Contract is a Fixed Lump Sum Contract and is not subject to re- LS 1 Included
measurement, unless it is specifically mentioned for specific elements of
work or Where the Engineer shall require measuring any part of work in
accordance with the contract condition the works shall be measured net
as fixed with its place notwithstanding any general or local custom which
should be considered by the contractor while pricing the works.
1.4 PRICING:
1.4.1 The Contractor shall satisfy himself as to the meaning of every item in the LS 1 Included
Bill of Quantities, rates and price inserted by him will be deemed to
cover all his obligations, liabilities and services under the contract.
1.4.2 The Contractor shall price all items for all sections which he considers LS 1 Included
have a value. If any items are to be of no values, it will be considered that
this value has been spread through out the rates of the other items and
included in the Contract Amount.
1.4.3 The Contractor shall investigate and verify the existence and location of LS 1 Included
any existing underground or over head services which may affect the
works.
1.4.4 The Contractor shall be held responsible for and deemed to have allowed LS 1 Included
in his pricing for the maintenance and protection and or re-routing of any
existing services.
1.4.5 The rates and prices included hereunder are fixed for duration of the LS 1 Included
works and shall not be subject to any adjustments for any reason or
matters whatever this reason or matter.
Sub- Total: - - -
Procare Riaya Hospital Expansion Page 3 of 7
Al-Khobar, Kingdom of Saudi Arabia
1.11.2 The Contractor shall produce a site layout showing existing levels to 5.00 LS 1 22,616.00 22,616.00 1.00 100.00% 22,616.00 - 0.00% -
mtr. grid in two direction and updated soil investigation report and
handed over a negative of the same to Employer during the mobilization
stage.
1.12.2 The Contractor shall supply all required material, install, maintain, clean LS 1 241,231.00 241,231.00 0.70 70.00% 168,861.70 0.30 30.00% 72,369.30
and service the site offices to achieve the satisfaction of the PM and
supervision consultant for the full duration of Contract period.
1.16 INSURANCE:
All Insurance Liabilities for all risk policy( CAR) and third party Liability, LS 1 - - 0.00% - 1.00 100.00% -
insurance and other insurance policies, and ensure all contractors, staffs,
Workers, Equipments and Labours as per KSA regulation for all
contractors and subcontractors, Vendors, Suppliers, the Supervision
Consultant staff ,Project Manager staff, the Employer Staff and the Project
Guests should be included.
1.17.4 The above rate will be 1.5 times for weekends( and any night shift LS 1 Included
between the hours of 10.00 PM and 6.00 AM ) and 2.00 times for
national holidays.
1.17.5 The total of such charges shall be deducted from contractor's account and LS 1 Included
the contractor shall be provided with a detailed list of the personal
involved and hours expended for his information.
1.18 TIE- IN CONNECTIONS:
The Contractor shall be responsible for the tie- in
connections of the following service line shown below:
Sub- Station/ Power LS 1
Telephone Line LS 1
Water Line LS 1
Sewer Line LS 1 Included with MEP
Storm Drainage Line LS 1 Works
Data/ Network (Fiber Optic) Line LS 1
Medical Gas Line LS 1
Sub- Total: - - -
2.2 Backfilling & compaction with selected material as per soil conditions in CU.M. 277 31.00 8,587.00 207.75 75.00% 6,440.25 69.25 25.00% 2,146.75
layers not to exceed 25 cm. thickness to be filled and compacted on the
proposed OPD extension.
2.3 Backfilling & compaction required under raft slab, footing, ground beams, CU.M. 446 47.00 20,962.00 446.00 100.00% 20,962.00 - 0.00% -
retaining wall backfill & slab on grade.
2.4 Lean concrete for blinding of foundation beams and slabs (25 Mpa). SQ. M 3014 47.00 141,658.00 3,014.00 100.00% 141,658.00 - 0.00% -
2.5 50 mm. thk. Concrete Screed protection (provisional item) M2 0 - - 0.00% - - 100.00% -
2.6 Termite Control Treatment under Raft Slab Footings, Grade Beams, Grade SQ. M 3,288 7.00 23,016.00 3,288.00 100.00% 23,016.00 - 0.00% -
Slab and Walkway all around the perimeter of the Building, 2.00 meters
minimum.
2.7 200 x 100 x 80 mm. thk. Interlocking Pavers on 50 mm. thk. Compacted SQ.M. 185 92.00 17,020.00 - 0.00% - 185.00 100.00% 17,020.00
sand bedding & 150 mm. thk. Aggregate base course.
2.8 Curbs & Gutter with approved Traffic Thermo- Reflective Paint marking. LM 622 61.00 37,942.00 - 0.00% - 622.00 100.00% 37,942.00
2.9 External colored stamped or textured concrete on approved patterns SQ.M. 425 122.00 51,850.00 - 0.00% - 425.00 100.00% 51,850.00
place and spread to 100 mm. thk concrete laid to fall, c/w approved color
hardener, curing agent and sealer, see &refer drwg. No.: A- 01.
MISCELLANEOUS WORKS
2.10 Construction of miscellaneous facilities as per approved detail drawings:
2.10.1 Construction of SCECO Sub- Station, 14675 (L) x 2100 (W)as per SCECO SQ.M. 30 3,016.00 90,480.00 - 0.00% - 30.00 100.00% 90,480.00
requirement & specifications, see & refer drwg. No.: A-01 & A- 03, scope
of works to be included but not limited to excavation, backfilling,
compaction, termite control, lean concrete, reinforced footings, beams,
columns, control, lean concrete, reinforced footings, beams, columns,
block wall, plastering, painting, steel doors, door hardware, accessories
and other miscellaneous works to complete as per SCECO sub- station
requirement.
2.10.2 Construction of 3.00 meter height Boundary Wall works include LM 82 1,509.00 123,738.00 - 0.00% - 82.00 100.00% 123,738.00
excavation, backfilling, compaction, termite include excavation,
backfilling, compaction, termite control, lean concrete, RC Footings,
Columns, Beams Block wall and 15 mm. thk. plastered painted wall
finishes on both sides.
2.10.3 Construction of Soak Away Pit w/ Gravel filled bedding, size: 400 x EA 25 3,771.00 94,275.00 - 0.00% - 25.00 100.00% 94,275.00
400mm w/ Galvanized Steel Grating covering.
2.11 Supply & installation of 25 mm. thk. Joint Filler Board for Separation & LM 915 61.00 55,815.00 - 0.00% - 915.00 100.00% 55,815.00
Control joint as per approved material
2.12 Pre- Cast Concrete Splash Block EA 25 529.00 13,225.00 - 0.00% - 25.00 100.00% 13,225.00
2.13 50 mm. thk. Asphalt wearing course + 50 mm. thk. Asphalt Base Course SQ.M 4358 76.00 331,208.00 - 0.00% - 4,358.00 100.00% 331,208.00
on 180 mm. thk. base course
2.14 Pre- cast concrete wheel stopper, 150(H) x 200(W) x 2000 (L) c/w EA 144 378.00 54,432.00 - 0.00% - 144.00 100.00% 54,432.00
approved Traffic- Thermo Reflective paint.
2.15 Sewer Manhole 600 x 600 mm. w/ heavy duty steel Manhole cover w/ EA 2 1,811.00 3,622.00 - 0.00% - 2.00 100.00% 3,622.00
English & Arabic encryption "SEWERAGE", size 600 x 600 mm, see &
refer drwg. No.: P- 46.
2.16 Cable Manhole (1.50 X 1.50 M) w/ heavy duty steel Cable Manhole (1.50 X EA 0 3,622.00 Rate only - 0.00% - - 100.00% -
1.50 M) w/ heavy duty steel Manhole cover w/ English & Arabic
encryption "ELECTRICAL CABLE", size 1.00 Mtr. Diameter, see & refer
drwg. No.:
2.17 PVC Water stop 250 mm. width for Retaining & Shear Walls from FOSROC LM 265 76.00 20,140.00 251.75 95.00% 19,133.00 13.25 5.00% 1,007.00
"Supercast PVC" or approved equal.
2.18 Electrical Cable Trench, L x 2.00(W) x 1.50(D) meter, min. LM 28 3,016.00 84,448.00 - 0.00% - 28.00 100.00% 84,448.00
2.19.1.1 Landscaping @ GF scope of works including but not limited Landscaping SQ.M 47 1,509.00 70,923.00 - 0.00% - 47.00 100.00% 70,923.00
@ GF scope of works including but not limited to Palm Trees, imported
fertile soil mix, ground covers, bushes, grass lawn and 4- sets of
decorative concrete benches.
2.19.1.2 Landscaping @ Roof Deck Level scope of works including Landscaping @ SQ.M 102 1,811.00 184,722.00 - 0.00% - 102.00 100.00% 184,722.00
Roof Deck Level scope of works including but not limited to Palm Trees,
imported fertile soil mix, ground covers, bushes, grass lawn and
decorative natural stones.
2.20.1 Parking Bay Line & Number Road Marking EA 145 114.00 16,530.00 - 0.00% - 145.00 100.00% 16,530.00
2.20.2 Pedestrian Crossing Road Marking EA 5 604.00 3,020.00 - 0.00% - 5.00 100.00% 3,020.00
-
2.20.3 Road Dividing Line (Straight/ No Overtaking Lane) LM 332 39.00 12,948.00 - 0.00% - 332.00 100.00% 12,948.00
2.20.4 Driveway Directional Arrow EA 55 453.00 24,915.00 - 0.00% - 55.00 100.00% 24,915.00
2.21.1 Disabled Parking Signage EA 4 1,509.00 6,036.00 - 0.00% - 4.00 100.00% 6,036.00
2.21.2 Road Traffic Signage: EA 10 1,509.00 15,090.00 - 0.00% - 10.00 100.00% 15,090.00
2.21.3 Pedestrian Crossing signage EA 5 1,509.00 7,545.00 - 0.00% - 5.00 100.00% 7,545.00
2.21.4 Disabled Parking Signage EA 4 1,509.00 6,036.00 - 0.00% - 4.00 100.00% 6,036.00
2.21.5 Traffic Direction Signage EA 10 1,509.00 15,090.00 - 0.00% - 10.00 100.00% 15,090.00
2.21.6 Speed Limit Signage EA 6 1,509.00 9,054.00 - 0.00% - 6.00 100.00% 9,054.00
2.25.1 Demolition of existing Utility Building area concrete structure as per LS 1 Not Included EXCLUDED
demarcated line, including demolition of existing foundation, including
site clearing, relocation of existing underground utilities, i.e, piping,
cables & etc. and removal & disposal of unwanted material from the
project site to the disposal area.
2.25.2 Backfilling & compaction on the demolished concrete structure excavated LS 1 Not Included EXCLUDED
foundation with approved backfilling materials.
2.25.3 Re- routing of all existing underground utilities, i.e sewer, water, LS 1 150,771.00 150,771.00 0.50 50.00% 75,385.50 0.50 50.00% 75,385.50
electrical cables, medical gas & etc. to be tied- in with the new location.
2.25.4 Re- ROUT re- installation, testing & pre- commissioning of all relocated LS 1 150,771.00 150,771.00 0.50 50.00% 75,385.50 0.50 50.00% 75,385.50
underground utilities to be tied- in with the new location.
2.26 Complete supply & installation of required Shoring System c/w 4 x 4 LS 1 452,309.00 452,309.00 1.00 100.00% 452,309.00 - 0.00% -
Timber planks, H- beams, accessories & etc.to be installed on the
excavated area for Link Tunnel, see& refer drwg. No.: A- 02 (only for
Tunnel construction )
BUILDING STRUCTURES:
Reinforced concrete shall be as per ACI 318 Building Code requirement
for reinforced concrete with cement per ASTM C-150 type I or type V and
aggregate as per ASTM C-33, Formwork shall be according to standard
ACI 347 “recommended Formwork for concrete works”. Deformed
reinforcing bars shall comply with ASTM A-615 grade 60 or SAS-2
Minimum yield strength 414 N.mm2. Concrete used for items of work
under this contract shall have a compressive strength of 35.0 Mpa.
* Pre- Cast Concrete Hollow Core Slabs as indicated in the drawing and as
per Specifications Section 03400.
3.1.1 Reinforced Concrete Raft Foundations CU.M. 2,575 1,176.00 3,028,200.00 2,060.00 80.00% 2,422,560.00 515.00 20.00% 605,640.00
3.1.2 Reinforced Concrete Isolated Footing CU.M. 16 1,086.00 17,376.00 16.00 100.00% 17,376.00 - 0.00% -
3.1.3 Reinforced Concrete Columns CU.M 1,390 2,489.00 3,459,710.00 1,381.66 99.40% 3,438,951.74 8.34 0.60% 20,758.26
3.1.4 Reinforced Concrete Beams CU.M 1,796 2,066.00 3,710,536.00 1,706.20 95.00% 3,525,009.20 89.80 5.00% 185,526.80
3.1.5 Reinforced Shear Walls for Elevator Shaft CU.M 265 2,187.00 579,555.00 265.00 100.00% 579,555.00 - 0.00% -
3.1.6 Reinforced Concrete Retaining Walls CU.M 445 2,187.00 973,215.00 422.75 95.00% 924,554.25 22.25 5.00% 48,660.75
3.1.7 Reinforced Concrete for Water Tank CU.M 89 1,644.00 146,316.00 80.10 90.00% 131,684.40 8.90 10.00% 14,631.60
3.1.8 R.C Solid Slab 150 mm. thk. SQ.M 780 408.00 318,240.00 779.38 99.92% 317,985.41 0.62 0.08% 254.59
3.1.9 R.C Solid Slab 200 mm. thk. SQ.M 532 574.00 305,368.00 372.40 70.00% 213,757.60 159.60 30.00% 91,610.40
3.1.10 R.C Solid Slab 250 mm. thk. SQ.M 110 699.00 76,890.00 77.00 70.00% 53,823.00 33.00 30.00% 23,067.00
3.1.11 R.C Waffle Slab SQ.M 283 980.00 277,340.00 283.00 100.00% 277,340.00 - 0.00% -
3.1.12 Lintel Beam and Stair Beam CU.M 153 1,886.00 288,558.00 149.94 98.00% 282,786.84 3.06 2.00% 5,771.16
3.1.13 R.C Staircase (Steps & Slab) CU.M 183 1,764.00 322,812.00 183.00 100.00% 322,812.00 - 0.00% -
3.1.14 Reinforced Concrete Grade Slab 150 mm. thk. SQ.M 2345 109.00 255,605.00 2,345.00 100.00% 255,605.00 - 0.00% -
3.1.15 Pre- Cast Concrete Wall Panel, 125 mm. thk.w/ exposed aggregate wall SQ.M 7155 680.00 4,865,400.00 6,123.96 85.59% 4,164,295.86 1,031.04 14.41% 701,104.14
finish (external) w/ 20 x 20 mm. horizontal & vertical groove.
3.1.16 Pre- Cast Hollow Core Slab (250 mm. thk.) SQ.M 11652 288.00 3,355,776.00 - 0.00% - 1,935.16 100.00% 557,325.80
3.1.17 Pre- Cast Hollow Core Slab (200 mm. thk.) SQ.M 83 272.00 22,576.00 - 0.00% - 83.00 100.00% 22,576.00
3.1.18 50 mm. thk. Concrete screed with 8 mm. dia. reinforcement @ 200 c/c SQ.M 11735 84.00 985,740.00 - 0.00% - 8,113.78 100.00% 681,557.20
wire mesh on top of pre- cast hollow core slab
3.1.19 Reinforced Concrete for Ramp CU.M 35 2,715.00 95,025.00 24.50 70.00% 66,517.50 10.50 30.00% 28,507.50
3.1.20 R.C Flat Slab - Ground Floor - Without Tunnel SQ.M 1596 190.5907 1,596.00 100.00% 304,182.80 - 0.00% -
3.1.21 R.C. Post tension Slab, 250mm thick - First + Typical floors SQ.M 12379 226.06 12,379.00 100.00% 2,798,450.20 - 0.00% -
4.1 Concrete Masonry Block work in cement mortar reinforced vertically &
horizontally and cells grouted as per details in standard drawings & in
accordance with specification, Section 04200: Masonry Units, Insulated
Masonry Units and Accessories. Mortar mix shall conform to the
requirement of the UBC Table 24- A, Type- M or Type- C.
4.1.1 200 mm. thk. CMU Wall Partition Reinforced with 10mm. Dia. Vertical SQ.M 7,149 98.00 700,602.00 6,306.85 88.22% 618,071.08 842.15 11.78% 82,530.92
bars @ 900mm. C/C and 8mm. Dia. Horizontal bars @ every two layer of
CHB.
4.1.2 150 mm. thk. CMU Wall Partition Reinforced with 10mm. Dia. Vertical SQ.M. 3,127 98.00 306,446.00 3,127.00 100.00% 306,446.00 - 0.00% -
bars @ 900mm. C/C and 8mm. Dia. Horizontal bars @ every two layer of
CHB.
4.1.3 100 mm. thk. CMU Wall Partition Reinforced with 10mm. Dia. Vertical SQ.M. 1,224 96.00 117,504.00 1,203.44 98.32% 115,529.93 20.56 1.68% 1,974.07
bars @ 900mm. C/C and 8mm. Dia. Horizontal bars @ every two layer of
CHB.
5.1 Furnish, fabricate and install miscellaneous metals, fabricate made out of
structural item such as anchors, supports, fastenings, backings, wooden
capping which are not part of the fixture and equipment. All works shall
conform with the approved specifications, Section 05500: Metal
Fabrications and approved detail drawings.
5.1.1 Supply and fix 50 mm. dia. Stainless Steel Handrail with 3- 38 mm. dia. LM 24 1,207.00 28,968.00 - 0.00% - 24.00 100.00% 28,968.00
Stainless Steel Railings c/w brackets, plate covers, fittings & accessories.
For Ramp Area
5.1.2 Supply and fix 50 mm. dia. Steel Epoxy Painted Handrail with 3- 38 mm. LM 49 906.00 44,394.00 - 0.00% - 49.00 100.00% 44,394.00
dia. Steel Epoxy Painted Railings c/w brackets, plate covers, fittings &
accessories for Main Staircase, see & refer drwg.no.: A- 52 up to A- 55.
5.1.3 Supply and fix 50 mm. dia. Steel Epoxy Painted Handrail with 3- 38 mm. LM 395 906.00 357,870.00 - 0.00% - 395.00 100.00% 357,870.00
dia. Steel Epoxy Painted Railings c/w brackets, plate covers, fittings &
accessories for Fire Escape Staircases, see & refer drwg.no.: A- 56 up to A-
72.
5.1.4 Supply and fix 50 mm. dia. Steel Epoxy Painted Handrail with 3- 38 mm. LM 12 906.00 10,872.00 - 0.00% - 12.00 100.00% 10,872.00
dia. Steel Epoxy Painted Railings c/w brackets, plate covers, fittings &
accessories for Fire Escape Staircase, see & refer drwg.no.: A- 73.
5.1.5 Supply & fix 25 mm. dia. Galvanized Steel Ladder Rung on Steel Angle LM 15 980.00 14,700.00 - 0.00% - 15.00 100.00% 14,700.00
Stringer c/w brackets, plates, nuts, bolts, fittings & accessories for
Elevator Pit, see & refer drwg. No.: A- 74 up to A- 81.
5.1.6 Supply & fix Maintenance Steel Ladder w/ Cage Hoop, epoxy painted LM 33 980.00 32,340.00 - 0.00% - 33.00 100.00% 32,340.00
finish c/w brackets, fittings & accessories for Roof Deck Area.
5.1.7 Supply & installation of 5 mm. thk. Stainless Steel Floor Joint Strip LM 381 151.00 57,531.00 - 0.00% - 381.00 100.00% 57,531.00
between Two (2) different type of floor finishes.
5.1.8 Supply and fix of Expansion Joint Covering for floors and walls. LM 409 227.00 92,843.00 - 0.00% - 409.00 100.00% 92,843.00
Recommended supplier: MMS System, USA Model: Classic Cover Series for
Flooring & Flexible Wall & Ceiling for Wall & Ceiling or approved equal.
5.1.9.1 Complete supply & installation of required Steel Stair Structure c/w Steel LM 10 3,016.00 30,160.00 - 0.00% - 10.00 100.00% 30,160.00
Column, Beam, Girder, Stringer, Tread, Risers, Chequered Plates,
Brackets, Plates, accessories, fittings & etc. c/w pre- fabricated primer
paint and to be Epoxy Painted finish, see & refer drwg.no.: A- 73.
5.1.10 Supply & installation of Stainless Steel Railing w/ 13.2 mm thk. LM 16 1,811.00 28,976.00 - 0.00% - 16.00 100.00% 28,976.00
Laminated Tempered Clear Glass Panel c/w 50 mm. dia. X 1.5 mm. thk.
Gr. 304, Mirror finish Top Rail &40 mm. dia. Fabricated glass holder with
20 mm. dia. Solid Rod including fittings, brackets, accessories & etc. as per
detail drawing, see & refer drwg. No.: A- 134.
5.1.11 Supply & installation of 500 x 500 mm. Hot Dipped Galvanized Manhole NO 1 1,509.00 1,509.00 - 0.00% - 1.00 100.00% 1,509.00
Cover c/w steel framing, brackets, plates, fittings, lockable bolt, & etc. for
Sweet Water Tank, see & refer drwg. No.: A- 132.
5.1.12 Supply & installation of Hot Dipped Galvanized Steel Rung Ladder c/w SET 1 7,540.00 7,540.00 - 0.00% - 1.00 100.00% 7,540.00
brackets, plates, fittings & etc. for Sweet Water Tank, see & refer drwg.
No.: A- 132.
5.1.13 Supply and fix 50 mm. dia. Steel Epoxy Painted Handrail with 3- 38 mm. LM 6 - - 0.00% - 6.00 100.00% -
dia. Steel Epoxy Painted Railings c/w brackets, plate covers, fittings &
accessories for Staircase from Kitchen to Gen- Set Room, see & refer
drwg.no.: A- 02.
5.1.14 Complete supply & installation of required Steel Stair Structure c/w Steel LM 4 3,771.00 15,084.00 - 0.00% - 4.00 100.00% 15,084.00
Column, Beam, Girder, Stringer, Tread, Risers, Chequered Plates,
Brackets, Plates, accessories, fittings & etc. c/w pre- fabricated primer
paint and to be Epoxy Painted finish from Kitchen to Gen- Set Room, see &
refer drwg. No.: A- 73
6.1 Furnish, fabricate and install all required wood and plastics works
conforms and in accordance with approved detail drawing and
specifications from Section 06100: Rough Carpentry, Section 06200:
Finish Carpentry & Section 6400:Architectural Woodwork.
6.1.4.1 Complete supply & installation of Console Station Counter HDF Wood LM 6 4,524.00 Rate only - 0.00% - 6.00 100.00% Rate only
Laminated Veneer Counter Top finishes c/w drawers, shelves and all
necessary fittings & accessories such as Hinges, Handles, Roller Guides for
Drawers, & etc. , see & refer drwg. No.:……..
Sub- Total: - - -
Procare Riaya Hospital Expansion Page 2 of 2
Al-Khobar, Kingdom of Saudi Arabia
Sub- Total: - - -
TOTAL FOR- WOOD AND PLASTICS 0.00 0.00 0.00
7.1 The Contrator shall supply,install & test all scope of worksfor Thermal
and Moisture Protection in compliance with theapproved detail drawings
and in accordance and as perspecifications and to make the system fully
functional.
7.1.1 Polyethylene Vapor Barrier (200 microns) under foundations, grade SQ.M. 2,646 7.00 18,522.00 2,249.10 85.00% 15,743.70 396.90 15.00% 2,778.30
beams, grade slab etc.
7.1.2 Waterproofing for all Toilets, Kitchen & to all Wet Areasof ARDEX WPM SQ.M. 869 76.00 66,044.00 - 0.00% - 869.00 100.00% 66,044.00
005, Two component flexible cementitiouselastomeric waterproofing
membrane, fast drying or approvedequal.
7.1.3 Damproofing with 2- coats of FOSROC "Nitoproof 120" Bituminous SQ.M. 3271 31.00 101,401.00 2,289.70 70.00% 70,980.70 981.30 30.00% 30,420.30
protecive/ flexible coating or approved equal.
7.1.4 2- layer of 4 mm. thk. "FOSROC" Proofex Engage, FullyBonded Pre- SQ.M. 2646 76.00 201,096.00 2,646.00 100.00% 201,096.00 - 0.00% -
applied waterproofing system including allfittings, accessories, cant strip,
flashing & etc. for Raft Foundations.
7.1.5 2- layer of 4 mm. thk. "FOSROC" Proofex Engage, FullyBonded Pre- SQ.M. 1135 76.00 86,260.00 908.00 80.00% 69,008.00 227.00 20.00% 17,252.00
applied waterproofing system including allfittings, accessories, cant strip,
flashing & etc. including25 mm. thk. Filler protection board for RC
Retaining Wall
7.1.6 Roof Covering and Waterproofing for Main Hospital Building Roof & Roof SQ.M. 1,223 151.00 184,673.00 - 0.00% - 1,223.00 100.00% 184,673.00
Deck Level.
7.1.7 1- layer of 4 mm. thk. "FOSROC" Fully- Bonded Pre-applied Waterproofing SQM 131 302.00 39,562.00 - 0.00% - 131.00 100.00% 39,562.00
System "Proofex Engage" w/ 25 mm. thk. Filler protection board c/w 150
x 150 x 8 mm.thk. GlazedCeramic Tiles w/ non- toxic grouting for Sweet
Water Tankas per detail drawing no.: A- 132.
The metal frames shall be 1.5 mm. thk. (Ga. 16) Steel Sheet Single
rebated wraparound knockdown frame notched, grout or plaster filled as
wherein applicable (see detail on Drwg. No.:…………..)
Contractor to provide all required UL/ Door Label for all Fire Rated
Doors.
Contractor to provide the following items but not limited to limited to:
Sub- Total: - - -
Procare Riaya Hospital Expansion Page 2 of 18
Al-Khobar, Kingdom of Saudi Arabia
8.1.1.2 DOOR # 1A: (with complete door hardwires) Double Hinged Aluminum SET 4 7,165.00 28,660.00 - 0.00% - 4.00 100.00% 28,660.00
Swing Glass Door with Powder coated finish Tempered, 6 mm. thk.
Reflective outside Panel, 12 . Air gap & 6 mm. thk. Clear Glass inside
Panel with weather-strip.
Size: 1800 W x 2200 H
8.1.1.3 DOOR # 2: Automatic Sliding Door Automatic Sliding Door w/ Stainless SET 2 27,291.00 54,582.00 - 0.00% - 2.00 100.00% 54,582.00
Steel framing, Mirror Polished finish, Single Glazing, 10 mm. thk.,
Tempered, Light Tinted and Electric operated mechanism with weather-
strip.
Size: 1800 W x 2200 H
8.1.1.4 DOOR # 2A: (with complete door hardwires) Double Hinged Aluminum SET 4 7,165.00 28,660.00 - 0.00% - 4.00 100.00% 28,660.00
Swing Glass Door with Powder coated finish, Single Glazing, 6 mm. thk.,
Light Tinted Glass Panell.
Size: 1800 W x 2200 H
8.1.1.5 DOOR # 3: Frameless Automatic Sliding Door Automatic Sliding SET 1 27,291.00 27,291.00 - 0.00% - 1.00 100.00% 27,291.00
Frameless Door , Single Glazing, 10 mm. thk. Tempered, Reflective c/w
Electric operated mechanism and with weather-strip.
Size: 1800 W x 2200 H
8.1.1.6 DOOR # 3A: Frameless Automatic Sliding Door Automatic Sliding SET 1 27,291.00 27,291.00 - 0.00% - 1.00 100.00% 27,291.00
Frameless Door , Single Glazing, 10 mm. thk. Tempered, Light Tinted c/w
Electric operated mechanism and with weather-strip.
Size: 1800 W x 2200 H
8.1.1.7 DOOR # 4: (with complete door hardwires) Hinged Flush Type Swing SET 2 4,524.00 9,048.00 - 0.00% - 2.00 100.00% 9,048.00
Steel Door, F- 90 Fire Rating, mineral core insulated , Ga. 16 steel sheet
facing w/ epoxy painted finish c/w wooden architrave/ trim varnished
finish with weather-strip.
Size: 900W x 2200H
8.1.1.8 DOOR #5 : (with complete door hardwires) Hinged Flush Type Swing SET 43 5,278.00 226,954.00 - 0.00% - 43.00 100.00% 226,954.00
Steel Door, F- 90 Fire Rating, mineral core insulated , Ga. 16 steel sheet
facing w/ 150 (W) x 700(L) mm Fire Rated Vision Glass Panell c/w
epoxy painted finish c/w wooden architrave/ trim varnished finish with
weather-strip.
Size: 900W x 2200H
8.1.1.9 DOOR # 6: (with complete door hardwires) Double Hinged Flush Type SET 29 17,057.00 494,653.00 - 0.00% - 29.00 100.00% 494,653.00
Swing Wooden Door, Solid Core Plasterboard, laminated wood veneer
facing, F- 90 Fire Rated w/ stainless steel pull handle/ push plate & 300
mm. high stainless steel kicker plate (satin finish) c/w wooden
architrave/ trim varnished finish, including 500 (W) x 700 (L) mm.
Vision Glass Panell.
Size: 1800W x 2200H
8.1.1.10 DOOR # 7: (with complete door hardwires) Double Hinged Flush Type SET 10 17,057.00 170,570.00 - 0.00% - 10.00 100.00% 170,570.00
Swing Steel Door, F- 90 Fire Rating, mineral insulated core, Ga. 16
Stainless Steel sheet facing w/ epoxy painted finish c/w wooden
architrave/ trim varnished finish, including 500 (W) x 700 (L) mm. Fire
Rated Vision Glass Panell.
Size: 1800W x 2200H
Sub- Total: 955,807.00 - 955,807.00
Procare Riaya Hospital Expansion Page 4 of 18
Al-Khobar, Kingdom of Saudi Arabia
8.1.1.11 DOOR # 8: (with complete door hardwires) Hinged Flush Type Swing SET 25 9,131.00 228,275.00 - 0.00% - 25.00 100.00% 228,275.00
Wooden Door, Solid Core Plasterboard, Laminated wood veneer facing
w/ F- 90 Fire Rated c/w wooden architrave/ trim varnished finish.
Size: 900W x 2200H
8.1.1.12 DOOR # 8A: (with complete door hardwires) Hinged Flush Type Swing SET 128 3,894.00 498,432.00 - 0.00% - 128.00 100.00% 498,432.00
Wooden Door, Solid Core Plasterboard, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish & 300 mm. high Stainless
Steel Kicker Plates
Size: 800W x 2200H
8.1.1.13 DOOR # 8B: (with complete door hardwires) Hinged Flush Type Swing SET 8 9,133.00 73,064.00 - 0.00% - 8.00 100.00% 73,064.00
Wooden Door, Solid Core Plasterboard, Laminated wood veneer facing
w/ F- 90 Fire Rated c/w wooden architrave/ trim varnished finish & 300
mm. high Stainless Steel Kicker Plates Size: 800W x 2200H
8.1.1.14 DOOR # 8C : (with complete door hardwires) Hinged Flush Type Swing SET 2 9,133.00 18,266.00 - 0.00% - 2.00 100.00% 18,266.00
Wooden Door, Solid Core Plasterboard, Laminated wood veneer facing, F-
90 Fire Rating w/ 150 (W) x 700(L) mm Fire Rated Vision Glass Panell
c/w wooden architrave/ trim varnished finish w/ 300 mm. high
Stainless Steel Kicker Plates and provision for card access door system
installation.
Size: 900W x 2200H
8.1.1.15 DOOR # 9: (with complete door hardwires) Hinged Aluminum Glass SET 6 3,620.00 21,720.00 - 0.00% - 6.00 100.00% 21,720.00
Swing Door Panell w/ Powder coated finish, Single Light Tinted,
Tempered, 6 mm. thk. Glass Panell
Size: 900W x 2200H
8.1.1.16 DOOR # 10: (with complete door hardwires) Hinged Aluminum Glass SET 1 3,771.00 3,771.00 - 0.00% - 1.00 100.00% 3,771.00
Swing Door Panell w/ Powder coated finish Tempered, 6 mm. thk. Light
Tinted outside Panel, 12 mm. thk. Air gap & 6 mm. thk. Clear Glass inside
Panel.
Size: 900W x 2200H
Sub- Total: 843,528.00 - 843,528.00
Procare Riaya Hospital Expansion Page 5 of 18
Al-Khobar, Kingdom of Saudi Arabia
8.1.1.17 DOOR # 11: (with complete door hardwires) Double Hinged Flush Type SET 3 6,786.00 20,358.00 - 0.00% - 3.00 100.00% 20,358.00
Swing Steel Door, Thermal insulated hollow core, Ga. 16 Stainless Steel
sheet facing w/ epoxy painted finish c/w wooden architrave/ trim
varnished finish with weather-strip.
Size: 1800W x 2200H
8.1.1.18 DOOR # 12: (with complete door hardwires) Hinged Flush Type Swing SET 7 4,524.00 31,668.00 - 0.00% - 7.00 100.00% 31,668.00
Steel Door, Mineral insulated hollow core, Ga. 16 Steel sheet facing w/
epoxy painted finish c/w wooden architrave/ trim & 300 mm. high
Stainless Steel Kicker Plate.
Size: 900W x 2200H
8.1.1.19 DOOR # 13: (with complete door hardwires) Hinged Flush Type Swing SET 9 9,133.00 82,197.00 - 0.00% - 9.00 100.00% 82,197.00
Wooden Door, Solid Core Plasterboard, Laminated wood veneer facing
w/ F- 90 Fire Rated c/w wooden architrave/ trim varnished finish & 300
mm. thk. Stainless Steel Kicker Plates w/ 500 (W) x 800 (H) mm. Vision
Glass Panell Size: 900W x 2200H
8.1.1.20 DOOR # 13A: (with complete door hardwires) Hinged Flush Type Swing SET 15 3,894.00 58,410.00 - 0.00% - 15.00 100.00% 58,410.00
Wooden Door, Solid Core Plasterboard, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish & 300 mm. high Stainless
Steel Kicker Plates w/ 500 (W) x 800 (H) mm. Vision Glass Panell.
Size: 900W x 2200H
8.1.1.21 DOOR # 14: (with complete door hardwires) Hinged Flush Type Swing SET 30 3,894.00 116,820.00 - 0.00% - 30.00 100.00% 116,820.00
Wooden Door, Solid Core Plasterboard, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish.
Size: 900W x 2200H
8.1.1.22 DOOR # 15: (with complete door hardwires) Hinged Flush Type Swing SET 14 4,524.00 63,336.00 - 0.00% - 14.00 100.00% 63,336.00
Steel Door, F- 90 Fire rated, Minera insulated hollow core, Ga. 16 Steel
sheet facing w/ epoxy painted finish c/w wooden architrave/ trim finish.
Size: 900W x 2200H
8.1.1.23 DOOR # 15A: (with complete door hardwires) Hinged Flush Type Swing SET 3 4,826.00 14,478.00 - 0.00% - 3.00 100.00% 14,478.00
Steel Door, F- 90 Fire rated, Minera insulated hollow core, Ga. 16 Steel
sheet facing w/ epoxy painted finish c/w wooden architrave/ trim finish.
Size: 1000W x 2200H
8.1.1.24 DOOR # 16: (with complete door hardwires) Hinged Flush Type Swing SET 1 9,133.00 9,133.00 - 0.00% - 1.00 100.00% 9,133.00
Wooden Door, Solid Core Plasterboard, F- 90 Fire Rated, Laminated
wood veneer facing c/w wooden architrave/ trim varnished finish & 300
mm. high Stainless Steel Kicker Plate.
Size: 900W x 2200H
8.1.1.25 DOOR # 17: (with complete door hardwires) Hinged Flush Type Swing SET 126 3,894.00 490,644.00 - 0.00% - 126.00 100.00% 490,644.00
Wooden Door, Hollow Core Grid Type, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish.
Size: 800W x 2200H
8.1.1.26 DOOR # 17A: (with complete door hardwires) Hinged Flush Type Swing SET 77 3,894.00 299,838.00 - 0.00% - 77.00 100.00% 299,838.00
Wooden Door, Hollow Core Grid Type, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish.
Size: 900W x 2200H
8.1.1.27 DOOR # 17B: (with complete door hardwires) Hinged Flush Type Swing SET 13 3,894.00 50,622.00 - 0.00% - 13.00 100.00% 50,622.00
Wooden Door, Hollow Core Grid Type, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish w/ 300 mm. high
Stainless Steel Kicker plate.
Size: 700W x 2200H
8.1.1.28 DOOR # 18: (with complete door hardwires) Hinged Flush Type Swing SET 2 4,071.00 8,142.00 - 0.00% - 2.00 100.00% 8,142.00
Wooden Door, Solid Core Plasterboard w/ Laminated wood veneer
facing c/w wooden architrave/ trim varnished finish & 2- 300 mm. high
Stainless Steel Kicker Plate, location see door schedule.
Size: 1200W x 2200H
Sub- Total: 872,857.00 - 872,857.00
Procare Riaya Hospital Expansion Page 7 of 18
Al-Khobar, Kingdom of Saudi Arabia
8.1.1.30 DOOR # 19: (with complete door hardwires) Hinged Flush Type Swing SET 1 13,947.00 13,947.00 - 0.00% - 1.00 100.00% 13,947.00
Wooden Door, Solid Core Plasterboard, F- 90 Fire Rated, Laminated
wood veneer facing c/w wooden architrave/ trim varnished finish & 300
mm. high Stainless Steel Kicker Plate c/w Lead Lining sheet.
Size: 1200W x 2200H
8.1.1.31 DOOR # 20: (with complete door hardwires) Double Hinged Flush Type SET 3 17,401.00 52,203.00 - 0.00% - 3.00 100.00% 52,203.00
Swing Wooden Door, Solid Core Plasterboard, F- 90 Fire Rated,
Laminated wood veneer facing c/w wooden architrave/ trim varnished
finish & 2- 300 mm. high Stainless Steel Kicker Plate c/w Lead Lining
sheet, see door schedule.
Size: 900W x 600W x 2200H
8.1.1.32 DOOR # 21: (with complete door hardwires) Hinged Flush Type Swing SET 4 11,309.00 45,236.00 - 0.00% - 4.00 100.00% 45,236.00
Wooden Door, Solid Core Plasterboard, F- 90 Fire Rated, Laminated
wood veneer facing c/w wooden architrave/ trim varnished finish & 300
mm. high Stainless Steel Kicker Plate c/w Lead Lining sheet.
Size: 900W x 2200H
8.1.1.33 DOOR # 22: (with complete door hardwires) Hinged Flush Type Swing SET 13 3,894.00 50,622.00 - 0.00% - 13.00 100.00% 50,622.00
Wooden Door, Hollow Core Grid Type, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish & 300 mm. high Stainless
Steel Kicker plate.
Size: 900W x 2200H
8.1.1.34 DOOR # 23: (with complete door hardwires) Hinged Flush Type Swing SET 5 3,894.00 19,470.00 - 0.00% - 5.00 100.00% 19,470.00
Wooden Door, Hollow Core Grid Type, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish & 300 mm. high Stainless
Steel Kicker plate.
Size: 900W x 2200H
8.1.1.35 DOOR # 24: (with complete door hardwires) Hinged Flush Type Swing SET 13 3,894.00 50,622.00 - 0.00% - 13.00 100.00% 50,622.00
Wooden Door, Hollow Core Grid Type, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish & 300 mm. high Stainless
Steel Kicker plate.
Size: 900W x 2200H
8.1.1.36 DOOR # 25: (with complete door hardwires) Hinged Swing Phenolic To be included in Item # 10.2.1 - 0.00% - - 100.00% - EXCLUDED
Type Door, MDF Core w/ 20 mm. thk. Phenolic facing & leaf thickness.
Size: 700W x 1800H
8.1.1.37 DOOR # 26: (with complete door hardwires) Hinged Flush Type Swing SET 3 3,894.00 11,682.00 - 0.00% - 3.00 100.00% 11,682.00
Wooden Door, Hollow Core Grid Type, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish & 300 mm. high Stainless
Steel Kicker plate.
Size: 900W x 2200H
8.1.1.38 DOOR # 27: (with complete door hardwires) Hinged Flush Type Swing SET 1 3,894.00 3,894.00 - 0.00% - 1.00 100.00% 3,894.00
Wooden Door, Hollow Core Grid Type, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish & 2- 300 mm. high
Stainless Steel Kicker plate, see door schedule.
Size: 800W x 2200H
8.1.1.39 DOOR # 28: (with complete door hardwires) Hinged Flush Type Swing SET 2 3,894.00 7,788.00 - 0.00% - 2.00 100.00% 7,788.00
Wooden Door, Hollow Core Grid Type, Laminated wood veneer facing
c/w wooden architrave/ trim varnished finish & 300 mm. high Stainless
Steel Kicker plate.
Size: 900W x 2200H
8.1.1.40 DOOR # 29: (with complete door hardwires) Hinged Flush Type Swing SET 1 3,894.00 3,894.00 - 0.00% - 1.00 100.00% 3,894.00
Wooden Door, Solid Core Plasterboard w/ Laminated wood veneer
facing c/w wooden architrave/ trim varnished finish & 300 mm. high
Stainless Steel Kicker Plate.
Size: 900W x 2200H
Sub- Total: 77,880.00 - 77,880.00
Procare Riaya Hospital Expansion Page 9 of 18
Al-Khobar, Kingdom of Saudi Arabia
8.1.1.41 DOOR # 30: (with complete door hardwires) Double Hinged Flush Type SET 1 30,155.00 30,155.00 - 0.00% - 1.00 100.00% 30,155.00
Swing Steel Door, Mineral insulated hollow core, Ga. 16 Stainless Steel
sheet facing c/w wooden architrave/ trim varnished finish 300 mm. high
stainless steel kicker plate (satin finish)
Size: 1800W x 2200H
8.1.1.42 DOOR # 31: (with complete door hardwires) Double Hinged Flush Type SET 18 7,540.00 135,720.00 - 0.00% - 18.00 100.00% 135,720.00
Swing Steel Door, Mineral insulated hollow core, Ga. 16 Steel sheet facing
w/ epoxy painted finish c/w wooden architrave/ trim varnished finish.
Size: 1800W x 2200H
8.1.1.43 DOOR # 32: (with complete door hardwires) Hinged Flush Type Swing SET 1 9,133.00 9,133.00 - 0.00% - 1.00 100.00% 9,133.00
Wooden Door, Solid Core Plasterboard w/ Laminated wood veneer
facing, F- 90 Fire rated, c/w wooden architrave/ trim varnished finish &
300 mm. high Stainless Steel Kicker plate& 500(W) x 1100(H) mm. Fire
rated Vision Clear Glass Panell.
Size: 900W x 2200H
8.1.1.44 DOOR # 33: (with complete door hardwires) Hinged Flush Type Swing SET 2 4,524.00 9,048.00 - 0.00% - 2.00 100.00% 9,048.00
Steel Door, Thermal insulated core, Ga. 16 Stainless Steel facing, Satin
Finish c/w c/w wooden architrave/ trim finished.
Size: 900W x 2200H
8.1.1.45 DOOR # 34: (with complete door hardwires) Double Hinged Flush Type SET 7 7,540.00 52,780.00 - 0.00% - 7.00 100.00% 52,780.00
Swing Aluminum Door, powder coated finish w/ 6 mm. Single Light
Tinted, Tempered glass Panell.
Size: 1800W x 2200H
8.1.1.46 DOOR # 35: (with complete door hardwires) Hinged Flush Type Swing SET 8 5,278.00 42,224.00 - 0.00% - 8.00 100.00% 42,224.00
Steel Door, Hollow Core Fire insulated w/ Ga. 16 Steel Sheet powder
coated facing, F- 90 Fire rated, c/w wooden architrave/ trim varnished
finish &2- 300 mm. high Stainless Steel Kicker plate & 500(W) x 700(H)
mm. Fire rated Vision glass Panell, see door schedule.
Size: 900W x 2200H
8.1.1.47 DOOR # 36: (with complete door hardwires) Double Hinged Flush Type SET 3 20,355.00 61,065.00 - 0.00% - 3.00 100.00% 61,065.00
Swing Wooden Door, Solid Core Plasterboard, F- 90 Fire Rated,
Laminated wood veneer facing c/w wooden architrave/ trim varnished
finish & 300 mm. high Stainless Steel Kicker Plate c/w Lead Lining sheet
& 500(W) X 700(H) mm. Vision Lead Glass Panell.
Size: 1800W x 2200H
8.1.1.48 DOOR # 36A: (with complete door hardwires) Double Hinged Flush Type SET 3 17,340.00 52,020.00 - 0.00% - 3.00 100.00% 52,020.00
Swing Wooden Door, Solid Core Plasterboard, F- 90 Fire Rated,
Laminated wood veneer facing c/w wooden architrave/ trim varnished
finish & 300 mm. high Stainless Steel Kicker Plate c/w 500(W) X 700(H)
mm. Fire rated Vision Glass Panell.
Size: 1800W x 2200H
8.1.1.49 DOOR # 37: (with complete door hardwires) Hinged Flush Type Swing SET 4 9,133.00 36,532.00 - 0.00% - 4.00 100.00% 36,532.00
Wooden Door, Solid Core Plasterboard w/ Laminated wood veneer
facing, F- 90 Fire rated, c/w wooden architrave/ trim varnished finish &
300 mm. high Stainless Steel Kicker plate.
Size: 900W x 2200H
-
8.1.1.50 DOOR # 38: (with complete door hardwires) Double Hinged Flush Type SET 9 17,340.00 156,060.00 - 0.00% - 9.00 100.00% 156,060.00
Swing Wooden Door, Solid Core Plasterboard, F- 90 Fire Rated,
Laminated wood veneer facing c/w wooden architrave/ trim varnished
finish & 300 mm. high Stainless Steel Kicker plate .
Size: 1800W x 2200H
8.1.1.51 DOOR # 39: (with complete door hardwires) Double Hinged Flush Type SET 3 15,831.00 47,493.00 - 0.00% - 3.00 100.00% 47,493.00
Swing Wooden Door, Solid Core Plasterboard, F- 90 Fire Rated,
Laminated wood veneer facing c/w wooden architrave/ trim varnished
finish & 300 mm. high Stainless Steel Kicker Plate c/w 400(W) X 700(H)
mm. Vision Glass Clear Panell.
Size: 1600W x 2200H
Sub- Total: 353,170.00 - 353,170.00
Procare Riaya Hospital Expansion Page 11 of 18
Al-Khobar, Kingdom of Saudi Arabia
8.1.1.52 DOOR # 40: (with complete door hardwires) Hinged Flush Type Swing SET 61 11,760.00 717,360.00 - 0.00% - 61.00 100.00% 717,360.00
Wooden Door, Solid Core Plasterboard w/ Laminated wood veneer
facing, F- 90 Fire rated, c/w wooden architrave/ trim varnished finish &
2- 300 mm. high Stainless Steel Kicker plate, see door schedule.
Size: 1200W x 2200H
8.1.1.53 DOOR # 41: (with complete door hardwires) Double Hinged Flush Type SET 1 30,155.00 30,155.00 - 0.00% - 1.00 100.00% 30,155.00
Swing Steel Door, Thermal insulated hollow core, Ga. 16 Stainless Steel
sheet facing mill finish c/w wooden architrave/ trim varnished finish.
Size: 1800W x 2200H
8.1.1.54 DOOR # 42: (with complete door hardwires) Hinged Flush Type Swing SET 2 9,133.00 18,266.00 - 0.00% - 2.00 100.00% 18,266.00
Wooden Door, Solid Core Plasterboard w/ Laminated wood veneer
facing, F- 90 Fire rated, c/w wooden architrave/ trim varnished finish.
Size: 900W x 2200H
8.1.1.55 DOOR # 43: (with complete door hardwires) Hinged Flush Type Swing SET 1 5,278.00 5,278.00 - 0.00% - 1.00 100.00% 5,278.00
Steel Door, F- 90 Fire rating Thermal & Acoustic insulated hollow core,
Ga. 16 Stainless Steel sheet facing mill finish for Gen- Set Room.
Size: 1000W x 2200H
8.1.1.56 DOOR # 44: (with complete door hardwires) Hinged Flush Type Swing 1 5,429.00 5,429.00 - 0.00% - 1.00 100.00% 5,429.00
Steel Door, F- 90 Fire rating Thermal & Acoustic insulated hollow core,
Ga. 16 Stainless Steel sheet facing mill finish for Gen- Set Room w/
weather strip.
Size: 1000W x 2200H
8.1.1.57 DOOR # 45: (with complete door hardwires) Double Hinged Flush Type SET 0 - - 0.00% - - 100.00% - EXCLUDED
Swing Steel Door, Mineral insulated hollow core, Ga. 16 Steel sheet facing
w/ epoxy painted finish c/w wooden architrave/ trim varnished finish.
Size: 1800W x 2200H
8.1.1.58 DOOR # 46: (with complete door hardwires) Hinged Flush Type Swing SET 1 4,826.00 4,826.00 - 0.00% - 1.00 100.00% 4,826.00
Steel Door, F- 90 Fire rating Thermal insulated hollow core, Ga. 16 Steel
sheet facing, w/ epoxy painted finish for Transformer Room.
Size: 1000W x 2200H
8.1.1.59 DOOR # 47: (with complete door hardwires) Double Hinged Flush Type SET 1 9,047.00 9,047.00 - 0.00% - 1.00 100.00% 9,047.00
Swing Steel Door, F- 90 Fire rating Thermal insulated hollow core, Ga. 16
Steel sheet facing w/ epoxy painted finish for Transformer Room.
Size: 1800W x 2200H
8.1.1.59 DOOR # 48: (with complete door hardwires) Double Hinged Flush Type SET 1 9,047.00 9,047.00 - 0.00% - 1.00 100.00% 9,047.00
Swing Aluminum Louver Door w/ powder coated finish
Size: 1800W x 2200H
* External Panel to be 6mm. Thk. K- Lite Heat Strength Glass Panell & 6
mm. thk. Internal Tempered Clear Glass Panell from Saudi American
Glass, Emirates Glass or approved equal.
8.1.2.1 WINDOW # 1/ W- 1: (Fixed Glass Window) Double glass tempered SET 2 4,247.00 8,494.00 - 0.00% - 2.00 100.00% 8,494.00
Reflective Glass 6mm. thk. Panel + 12mm. Air gap + 6mm. thk. Tempered
Clear Glass Panell, aluminum powder coated, verify window opening.
(Structural Glazing)
Size: 1600W x 2200H
8.1.2.2 WINDOW # 2/ W- 2: (Fixed Glass Window) Single Tempered Clear Glass SET 2 12,062.00 24,124.00 - 0.00% - 2.00 100.00% 24,124.00
Panell, 6 mm. thk. w/ Aluminum powder coated finish, verify window
opening. (Structural Glazing)
Size: 2250W (2 Eq. Panells) x 2200H
8.1.2.3 WINDOW # 2A/ W- 2A: (Fixed Glass Window) Single Tempered Light SET 1 2,654.00 2,654.00 - 0.00% - 1.00 100.00% 2,654.00
Tinted Glass Panell, 6 mm. thk. w/ Aluminum powder coated finish,
verify window opening. (Structural Glazing)
Size: 1000W x 2200H
8.1.2.4 WINDOW # 2B/ W- 2B: Ditto SET 1 3,185.00 3,185.00 - 0.00% - 1.00 100.00% 3,185.00
Size: 1200W x 2200H
8.1.2.5 WINDOW # 3/ W- 3: (Fixed Glass Window) Double glass tempered SET 1 12,544.00 12,544.00 - 0.00% - 1.00 100.00% 12,544.00
Reflective Glass 6mm. thk. Panel + 12mm. Air gap + 6mm. thk. Tempered
Clear Glass Panell, aluminum powder coated, verify window opening
(Structural Glazing)
Size: 4000W (2- Eq Panells) x 1300H
8.1.2.6 WINDOW # 4/ W- 4: Ditto SET 1 19,600.00 19,600.00 - 0.00% - 1.00 100.00% 19,600.00
Size: 12420W x 1300H
8.1.2.7 WINDOW # 5/ W- 5: (Ditto SET 1 27,140.00 27,140.00 - 0.00% - 1.00 100.00% 27,140.00
Size: 17185W x 1300H
8.1.2.8 WINDOW # 6/ W- 6:Ditto SET 1 15,680.00 15,680.00 - 0.00% - 1.00 100.00% 15,680.00
Size: 10000W x 1300H
8.1.2.9 WINDOW # 7/ W- 7: Ditto SET 2 25,631.00 51,262.00 - 0.00% - 2.00 100.00% 51,262.00
Size: 5900W x 3550H
8.1.2.10 WINDOW # 7A/ W- 7A: (Fixed Glass Panell Window) Single Tempered SET 2 25,631.00 51,262.00 - 0.00% - 2.00 100.00% 51,262.00
Clear Glass Panell, 6 mm. thk. w/ Aluminum powder coated finish, verify
window opening. (Structural Glazing)
Size: 5900W x 3550H
8.1.2.11 WINDOW # 8/ W- 8: (Fixed Glass Panell Window) Double glass SET 1 14,324.00 14,324.00 - 0.00% - 1.00 100.00% 14,324.00
tempered Reflective Glass 6mm. thk. Panel + 12mm. Air gap + 6mm. thk.
Tempered Clear Glass Panell, aluminum powder coated, verify window
opening (Structural Glazing)
Size: 4220W x 2700H
8.1.2.12 WINDOW # 9/ W- 9: Ditto SET 1 70,109.00 70,109.00 - 0.00% - 1.00 100.00% 70,109.00
Size: 21500W x 2700H
8.1.2.13 WINDOW # 10/ W- 10: (Ditto SET 2 8,595.00 17,190.00 - 0.00% - 2.00 100.00% 17,190.00
Size: 1600W (2- Eq. Panells) x 2200H
8.1.2.14 WINDOW # 10A/ W- 10A: Ditto SET 3 10,555.00 31,665.00 - 0.00% - 3.00 100.00% 31,665.00
Size: 1950W (2- Eq. Panells) x 2200H
8.1.2.15 WINDOW # 11/ W- 11: Ditto SET 6 98,000.00 588,000.00 1.80 30.00% 176,400.00 4.20 70.00% 411,600.00
Size: 1300W (2- Eq. Panells) x 30840H
8.1.2.16 WINDOW # 12/ W- 12:Ditto SET 1 90,462.00 90,462.00 - 0.00% - 1.00 100.00% 90,462.00
Size: 7600W x 27500H
8.1.2.17 WINDOW # 13/ W- 13: (Fixed Glass Panell Window) Double glass SET 6 51,262.00 307,572.00 1.80 30.00% 92,271.60 4.20 70.00% 215,300.40
tempered Reflective Glass 6mm. thk. Panel + 12mm. Air gap + 6mm. thk.
Tempered Clear Glass Panell, aluminum powder coated, verify window
opening (Structural Glazing)
Size: 32420W x 1300H
8.1.2.18 WINDOW # 14/ W- 14:Ditto SET 1 46,740.00 46,740.00 0.30 30.00% 14,022.00 0.70 70.00% 32,718.00
Size: 29335W x 1300H
8.1.2.19 WINDOW # 15/ W- 15: Ditto SET 6 19,600.00 117,600.00 1.80 30.00% 35,280.00 4.20 70.00% 82,320.00
Size: 12420W x 1300H
8.1.2.20 WINDOW # 16/ W- 16: Ditto SET 1 170,371.00 170,371.00 - 0.00% - 1.00 100.00% 170,371.00
Size: 5900W x 23780H
8.1.2.21 WINDOW # 17/ W- 17: Ditto SET 6 24,124.00 144,744.00 1.80 30.00% 43,423.20 4.20 70.00% 101,320.80
Size: 15320W x 1300H
8.1.2.22 WINDOW # 18/ W- 18:Ditto SET 1 37,693.00 37,693.00 - 0.00% - 1.00 100.00% 37,693.00
Size: 27070W (verify) x 1300H
8.1.2.23 WINDOW # 18A/ W- 18A: (Fixed Glass Window) Double glass tempered SET 1 25,631.00 25,631.00 0.30 30.00% 7,689.30 0.70 70.00% 17,941.70
Reflective Glass 6mm. thk. Panel + 12mm. Air gap + 6mm. thk. Tempered
Clear Glass Panell, aluminum powder coated, verify window opening
(Structural Glazing), see window schedule.
Size: 16000W (verify) x 1300H
8.1.2.24 WINDOW # 19/ W- 19: Ditto SET 1 12,816.00 12,816.00 0.30 30.00% 3,844.80 0.70 70.00% 8,971.20
Size: 8000W x 1300H
8.1.2.25 WINDOW # 20/ W- 20:Ditto SET 6 24,124.00 144,744.00 1.80 30.00% 43,423.20 4.20 70.00% 101,320.80
Size: 15240W x 1300H
8.1.2.26 WINDOW # 21/ W- 21: Ditto SET 1 51,262.00 51,262.00 0.30 30.00% 15,378.60 0.70 70.00% 35,883.40
Size: 32000W (verify) x 1300H
8.1.2.27 WINDOW # 22/ W- 22:Ditto SET 3 6,786.00 20,358.00 0.90 30.00% 6,107.40 2.10 70.00% 14,250.60
Size: 4000W x 1300H
8.1.2.28 WINDOW # 23/ W- 23: Ditto SET 6 7,087.00 42,522.00 1.80 30.00% 12,756.60 4.20 70.00% 29,765.40
Size: 4475W x 1300H
8.1.2.29 WINDOW # 24/ W- 24: (Fixed Glass Panell Window) Double glass SET 1 51,262.00 51,262.00 0.30 30.00% 15,378.60 0.70 70.00% 35,883.40
tempered Reflective Glass 6mm. thk. Panel + 12mm. Air gap + 6mm. thk.
Tempered Clear Glass Panell, aluminum powder coated, verify window
opening (Structural Glazing), see window schedule.
Size: 32000W (verify) x 1300H
8.1.2.30 WINDOW # 25/ W- 25: Ditto SET 5 37,693.00 188,465.00 1.50 30.00% 56,539.50 3.50 70.00% 131,925.50
Size: 23205W x 1300H
8.1.2.31 WINDOW # 26/ W- 26: Ditto SET 1 51,262.00 51,262.00 0.30 30.00% 15,378.60 0.70 70.00% 35,883.40
Size: 32000W (verify) x 1300H
8.1.2.32 WINDOW # 27/ W- 27: Ditto SET 1 51,262.00 51,262.00 0.30 30.00% 15,378.60 0.70 70.00% 35,883.40
Size: 32000W (verify) x 1300H
8.1.2.33 WINDOW # 28/ W- 28:Ditto SET 1 51,262.00 51,262.00 0.30 30.00% 15,378.60 0.70 70.00% 35,883.40
Size: 32000W (verify) x 1300H
8.1.2.34 WINDOW # 29/ W- 29: Ditto SET 1 37,693.00 37,693.00 0.30 30.00% 11,307.90 0.70 70.00% 26,385.10
Size: 24000W x 1300H
8.1.2.35 WINDOW # 30/ W- 30: (Fixed Glass Panell Window) Double glass SET 1 27,140.00 27,140.00 0.30 30.00% 8,142.00 0.70 70.00% 18,998.00
tempered Reflective Glass 6mm. thk. Panel + 12mm. Air gap + 6mm. thk.
Tempered Clear Glass Panell, aluminum powder coated, verify window
opening (Structural Glazing)
Size: 16535W x 1300H
8.1.2.36 WINDOW # 31/ W- 31: Ditto SET 1 45,231.00 45,231.00 - 0.00% - 1.00 100.00% 45,231.00
Size: 16380W x 2200H
8.1.2.37 WINDOW # 32/ W- 32: Ditto SET 1 21,109.00 21,109.00 - 0.00% - 1.00 100.00% 21,109.00
Size: 13220W x 1300H
8.1.2.38 WINDOW # 33/ W- 33: Ditto SET 2 3,167.00 6,334.00 0.60 30.00% 1,900.20 1.40 70.00% 4,433.80
Size: 2000W x 1300H
8.1.2.39 WINDOW # 34/ W- 34: Ditto SET 3 1,207.00 3,621.00 0.90 30.00% 1,086.30 2.10 70.00% 2,534.70
Size: 600W x 1300H
8.1.2.40 WINDOW # 35/ W- 35: (Steel Louver Window) Steel Louver Window SET 3 2,413.00 7,239.00 - 0.00% - 3.00 100.00% 7,239.00
w/ Sand Trap, Ga. 16 Steel Sheet Louver Facing c/w epoxy painted finish.
Size: 3000W x 600H
8.1.2.41 WINDOW # 36/ W- 36: (Fixed Aluminum Louver) Steel Louver Window SET 3 5,278.00 15,834.00 - 0.00% - 3.00 100.00% 15,834.00
w/ Sand Trap, Ga. 16 Steel Sheet Louver Facing c/w epoxy painted finish.
Size: 2100W x 2650H
8.1.2.42 WINDOW # 37/ W- 37: (Fixed Glass Panell Window) Single Tempered SET 3 1,886.00 5,658.00 0.90 30.00% 1,697.40 2.10 70.00% 3,960.60
Clear Glass Panell, 6 mm. thk. w/ Aluminum powder coated finish, verify
window opening. (Structural Glazing)
Size: 1200W x 1300H
8.1.2.43 WINDOW # 38/ W- 38: Ditto SET 1 12,213.00 12,213.00 - 0.00% - 1.00 100.00% 12,213.00
Size: 1870W (2- Eq. Panells) x 2700H
8.1.2.44 WINDOW # 39/ W- 39: Ditto SET 1 6,333.00 6,333.00 - 0.00% - 1.00 100.00% 6,333.00
Size: 3895W x 2200H
8.1.2.45 WINDOW # 40/ W- 40: Ditto SET 8 1,660.00 13,280.00 - 0.00% - 8.00 100.00% 13,280.00
Size: 1000W x 1300H
8.1.2.46 WINDOW # 41/ W- 41:Ditto SET 1 7,087.00 7,087.00 - 0.00% - 1.00 100.00% 7,087.00
Size: 1320W (2- Eq. Panells) x 2200H
8.1.2.47 WINDOW # 42/ W- 42: Ditto SET 2 3,167.00 6,334.00 - 0.00% - 2.00 100.00% 6,334.00
Size: 2000W x 1300H
8.1.2.48 WINDOW # 43/ W- 43:Ditto SET 1 4,826.00 4,826.00 0.30 30.00% 1,447.80 0.70 70.00% 3,378.20
Size: 2900W x 1300H
8.1.2.49 WINDOW # 44/ W- 44: (Fixed Glass Panell Window) Single Tempered SET 1 4,222.00 4,222.00 - 0.00% - 1.00 100.00% 4,222.00
Clear Glass Panell, 6 mm. thk. w/ Aluminum powder coated finish, verify
window opening. (Structural Glazing)
Size: 1460W x 2200H
8.1.2.50 WINDOW # 45/ W- 45: Ditto SET 6 1,660.00 9,960.00 - 0.00% - 6.00 100.00% 9,960.00
Size: 600W x 2200H
8.1.2.51 WINDOW # 46/ W- 46: Ditto SET 1 9,047.00 9,047.00 - 0.00% - 1.00 100.00% 9,047.00
Size: 5610W x 1300H
8.1.2.52 WINDOW # 46A/ W- 46A: Ditto SET 1 1,207.00 1,207.00 - 0.00% - 1.00 100.00% 1,207.00
Size: 350W x 1300H
8.1.2.53 WINDOW # 47/ W- 47: Ditto SET 1 7,087.00 7,087.00 - 0.00% - 1.00 100.00% 7,087.00
Size: 4440W x 1300H
8.1.2.54 WINDOW # 47A/ W- 47A: Ditto SET 1 3,393.00 3,393.00 - 0.00% - 1.00 100.00% 3,393.00
Size: 2120W x 1300H
8.1.2.55 WINDOW # 48/ W- 48: Ditto SET 1 8,293.00 8,293.00 - 0.00% - 1.00 100.00% 8,293.00
Size: 5200W x 1300H
8.1.2.56 WINDOW # 49/ W- 49: (Fixed Glass Panell Window) Single Tempered SET 1 9,198.00 9,198.00 0.30 30.00% 2,759.40 0.70 70.00% 6,438.60
Clear Glass Panell, 6 mm. thk. w/ Aluminum powder coated finish, verify
window opening. (Structural Glazing)
Size: 5800W x 1300H
8.1.2.57 WINDOW # 50/ W- 50: Ditto SET 1 3,469.00 3,469.00 0.30 30.00% 1,040.70 0.70 70.00% 2,428.30
Size: 2175W x 1300H
8.1.2.58 WINDOW # 50A/ W- 50A: Ditto SET 1 6,936.00 6,936.00 - 0.00% - 1.00 100.00% 6,936.00
Size: 4375W x 1300H
* All scope of works executed under this Division shall conform and comply
to the specifications, schedule of finishes and approved engineering
detail drawings.
* All materials to be used are subject and as per Client selection and
approval.
* See & refer "Schedule of Room Finishes" drwg. No.: A- 125,A- 126, A- 127,
A- 128, A- 129, A- 130, A- 131 & A- 132.
9.1.1 3.0 mm. thk. Anti- Bacterial, Homogenous, Heavy Duty, PUR, Vinyl Sheet SQM 6670 227.00 1,514,090.00 - 0.00% - 6,670.00 100.00% 1,514,090.00
Flooring, non- directional, fully flexible, abrasion resistance from KNOPP,
RESPONSIVE or approved equal installed on ARDEX EZM screed,
ARDEXCL1 self- levelling compound and ARDEX AF 190 multi-purpose,
rapid strength flooring adhesive or approved equal.
9.1.2 3.0 mm. thk. Anti- Static, Anti- Bacterial, Homogenous, PUR Heavy Duty SQM 322 227.00 73,094.00 - 0.00% - 322.00 100.00% 73,094.00
endurance, non- directional, fully flexible, abrasion resistance from
KNOPP, RESPONSIVE or approved equal installed on ARDEX EZM screed,
ARDEXCL1 self- levelling compound and ARDEX AF 190 multi-purpose,
rapid strength flooring adhesive or approved equal.
9.1.3 3.0 mm. thk. Anti- Bacterial, Homogenous, Heavy , Vinyl Sheet Flooring, SQM 459 227.00 104,193.00 - 0.00% - 459.00 100.00% 104,193.00
non- directional, fully flexible, abrasion resistance from KNOPP,
RESPONSIVE or approved equal installed on ARDEX EZM screed,
ARDEXCL1 self- levelling compound and ARDEX AF 190 multi-purpose,
rapid strength flooring adhesive or approved equal.
9.1.4 8 mm. thk. Edge- Fixed (Broadloom) Carpet Floor Sheet, anti- bacteria, on SQM 302 378.00 114,156.00 - 0.00% - 302.00 100.00% 114,156.00
concrete floor screed c/w insulated floor backing material, acoustic
insulated on ARDEX EZM floor screed and ARDEX CL1 self- levelling
compound or approve equal.
9.1.5 8 mm. thk. Glued Down Broadloom Carpet sheet with Standard Praying SQM 42 378.00 15,876.00 - 0.00% - 42.00 100.00% 15,876.00
bay decorative demarcation on concrete floor screed c/w insulated floor
backing material, acoustic insulated on ARDEX EZM floor screed and
ARDEX CL1 self- levelling compound or approved equal.
9.1.6 25 mm. thk. Natural Hardwood Decorative Floor finish with anti- SQM 115 680.00 78,200.00 - 0.00% - 115.00 100.00% 78,200.00
Bacterial/ varnish coating w/ wooden backing and insulation.
9.1.7 HDL Laminated Flooring Tiles strip from Berry Floor-USA c/w insulated SQM 120 680.00 81,600.00 - 0.00% - 120.00 100.00% 81,600.00
backing materials or approved equal.
9.1.8 30 mm. thk. Decorative Polished Marble from ITALY w/floor design, SQM 0 NA
border & marginal marble tiles installed with ARDEX S16 adhesive and
ARDEX MG grout or approved equal.
9.1.9 30 mm. thk. Polished Marble from ITALY w/ decorative elements, SQM 0 NA
borders, strips and HDL Laminated Wooden Floor Strips including
insulated backing material as per design detail, see & refer drwg. No.:…..
9.1.10 30 mm. thk. Polished Marble from ITALY w/ decorative elements, SQM 0 NA
borders, strips, marginal tiles installed with ARDEXS16 adhesives and
ARDEX MG grout or approved equal &as per design details, see & refer
drwg. No.:…….
9.1.11 30 mm. thk. Polished Marble Slab From ITALY for Main Staircase stair SQM 108 755.00 81,540.00 46.62 43.17% 35,200.82 61.38 56.83% 46,339.18
landing and Stair Tread w/ Anti- Slip Abrasive strips and 20 mm. thk.
Marble slab for Stair Riser as per detail drawing, see & refer drwg.
No.:….(Max. Mat. Price - SR.340 / M²)
9.1.12 300 x 300 x 10 mm. thk. Unglazed Ceramic Floor Tiles from Johnson & SQ.M. 178 182.00 32,396.00 - 0.00% - 178.00 100.00% 32,396.00
Johnson, RAK or approved equal installed ARDEX X7 adhesive and ARDEX
C2 grout or approved equal.
9.1.13 300 x 300 x 10 mm. thk. Anti- Slip Ceramic Floor Tiles from Johnson & SQ.M. 683 182.00 124,306.00 - 0.00% - 683.00 100.00% 124,306.00
Johnson, RAK or approved equal installed ARDEX X7 adhesive and ARDEX
C2 grout or approved equal.
9.1.14 300 x 300 x 10 mm. thk. Chemical Resistant Unglazed Ceramic Floor Tiles SQ.M. 66 182.00 12,012.00 - 0.00% - 66.00 100.00% 12,012.00
from Johnson & Johnson, RAK or approved equal installed with ARDEX
X78 adhesive and ARDEX EG8 grout or approved equal.
9.1.15 150 x 150 x 10 mm. thk. Unglazed Ceramic Floor Tiles from Johnson & SQ.M. 855 151.00 129,105.00 - 0.00% - 855.00 100.00% 129,105.00
Johnson, RAK or approved equal.
9.1.16 150 x 150 x 10 mm. thk. Anti- Slip Ceramic Floor Tiles from Johnson & SQ.M. 305 151.00 46,055.00 - 0.00% - 305.00 100.00% 46,055.00
Johnson, RAK or approved equal.
9.1.17 150 x 150 x 10 mm. thk. Chemical Resistant Ceramic Floor Tiles from SQ.M. 8 151.00 1,208.00 - 0.00% - 8.00 100.00% 1,208.00
Johnson & Johnson, RAK or approved equal.
9.1.18 150 x 150 x 10 mm. thk. Anti- Slip & Anti- Bacterial Ceramic Tiles from SQ.M. 315 151.00 47,565.00 - 0.00% - 315.00 100.00% 47,565.00
Johnson & Johnson, RAK or approved equal.
9.1.19 400 x 400 x 10 mm. thk. Unglazed Porcelain Floor Tiles, Marblelized SQ.M. 0 NA - 0.00% - - 100.00% -
finish surfaced from Johnson & Johnson, RAK or approved equal.
9.1.20 600 x 600 x 10 mm. thk. Porcelain Floor Tiles, Marblelized finish surfaced SQ.M. 0 NA - 0.00% - - 100.00% -
from Johnson & Johnson, RAK or approved equal.
9.1.21 300 x 300 x 10 mm. thk. Active Clean Air & Anti- Bacterial Unglazed SQ.M. 53 182.00 9,646.00 - 0.00% - 53.00 100.00% 9,646.00
Ceramic Tiles from SAVONA- Canada or approved equal.
9.1.22 Epoxy based paint w/ Polyurethane Top Coat on concrete w/ self- SQ.M. 1018 227.00 231,086.00 - 0.00% - 1,018.00 100.00% 231,086.00
levelling surfaced hardener using ARDEX R25E and ARDEX R 160P or
approved equal.
9.1.23 75 mm. thk. Smooth screed , approved SQ.M. 14646 76.00 1,113,096.00 11,183.69 76.36% 849,960.11 3,462.31 23.64% 263,135.89
9.1.24 10 mm. thk. Polished Marble Door Threshold for wet area entrances. LM 145 92.00 13,340.00 - 0.00% - 145.00 100.00% 13,340.00
9.2.1 100 mm. high Vinyl Base Skirting w/ vinyl or rubberized capping, heavy LM 6038 47.00 283,786.00 - 0.00% - 6,038.00 100.00% 283,786.00
duty from KNOPP, RESPONSIVE or approved equal.
9.2.2 100 mm. high Anti- Static Vinyl Base Skirting w/ vinyl or rubberized LM 321 47.00 15,087.00 - 0.00% - 321.00 100.00% 15,087.00
capping, heavy duty from KNOPP, RESPONSIVE or approved equal.
9.2.3 100 mm. high Carpet skirting c/w fittings & accessories. LM 27 31.00 837.00 - 0.00% - 27.00 100.00% 837.00
9.2.4 100 mm. high Hardwood Timber skirting Painted/ Varnished finish. LM 120 53.00 6,360.00 - 0.00% - 120.00 100.00% 6,360.00
9.2.5 100 mm. high x 10 mm. thk. Hardwood Timber skirting Painted/ LM 117 69.00 8,073.00 - 0.00% - 117.00 100.00% 8,073.00
Varnished finish.
9.2.6 100 mm. high Polished Marble Skirting from ITALY. LM 600 61.00 36,600.00 - 0.00% - 600.00 100.00% 36,600.00
9.2.7 20 mm. thk. Marble/ Granite Decorative strips. LM 360 122.00 43,920.00 - 0.00% - 360.00 100.00% 43,920.00
9.2.8 100 mm high x 300 mm.(L) High Active Clean Air and Anti- Bacterial LM 38 61.00 2,318.00 - 0.00% - 38.00 100.00% 2,318.00
Glazed Ceramic Skirting Tiles.
9.2.9 100 mm. high x 150 mm(L) Chemical Resistant Glazed Ceramic Tiles. LM 46 61.00 2,806.00 - 0.00% - 46.00 100.00% 2,806.00
9.2.10 600 (L) x 100 mm. high Porcelain Skirting Tiles. LM 0 61.00 - - 0.00% - - 100.00% -
9.2.11 400 (L) x 100 mm. high Porcelain Skirting Tiles. LM 0 61.00 - - 0.00% - - 100.00% -
9.2.12 300 (L) x 100 mm. high Glazed Ceramic Skirting Tiles. LM 0 53.00 - - 0.00% - - 100.00% -
-
9.2.13 150 (L) x 100 mm. high Glazed Ceramic Skirting Tiles. LM 2219 53.00 117,607.00 - 0.00% - 2,219.00 100.00% 117,607.00
9.2.14 150 (L) x 150 mm. high Glazed Ceramic Skirting Tiles. LM 264 53.00 13,992.00 - 0.00% - 264.00 100.00% 13,992.00
9.2.15 300 (L) x 100 mm. high Ceramic Skirting Cove Tiles. LM 246 53.00 13,038.00 - 0.00% - 246.00 100.00% 13,038.00
9.2.16 100 mm. high Epoxy Painted Skirting. LM 676 31.00 20,956.00 - 0.00% - 676.00 100.00% 20,956.00
Note: All Gypsum Wall Partition for Main & Secondary Corridors &
Departamental Area are to be F- 90 Fire Rating & full height. Other wall
partition height are to be referred to each details.
9.3.1.1 150 mm. thk. Gypsum Board Wall Partition, F- 90 Fire Rated, Full Height SQ.M. 4104 227.00 931,608.00 3,535.60 86.15% 802,580.29 568.40 13.85% 129,027.71
w/ mineral wool fiberglass insulations light gauge steel galvanized
framing.
9.3.1.2 130 mm. thk. Gypsum Board Wall Partition, F- 90 Fire Rated, Full Height SQ.M. 0 - - 95.43% - - 4.57% - EXCLUDED
w/ mineral wool fiberglass insulations light gauge steel galvanized
framing.
9.3.1.3 130 mm. thk. Gypsum Board Wall Partition w/ 2 mm. thk. Lead Lining on SQ.M. 341 529.00 180,389.00 325.42 95.43% 172,145.22 15.58 4.57% 8,243.78
6 mm. thk. Plywood backing, Full Height c/w light gauge steel galvanized
framing, F- 90 Fire rated, w/ mineral wool fiberglass insulation.
-
9.3.1.4 15 mm. thk. Gypsum Board Wall Cladding w/ 50 . Thermal insulation SQ.M. 7091 145.00 1,028,195.00 5,318.25 75.00% 771,146.25 1,772.75 25.00% 257,048.75
(back of pre- cast wall panel) c/w light gauge steel galvanized framing.
9.3.1.5 15 mm. thk. Gypsum Board on metal stud, space @ 600mm. O.C., moisture SQ.M. 1559 151.00 235,409.00 - 0.00% - 1,559.00 100.00% 235,409.00
resistant, on top of 100 mm. high CMU wall.
9.3.2.1 20 mm. thk. Marble/ Granite Wall Cladding with Decorative Strips and SQM 621 453.00 281,313.00 - 0.00% - 621.00 100.00% 281,313.00
Design from ITALY installed with ARDEX S16adhesives and ARDEX MG
grout or approved equal.
(Mechanical Fixing)(Max. Mat. Price - SR.200 / M²)
9.3.2.2 20 mm. thk. Polished Marble Wall Cladding with decorative element, SQM 84 453.00 38,052.00 - 0.00% - 84.00 100.00% 38,052.00
border & strips from ITALY.(Mechanical Fixing)
(Max. Mat. Price - SR.200 / M²)
9.3.2.3 150 x 100 mm. Glazed Ceramic Wall Tiles (Full Height) from Johnson & SQM 4725 227.00 1,072,575.00 - 0.00% - 4,725.00 100.00% 1,072,575.00
Johnson, RAK or approved equal.
9.3.2.4 150 x 150 mm. Glazed Ceramic Tiles from Johnson & Johnson, RAK or SQM 321 182.00 58,422.00 - 0.00% - 321.00 100.00% 58,422.00
approved equal.
9.3.2.5 150 x 150 mm. Glazed Ceramic Tiles @ 1200 mm. high rest by Anti- SQM 230 182.00 41,860.00 - 0.00% - 230.00 100.00% 41,860.00
Bacterial Hygienic Performance Internal paint finish w/ primer, putty & 2-
coats from ARDEX 820P,SIGMA, JOTUN or approved equal.
9.3.2.6 150 x 150 mm. Glazed Ceramic Tiles splash baack in between floor and SQM 99 182.00 18,018.00 - 0.00% - 99.00 100.00% 18,018.00
wall mounted cabinet.
9.3.2.7 150 x 100 mm. Chemical Resistant Glazed Ceramic Tilesat 1200 mm. high SQM 55 182.00 10,010.00 - 0.00% - 55.00 100.00% 10,010.00
rest by Anti- Bacterial Hygienic Performance Internal paint finish w/
primer, putty & 2- coats from ARDEX 820P, SIGMA, JOTUN or approved
equal.
9.3.2.8 300 x 300 mm. Active Clean Air and Anti- Bacterial Glazed Ceramic Tiles SQM 1082 227.00 245,614.00 - 0.00% - 1,082.00 100.00% 245,614.00
from SAVOLA Canada @ 1200mmhigh, rest by Anti- Bacterial Hygienic
Performance internal paint finish w/ primer, putty & 2- coats from
ARDEX820P, SIGMA, JOTUN or approved equal.
9.3.3.1 Decorative Wall Paper, Anti- Bacterial, washable w/putty, adhesive & SQM 396 378.00 149,688.00 - 0.00% - 396.00 100.00% 149,688.00
consumables from USA or approved equal.
9.3.3.2 Laminated Wood Veneer Wall Panels w/ acoustical Backing and sound SQM 279 980.00 273,420.00 - 0.00% - 279.00 100.00% 273,420.00
absorption materials c/w brackets,
9.3.4.1 15 mm. thk. (minimum) Cement Plastered wall finish SQ.M. 25,491 39.00 994,149.00 23,561.33 92.43% 918,891.92 1,929.67 7.57% 75,257.08
9.3.5 PAINTING:
9.3.5.1 Anti- Bacterial Hygienic Performance wall internal paint finish c/w SQM 22,158 47.00 1,041,426.00 - 0.00% - 22,158.00 100.00% 1,041,426.00
compatible primer, putty & Two (2) Top coats as per specifications &
manufacturers recommendations from SIGMA, JOTUN or approved equal.
9.3.5.2 Epoxy Hygienic Performance wall internal paint finish c/w compatible SQM 3456 61.00 210,816.00 - 0.00% - 3,456.00 100.00% 210,816.00
primer, putty & Two (2) Top coats as per specifications & manufacturers
recommendations from SIGMA, JOTUN or approved equal.
9.3.5.3 Anti- Bacterial Hygienic Performance Paint Coating from SIGMA, JOTUN SQM 477 47.00 22,419.00 - 0.00% - 477.00 100.00% 22,419.00
or approved equal w/ Decorative Veneer Tapestry and Stainless Steel
strips polished finish.
For 15 mm. thk. Gypsum Board Ceiling, all shall be "Fire & Moisture"
resistant, suspension system from Armstrong- USA or USG with complete
framing system, shapes, levels & surface preparation
9.4.1.1 600 x 600 x 15 mm. thk. Acoustic Ceiling board, "Dune Supreme" on semi SQ.M. 2981 92.00 274,252.00 - 0.00% - 2,981.00 100.00% 274,252.00
recessed metal T- runner ceiling system from Armstrong, USG or
approved equal
9.4.1.2 600 mm. x 600 mm. Perforated Metal Ceiling Panel on light gauge metal T- SQ.M. 240 227.00 54,480.00 - 0.00% - 240.00 100.00% 54,480.00
runner suspension ceiling system from Armstrong, USG or approved
equal
9.4.1.3 600 x 600 x 15 mm. thk. Acoustic Ceiling board, "Dune Supreme" on semi SQ.M. 50 122.00 6,100.00 - 0.00% - 50.00 100.00% 6,100.00
recessed metal T- runner ceiling system, moisture resistant, from
Armstrong, USG or approved equal.
9.4.1.4 RH 215 Custom Faceted Ceiling System "Metalworks",Barrel Vault Design SQ.M. 8 3,016.00 24,128.00 - 0.00% - 8.00 100.00% 24,128.00
from Armstrong or approved equal.
9.4.1.5 15 mm. thk. Gypsum Board Ceiling (Fire Rated), painted finish w/ 600 x SQ.M. 2290 137.00 313,730.00 - 0.00% - 2,290.00 100.00% 313,730.00
600 x 15 mm. thk. Acoustic Ceiling Board "Dune Supreme" on semi-
recessed metal- T- runner ceiling system from Armstrong, USG or
approved equal.
9.4.1.6 15 mm. thk. Gypsum Board Ceiling (Fire Rated), painted finish on light SQ.M. 1044 122.00 127,368.00 - 0.00% - 1,044.00 100.00% 127,368.00
gauge steel suspension ceiling system.
9.4.1.7 15 mm. thk. Gypsum Board Ceiling, moisture resistant, painted finish on SQ.M. 980 137.00 134,260.00 - 0.00% - 980.00 100.00% 134,260.00
light gauge steel suspension ceiling system.
9.4.1.8 15 mm. thk. Gypsum Board Ceiling (Fire Rated), painted finish with HPL SQ.M. 374 906.00 338,844.00 - 0.00% - 374.00 100.00% 338,844.00
Laminated Wood Ceiling Panel on light gauge steel ceiling suspension
system from Armstrong, USG or approved equal.
9.4.1.9 600 x 600 mm. "Metalworks" Custom Perforated Ceiling Metal Panels on SQ.M. 35 378.00 13,230.00 - 0.00% - 35.00 100.00% 13,230.00
light gauge steel ceiling suspension system from Armstrong, USG or
approved equal.
9.4.1.10 600 x 600 x 15 mm. thk. Clean Room Compliant Moisture& Fire Resistant SQ.M. 85 453.00 38,505.00 - 0.00% - 85.00 100.00% 38,505.00
Acoustic Ceiling Board "ULTIMA" on semi recessed metal T- runner
ceiling system from from Armstrong, USG or approved equal.
9.4.1.10 15 mm. thk. Gypsum Board Ceiling (Fire Rated), painted finish with SQ.M. 478 604.00 288,712.00 - 0.00% - 478.00 100.00% 288,712.00
Laminated Wood Veneer Decorative ceiling element and Stainless Steel
Strips on light gauge steel ceiling suspension system from Armstrong,
USG or approved equal.
9.4.1.11 Pre- insulated Custom Made Suspended Aluminum Ceiling Panel on light SQ.M. 15 378.00 5,670.00 - 0.00% - 15.00 100.00% 5,670.00
gauge steel suspension ceiling system.
9.4.1.12 15 mm. thk. single Level Gypsum Board Ceiling Panel w/ painted finish SQ.M. 0 - - 0.00% - - 100.00% - EXCLUDED
c/w primer, putty & 2- Top coats.
9.4.1.13 Painted ceiling finish on as- built fair faced concrete including primer, SQ.M. 1009 25.00 25,225.00 - 0.00% - 1,009.00 100.00% 25,225.00
putty & Two (2) top coats
9.4.1.14 Painted ceiling finish on plastered ceiling cement finish, including primer, SQ.M. 2064 25.00 51,600.00 - 0.00% - 2,064.00 100.00% 51,600.00
putty & Two (2) top coats
Different sizes varying from 200 x 200 mm.to 600 x 600 mm. as LOT 1 52,771.00 52,771.00 - 0.00% - 1.00 100.00% 52,771.00
requirement. Product to be of foreign or local manufacturer, to have
straight & even alignment all around such as supplied by Saudi Pan Gulf
from UK or approved equal/ or approved by the Client.
9.5.1.2 600 x 300 x 30 mm. thk. Marble Floor Tiles from ITALY or approved equal SQ.M. 48 635.00 30,480.00 - 0.00% - 48.00 100.00% 30,480.00
for Main Entrance & Entry Porch Area, including 70 mm. thk. Concrete
Floor screeding.
(Max. Mat. Price - SR.350 / M²)
9.5.1.2 600 x 400 x 25 mm. thk. Marble Tile finish, Treads with Anti- slip Nosing LM 69 635.00 43,815.00 - 0.00% - 69.00 100.00% 43,815.00
& Riser in full length for Main Entrance Stair & Entry Porch Stair Area,
including mortar bedding & concrete floor screeding as per required
thickness.
(Max. Mat. Price - SR.380 / M²)
9.5.1.3 600 x 300 x 30 mm. thk. Marble Floor Tiles from ITALY or approved SQ.M. 27 635.00 17,145.00 - 0.00% - 27.00 100.00% 17,145.00
equal, Flamed Surfaced finish for Ramp Area, including concrete floor
screeding, as per required thickness.
(Max. Mat. Price - SR.350 / M²)
9.5.2.1 100 mm. high Polished Marble Skirting Tiles. LM 18 76.00 1,368.00 - 0.00% - 18.00 100.00% 1,368.00
9.5.3.1 4 mm. thk. Aluminum Composite Wall Cladding from "ALPOLIC- SQ.M. 78 680.00 53,040.00 - 0.00% - 78.00 100.00% 53,040.00
Mitsubishi" or approved equal w/ External Textured Painted Wall finish
c/w primer, putty & 2- Topcoats.
9.5.3.2 Painted External Wall finish including primer, putty & Two (2) top coats SQ.M. 0 31.00 - - 0.00% - - 100.00% -
on cement plastered ceiling finish
9.5.4.1 15 mm. thk. (min.) External Cement Plastered Wall Finish SQ.M. 0 47.00 - - 0.00% - - 100.00% -
9.5.5.1 200 X 200 X 100mm. Thk. Glass Block Sand blasted Surfaced finish c/w SQ.M. 8 755.00 6,040.00 - 0.00% - 8.00 100.00% 6,040.00
bonding agent, grout & etc.
DIV. 10 SPECIALITIES:
10.1.1 Complete supply & installation of 30 mm. thk. Cultured Marble Counter LM 73 2,801.00 204,473.00 - 0.00% - 73.00 100.00% 204,473.00
Top c/w framing, bracket, fittings & accessories w/ built- in ovalyn design
bowl sink c/w water & drain provisions by Crestwood, Maromix or
approved equal.
10.2.1 Complete supply & installation of Demountable Toilet Wall Partition in LM 95 1,401.00 133,095.00 - 0.00% - 95.00 100.00% 133,095.00
complete package including Door Panels, hardware's, fittings &
accessories from Plastica Max Phenolic Core, Zamil Partitions or approve
equal/ or approved by the Client.
10.3.1 Supply & application of Fire Retardant Sealant or material or all Electro- LS 1 210,001.00 210,001.00 - 0.00% - 1.00 100.00% 210,001.00
Mechanical & Auxiliary utilities penetrations from wall & above ceiling
from "HILTI" or approved equal.
10.4.1 Complete supply & installation of 36 mm. thk. Non- Combustible SQ.M. 132 1,051.00 138,732.00 - 0.00% - 132.00 100.00% 138,732.00
Synthetic Sulphate Mineral poured in steel pan Raised Floor Panel/
System. High humidity levels compliance, fire resistant, sound & thermal
insulated c/w steel base pedestals, brackets, fittings, plates &accessories
c/w 2.0 mm. thk. Anti- Static Vinyl Tiles floor finish from "MERO- UK" or
approved equal
10.5.1 Basement Level LM 201 490.00 98,490.00 - 0.00% - 201.00 100.00% 98,490.00
10.5.2 Ground Floor Level LM 64 490.00 31,360.00 - 0.00% - 64.00 100.00% 31,360.00
10.5.2 1st Floor Level LM 270 490.00 132,300.00 - 0.00% - 270.00 100.00% 132,300.00
10.5.3 2nd Floor Level LM 237 490.00 116,130.00 - 0.00% - 237.00 100.00% 116,130.00
10.5.4 3rd Floor Level LM 151 490.00 73,990.00 - 0.00% - 151.00 100.00% 73,990.00
10.5.3 4th Floor Level LM 179 490.00 87,710.00 - 0.00% - 179.00 100.00% 87,710.00
10.5.3 5th Floor Level LM 179 490.00 87,710.00 - 0.00% - 179.00 100.00% 87,710.00
10.5.3 6th Floor Level LM 179 490.00 87,710.00 - 0.00% - 179.00 100.00% 87,710.00
10.6.1 Complete supply & installation of required Stainless Sunshade Canopy SQ.M. 65 3,501.00 227,565.00 - 0.00% - 65.00 100.00% 227,565.00
c/w brackets, fittings, accessories, & etc. as per required design detail, see
& refer drwg. No.: A- 12, A- 13, A- 14 & A- 15. Recommended
manufacturer: ZAMIL Architectural Co., RATTAL or approved equal.
10.7.1 Supply & installation in complete package of Aluminum Anodized Curtain O.F.M (Owner's Furnished Materials) EXCLUDED
Tracks & Carriers including Curtains, Accessories & etc. from "SALSBURY
Industries (USA)" or approved equal,
10.8.1 Supply & installation of Internal Room/ Door Signage similar to the LS 1 527,693.00 Rate Only - 0.00% - 1.00 100.00% Rate Only
existing Hospital signage, i.e frame, vinyl window brackets, color,
standard graphics, satin aluminum header panel & etc., worded in Arabic
& English size proportions between the Two languages shall be constant
throughout range. Fixing to walls or doors using screws or approved
adhesives, w/ 24pt. Grade 2 Braille per USA ADAAG standard.
(Provisional item)
* Recommended manufacturers ASI- Modulex Signage Products or EXCLUDED
approved equal, see & refer drwg. No.:
10.9.1 Supply & installation of required Triple Rows Tier Steel Locker, 12" (W) LM 28 2,801.00 78,428.00 - 0.00% - 28.00 100.00% 78,428.00
with heavy gauge steel lockers include tamper proof hinges, horizontal
louvers for ventilation and full length door stiffeners to add rigidity and
deaden sound when opening & closing from RIYADH HOUSE- JERAISY or
approved equal with the following built- in features to be included as
follows:
1. Hat shelf, coat rod, recessed black metal handlers
2. 3- point locking mechanism for complete security
3. Number plates for Locker Identification and padlock hasps on each
door
4. Standard nuts & bolts to ganged up Multiple Rows Tiers Lockers
For Layout & detail drawing, see & refer drwg. No.:
10.10.1 Supply & installation complete Counter Top, Sidings, Drawers, Sink, O.F.M (Owner's Furnished Materials) EXCLUDED
Framing & necessary Electro- Mechanical& Medical Gases provision from
approved manufacturer such as DUPONT (USA), MOTT (CANADA),
LABTEC or approved equal/ or approved by the Client
a. Laboratory Benches
b. Dental Benches
c. Nurses Station
d. Procedure Room
e. Reception Counters
f. Ultra- Sound Rooms
g. Lavatories
h. Pharmacy Lavatories
i. Pharmacy Dispensing Counters
j. Clean Utility
DIV. 11 EQUIPMENT
11.1.1 Complete supply, installation, testing & commissioning of required Unit O.F.M (Owner's Furnished Materials) EXCLUDED
Kitchens & Kitchen Equipment as per approved Kitchen Layout, Design &
Specifications, see& refer drwg. No.: …..
11.2.1 Complete supply, installation, testing & commissioning of required Cold/ O.F.M (Owner's Furnished Materials) EXCLUDED
Freezer Storage Room c/w pre- fabricated Thermal Insulated Floor, Wall
& Ceiling Panel, Thermal Insulated Door, equipment, fittings &
accessories.
11.3.1 Complete supply, installation, testing & commissioning of required SET 1 630,001.00 630,001.00 - 0.00% - 1.00 100.00% 630,001.00
Monorail Window Cleaning System c/w suspended steel platform,
gondola, cradle, swing stages, cables & etc. for the system to be
operational from ROZTEK- Finland or approved equal, see & refer drwg.
No.: A- 12, nA- 13, A- 14, A- 15, A- 16 & A- 17.
DIV. 12 FURNISHING
12.1.1 Complete supply & installation of 1.14 x 2.43, Bi- level, Rubber Backed, EA 4 10,454.00 41,816.00 - 0.00% - 4.00 100.00% 41,816.00
Non- Crushable Entrance Mat from Mat 4U, U.K. or approved equal.
12.2.1 Complete supply & installation of Lecture Hall Seating from Euro Seating- NO 212 1,830.00 387,960.00 - 0.00% - 212.00 100.00% 387,960.00
Spain, c/w the latest technological innovations, such as strengthened
polypropylene sides and a backrest made using the “UNIBLOCK II”
system, injection moulded side, from Euro seating Seat Centers:
52cm./20.472” (round armrests) & 54cm /21.259” (Without Cup holder
with writing tablet) Straight rows. Overall height: 95cm./37.401”
Back: UNIBLOCK II upholstery syst4em. Textured polypropylene outer
back. Seat: Fixed or Tip-up with double spring. UNIBLOCK II upholstery
system. Fully upholstered with zip lso available. Textured polypropylene
seat shell with perforations for acoustics.
Standard: strengthened and textured polypropylene. Steel also available.
Armrest: Injected and Textured polypropylene.
Polyurethane Foam: Seat density: 65kg/m3, Polypropylene: PPR 1042
Resistance to tearing DIN 53455/ resistance to impact DIN 53453/
Resistance to bending DIN 53452
SAFETY: UNE 23727 BS 5852
Fabric M-1 0 and 1
Foam M-4 5
Weight: 16.8 KGs
13.1.1 Complete supply & installation of required Tensioned Fabric Structures SET 2 78,400.00 156,800.00 - 0.00% - 2.00 100.00% 156,800.00
c/w steel structures, mast, trusses, struts, beams, cables, HDPE Woven
Mesh Fabric (fire- resistant), brackets fasteners, accessories, plates, & etc.
as per required design detail and Specifications for Roof Deck Level, see &
refer drwg. No.: A- 10 & A- 11
13.2.1.1 Supply and install acoustic panel 25 mm density 10g/cm3 to prevent the SQM 200 1,176.00 235,200.00 - 0.00% - 200.00 100.00% 235,200.00
spread of sound inside the hall and to prevent the exchange voice in all-
out the hall the panel are covered by a large of special fabric (from
CAMIRA-UK)
13.2.1.2 Supply and install wood 18mm MDF wood covered by natural wood SQM 100 916.00 91,600.00 - 0.00% - 100.00 100.00% 91,600.00
veneer from Oak or Cherry
13.2.1.3 Carpet: Supply and install Anti static 7 mm thickness tile carpet 50x50cm, SQM 270 392.00 105,840.00 - 0.00% - 270.00 100.00% 105,840.00
rubber layer from backside fixed for smooth concrete flooring design by
site contractor (from BURMATEX-UK)
13.2.1.4 PVC Nose for Steps LM 9 196.00 1,764.00 - 0.00% - 9.00 100.00% 1,764.00
13.2.1.5 Ceiling gypsum board 12mm thickness fixing by stead and runner SQM 285 262.00 74,670.00 - 0.00% - 285.00 100.00% 74,670.00
including painting with special design and color to be suitable with
decoration, scaffolding to be included.
13.2.1.6 12 mm. thk. Gypsum Board Wall, fixing by Light gauge galvanized studs SQM 300 262.00 78,600.00 - 0.00% - 300.00 100.00% 78,600.00
and runner including painting with special design and color to be suitable
with decoration, scaffolding to be included.
13.2.1.7 Painted Gypsum Board Ceiling: Color selection as per approved interior SQM 285 262.00 74,670.00 - 0.00% - 285.00 100.00% 74,670.00
design or suitable to the decoration.
13.2.1.8 14 mm Multi- layer Natural Wood Parquet fixed on smooth concrete LM 36 2,614.00 94,104.00 - 0.00% - 36.00 100.00% 94,104.00
stage, (from HARO- Germany)
13.2.1.9 Stage Front area made of 18 mm thk. MDF Wood covered by Natural LS 1 52,268.00 52,268.00 - 0.00% - 1.00 100.00% 52,268.00
Wood Veneer from Oak or Cherry.
13.2.1.10Stage table for 3 person made of 18mm MDF wood width 4.3m covered by EA 1 52,268.00 52,268.00 - 0.00% - 1.00 100.00% 52,268.00
artificial leather at writing area
13.2.1.11Stage Table Movable Seats covered by Artificial Leather EA 3 117,600.00 352,800.00 - 0.00% - 3.00 100.00% 352,800.00
14.1.1.1 PASSENGER ELEVATORS- 1:1-4 UNIT 4 326,668.00 1,306,672.00 - 0.00% - 4.00 100.00% 1,306,672.00
a. Model: NEXIEZ- Series- MR
b. Type: Standard Machine Room System
c. Capacity: 11 Persons (750 kgs)
d. Qty.: 4- Set In- line
e. Stops/ Openings: 8 Stops: BF, GF,1F,2F,3F,4F,5F & 6F
f. Speed: 60 M/ Min. (1M/ Sec.)
g. Control: AC Variable Voltage Variable Frequency
h. Operation: Duplex Selective Collective
1. Jamb: Splayed Jamb w/ Transom Panel
14.1.1.2 HOSPITAL BED ELEVATOR- 2:5-6 UNIT 2 378,934.00 757,868.00 0.40 20.00% 151,573.60 1.60 80.00% 606,294.40
a. Model: NEXIEZ- Series- MR
b. Type: Standard Machine Room System
c. Capacity: 25 Persons (1000 kgs)
d. Qty.: 2 Set- In- Line
e. Stops/ Openings: 8 Stops: BF, GF,1F,2F,3F,4F,5F & 6F
f. Speed: 60 M/ Min. (1M/ Sec.)
g. Control: AC Variable Voltage Variable Frequency
h. Operation: Duplex Selective Collective
1. Jamb: Splayed Jamb w/ Transom Panel
14.1.1.3 PASSENGER ELEVATORS- 3:7-8 UNIT 2 326,668.00 653,336.00 - 0.00% - 2.00 100.00% 653,336.00
a. Model: NEXIEZ- Series- MR
b. Type: Standard Machine Room System
c. Capacity: 11 Persons (750 kgs)
d. Qty.: 2 Set In- line
e. Stops/ Openings: 7 Stops: GF.1F,2F,3F,4F,5F & 6F
f. Speed: 60 M/ Min. (1M/ Sec.)
g. Control: AC Variable Voltage Variable Frequency
h. Operation: Duplex Selective Collective
1. Jamb: Splayed Jamb w/ Transom Panel
14.1.1.4 PASSENGER ELEVATORS- 4:9,10 UNIT 2 261,334.00 522,668.00 1.80 90.00% 470,401.20 0.20 10.00% 52,266.80
a. Model: ELENESSA- Series- AP Version 2
b. Type: Machine Room- Less System
c. Capacity: 6 Persons (450 kgs/ Wide Type)
d. Qty.: 2 Set
e. Stops/ Openings: 4 Stops: BF,GF.1F & 2F
f. Speed: 60 M/ Min. (1M/ Sec.)
g. Control: AC Variable Voltage Variable Frequency
h. Operation: Duplex Selective Collective
1. Jamb: Splayed Jamb w/ Transom Panel
14.1.1.5 FREIGHT/ SERVICE ELEVATO 5:11 UNIT 1 980,000.00 980,000.00 0.80 80.00% 784,000.00 0.20 20.00% 196,000.00
a. Model: Freight Elevator Series GFC-L2
b. Type: Standard Machine Room System
c. Capacity: 2500 kgs.
d. Qty.: 1 Set- In- Line
e. Stops/ Openings: 8 Stops: BF, GF,1F,2F,3F,4F,5F & 6F
f. Speed: 60 M/ Min. (1M/ Sec.)
g. Control: AC Variable Voltage Variable Frequency
h. Operation: Duplex Selective Collective
1. Jamb: Splayed Jamb w/ Transom Panel
14.1.1.6 DUMBWAITER- 1: UNIT 2 104,534.00 209,068.00 1.80 90.00% 188,161.20 0.20 10.00% 20,906.80
a. Model: RU TYPE- 75S- 45
b. Type: Standard Machine Room system
c. Capacity: 75 kgs.
d. Qty.: 2 Set (Single Opening)
e. Stops/ Openings: 5 Stops: BF, GF,1F,2F & 3F
f. Speed: 45 M/ Min. (1M/ Sec.)
14.1.1.7 DUMBWAITER- 2: UNIT 1 196,000.00 196,000.00 0.80 80.00% 156,800.00 0.20 20.00% 39,200.00
a. Model: Rl TYPE- 500S- 23
b. Type: Standard Machine Room system
c. Capacity: 500 kgs.
d. Qty.: 1 Set (Single Opening)
e. Stops/ Openings: 2 Stops: BF & RD
f. Speed: 23 M/ Min. (1M/ Sec.)
1.00 The bill of quantity is only for the guidance for the contractor has to
ensure the closest possible quantity take offs, its deemed to be
responsibility of contractor to calculate the actual quantities of all works
for the subject project contract. The Contractor must bring the notice of
the Employer PM or the consultant office for any conflict in quantities,
missing items, variations, duplications, misconception etc.(if any)
3.00 The Contractor shall coordinate all services so that they are installed in
such manner to ensure proper performance and adequate fixing to the
structure and to avoid any conflicts in the positioning and leveling of the
various ducts, pipes, lighting and other items of service installations. Any
amendments to the engineering services Drawings dependent on the
coordination of the various engineering services, shall be made by the
Contractor prior to such Drawings being submitted for approval to the
Engineer. The coast implication of any remedial or additional works
incurred shall be borne by the Contractor.
4.00 The Contractor shall be fully responsible to communicate and coordinate Noted
with all Government authorities such as not limited to civil defense, road,
electricity for all proper drawings and works require to get the approval.
5.00 Design plan and material specification shall be strictly followed Noted
accordingly, any deviation from plan shall be given a full required
information for the reason of change(s)including full technical and
financial compression submission to the Project Manager and Engineer to
take the required action and any delay due to this change(s) shall
attribute to the Contractor
6.00 The Contractor must have an approval from the Employer in the event Noted
that the material specified herein is not available in the market or any
changes wishes by the Employer on especial cases.
Procare Riaya Hospital Expansion Page 2 of 81
Al-Khobar, Kingdom of Saudi Arabia
B The rate of items of work included In the Bill of Quantities are fixed for
the duration of the works and shall not be subject to any adjustments for
any reason or matter whatever this reason or matter and includes all cost
related to the following unless mentioned separately:
DISCLIMER (Continuation)
(i) All materials, fixing materials, accessories operation, appliances, tools, Noted
plant, equipment, transport, labor and incidents required in preparation
for the full and entire execution, testing, balancing, commissioning and
completion of the work called in the item and as per specification and
drawings
(ii) Wastage on materials and labor are included in the quoted price for all Noted
works.
(iii) Loading, transporting, unloading, handling, lifting to all levels, protecting Noted
and disposal of unwanted materials and all other labor force necessary in
and for the full and entire execution and to fully complete the job in
accordance with contract documents.
(iv) All the requirements of specifications, whether such requirements are Noted
mentioned in the item or not. The specifications and drawings where
available or are to be read as complimentary to and part of the schedule
of quantities and any work called for in one shall be taken as required for
all
(v) In the event of conflict between Bill of Quantities and other documents Noted
including the specifications, the most stringent shall apply in favor of the
Employer and to be decided by the Employer.
DISCLIMER (Continuation)
C The unit rates of each equipment or materials shall include cost for Noted
equipment and material including local duty, and also including
forwarding, freight and insurance up to construction stage at site, storage,
installation, testing, balancing, commissioning and other works required.
D All equipment, quantities and technical data indicated in this bill of Noted
quantities are for the contractor's guidance only. Are based on the
documents prepared by the Consultant. This schedule must be read in
conjunction with these documents.
Procare Riaya Hospital Expansion Page 3 of 81
Al-Khobar, Kingdom of Saudi Arabia
DISCLIMER (Continuation)
G Provisional Items. The Contractor is to note that the provisional sums Noted
included in the bills of quantities may be expanded in full or part or may
be removed from the contract in their entirety. Should these sums not be
expanded or removed and the works awarded to others not forming part
of this contract. The Contractor will not claim for any of loss of profit or
otherwise associated with such actions
1.20 SPECIFICATIONS
Procare Riaya Hospital Expansion Page 4 of 81
Al-Khobar, Kingdom of Saudi Arabia
1.2.1 The required Shop Drawings. LS 1 40,000 40,000.00 0.72 72.00% 28,800.00 0.28 28.00% 11,200.00
1.2.2 As-Built Drawings. LS 1 18,000 18,000.00 - 0.00% - 1.00 100.00% 18,000.00
1.2.3 Maintenance Manuals. LS 1 25,000 25,000.00 - 0.00% - 1.00 100.00% 25,000.00
1.2.4 All required Testing Works. LS 1 55,000 55,000.00 - 0.00% - 1.00 100.00% 55,000.00
1.2.5 Third party inspection ,testing and certificates for works and Equipment LS 1 102,000 102,000.00 - 0.00% - 1.00 100.00% 102,000.00
according to the Employer /Consultant(s) requirement and instruction.
1.30 MEASUREMENTS :
The contract is a fixed Lump Sum Contract and is not subject to re- LS 1 15,000 15,000.00 1.00 100.00% 15,000.00 - 0.00% -
measurement, unless it is specifically mentioned for specific elements of
work or where the Engineer shall require measuring any part of work in
accordance with the contract condition the works shall be measured net
as fixed with its place not with standing any general or local custom
which should be considered by the contractor while pricing the works.
1.40 PRICING :
1.4.1 The contractor shall satisfy as to meaning of every item in the Bill of LS 1 18,000 18,000.00 1.00 100.00% 18,000.00 - 0.00% -
Quantities, rates and price inserted by him will be deemed to cover all his
obligations, liabilities and services under the contract.
1.4.2 The contractor shall price all items for all sections which he considers LS 1 18,000 18,000.00 1.00 100.00% 18,000.00 - 0.00% -
have a value. If any items are to be of no values, it will be considered that
this value has been spread through out the rates of the other items and
included in the Contract Amount.
1.4.3 The Contractor shall investigate and verify the existence and location of LS 1 Included
any existing underground or over head services which may effect the
work.
1.4.4 The Contractor shall be held responsible for and deemed to have allowed LS 1 Included
in his pricing for the maintenance and protection and or re-routing of any
existing services.
1.4.5 The rates and prices included hereunder are fixed for duration of the LS 1 Included
works and shall not be subject to any adjustments for any reason or
matters whatever this reason or matter.
1.80 WATER:
The contractor shall arrange for and pay all charges in connection with LS 1 By Main
adequate supply of water for the works suitable for all purposes including Contractor
drinking sweet water for labours and staff.
1.90 RECORDS:
Upon completion of all scope of works work, the contractor shall submit LS 1 18,000 18,000.00 - 0.00% - 1.00 100.00% 18,000.00
three (3) sets of As built Drawings along with Electronic File(Auto CAD
Format) to the Employer. These drawings shall include all deviations
from the contract drawings including dimensions, quantities, material
and products
1.11.2 The contractor shall produce a site layout showing existing levels to5.00 LS 1 By Main
mtr. grid in two direction and updated soil investigation report and Contractor
handed over a negative of the same to Employer during the mobilization
stage.
1.16 INSURANCE:
All Insurance Liabilities for all risk policy (CAR) and third party Liability, LS 1 By Main
insurance and other insurance policies, and ensure all contractors, staffs, Contractor
workers, Equipment and Labours as per KSA regulation for all
contractors and subcontractors, Vendors, Suppliers, the supervision
Consultant staff, Project Manager Staff, the Employer Staff and the Project
Guests should be included
1.17.2 Over time period are any time period in excess of eight (8) normal LS 1 Included
working day light hours from Saturday to Wednesday and five (5) normal
working daylight hours on Thursday of any week.
1.17.3 All overtime supervision will be paid for by the Contractor at the LS 1 Included
following rate.
Project Engineer SAR.xxxx for each hour on site.
Engineer SAR.xxx for each hour on site.
Inspector SAR.xxx for each hour on site.
Document Controller SAR.xxx for each hour on site.
1.17.4 The above rates will be 1.5 times for weekends (and any night shift LS 1 Included
between the hours of 10.00 PM and 6.00 AM) and 2.00 times for national
holidays.
1.17.5 The total of such charges shall be deducted from the Contractors account LS 1 Included
and the contractor shall be provided with a detailed list of the personal
involved and hours expended for his information.
I
…………………………………………….
II
…………………………………………….
III
…………………………………………….
IV
…………………………………………….
Sub- Total: 55,000.00 0.00 55,000.00
TOTAL FOR - GENERAL REQUIREMENTS 490,000.00 23.02% 112,800.00 76.98% 377,200.00
Furnish, install and test Vitreous China Toilet Fixtures and Kitchen
Fixtures of standard and approved quality, complete with fittings and
accessories. All sanitary fixtures shall be from American Standard, Ideal
Standard, Bagno Design (Italy) or approved equal/approved by the Client
15.A.1.1.1 PANTRY:
a. Kitchen Sink:
"TANGO" R4585 AA, waste chrome, 2 Bowl sink, rub seal c/w EA 3 2,138 6,414.00 - 0.00% - 3.00 100.00% 6,414.00
draining board from Ideal Standard
b. Faucet: Celia One Hole Kitchen Mixer, Model #: A 3445 XX from Ideal EA 3 2,776 8,328.00 - 0.00% - 3.00 100.00% 8,328.00
Standard
a. Lavatory: Galassia "ARKE" Console Wash Basin, Model #: 8860, White EA 3 3,609 10,827.00 - 0.00% - 3.00 100.00% 10,827.00
From Bagno Design (ITALY)
Matching Faucet: "ZUCCHETTI", Model #: ZSB249, Chrome from Bagno EA 3 730 2,190.00 - 0.00% - 3.00 100.00% 2,190.00
Design (ITALY)
Procare Riaya Hospital Expansion Page 9 of 81
Al-Khobar, Kingdom of Saudi Arabia
b. Water Closet: "GSI TRACCIA", Model #: 6918- 11, Wall Mounted EA 3 4,848 14,544.00 - 0.00% - 3.00 100.00% 14,544.00
Water Closet with Concealed Flushing Cistern, "SAMBA" Flush Plate
(Dual Flush), chrome, Model #: 115.770.21.1, GEB- 111.300.00.1
Gerberit DuoFix Concealed Cistern in frame from Bagno Design (ITALY)
1. Towel Bar: Art #- BER- 3012 Towel Rail, 730 mm. Chrome EA 3 472 1,416.00 - 0.00% - 3.00 100.00% 1,416.00
2. Robe Hook: Art #: BER- 3015- Single Hook, Chrome EA 3 245 735.00 - 0.00% - 3.00 100.00% 735.00
3. Glass Holder: Art #: BER- 3000, Crystal Tumbler Holder, Chrome EA 3 368 1,104.00 - 0.00% - 3.00 100.00% 1,104.00
4. Toilet Paper Holder: Art #: BER- 3003, Toilet Paper Roll Holder w/ EA 3 415 1,245.00 - 0.00% - 3.00 100.00% 1,245.00
Lid, Chrome
5. Soap Dish: Art #: BER- 3001, Crystal Soap Dish, Chrome EA 3 348 1,044.00 - 0.00% - 3.00 100.00% 1,044.00
6. Towel Ring: Art #: BER- 3004, Towel Ring Chrome EA 3 377 1,131.00 - 0.00% - 3.00 100.00% 1,131.00
7. Glass Shelf: Art #: BER- 3007, Frosted Crystal Shelf, 600 mm, Chrome EA 3 652 1,956.00 - 0.00% - 3.00 100.00% 1,956.00
8. Mirror: Art #: IMA- 641250, Carlo Dizetto, Rectangular, Chrome EA 3 2,989 8,967.00 - 0.00% - 3.00 100.00% 8,967.00
Framed Mirror with Frosted Light Bulb, 230/ 240 V, 2 x 18 W
9. Perennial Spray: Nikita Ablution Set, Art #: BOS-C04045, Chrome EA 3 449 1,347.00 - 0.00% - 3.00 100.00% 1,347.00
10. Doctor Hand Wash: Art Ceram Fontana, Art #: L 045 Fontana, semi- EA 3 5,716 17,148.00 - 0.00% - 3.00 100.00% 17,148.00
recessed wash basin 45 w/ overflow on laminated wooden counter top
(Wenge) with under counter towel railing, Counter size: 450 W x 1200
L x 200 mm. Splash back
11 Matching Faucet: "ZUCCHETTI", Model #: 2SB249, Chrome EA 3 705 2,115.00 - 0.00% - 3.00 100.00% 2,115.00
a. Lavatory: "SMALL T0123" Counter Top Wash Basin 900 mm., central EA 3 6,184 18,552.00 - 0.00% - 3.00 100.00% 18,552.00
hole punched Lavatory on "SMALL T0679" Wall Hung Cabinet with
drawer & door on the left side, Wenge finish from IDEAL Standard
Matching Faucet: "ZUCCHETTI", Model # ZSB249, Chrome from Bagno EA 3 705 2,115.00 - 0.00% - 3.00 100.00% 2,115.00
Design (ITALY)
Procare Riaya Hospital Expansion Page 10 of 81
Al-Khobar, Kingdom of Saudi Arabia
c. Toilet Accessories:
1. Towel Bar: Art #: BER- 578, Double Towel Bar, 660 mm., Chrome EA 3 538 1,614.00 - 0.00% - 3.00 100.00% 1,614.00
2. Robe Hook: Art #: BER- 3015, Hook, Chrome EA 3 245 735.00 - 0.00% - 3.00 100.00% 735.00
3. Glass Holder: "ISYBAGNO", Art #: ZAC313, Glass Holder, Wenge EA 3 301 903.00 - 0.00% - 3.00 100.00% 903.00
wood
4. Toilet Paper Holder: Art #: ZUC- ZAC331, Paper Holder with cover, EA 3 444 1,332.00 - 0.00% - 3.00 100.00% 1,332.00
Chrome
5. Soap Dish: "ISYBAGNO", Art #: ZAC310, Soap Holder, Wenge wood EA 3 311 933.00 - 0.00% - 3.00 100.00% 933.00
6. Towel Ring: Art #: BER- 3004, Towel Ring Chrome EA 3 377 1,131.00 - 0.00% - 3.00 100.00% 1,131.00
7. Glass Shelf: "ISYBAGNO", Art #: ZAC 301, Shelf 600 mm., Wenge EA 3 443 1,329.00 - 0.00% - 3.00 100.00% 1,329.00
wood
8. Mirror: "Open Sky", Art #:IMA- 648061 w/ large designed lamo in EA 3 2,138 6,414.00 - 0.00% - 3.00 100.00% 6,414.00
stainless steel, illuminating through the bottom & top, 230/ 240 V, 4 x
80 W
9. Grab Bar: Art #: BER- 583, Grab Bar, 440 mm. Chrome EA 3 415 1,245.00 - 0.00% - 3.00 100.00% 1,245.00
10. Perennial spray: Nikita Ablution Set, Art #: BOS-C04045, Chrome EA 3 462 1,386.00 - 0.00% - 3.00 100.00% 1,386.00
d. Shower Enclosure:
1. Fixed Clear Tempered Glass, 6 mm. thk. With chrome framing & EA 6 3,657 21,942.00 - 0.00% - 6.00 100.00% 21,942.00
edging, 1600 W x 2000 H with Sliding Glass Door 1000 W x 2000 H
c/w door hardware's & accessories
2. Shower Mixer: "TONIC" A5223AA & Tonic A5151 Shower Head & EA 6 2,423 14,538.00 - 0.00% - 6.00 100.00% 14,538.00
Rail Assembly & Mixer, Chrome from IDEAL Standard
3. Shower Seat: Art #: EST- S0052011, Folding Shower Seat w/ EA 6 1,665 9,990.00 - 0.00% - 6.00 100.00% 9,990.00
Bracket, Aluminum
a. Pantry Sink: "TANGO" R4584AA, waste chrome sink, rub seal & EA 8 2,138 17,104.00 - 0.00% - 8.00 100.00% 17,104.00
wash, single bowl w/ drain board
Procare Riaya Hospital Expansion Page 11 of 81
Al-Khobar, Kingdom of Saudi Arabia
b. Lavatory: Ravenna Semi- Pedestal, Model #: 0258.444 white with EA 15 718 10,770.00 - 0.00% - 15.00 100.00% 10,770.00
integral Towel bar from American Standard.
Matching Faucet: N10 Single Lever Basin Mixer w/ pop- up waste by EA 15 928 13,920.00 - 0.00% - 15.00 100.00% 13,920.00
American Standard
c. Shower Enclosure: 6 mm. thk. Tempered Clear Glass shower EA 8 3,754 30,032.00 - 0.00% - 8.00 100.00% 30,032.00
enclosure with chrome framing & edging with 800 W x 2000 H c/w
door hardware's & accessories
d. Shower Tray: "ALCOVE" Shower Base, Model #: 4834. ST from EA 4 1,996 7,984.00 - 0.00% - 4.00 100.00% 7,984.00
American Standard
Matching Shower Mixer: "CERAWELL 100" Shower Kit, Model #: EA 12 1,094 13,128.00 - 0.00% - 12.00 100.00% 13,128.00
B3153AA & "CERATHERM 100" Bath & Shower Mixer from IDEAL
Standard
e. Water Closet: "AFWALL" Elongated 16 gpf Flushometer Model #: EA 15 3,052 45,780.00 - 0.00% - 15.00 100.00% 45,780.00
3352.160, White w/ American Standard Selectronic # 6065.161.002
(Top Spud) c/w accessories & fittings from American Standard
1. Towel Bar: "TONIC 4600", Art #: A46184 EA 12 415 4,980.00 - 0.00% - 12.00 100.00% 4,980.00
2. Robe Hook: "TONIC 46200", Art #: A46160 EA 12 178 2,136.00 - 0.00% - 12.00 100.00% 2,136.00
3. Glass Holder: "TONIC 4600", Art #: A46100 EA 12 301 3,612.00 - 0.00% - 12.00 100.00% 3,612.00
4. Toilet Paper Holder: "TONIC 4600", Art #: 4626B EA 12 396 4,752.00 - 0.00% - 12.00 100.00% 4,752.00
5. Soap Dish: "TONIC 4600", Art #: 46110 EA 12 396 4,752.00 - 0.00% - 12.00 100.00% 4,752.00
6. Towel Ring: "TONIC 4600", Art #: 46160 EA 12 528 6,336.00 - 0.00% - 12.00 100.00% 6,336.00
7. Glass Shelf: "TONIC 4600", Art #: 46080 EA 12 727 8,724.00 - 0.00% - 12.00 100.00% 8,724.00
8. Grab Bar: Art #: SIM- 401B605, Glazed Steel by Bagno Design EA 12 680 8,160.00 - 0.00% - 12.00 100.00% 8,160.00
(ITALY)
9. Perennial Spray: PATTY Ablution Set, Art #: BOS- C03075, Chrome EA 15 462 6,930.00 - 0.00% - 15.00 100.00% 6,930.00
by Bagno Design (ITALY)
10. Doctor Hand Wash: Cultured Granite Counter Top w/ built- in EA 8 2,515 20,120.00 - 0.00% - 8.00 100.00% 20,120.00
single bowl from Dupont Corian or approved equal
Matching Faucet: N10, Single Lever Basin Mixer w/ pop- up waste by EA 8 928 7,424.00 - 0.00% - 8.00 100.00% 7,424.00
American Standard
a. Doctor Hand Wash: Cultured Granite Counter Top w/ built- in single EA 29 2,515 72,935.00 - 0.00% - 29.00 100.00% 72,935.00
bowl from Dupont Corian or approved equal
Matching Faucet: N10, Single Lever Basin Mixer w/ pop- up waste by EA 29 928 26,912.00 - 0.00% - 29.00 100.00% 26,912.00
American Standard
b. Lavatory: Ovalyn Universal Access Sink, Model #: 9482.00 from EA 29 718 20,822.00 - 0.00% - 29.00 100.00% 20,822.00
American Standard
Matching Faucet: N10 Single Lever Basin Mixer w/ pop- up waste by EA 29 928 26,912.00 - 0.00% - 29.00 100.00% 26,912.00
American Standard
c. Water Closet: "AFWALL" Elongated 16 gpf Flushometer Model #: EA 29 3,052 88,508.00 - 0.00% - 29.00 100.00% 88,508.00
3352.160, White w/ American Standard Selectronic # 6065.161.002
(Top Spud) c/w accessories & fittings from American Standard
d. Shower Tray: "ALCOVE" Shower Base, Model #: 4834. ST from EA 14 1,996 27,944.00 - 0.00% - 14.00 100.00% 27,944.00
American Standard
Matching Shower Mixer: "CERAWELL 100" shower kit, Model # EA 29 1,094 31,726.00 - 0.00% - 29.00 100.00% 31,726.00
B3153AA & A5394AA exposed wall mounted Single lever Bath &
Shower Mixer from American Standard
1. Towel Bar: "WASHPOINT N 1043", Towel Bar 600 mm. EA 29 326 9,454.00 - 0.00% - 29.00 100.00% 9,454.00
2. Robe Hook: "WASHPOINT N1034" EA 29 159 4,611.00 - 0.00% - 29.00 100.00% 4,611.00
3. Glass Holder: "WASHPOINT N1038" EA 29 263 7,627.00 - 0.00% - 29.00 100.00% 7,627.00
4. Toilet Paper Holder: "WASHPOINT N1040" EA 29 348 10,092.00 - 0.00% - 29.00 100.00% 10,092.00
5. Soap Dish: "WASHPOINT N 1037" EA 29 283 8,207.00 - 0.00% - 29.00 100.00% 8,207.00
6. Glass Shelf: Model #: 7010.024 24" Glass Shelf "Green Tea" from EA 29 585 16,965.00 - 0.00% - 29.00 100.00% 16,965.00
American Standard
7. Grab Bars: Model #: B- 6806.49, 600 mm. with peened non- slip EA 29 415 12,035.00 - 0.00% - 29.00 100.00% 12,035.00
grip from Bobrick
8. Mirror: "TONIC" A 4915AA, 500 x 750 mm. with light by IDEAL EA 29 2,326 67,454.00 - 0.00% - 29.00 100.00% 67,454.00
Standard
9. Perennial Spray: Patty Ablution Set, Art 3: BOS-C03075, Chrome EA 29 462 13,398.00 - 0.00% - 29.00 100.00% 13,398.00
by Bagno Design (ITALY)
10. Shower Curtain c/w Track Railing & accessories EA 15 415 6,225.00 - 0.00% - 15.00 100.00% 6,225.00
a. Doctor Hand Wash: Cultured Granite Counter Top w/ built- in single EA 4 2,515 10,060.00 - 0.00% - 4.00 100.00% 10,060.00
bowl from Dupont Corian or approved equal.
Procare Riaya Hospital Expansion Page 13 of 81
Al-Khobar, Kingdom of Saudi Arabia
Matching Faucet: N10, Single Lever Basin Mixer w/ pop- up waste by EA 4 928 3,712.00 - 0.00% - 4.00 100.00% 3,712.00
American Standard.
b. Lavatory: Murro Universal Design Sink, Model #: 0954.000 w/ EA 4 955 3,820.00 - 0.00% - 4.00 100.00% 3,820.00
Shroud/ Knee Contact Guard, Model #: 0059.020 from American
Standard.
Matching Faucet: N10, Single Lever Basin Mixer w/ pop- up waste by EA 4 928 3,712.00 - 0.00% - 4.00 100.00% 3,712.00
American Standard.
c. Water Closet: "AFWALL" Elongated 16 gpf Flushometer Model #: EA 4 3,052 12,208.00 - 0.00% - 4.00 100.00% 12,208.00
3352.160, White w/ American Standard Selectronic # 6065.161.002
(Top Spud) c/w accessories & fittings from American Standard.
d. Shower Enclosure: 6 mm. thk. Tempered Clear Glass shower EA 1 3,754 3,754.00 - 0.00% - 1.00 100.00% 3,754.00
enclosure with chrome framing & edging with 800 W x 2000 H c/w
door hardware's & accessories.
e. Shower Tray: "ALCOVE" Shower Base, Model #: 4834. ST from EA 3 2,045 6,135.00 - 0.00% - 3.00 100.00% 6,135.00
American Standard.
Matching Shower Mixer: "CERAWELL 100" shower kit, Model # EA 4 1,143 4,572.00 - 0.00% - 4.00 100.00% 4,572.00
B3153AA & A5394AA exposed wall mounted Single lever Bath &
Shower Mixer from American Standard
1. Towel Bar: "WASHPOINT N 1043", Towel Bar 600 mm. EA 4 326 1,304.00 - 0.00% - 4.00 100.00% 1,304.00
2. Robe Hook: "WASHPOINT N1034" EA 4 159 636.00 - 0.00% - 4.00 100.00% 636.00
3. Glass Holder: "WASHPOINT N1038" EA 4 263 1,052.00 - 0.00% - 4.00 100.00% 1,052.00
4. Toilet Paper Holder: "WASHPOINT N1040" EA 4 348 1,392.00 - 0.00% - 4.00 100.00% 1,392.00
5. Soap Dish: "WASHPOINT N 1037" EA 4 283 1,132.00 - 0.00% - 4.00 100.00% 1,132.00
6. Glass Shelf: Model #: 7010.024 24" Glass Shelf "Green Tea" from EA 4 585 2,340.00 - 0.00% - 4.00 100.00% 2,340.00
American Standard
7. Grab Bars: Model #: B- 6806.49, 600 mm. with peened non- slip EA 4 415 1,660.00 - 0.00% - 4.00 100.00% 1,660.00
grip from Bobrick
8. Mirror: "TONIC" A 4915AA, 500 x 750 mm. with light by IDEAL EA 4 2,326 9,304.00 - 0.00% - 4.00 100.00% 9,304.00
Standard
9. Perennial Spray: Patty Ablution Set, Art 3: BOS- C03075, Chrome EA 4 462 1,848.00 - 0.00% - 4.00 100.00% 1,848.00
by Bagno Design (ITALY)
10. Shower Curtain c/w Track Railing & accessories EA 4 415 1,660.00 - 0.00% - 4.00 100.00% 1,660.00
a. Kitchen Sink: Cultured Granite Counter Top w/ built- in Double EA 4 3,366 13,464.00 - 0.00% - 4.00 100.00% 13,464.00
Basin w/ drain board by Dupont/ Corian or approved equal, (Pantry
Area)
Procare Riaya Hospital Expansion Page 14 of 81
Al-Khobar, Kingdom of Saudi Arabia
b. Kitchen Sink: Cultured Granite Counter Top w/ built- in single basin EA 31 2,515 77,965.00 - 0.00% - 31.00 100.00% 77,965.00
w/ drain board by Dupont/ Corian or approved equal, (Pantry Area)
Matching Faucet: Model #: A 5396AA "SLIMLINE" series from IDEAL EA 35 643 22,505.00 - 0.00% - 35.00 100.00% 22,505.00
Standard
c. Lavatory: Murro Universal Design Sink, Model #: 0954.000 w/ EA 64 955 61,120.00 - 0.00% - 64.00 100.00% 61,120.00
Shroud/ Knee Contact Guard, Model #: 0059.020 from American
Standard
Matching Faucet: Model #: A 5390AA, "SLIMLINE" series from IDEAL EA 64 406 25,984.00 - 0.00% - 64.00 100.00% 25,984.00
Standard
b. Lavatory: Murro Universal Design Sink, Model #: 0954.000 w/ EA 4 955 3,820 - 0.00% - 4.00 100.00% 3,820.00
Shroud/ Knee Contact Guard, Model #: 0059.020 from American
Standard
Matching Faucet: N10, Single Lever Basin Mixer w/ pop- up waste by EA 4 928 3,712 - 0.00% - 4.00 100.00% 3,712.00
American Standard
d. Lavatory (Public Toilet): Ovalyn Universal Access Sink, Model # EA 51 2,515 128,265.00 - 0.00% - 51.00 100.00% 128,265.00
9482.00 from American Standard on Cultured Granite Counter Top
from Dupont/ Corian
Matching Faucet: Model #: A 5390AA, "SLIMLINE" or approved equal EA 51 406 20,706.00 - 0.00% - 51.00 100.00% 20,706.00
e. Water Closet: "AFWALL" FloWise ADA Elongated Flushometer 1.28 EA 99 3,052 302,148.00 - 0.00% - 99.00 100.00% 302,148.00
gpf, Model # 3352.128 w/ American Standard Selectronic #
6065.121.002 (Top Spud) c/w accessories & fittings from American
Standard
Procare Riaya Hospital Expansion Page 15 of 81
Al-Khobar, Kingdom of Saudi Arabia
g. Shower Kit & Mixer: "CERAWELL 100S" Shower Kit with EA 4 1,143 4,572.00 - 0.00% - 4.00 100.00% 4,572.00
"SLIMLINE" series, Model #: A5394 AA, chromium plated, wall
mounted, single lever bath & shower mixer, 1/2 " from IDEAL
Standard
1. Tissue Paper Dispenser: Model #: B- 36903 Recessed Paper Towel EA 17 1,471 25,007.00 - 0.00% - 17.00 100.00% 25,007.00
Dispenser/ Waste Receptacle from Bobrick
2. Hand Dryer: Model # B- 715, surface mounted hand dryer "ELAN" EA 17 1,731 29,427.00 - 0.00% - 17.00 100.00% 29,427.00
w/ stainless steel louver from Bobrick
3. Liquid Soap Dispenser: "CONTURA", Model #: B- 8226 series EA 94 273 25,662.00 - 0.00% - 94.00 100.00% 25,662.00
lavatory mounted soap dispenser from Bobrick
4. Toilet Paper Holder: "EXPORT 2200", Model #: A22260 w/ lid EA 99 301 29,799.00 - 0.00% - 99.00 100.00% 29,799.00
cover from INDA Accessories
5. Mirror: 6 mm. thk. Tempered Glass Mirrors, Model #: B- 2908- EA 86 747 64,242.00 - 0.00% - 86.00 100.00% 64,242.00
1836, welded frame from Bobrick
7. Perennial Spray: N 9432AA Chromium plated, ablution faucet w/ EA 99 415 41,085.00 - 0.00% - 99.00 100.00% 41,085.00
back flow preventer
8. Soap Dish: "WASHPOINT N 1037" EA 4 283 1,132.00 - 0.00% - 4.00 100.00% 1,132.00
9. Towel Bar: "WASHPOINT N 1043", Towel Bar 600 mm. EA 4 348 1,392.00 - 0.00% - 4.00 100.00% 1,392.00
10. Shower Curtain c/w Track Railing & accessories EA 4 415 1,660.00 - 0.00% - 4.00 100.00% 1,660.00
11. Grab Bars: Model #: B- 6806.49, 600 mm. with peened non- slip EA 18 415 7,470.00 - 0.00% - 18.00 100.00% 7,470.00
grip from Bobrick
i. Drinking Fountain: "ELKAY", Model #: EDFP217C No lead, two level EA 30 9,235 277,050.00 - 0.00% - 30.00 100.00% 277,050.00
drinking fountain soft sides, wall mount- fully exposed w/ wall plate
c/w valve in flow regulator (20 to 105 psi), & LK464 drain, trap
assemblies & vandal resistant bottom cover plates
j. Janitor Sink: Lake well Service Sink, Model # 7692.008 c/w P- trap # SET 20 3,633 72,660.00 - 0.00% - 20.00 100.00% 72,660.00
T00- 003 IPS Matching Faucet: Model #: 8340.243 Exposed Yoke wall
mount utility faucet from American
k. Faucet for Laboratory Casework & Counter Top : Model; # A EA 76 406 30,856.00 - 0.00% - 76.00 100.00% 30,856.00
5390AA, "SLIMLINE" series from Standard
l. Scrub Sink: Two Station Wall Mount Scrub Sink w/ "OPTIMA" sensor SET 2 49,086 98,172.00 - 0.00% - 2.00 100.00% 98,172.00
activated matching faucets.
Procare Riaya Hospital Expansion Page 16 of 81
Al-Khobar, Kingdom of Saudi Arabia
m. Doctor Hand Wash: Cultured Granite Counter Top w/ built- in SET 37 2,515 93,055.00 - 0.00% - 37.00 100.00% 93,055.00
single bowl from Dupont Corian or approved equal for all Clinic
Rooms
Matching Faucet: N10, Single Lever Basin Mixer w/ pop- up waste by EA 37 928 34,336.00 - 0.00% - 37.00 100.00% 34,336.00
American Standard
n. Laboratory Sink: Single Bowl, Stainless Steel w/ dryer strip or EA 76 4,418 335,768.00 - 0.00% - 76.00 100.00% 335,768.00
approved equal for applicable to all medical rooms as shown on the
drawings.
15.A.1.1.7.1 Supply, installation, testing & commissioning of complete package for SET 3 81,162 243,486.00 - 0.00% - 3.00 100.00% 243,486.00
bathroom fixtures, accessories, equipment & etc. for Disabled Toilet as
per plan & design detail, see & refer drwg. No.: A-07, A-08 & A-09.
15.2.1.2 CALORIFIER: Capacity - 500 litres Maximum operating pressure at SET 4 70,349 281,396.00 - 0.00% - 4.00 100.00% 281,396.00
primary - 10 Bar Maximum operating pressure at secondary - 10 Bar
Maximum operating temperature at primary - 110 deg c Maximum
operating temperature of stored water - 70 deg c Heat Input - 500 kw
Recovery time - (10 - 60) minutes
15.2.1.3 BOILER: Capacity - 500 litres Maximum operating pressure at primary - SET 1 517,312 517,312.00 - 0.00% - 1.00 100.00% 517,312.00
10 Bar Maximum operating pressure at secondary - 10 Bar Maximum
operating temperature at primary - 110 deg c Heat Input - 600 kw
Recovery time - (10 - 60) minutes
15.2.1.4.1 Hot water Re- Circulating Pump: ( 1 Duty & 1 Stand By ) SET 1 30,812 30,812.00 - 0.00% - 1.00 100.00% 30,812.00
Capacity: 10 GPM
Head: 110 Ft.
Rated Hp: 2Hp
Power supply: 220V/ 3Ph/ 60 Hz
Procare Riaya Hospital Expansion Page 17 of 81
Al-Khobar, Kingdom of Saudi Arabia
15.2.1.4.2 Triplex Booster Pump Set w/ Pressure Tank: - Raw Water SET 1 73,040 73,040.00 - 0.00% - 1.00 100.00% 73,040.00
Capacity: 85 GPM
Head: 236 Ft.
Rated Hp: 8 Hp
Power supply: 380/ 127V/ 3Ph/ 60 Hz
15.2.1.4.3 Pressure Pump: SET 1 10,996 10,996.00 - 0.00% - 1.00 100.00% 10,996.00
Capacity: 10 GPM
Head: 92 Ft.
Rated Hp: 3/4 Hp
Power supply: 220V/ 1Ph/ 60 Hz
15.2.1.4.4 Lift Pump # 1:( 1 Duty & 1 Stand By ) SET 1 27,070 27,070.00 - 0.00% - 1.00 100.00% 27,070.00
Capacity: 60 GPM
Head: 65 Ft.
Rated Hp: 2 Hp
Power supply: 220V/ 1 Ph/ 60 Hz
15.2.1.4.5 Lift Pump # 2: ( 1 Duty & 1 Stand By ) SET 1 24,737 24,737.00 - 0.00% - 1.00 100.00% 24,737.00
Capacity: 20 GPM
Head: 65 Ft.
Rated Hp: 3/4 Hp
Power supply: 220V/ 1 Ph/ 60 Hz
15.2.1.4.6 Lift Pump # 3: ( Alternate Operation ) Rated Hp: 3/4 Hp SET 0 0 0.00 - 0.00% - - 100.00% -
15.2.1.4.7 Lift Pump # 4: ( Alternate Operation ) Rated Hp: 2 Hp SET 0 0 0.00 - 0.00% - - 100.00% -
15.2.1.4.8 Triplex Booster Pump Set w/ Pressure Tank: - Sweet Water SET 1 72,433 72,433.00 - 0.00% - 1.00 100.00% 72,433.00
Capacity: 139 GPM
Head: 236 Ft.
Rated Hp: 14 Hp
Power supply: 380/ 127V/ 3Ph/ 60 Hz
15.2.1.4.9 Make up pump for Boiler : ( 1 Duty & 1 Stand By ) SET 1 21,434 21,434.00 - 0.00% - 1.00 100.00% 21,434.00
Capacity: 6 GPM
Head: 110 Ft.
Rated Hp: 1 Hp
Power supply: 220V/ 3 Ph/ 60 Hz
15.2.1.6.1.1 Capacity: 2000 Gallons SET 2 14,489 28,978.00 - 0.00% - 2.00 100.00% 28,978.00
Pipes and fittings shall be "u-PVC Schedule 80" for cold water supply &
"cPVC Schedule 80"
15.2.2.1.1 1/2" Ø LM 2770 54 149,580.00 1,590.25 57.41% 85,873.42 1,179.75 42.59% 63,706.58
15.2.2.1.2 3/4" Ø LM 697 65 45,305.00 389.05 55.82% 25,288.25 307.95 44.18% 20,016.75
15.2.2.1.3 1" Ø LM 590 71 41,890.00 329.90 55.92% 23,422.90 260.10 44.08% 18,467.10
15.2.2.1.4 1 1/2 Ø LM 285 111 31,635.00 156.44 54.89% 17,364.45 128.56 45.11% 14,270.55
15.2.2.1.5 2" Ø LM 438 131 57,378.00 240.07 54.81% 31,448.88 197.93 45.19% 25,929.12
15.2.2.1.6 3" Ø LM 475 155 73,625.00 268.42 56.51% 41,605.49 206.58 43.49% 32,019.51
15.2.2.1.7 4" Ø LM 411 304 124,944.00 207.76 50.55% 63,159.19 203.24 49.45% 61,784.81
15.2.2.2.1 1/2" Ø LM 3080 81 249,480.00 1,391.24 45.17% 112,690.12 1,688.76 54.83% 136,789.88
15.2.2.2.2 3/4" Ø LM 970 94 91,180.00 470.26 48.48% 44,204.06 499.74 51.52% 46,975.94
15.2.2.2.1 1" Ø PE LM 536 101 54,136.00 270.09 50.39% 27,279.13 265.91 49.61% 26,856.87
15.2.2.2.2 1 1/2" Ø LM 650 150 97,500.00 310.31 47.74% 46,546.50 339.69 52.26% 50,953.50
15.2.2.2.1 2" Ø LM 650 176 114,400.00 335.14 51.56% 58,984.64 314.86 48.44% 55,415.36
15.2.2.2.2 3" Ø LM 425 214 90,950.00 204.00 48.00% 43,656.00 221.00 52.00% 47,294.00
15.2.2.3.1 1/2" valve EA 631 145 91,495.00 358.60 56.83% 51,996.61 272.40 43.17% 39,498.39
15.2.2.3.2 3/4" valve EA 109 147 16,023.00 62.00 56.88% 9,113.88 47.00 43.12% 6,909.12
15.2.2.3.3 1" valve EA 82 194 15,908.00 47.50 57.93% 9,215.50 34.50 42.07% 6,692.50
15.2.2.3.4 1 1/4" valve EA 4 270 1,080.00 3.60 90.00% 972.00 0.40 10.00% 108.00
15.2.2.3.5 1 1/2" valve EA 29 335 9,715.00 16.30 56.21% 5,460.80 12.70 43.79% 4,254.20
15.2.2.3.6 2 " Valve EA 16 657 10,512.00 10.40 65.00% 6,832.80 5.60 35.00% 3,679.20
15.2.2.3.7 3 " valve EA 22 2,261 49,742.00 12.90 58.64% 29,168.71 9.10 41.36% 20,573.29
15.2.2.3.8 4 " valve EA 7 2,827 19,789.00 5.20 74.29% 14,701.25 1.80 25.71% 5,087.75
15.2.2.4 Water Hammer Arrestor (WHA): EA 508 204 103,632.00 215.09 42.34% 43,877.79 292.91 57.66% 59,754.21
15.2.2.4.4 Brass Type Hose Bibb EA 18 149 2,682.00 - 0.00% - 18.00 100.00% 2,682.00
15.2.2.4.5 Brass Type Check Valve EA 8 2,538 20,304.00 - 0.00% - 8.00 100.00% 20,304.00
15.2.3.1.1 2''Ø LM 1123 49 55,027.00 897.00 79.88% 43,953.00 226.00 20.12% 11,074.00
15.2.3.1.2 3'' Ø LM 850 61 51,850.00 677.10 79.66% 41,303.10 172.90 20.34% 10,546.90
15.2.3.1.3 4'' Ø LM 1426 88 125,488.00 1,145.50 80.33% 100,804.00 280.50 19.67% 24,684.00
15.2.3.1.4 6'' Ø LM 560 133 74,480.00 420.40 75.07% 55,913.20 139.60 24.93% 18,566.80
PIPES AND FITTINGS: Supply and Installation of pipes including fittings, valves,
fittings, hangers and all other accessories.
15.2.3.2.1 1-1/2'' LM 730 32 23,360.00 518.40 71.01% 16,588.80 211.60 28.99% 6,771.20
15.2.3.2.2 2'' LM 870 49 42,630.00 593.30 68.20% 29,071.70 276.70 31.80% 13,558.30
15.2.3.2.3 2 1/2'' LM 2123 53 112,519.00 1,410.10 66.42% 74,735.30 712.90 33.58% 37,783.70
15.2.3.2.4 3'' LM 750 61 45,750.00 487.70 65.03% 29,749.70 262.30 34.97% 16,000.30
15.2.3.3.1 3" Ø pvc pipe schedule 40 LM 362 56 20,272.00 - 0.00% - 362.00 100.00% 20,272.00
15.2.3.3.2 2" Ø pvc pipe schedule 40 LM 18 30 540.00 - 0.00% - 18.00 100.00% 540.00
15.2.3.4.1 4" Ø Roof Drain PCS 22 373 8,206.00 - 0.00% - 22.00 100.00% 8,206.00
15.2.3.5.2 4" Ø pvc pipe schedule 40 EA 4 1,627 6,508.00 - 0.00% - 4.00 100.00% 6,508.00
15.2.3.6.1 4" Ø Floor Drain w/ heavy duty round stainless steel adjustable strainer EA 340 642 218,280.00 - 0.00% - 340.00 100.00% 218,280.00
from MIFAB Brand F- 1000- C series.
15.2.3.7.2 4" Ø Floor Cleanout w/ stainless steel round top from MIFAB Brand, EA 348 642 223,416.00 - 0.00% - 348.00 100.00% 223,416.00
C1000- R series or approved equal
15.2.3.7.3 6" Ø Floor Cleanout w/ stainless steel round top from MIFAB Brand, EA 40 930 37,200.00 - 0.00% - 40.00 100.00% 37,200.00
C1000- R series or approved equal
15.2.3.10.1 6" Clean Out EA 2 915 1,830.00 - 0.00% - 2.00 100.00% 1,830.00
15.2.3.10.2 4" Clean Out EA 1 761 761.00 - 0.00% - 1.00 100.00% 761.00
Procare Riaya Hospital Expansion Page 21 of 81
Al-Khobar, Kingdom of Saudi Arabia
15.3.1.1.1 160 mm dia. G.I Pipe. LM 27 384 10,368.00 - 0.00% - 27.00 100.00% 10,368.00
15.3.1.2.1 160 mm dia. Carbon Steel, Sch. 40 pipe. LM 50 290 14,500.00 43.50 87.00% 12,615.00 6.50 13.00% 1,885.00
15.3.1.2.2 110 mm dia. Carbon Steel, Sch. 40 pipe. LM 415 191 79,265.00 358.25 86.33% 68,425.75 56.75 13.67% 10,839.25
15.3.1.2.3 75 mm dia. Carbon Steel, Sch. 40 pipe. LM 482 145 69,890.00 415.95 86.30% 60,312.75 66.05 13.70% 9,577.25
15.3.1.2.4 65 mm dia. Carbon Steel, Sch. 40 pipe. LM 305 121 36,905.00 263.10 86.26% 31,835.10 41.90 13.74% 5,069.90
15.3.1.2.5 50 mm dia. Carbon Steel, Sch. 40 pipe. LM 925 101 93,425.00 798.18 86.29% 80,616.43 126.82 13.71% 12,808.57
15.3.1.2.6 40 mm dia. Carbon Steel, Sch. 40 pipe. LM 448 70 31,360.00 386.71 86.32% 27,069.95 61.29 13.68% 4,290.05
15.3.1.2.7 32 mm dia. Carbon Steel, Sch. 40 pipe. LM 605 57 34,485.00 522.25 86.32% 29,768.25 82.75 13.68% 4,716.75
15.3.1.2.8 25 mm dia. Carbon Steel, Sch. 40 pipe. LM 3800 45 171,000.00 3,150.20 82.90% 141,759.00 649.80 17.10% 29,241.00
15.3.1.3.1 Supply and install Fire Hose Cabinet (FHC), recessed type, annealed cold EA 65 3,880 252,200.00 - 0.00% - 65.00 100.00% 252,200.00
sheet steel made 1.6 mm thickness, Clear Glass Door with Stainless Steel
Handle, Polished with complete Hose Reel assembly, 25 mm. dia. Landing
Valve of 40 mm. x 25 mm. Plain Hose Pipe Nozzle (adjustable, shut off/
stream/ straight,25 mm. dia. X 30.00 meters rubber fire hose, lock pull
handle and Fire Extinguisher, 6 Kg. DCP/ CO2.
15.3.1.4.1 Siamese Inlet complete with Check Valves and accessories, 100 x 65 x 65 EA 5 2,649 13,245.00 - 0.00% - 5.00 100.00% 13,245.00
mm. w/ Cap & Chain, round escutcheon plate w/ "STANDPIPE" branding
body.
15.3.1.6 PENDANT TYPE SPRINKLER ( CONCEALED TYPE - LIFECO )1/2" Orifice EA 1410 121 170,610.00 - 0.00% - 1,410.00 100.00% 170,610.00
dia. 57 degrees Thermal sensitivity k=5.5, Chrome Plated Brass Body
1/2" NPT U/L.
15.3.1.7 UPRIGHT TYPE SPRINKLER( LIFECO )1/2" Orifice dia. 68 degrees EA 255 49 12,495.00 - 0.00% - 255.00 100.00% 12,495.00
Thermal sensitivity k=5.5, Chrome Plated Brass Body 1/2" NPT U/L.
15.3.1.8 ZONE VALVE (ZV) 200 PSIG, Cast Iron, Flanged type with OS&Y Gate EA 12 3,237 38,844.00 5.01 41.75% 16,217.37 6.99 58.25% 22,626.63
valve, water flow switch, tamper switch, pressure gauge, inspection test
drain system. As shown on the pipe detail.
15.3.1.9.2 FE-2- Portable Fire Extinguisher CO2 Type capacity - 4.5 kg. NO 31 1,279 39,649.00 - 0.00% - 31.00 100.00% 39,649.00
15.3.1.11.1 Supply, Install and Commission of Wet Chemical Fire Suppression System SET 1 67,120 67,120.00 - 0.00% - 1.00 100.00% 67,120.00
complete with piping, sprinkler and all other accessories required as per
NFPA standards and drawing for Kitchen.
15.3.1.12.1 Alarm check valve riser element with complete set of Retard Chamber, SET 1 5,076 5,076.00 - 0.00% - 1.00 100.00% 5,076.00
Inspector Test, Pressure Gauge, Pressure Releasing Valve, Water Alarm
Motor, Gate Valve and all other standard accessories required.
15.3.1.13.1.3 JOCKEY PUMP: NO. 1 15,795 15,795.00 - 0.00% - 1.00 100.00% 15,795.00
Flow Discharge :- 50 US GPM
Head :- 300 Ft
Pump HP :- 15 HP
Power Supply :-380 V / 3 PH / 60 HZ
15.3.1.16 Pre- Action Double Interlock Sprinkler System for Operation Theater NO 1 69,188 69,188.00 - 0.00% - 1.00 100.00% 69,188.00
15.3.2.1 Medical system includes the supply of Oxygen, Nitrous Oxide Vacuum
line, Medical Air, Anesthetic Gas Suction & Nitrogen Recommended
supplier: MIDAS, MLS or approved equal.
15.3.2.1.1 Medical Air compressor - 4 Bar ( 1 Duty & 1 Standby ) SET 1 554,040 554,040.00 - 0.00% - 1.00 100.00% 554,040.00
Reciprocating Compressor
HP - 5
SCFM @ 100 PSI Per Compressor - 18
Receiver Gallons - 120
Power - 380V/3Ph/60Hz
Procare Riaya Hospital Expansion Page 24 of 81
Al-Khobar, Kingdom of Saudi Arabia
15.3.2.1.3 Medical Vacuum Pump ( 1 Duty & 1 Standby ) SET 1 225,990 225,990.00 - 0.00% - 1.00 100.00% 225,990.00
Dry Running Rotary
HP - 7.5Flow
CFM - 38
Receiver Gallons - 200
Power - 380V/3Ph/60Hz
Maximum Continuous Vacuum inch HG - 29 9
15.3.2.1.1.1 38 mm Dia LM 625 413 258,125.00 118.06 18.89% 48,759.81 506.94 81.11% 209,365.19
15.3.2.1.1.2 25 mm Dia LM 350 257 89,950.00 258.30 73.80% 66,383.10 91.70 26.20% 23,566.90
15.3.2.1.1.3 19 mm Dia LM 960 210 201,600.00 729.20 75.96% 153,132.00 230.80 24.04% 48,468.00
15.3.2.1.1.4 12 mm Dia LM 325 108 35,100.00 186.50 57.38% 20,142.00 138.50 42.62% 14,958.00
15.3.2.1.1.5 6 mm Dia LM 27 102 2,754.00 14.90 55.19% 1,519.93 12.10 44.81% 1,234.07
15.3.2.1.2 AIR OUTLET POINTS WITH ALL VALVES AND REQUIRED ACCESSORIES
15.3.2.1.2.1 Oxygen NO. 101 1,112 112,312.00 - 0.00% - 101.00 100.00% 112,312.00
15.3.2.1.2.2 Vacuum NO. 101 1,112 112,312.00 - 0.00% - 101.00 100.00% 112,312.00
15.3.2.1.2.3 Nitrous Oxide NO. 7 1,112 7,784.00 - 0.00% - 7.00 100.00% 7,784.00
15.3.2.1.2.4 Medical Air-4 Bar NO. 26 1,112 28,912.00 - 0.00% - 26.00 100.00% 28,912.00
15.3.2.1.2.5 Medical Air-7 Bar NO. 1 1,112 1,112.00 - 0.00% - 1.00 100.00% 1,112.00
15.3.2.1.2.6 Anesthetic gas suction NO. 7 1,592 11,144.00 - 0.00% - 7.00 100.00% 11,144.00
15.3.2.1.2.7 Nitrogen NO. 12 1,592 19,104.00 - 0.00% - 12.00 100.00% 19,104.00
15.3.2.1.3 Alarm Panel ( MP -26 ) from HILLROM or approved equal. SET 16 10,207 163,312.00 - 0.00% - 16.00 100.00% 163,312.00
15.3.2.1.4 Alarm Panel ( MP -125 ) from HILLROM or approved equal. SET 1 8,141 8,141.00 - 0.00% - 1.00 100.00% 8,141.00
15.3.2.1.5 Oxygen Emergency Standby Manifold 2 x 1 SET 1 29,160 29,160.00 - 0.00% - 1.00 100.00% 29,160.00
Procare Riaya Hospital Expansion Page 25 of 81
Al-Khobar, Kingdom of Saudi Arabia
* Bed Head Units will be under provisional item or supplied by the Client/
Owner.
15.3.2.1.6.1 Isolation Room SET 4 1,436 5,744.00 - 0.00% - 4.00 100.00% 5,744.00
15.3.2.1.6.2 ICU SET 4 1,436 5,744.00 - 0.00% - 4.00 100.00% 5,744.00
15.3.2.1.6.3 Patient Room SET 41 1,436 58,876.00 - 0.00% - 41.00 100.00% 58,876.00
15.3.2.1.6.4 Recovery Room SET 5 1,436 7,180.00 - 0.00% - 5.00 100.00% 7,180.00
15.1.1.1 AIR COOLED LIQUID CHILLER- ACCLC SET 4 664,666 2,658,664.00 - 0.00% - 4.00 100.00% 2,658,664.00
Flow : 786 GPM
Capacity: 360 Ton
Power : 380 V / 60 HZ / 3 PH
Procare Riaya Hospital Expansion Page 26 of 81
Al-Khobar, Kingdom of Saudi Arabia
15.1.1.3 SECONDARY PUMP ( VFD Type ) CHWSP SET 3 74,816 224,448.00 - 0.00% - 3.00 100.00% 224,448.00
Flow : 1180 GPM
Head - 150 ft.
Power : 380 V / 60 HZ / 3 PH
15.2.1.11 OAHU- 1A&1B With ERU SET 2 263,508 527,016.00 - 0.00% - 2.00 100.00% 527,016.00
Cooling Capacity: 1714 MBH
Supply Air Flow: 15103 CFM
Power: 380V / 3PH / 60 HZ
ESP: 4" WG
Water Flow Rate : 312 GPM
Procare Riaya Hospital Expansion Page 28 of 81
Al-Khobar, Kingdom of Saudi Arabia
15.2.1.14 FCU'S
15.4.1.1 Supply, install, test chilled water pipes (supply and return) system
complete with piping, insulations, fittings, sleeves and all other required
accessories. Pipes and fittings shall be Carbon Steel ATSM A53 Sch.40,
Black Steel, Seamless Pipe.
15.4.1.1.1 25 mm. pipe diameter LM 2420 49 118,580.00 1,811.00 74.83% 88,739.00 609.00 25.17% 29,841.00
15.4.1.1.2 38 mm. pipe diameter LM 520 71 36,920.00 386.20 74.27% 27,420.48 133.80 25.73% 9,499.52
15.4.1.1.3 50 mm. pipe diameter LM 655 107 70,085.00 471.51 71.99% 50,451.36 183.49 28.01% 19,633.64
15.4.1.1.4 75 mm. pipe diameter LM 820 150 123,000.00 574.35 70.04% 86,152.50 245.65 29.96% 36,847.50
15.4.1.1.5 100 mm. pipe diameter LM 295 187 55,165.00 181.72 61.60% 33,981.64 113.28 38.40% 21,183.36
15.4.1.1.6 150 mm. pipe diameter LM 120 534 64,080.00 86.00 71.67% 45,926.14 34.00 28.33% 18,153.86
15.4.1.1.7 200 mm. pipe diameter LM 150 716 107,400.00 114.00 76.00% 81,624.00 36.00 24.00% 25,776.00
15.4.1.1.8 250 mm. pipe diameter LM 60 868 52,080.00 44.00 73.33% 38,192.00 16.00 26.67% 13,888.00
15.4.1.1.9 300 mm. pipe diameter LM 110 1,032 113,520.00 74.00 67.27% 76,368.00 36.00 32.73% 37,152.00
15.5.1.1.1 Supply Duct, Ga # 22 SQM 5750 189 1,086,750.00 4,776.00 83.06% 902,664.00 974.00 16.94% 184,086.00
15.5.1.1.2 Return Duct, Ga.# 22 SQM 3500 189 661,500.00 3,139.10 89.69% 593,289.90 360.90 10.31% 68,210.10
15.5.1.1.3 Exhaust Duct, Ga.# 22 SQM 4750 189 897,750.00 4,264.50 89.78% 805,990.50 485.50 10.22% 91,759.50
15.5.1.1.4 Fresh Air Duct, Ga.# 22 SQM 2825 189 533,925.00 2,546.90 90.16% 481,364.10 278.10 9.84% 52,560.90
15.5.2 Take-offs Balancing Volume Dampers, Main and Branches Balancing LOT 1 460,378 460,378.00 - 0.00% - 1.00 100.00% 460,378.00
Volume Dampers (see HVAC plan)
15.5.3 Fire Dampers (see HVAC plan ) LOT 1 73,629 73,629.00 0.66 66.00% 48,595.14 0.34 34.00% 25,033.86
Procare Riaya Hospital Expansion Page 36 of 81
Al-Khobar, Kingdom of Saudi Arabia
15.5.5.2 Duct Insulation, 25 mm thick fiberglass board, 36kg/m³ w/ density to LOT 1 125,315 125,315.00 0.82 81.71% 102,398.28 0.18 18.29% 22,916.72
include fittings, accessories & w/ nylon lining.
15.5.7.1.1 600 X 600 mm. size NO. 940 448 421,120.00 - 0.00% - 940.00 100.00% 421,120.00
15.5.7.1.2 300 X 300 mm. size NO. 30 360 10,800.00 - 0.00% - 30.00 100.00% 10,800.00
15.5.7.2.1 600 X 600 mm. size NO. 380 409 155,420.00 - 0.00% - 380.00 100.00% 155,420.00
15.5.7.2.2 300 X 300 mm. size NO. 10 238 2,380.00 - 0.00% - 10.00 100.00% 2,380.00
15.5.7.3.1 Supply Air Flow Rate (CFM): 1500 CFM NO. 1 2,753 2,753.00 - 0.00% - 1.00 100.00% 2,753.00
15.5.7.3.2 Supply Air Flow Rate (CFM): 2000 CFM NO. 5 2,987 14,935.00 - 0.00% - 5.00 100.00% 14,935.00
15.5.7.4.1 Filter Size (400mm X 400mm) NO. 3 1,576 4,728.00 - 0.00% - 3.00 100.00% 4,728.00
15.5.7.4.2 Filter Size (400mm X 350mm) NO. 1 1,702 1,702.00 - 0.00% - 1.00 100.00% 1,702.00
15.5.7.4.3 Filter Size (450mm X 450mm) NO. 1 1,973 1,973.00 - 0.00% - 1.00 100.00% 1,973.00
15.5.7.4.4 Filter Size (500mm X 350mm) NO. 1 2,101 2,101.00 - 0.00% - 1.00 100.00% 2,101.00
15.5.7.5.1.1 600 X 600 mm. size NO. 130 391 50,830.00 - 0.00% - 130.00 100.00% 50,830.00
15.5.7.5.1.2 300 X 300 mm. size NO. 185 238 44,030.00 - 0.00% - 185.00 100.00% 44,030.00
15.5.7.6.1 300 mm X 150 mm. size NO. 4 202 808.00 - 0.00% - 4.00 100.00% 808.00
15.5.7.6.2 300 mm X 200 mm. size NO. 16 206 3,296.00 - 0.00% - 16.00 100.00% 3,296.00
15.5.7.6.3 300 mm X 300 mm. size NO. 2 211 422.00 - 0.00% - 2.00 100.00% 422.00
15.5.7.6.4 400 mm X 150 mm. size NO. 6 218 1,308.00 - 0.00% - 6.00 100.00% 1,308.00
15.5.7.6.5 400 mm X 200 mm. size NO. 1 242 242.00 - 0.00% - 1.00 100.00% 242.00
15.5.7.6.6 400 mm X 300 mm. size NO. 19 254 4,826.00 - 0.00% - 19.00 100.00% 4,826.00
15.5.7.6.7 400 mm X 400 mm. size NO. 6 284 1,704.00 - 0.00% - 6.00 100.00% 1,704.00
15.5.7.6.8 500 mm X 100 mm. size NO. 4 258 1,032.00 - 0.00% - 4.00 100.00% 1,032.00
15.5.7.6.9 500 mm X 150 mm. size NO. 2 271 542.00 - 0.00% - 2.00 100.00% 542.00
15.5.7.6.10 500 mm X 200 mm. size NO. 10 288 2,880.00 - 0.00% - 10.00 100.00% 2,880.00
15.5.7.6.11 500 mm X 300 mm. size NO. 8 312 2,496.00 - 0.00% - 8.00 100.00% 2,496.00
15.5.7.6.12 500 mm X 400 mm. size NO. 5 346 1,730.00 - 0.00% - 5.00 100.00% 1,730.00
15.5.7.6.13 600 mm X 200 mm. size NO. 2 329 658.00 - 0.00% - 2.00 100.00% 658.00
15.5.7.6.14 600 mm X 400 mm. size NO. 1 390 390.00 - 0.00% - 1.00 100.00% 390.00
15.5.7.6.15 600 mm X 600 mm. size NO. 3 498 1,494.00 - 0.00% - 3.00 100.00% 1,494.00
15.5.7.6.16 1000 mm X 500 mm. size NO. 3 775 2,325.00 - 0.00% - 3.00 100.00% 2,325.00
15.5.7.6.17 700 mm X 450 mm. size NO. 1 450 450.00 - 0.00% - 1.00 100.00% 450.00
15.5.7.6.18 1250 mm X 900 mm. size NO. 1 1,067 1,067.00 - 0.00% - 1.00 100.00% 1,067.00
15.5.7.6.19 1200 mm X 600 mm. size NO. 1 1,027 1,027.00 - 0.00% - 1.00 100.00% 1,027.00
15.5.7.12 HEPA Filters ( See HVAC plan and control diagram ) NO. 6 2,880 17,280.00 - 0.00% - 6.00 100.00% 17,280.00
15.5.7.13.1 2500 X 1000 NO. 1 12,880 12,880.00 - 0.00% - 1.00 100.00% 12,880.00
15.5.7.13.2 600 mm X 100 NO. 1 7,048 7,048.00 - 0.00% - 1.00 100.00% 7,048.00
15.5.7.13.3 600 mm X 200 NO. 1 7,412 7,412.00 - 0.00% - 1.00 100.00% 7,412.00
15.12.1.1.1 EF - 1, AIR FLOW -1085 CFM SET 1 4,271 4,271.00 - 0.00% - 1.00 100.00% 4,271.00
Static Pressure: 3.5"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.2 EF - 2, AIR FLOW -3568 CFM SET 1 9,890 9,890.00 - 0.00% - 1.00 100.00% 9,890.00
Static Pressure: 4"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
Procare Riaya Hospital Expansion Page 39 of 81
Al-Khobar, Kingdom of Saudi Arabia
15.12.1.1.4 EF - 4, AIR FLOW -1644 CFM SET 1 5,540 5,540.00 - 0.00% - 1.00 100.00% 5,540.00
Static Pressure: 3.5"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.6 EF - 6A&6B, AIR FLOW -1322 CFM SET 2 4,617 9,234.00 - 0.00% - 2.00 100.00% 9,234.00
Static Pressure: 3.5"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.7 EF - 7, AIR FLOW -4594 CFM SET 1 8,074 8,074.00 - 0.00% - 1.00 100.00% 8,074.00
Static Pressure: 4"
Power: 380 V /3 PH / 60 HZ
Type : Centrifugal
15.12.1.1.8 EF - 8, AIR FLOW -5425 CFM SET 1 8,280 8,280.00 - 0.00% - 1.00 100.00% 8,280.00
Static Pressure: 4"
Power: 380 V / 3 PH / 60 HZ
Type : Centrifugal
15.12.1.1.9 EF - 9, AIR FLOW -1101 CFM SET 1 4,708 4,708.00 - 0.00% - 1.00 100.00% 4,708.00
Static Pressure: 3.5"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.10 EF - 10, AIR FLOW -1024 CFM SET 1 4,189 4,189.00 - 0.00% - 1.00 100.00% 4,189.00
Static Pressure: 3.5"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.11 EF - 11, AIR FLOW -1212 CFM SET 1 4,592 4,592.00 - 0.00% - 1.00 100.00% 4,592.00
Static Pressure: 3.5"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
Procare Riaya Hospital Expansion Page 40 of 81
Al-Khobar, Kingdom of Saudi Arabia
15.12.1.1.13 EF - 13, AIR FLOW -1370 CFM SET 1 5,641 5,641.00 - 0.00% - 1.00 100.00% 5,641.00
Static Pressure: 3.5"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.14 EF - 14, AIR FLOW -1398 CFM SET 1 6,044 6,044.00 - 0.00% - 1.00 100.00% 6,044.00
Static Pressure: 2"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.15 EF - 15, AIR FLOW -1300 CFM SET 1 5,582 5,582.00 - 0.00% - 1.00 100.00% 5,582.00
Static Pressure: 2"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.16 PF - 01, AIR FLOW -6000 CFM SET 1 14,362 14,362.00 - 0.00% - 1.00 100.00% 14,362.00
Static Pressure: 1"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.17 PF - 02, AIR FLOW -5000 CFM SET 4 16,069 64,276.00 - 0.00% - 4.00 100.00% 64,276.00
Static Pressure: 1"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.18 CF - 01, AIR FLOW -800 CFM SET 2 4,246 8,492.00 - 0.00% - 2.00 100.00% 8,492.00
Static Pressure: 1.5"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.12.1.1.19 CF - 02, AIR FLOW -1800 CFM SET 1 13,160 13,160.00 - 0.00% - 1.00 100.00% 13,160.00
Static Pressure: 1.5"
Power: 220 V / 1 PH / 60 HZ
Type : Centrifugal
15.14.2 System Commissioning Report in colored copies. SET 5 9,659 48,295.00 - 0.00% - 5.00 100.00% 48,295.00
All Electrical Works shall be constructed according to the SASO and latest
NEC code.
The Contractor shall supply and erect all electrical panelboard, circuit
breakers, lighting fixtures, power points sockets, telephone, and alarm
system, switches with all wirings conduits and fittings, wires and
markers, identification plates, supports, straps, hangers, etc. as detailed
on drawings and as per specifications and to make the system fully
operational/functional
The Contractor scope of works will include supply, installation, Testing &
Commissioning of equipment, devices, machineries and materials,
16.1.1 The Contractor shall supply and install all lighting points, with all wiring,
conduit, fittings, tie wires, markers identification, plates, supports, straps,
hangers, anchors, etc., as required by the system to make it fully
functional/ operational.
16.1.1 Lighting points NOS 3,816 145 553,320.00 3,816.00 100.00% 553,320.00 - 0.00% -
16.1.2 Lighting Switch points NOS 760 69 52,440.00 760.00 100.00% 52,440.00 - 0.00% -
16.2.1 The Contractor shall supply, and install all lighting fixtures, switches with
all wiring, conduit, fittings, tie wires, markers, identification, plates,
supports, straps, hangers, anchors, etc.,. as required by the system to
make it fully functional/ operational. Lighting Fixtures shall be from
Saudi Lighting National Lighting or approved equal
16.2.1.1 Type A1: Recessed downlight for compact fluorescent, fixed clear EA 597 428 255,516.00 - 0.00% - 597.00 100.00% 255,516.00
decorative cover, 2x26WC.F 220V, 1-Phase, 60Hz, IP44
16.2.1.2 Type A2: Recessed / surface mounted indoor downlight luminaire with EA 299 685 204,815.00 - 0.00% - 299.00 100.00% 204,815.00
closed dome reflector, 1x26W, 220V, 60Hz, SLC CAT #6340 or equal
16.2.1.3 Type B1: Recessed "LAID-IN" 4x18W, mounted on modular ceiling indoor EA 1,985 446 885,310.00 - 0.00% - 1,985.00 100.00% 885,310.00
commercial luminaire with diffuser sheet louver in hinged and latched
frame.
16.2.1.4 Type B2: Recessed "LAID-IN" 4x18W, mounted on modular ceiling indoor EA 206 860 177,160.00 - 0.00% - 206.00 100.00% 177,160.00
commercial luminaire with diffuser sheet louver in hinged and latched
frame w/ 3- hrs. emergency pack .
16.2.1.5 Type B3: Recessed "DRAWN-IN" 4x36W,modular ceiling indoor EA 100 661 66,100.00 - 0.00% - 100.00 100.00% 66,100.00
commercial luminaire with diffuser sheet in hinged and latched frame.
16.2.1.6 Type B4: Recessed "DRAWN-IN" 4x36W,modular ceiling indoor EA 10 1,119 11,190.00 - 0.00% - 10.00 100.00% 11,190.00
commercial luminaire with diffuser sheet in hinged and latched frame w/
3hrs. Emergency pack unit.
16.2.1.7 Type B4: Recessed "DRAWN-IN" 4x36W, non modular on modular ceiling EA 22 1,507 33,154.00 - 0.00% - 22.00 100.00% 33,154.00
hygienic indoor hospital luminaire with clear glass lens and over lay
diffuser in frame.
16.2.1.8 Type C1; Semi recessed mounted outdoor 2x26W, amenity/landscape EA 38 570 21,660.00 - 0.00% - 38.00 100.00% 21,660.00
luminaire with six various cell face styles and opal bowl diffuser
16.2.1.9 Type C2: Wall direct mounted 1x26W C.F, semi-sphere outdoor EA 17 529 8,993.00 - 0.00% - 17.00 100.00% 8,993.00
amenity/landscape luminaire with six various cell face styles and opal
bowl diffusers.
16.2.1.10 Type C3: 1 x 8W T5, maintained emergency bulkhead, IP65 EA 138 529 73,002.00 - 0.00% - 138.00 100.00% 73,002.00
16.2.1.11 Type D: Surface direct mounted 36W, T8, fluorescent dust indoor EA 135 328 44,280.00 - 0.00% - 135.00 100.00% 44,280.00
commercial luminaire w/ moulded diffuser
16.2.1.12 Type D1: Surface mounted indoor 2x18W industrial luminaire with open EA 18 299 5,382.00 - 0.00% - 18.00 100.00% 5,382.00
end wrap diffuser, Saudi Lighting Co. CAT#7266 220VAC, 60Hz
(630mmx210mm)
Procare Riaya Hospital Expansion Page 43 of 81
Al-Khobar, Kingdom of Saudi Arabia
16.2.1.13 Type D1E: Surface mounted indoor 2x18W industrial luminaire with EA 20 714 14,280.00 - 0.00% - 20.00 100.00% 14,280.00
1.5hrs EM battery back-up, Saudi Lighting Co. CAT#7266 220VAC, 60Hz
(630mmx210mm)
16.2.1.14 Type E: Twin spot, 2 x 20W non maintained, 3- hrs. emergency lightings EA 35 1,036 36,260.00 - 0.00% - 35.00 100.00% 36,260.00
16.2.1.15 Type F; Direct mounted above mirror indoor commercial luminaire with EA 114 230 26,220.00 - 0.00% - 114.00 100.00% 26,220.00
diffuser integrated with switch.
16.2.1.16 Type H1; Multi-mounting single face sign / directional indoor luminaire EA 30 660 19,800.00 - 0.00% - 30.00 100.00% 19,800.00
8W, T5 fluorescent for high frequency "HF" ballast with emergency back-
up.
16.2.1.17 Type H2; Multi-mounting double face sign / directional indoor luminaire EA 12 668 8,016.00 - 0.00% - 12.00 100.00% 8,016.00
with back-up 8W, T5 fluorescent for high frequency "HF" ballast
16.2.1.18 Provision Door Lamp (Same as per existing hospital) EA 10 1,726 17,260.00 - 0.00% - 10.00 100.00% 17,260.00
16.2.1.19 Warning Lights (X- Ray Rooms) 230V, Slim-line LED Backlit Sign; Energy EA 2 2,522 5,044.00 - 0.00% - 2.00 100.00% 5,044.00
efficient LED lamps(Text as per Client Requirements)
16.3.3.1 For recessed mounting in the floor, wall or ground. Installation springs LOT 0 0 0.00 - 0.00% - - 100.00% - EXCLUDED
for quick assembly ( Weatherproof)
16.3.4.1 Complete supply & installation of lighting poles including wirings, LOT 1 150,000 150,000.00 - 0.00% - 1.00 100.00% 150,000.00
conduiting, terminal blocks, and necessary accessories needed to make
the system fully functional/operational. Lighting fixture shall be Metal
Halide, 400W & 250W respectively as shown in the drawing, 230V 60Hz,
Dust proof. Contractor to coordinate with MAJOR manufacturers only.
Lighting Pole shall be 6 meters in Height, Hot Dip Galvanized including
anchor bolts & nuts. Costing of lighting poles shall include installation,
fabrication & concreting of foundation
Normal site areas, including handicap areas, intended for night use shall
be illuminated by an average of 10.76 LUX(1 foot candles), measured in 1
foot intervals of incident light on the area served. Parking areas shall be
illuminated with high pressure sodium fixtures equipped with lamps with
dual restrike elements
16.4.2 Two gang single switch EA 193 120 23,160.00 - 0.00% - 193.00 100.00% 23,160.00
16.4.3 Three gang single switch EA 23 131 3,013.00 - 0.00% - 23.00 100.00% 3,013.00
16.4.4 Three way switch EA 40 131 5,240.00 - 0.00% - 40.00 100.00% 5,240.00
16.4.5 Push button switch integrated with relay EA 37 120 4,440.00 - 0.00% - 37.00 100.00% 4,440.00
16.4.6 Switch bank, modular type, SPST, no. of gang as per indicated in the EA 6 196 1,176.00 - 0.00% - 6.00 100.00% 1,176.00
drawing. Recommended manufacturer shall be MK or LEGRAND, 220V
60Hz.
16.4.7 Power supply for examination lamp EA 21 200 4,200.00 - 0.00% - 21.00 100.00% 4,200.00
16.5.1 The Contractor shall supply and install all receptacle outlet and
disconnect switch points, with complete wirings, conduits, fittings,
markers, identification plates, supports, etc. as required by the system to
make it fully operational.
16.5.1.1 Receptacle Outlet Points NO 1,535 130 199,550.00 1,535.00 100.00% 199,550.00 - 0.00% -
16.5.1.2 Disconnect Switch Points NO 202 879 177,558.00 202.00 100.00% 177,558.00 - 0.00% -
Procare Riaya Hospital Expansion Page 45 of 81
Al-Khobar, Kingdom of Saudi Arabia
16.6.1 The Contractor shall supply, and install all receptacles, outlets, switches
and disconnect switches with all wirings, conduits, fittings, tie wires,
markers, identification plates, supports etc., as required by system to
make it fully functional. Wiring devices Wiring Devices shall be from
LEGRAND or approved equal and for Disconnect Switch shall be from
SQUARE D or approved equal
16.6.1.1 Duplex 220V, 13A Outlet EA 569 116 66,004.00 - 0.00% - 569.00 100.00% 66,004.00
16.6.1.2 Duplex 110V, 15A Outlet EA 61 116 7,076.00 - 0.00% - 61.00 100.00% 7,076.00
16.6.1.3 Duplex 220V, 15A Outlet, WP EA 10 232 2,320.00 - 0.00% - 10.00 100.00% 2,320.00
16.6.1.4 Duplex 220V, 13A Outlet, Hospital Grade EA 50 451 22,550.00 - 0.00% - 50.00 100.00% 22,550.00
16.6.1.5 Special purpose outlet 32-walther mondo outlet 5-pin CAT no.435 509, IP- EA 6 381 2,286.00 - 0.00% - 6.00 100.00% 2,286.00
44
ADDENDUM -3( KIDNEY DIALYSIS ROOM &CSSD )
ELECTRICAL WORKS:
Duplex 220V 13A OUTLET EA 60 116 6,960 - 0.00% - 60.00 100.00% 6,960.00
Duplex 110V 13A OUTLET EA 52 116 6,032 - 0.00% - 52.00 100.00% 6,032.00
Single 220V, 13A Outlet WP EA 9 232 2,088 - 0.00% - 9.00 100.00% 2,088.00
30 Amps Isolator EA 2 626 1,252 - 0.00% - 2.00 100.00% 1,252.00
16.6.1.7 Single 220V, 13A Outlet WP EA 15 116 1,740.00 - 0.00% - 15.00 100.00% 1,740.00
16.6.1.8 Single 220V, 13A Outlet with Weatherproof Cover EA 10 129 1,290.00 - 0.00% - 10.00 100.00% 1,290.00
16.6.1.9 Single 220V,13A outlet for emergency lights connected to lights EA 18 110 1,980.00 - 0.00% - 18.00 100.00% 1,980.00
connected to life safety branch 7'-6" above finish floor.
16.6.1.10 Ground Fault Circuit Interrupter Hospital Grade 20A NEMA 6-20R 250V EA 51 457 23,307.00 - 0.00% - 51.00 100.00% 23,307.00
16.6.1.11 Floor Receptacle Outlet 13A, 220V, with Data EA 10 370 3,700.00 - 0.00% - 10.00 100.00% 3,700.00
16.6.1.12 Emergency Push Button EA 3 122 366.00 - 0.00% - 3.00 100.00% 366.00
16.6.1.14 Ceiling mounted power supply and communication EA 2 122 244.00 - 0.00% - 2.00 100.00% 244.00
16.6.1.15 Ceiling mounted single 220V, 13A, outlet EA 14 63 882.00 - 0.00% - 14.00 100.00% 882.00
16.6.1.16 Celling mounted junction box EA 4 76 304.00 - 0.00% - 4.00 100.00% 304.00
16.6.1.17 Type celling mounted junction box EA 16 76 1,216.00 - 0.00% - 16.00 100.00% 1,216.00
16.6.1.18 Disconnect switch non-fusible, 30A 3P EA 178 437 77,786.00 178.00 100.00% 77,786.00 - 0.00% -
16.6.1.19 Combination motor controller with H.O.P selector, 60A, 3P EA 3 1,470 4,410.00 - 0.00% - 3.00 100.00% 4,410.00
Procare Riaya Hospital Expansion Page 46 of 81
Al-Khobar, Kingdom of Saudi Arabia
16.6.1.21 Disconnect switch fuseable 150A,220V, 3PH EA 2 1,885 3,770.00 - 0.00% - 2.00 100.00% 3,770.00
16.6.1.22 Disconnect switch fuseable, 100A,220V, 3PH EA 9 1,365 12,285.00 - 0.00% - 9.00 100.00% 12,285.00
16.6.1.23 Disconnect switch non- fuseable, 1600A, 220V, 3PH EA 9 9,682 87,138.00 - 0.00% - 9.00 100.00% 87,138.00
16.7.1 Supply, laid and connect the necessary XLPE/PVCL.V. cables in PVC
conduits as per drawings in suitable arrangements, easy to draw with
connection, accessories, markings, labeling, jointing, supporting, etc. from
Transformers to MDB and from MDB to all panels at different locations in
the building including all accessories, fixing etc. as per specifications and
drawings. Wires and cables shall be BAHRA Cables, or approved equal.
16.7.1.8 UPS (125KVA) to SDP-CR-E4 LM 69 473 32,637.00 - 0.00% - 69.00 100.00% 32,637.00
Procare Riaya Hospital Expansion Page 47 of 81
Al-Khobar, Kingdom of Saudi Arabia
16.8.1.1 SWGR-1 : 3500A MAIN ACB, 3P+N+E, 24 branches min. Refer to single EA 1 418,634 418,634.00 - 0.00% - 1.00 100.00% 418,634.00
line diagram
16.8.1.2 SWGR-2 : 4500A, ACB, 3P+N+E, 24 branches min. Refer to single line EA 1 444,613 444,613.00 - 0.00% - 1.00 100.00% 444,613.00
diagram
16.8.1.3 Incomer Ckt. Breaker for SWGR-1, 3500A 3P+N+E, ACB. with Enclosure. EA 1 117,399 117,399.00 - 0.00% - 1.00 100.00% 117,399.00
16.8.1.4 Incomer Ckt. Breaker for SWGR-2, 4500A 3P+N+E, ACB. with Enclosure. EA 1 131,979 131,979.00 - 0.00% - 1.00 100.00% 131,979.00
16.8.1.5 Incomer Ckt. Breaker for MCC-1, 4000A 3P+N+E, ACB. with Enclosure. EA 1 129,549 129,549.00 - 0.00% - 1.00 100.00% 129,549.00
16.8.1.6 Incomer Ckt. Breaker for SDP-1, 400A 3P+N+E, MCCB. with Enclosure. EA 1 11,150 11,150.00 - 0.00% - 1.00 100.00% 11,150.00
16.8.1.7 Incomer Ckt. Breaker for SDP-2, 400A 3P+N+E, MCCB. with Enclosure. EA 1 11,150 11,150.00 - 0.00% - 1.00 100.00% 11,150.00
16.8.1.8 Incomer Ckt. Breaker for SDP-3, 400A 3P+N+E, MCCB. with Enclosure. EA 1 11,150 11,150.00 - 0.00% - 1.00 100.00% 11,150.00
16.9.1 Supply, install, testing and commissioning of MDP-1 and panel boards as
per drawings and S.L.D. Panel boards shall be IEC standard Merlin Gerin,
ABB or approved equal. Discrimination, protection coordination and
short-circuit protection shall be guaranteed by panel manufacturer.
16.9.1.59 CR-E43P1-1F ( ISOLATION PANEL ) EA 1 5,600 5,600.00 - 0.00% - 1.00 100.00% 5,600.00
Main : 40AT/100AF MCCB, 3Ph, 4 wire + Earth
30Ways, as per load schedule & Schematic Diagram
400/230V 60 Hz.
16.9.1.60 CR-E43P1-2F ( ISOLATION PANEL ) EA 1 5,600 5,600.00 - 0.00% - 1.00 100.00% 5,600.00
Main : 40AT/100AF MCCB, 3Ph, 4 wire + Earth
30Ways, as per load schedule & Schematic Diagram
400/230V 60 Hz.
16.9.1.65 AUTOMATIC TRANSFER SWITCH EA 4 97,109 388,436.00 - 0.00% - 4.00 100.00% 388,436.00
400A, 3Ph+N+E
As per Power Single Line Diagram
400/230V 60 Hz.
Procare Riaya Hospital Expansion Page 65 of 81
Al-Khobar, Kingdom of Saudi Arabia
16.9.1.70 LCP-1 (Lighting Contactor Panel) EA 1 32,805 32,805.00 - 0.00% - 1.00 100.00% 32,805.00
Main : 40AT/40AF MCCB, 3Ph, 4 wire + Earth
as per Power Single Line Diagram
400/230V 60 Hz.
16.9.1.71 LCP-2 (Lighting Contactor Panel) EA 1 32,805 32,805.00 - 0.00% - 1.00 100.00% 32,805.00
Main : 40AT/40AF MCCB, 3Ph, 4 wire + Earth
as per Power Single Line Diagram
400/230V 60 Hz.
16.10.1.1 Panel consisting of: ID-10HH05KSP-A205-A211-LM Interior Assembly- UNIT 2 62,816 125,632.00 - 0.00% - 2.00 100.00% 125,632.00
10kVA dual output voltage isolated power panel primary main CB.
60A/2P, SQD
Procare Riaya Hospital Expansion Page 66 of 81
Al-Khobar, Kingdom of Saudi Arabia
16.10.1.5 B513408:
Back box-galvanized steel 51" x 34"x 8" (HxWxD)
16.10.1.6 T5336:
Front trim-304SS, with #4 brushed finish. Provisions for receptacle
sectional 53"x36" (HxW)
16.11.1 Complete and installation of VFD with all necessary accessories and
required finishes. VFD shall be provided in NEMA Type- 1wall mounted.
Enclosure shall be constructed of sheet steel to reduce radio frequency
interference (RFI)and electromagnetic interference (EMI) and to provide
maximum physical protection for all internally mounted components.
Variable frequency drive shall be SIEMENS,ABB or approved equal
16.11.1.1 10 HP; 400V input voltage for CHW-PP1 to CHW-PP4 and PP5 EA 4 46,322 185,288.00 - 0.00% - 4.00 100.00% 185,288.00
16.11.1.2 60 HP; 400V input voltage for CHWSP-1 & CHWSP-2 and PP5 EA 2 80,767 161,534.00 - 0.00% - 2.00 100.00% 161,534.00
16.12.1 Power factor correction unit (PFC), factory assembled and pre-wired
equipment consisting of unit capacitors, power factor sensing and control
equipment and all necessary accessories and required finishes all in
accordance with the specifications
16.12.1.1 Maximum 365 kVAR at rated voltage and frequency. EA 1 102,880 102,880.00 - 0.00% - 1.00 100.00% 102,880.00
16.13.1 Diesel engine electric generating unit including generator control panel,
protection, wiring and accessories for automatic start/stop sequencing
complete. Engine generator sets for medical facilities shall be powered by
diesel. The preferred generating voltage is the highest voltage proposed
for the facility. Normally 400V/230V3-phase, 60Hz, 4 wire system is the
highest utilization voltage. Generator sets shall be CATERPILLAR or
approved equal
16.13.1.1 500KVA; 400/230V; 3P + N + E, 3 PHASE EA 1 371,638 371,638.00 - 0.00% - 1.00 100.00% 371,638.00
16.13.1.2 Fuel oil system including pipework, fill connection, fuel oil pump sets and
all necessary accessories all in accordance with the Specifications (for 1
Generators)
16.13.1.3 Diesel fuel storage tank and daily storage tank complete as described all Included
in accordance with the Specifications (for 1Generators)
16.13.1.4 All necessary ductwork for genset exhaust complete as required all in
accordance with the Specifications (for 1Generators)
16.14.1.1 125 KVA, 3P + N + E, 400/230V 60 HZ. 1 257,732 257,732.00 - 0.00% - 1.00 100.00% 257,732.00
16.14.1.2 UPS battery back-up complete with all necessary accessories and all in Included
accordance with the Specifications.
16.15.1 Fire alarm system includes wiring, conduit, boxes and all accessories
required to make it fully operational. Fire alarm system equipment and
devices shall be SIMPLEX , GENT, WACHTER or approved equal.
16.15.1.1 Fire Alarm Control Panel Addressable Type EA 1 73,204 73,204.00 - 0.00% - 1.00 100.00% 73,204.00
16.15.1.2 Photo-electric Smoke Detector EA 609 398 242,382.00 213.15 35.00% 84,833.70 395.85 65.00% 157,548.30
16.15.1.3 Rate of rise Heat Detector EA 20 362 7,240.00 7.00 35.00% 2,534.00 13.00 65.00% 4,706.00
Procare Riaya Hospital Expansion Page 68 of 81
Al-Khobar, Kingdom of Saudi Arabia
16.15.1.4 Fire Alarm Manual Pull Station with Protective Cover EA 73 436 31,828.00 25.55 35.00% 11,139.80 47.45 65.00% 20,688.20
16.15.1.5 Audio Visual Alarm Sounder EA 28 601 16,828.00 9.80 35.00% 5,889.80 18.20 65.00% 10,938.20
16.15.1.6 Duct Smoke detector EA 45 1,022 45,990.00 - 0.00% - 45.00 100.00% 45,990.00
16.15.1.7 Magnetic Door Holder EA 38 687 26,106.00 - 0.00% - 38.00 100.00% 26,106.00
Rate of rise Heat Detector EA 4 362 1,448 - 0.00% - 4.00 100.00% 1,448.00
Fire Alarm Manual Pull Station with Protective Cover EA 4 436 1,744 - 0.00% - 4.00 100.00% 1,744.00
Audio Visual Alarm Sounder EA 4 601 2,404 - 0.00% - 4.00 100.00% 2,404.00
16.16.1.1 TV Outlet Points NO 100 346 34,600.00 35.00 35.00% 12,110.00 65.00 65.00% 22,490.00
16.16.1.3 TV Splicing Box, with Splitter and Power Supply EA 100 621 62,100.00 - 0.00% - 100.00 100.00% 62,100.00
16.16.1.8 Control Box : Including new technology digital amplifier and receiver's SET 1 129,337 129,337.00 - 0.00% - 1.00 100.00% 129,337.00
electronic card system to feed each floor and service area by high
efficiency signal.
16.17.1 Complete supply and installation conduit box, wires for the following
nurse call equipment shall be BENDER or approved equal. Existing nurse
call system shall be integrated to the proposed expansion building.
16.17.1.1 Nurse call presence switch points NO 82 208 17,056.00 - 0.00% - 82.00 100.00% 17,056.00
16.17.1.2 Nurse Call Emergency Switch Shower Points NO 102 203 20,706.00 - 0.00% - 102.00 100.00% 20,706.00
16.17.1.3 Nurse Call Corridor Light Points NO 63 203 12,789.00 - 0.00% - 63.00 100.00% 12,789.00
16.17.1.4 Nurse Call Station Points NO 13 203 2,639.00 - 0.00% - 13.00 100.00% 2,639.00
16.17.1.5 Nurse Call Presence Switch EA 82 812 66,584.00 - 0.00% - 82.00 100.00% 66,584.00
16.17.1.6 Nurse Call Emergency Switch Shower EA 102 501 51,102.00 - 0.00% - 102.00 100.00% 51,102.00
16.17.1.7 Nurse Call Corridor Light EA 63 708 44,604.00 - 0.00% - 63.00 100.00% 44,604.00
16.17.1.8 Nurse Call Station EA 13 26,929 350,077.00 - 0.00% - 13.00 100.00% 350,077.00
16.17.1.9 Nurse calling control box & software EA 1 80,191 80,191.00 - 0.00% - 1.00 100.00% 80,191.00
16.17.1.10 Nurse calling Patient Station EA 55 1,680 92,400.00 - 0.00% - 55.00 100.00% 92,400.00
* Bed Head Units will be under provisional item or supplied by the Client/
Owner.
16.17.2.1.1 Bed Head Unit, Patient Type and Clinic. EA 78 3,287 256,386.00 - 0.00% - 78.00 100.00% 256,386.00
16.17.2.1.2 Bed Head Unit, ICU EA 4 5,717 22,868.00 - 0.00% - 4.00 100.00% 22,868.00
16.17.2.1.3 Bed Head Unit, Operation/ Recovery Room EA 2 8,147 16,294.00 - 0.00% - 2.00 100.00% 16,294.00
16.18.1.1 Master Clock Programmers NO 1 18,832 18,832.00 - 0.00% - 1.00 100.00% 18,832.00
(WDP-Y) with LAN card
16.18.1.2 Memory 300 mm (12”) diameter Single Face Slave Clock with 3 Arms (H , EA 55 755 41,525.00 18.65 33.91% 14,081.13 36.35 66.09% 27,443.87
M & S ) in round Aluminum Housing,
16.18.1.3 Memory 300 mm (12”) diameter Double Face Slave Clock with 3 Arms (H EA 21 1,429 30,009.00 7.35 35.00% 10,503.15 13.65 65.00% 19,505.85
, M & S ) in round Aluminum Housing,
16.18.1.4 Electronic Impulse Amplifier EA 1 2,182 2,182.00 - 0.00% - 1.00 100.00% 2,182.00
16.18.1.5 Radio Synchronization GPS EA 1 2,676 2,676.00 - 0.00% - 1.00 100.00% 2,676.00
16.19.1.1 CCTV Camera Points NO 72 214 15,408.00 16.80 23.33% 3,595.20 55.20 76.67% 11,812.80
16.19.1.2 IP CCTV Dome Camera EA 72 2,305 165,960.00 - 0.00% - 72.00 100.00% 165,960.00
16.19.1.3 High resolution 16-channel Network Video Recorder c/w minimum 2TB SET 1 123,170 123,170.00 - 0.00% - 1.00 100.00% 123,170.00
hard drive on board , 220V, 60Hz mpeg-2compression with up to 100
frames per second.
CCTV SYSTEM:
IP CCTV dome camera EA 3 2,305 6,915 - 0.00% - 3.00 100.00% 6,915.00
16.20.1.1 Access Control proximity Card Reader Points NO 48 212 10,176.00 16.80 35.00% 3,561.60 31.20 65.00% 6,614.40
16.20.1.2 Access Control Magnetic Lock Points NO 40 212 8,480.00 14.00 35.00% 2,968.00 26.00 65.00% 5,512.00
16.20.1.3 Security Access Control (SAC) Card Reader EA 48 884 42,432.00 - 0.00% - 48.00 100.00% 42,432.00
16.20.1.4 Security Access Control (SAC) Magnetic Lock EA 40 678 27,120.00 - 0.00% - 40.00 100.00% 27,120.00
16.20.1.6 Data Network System EA 9 3,845 34,605.00 - 0.00% - 9.00 100.00% 34,605.00
16.21.1 Contractor to supply, install, test and commission the system and shall LS 1 2,574,282 2,574,282.00 0.15 15.00% 386,142.30 0.85 85.00% 2,188,139.70
include conduiting, cabling, cable tray system, etc. Shall be able to prepare
their own design based on the project requirements if deemed necessary
without any additional cost on the project. The system shall consist of the
following criteria;
16.21.1.3 4 hours of training of user trainer (train the trainer) and2 days To be Included
administrator training plus pdf copy of user documentation.
16.22.1 Complete supply and installation of Hot Dipped Galvanized Perforated LOT 1 459,574 459,574.00 0.85 85.40% 392,476.20 0.15 14.60% 67,097.80
Cable Tray complete with bracket and supports, auxiliary connectors and
shall be outside flange.
16.22.1.3 Contractor shall prepare his own design and to be submitted as a shop
drawing prior to execution / implementation to satisfy the project
requirements and for Consultant approval.
16.23.1 Complete Supply, Installation, Testing & Commissioning c/w & including
conduiting, cabling of the system. Existing system shall be integrated to
the proposed expansion building. Necessary accessories are to be
considered in costing & estimate to make the system fully functional \
operational from RCF or approved equal
16.23.1.1 6 Watts ceiling mounted speaker EA 313 350 109,550.00 46.95 15.00% 16,432.50 266.05 85.00% 93,117.50
16.23.1.2 Receiver Mixer Unit EA 1 6,744 6,744.00 - 0.00% - 1.00 100.00% 6,744.00
16.23.1.3 320 Watts RMS power amplifier EA 2 4,952 9,904.00 - 0.00% - 2.00 100.00% 9,904.00
16.23.1.4 160 Watts RMS power amplifier EA 4 4,952 19,808.00 - 0.00% - 4.00 100.00% 19,808.00
16.23.1.5 120 Watts RMS power amplifier EA 14 1,933 27,062.00 - 0.00% - 14.00 100.00% 27,062.00
16.23.1.6 Digital Recorder Announcement EA 1 1,172 1,172.00 - 0.00% - 1.00 100.00% 1,172.00
16.23.1.7 USB, MP3, CD & FM Tuner EA 1 5,521 5,521.00 - 0.00% - 1.00 100.00% 5,521.00
Procare Riaya Hospital Expansion Page 73 of 81
Al-Khobar, Kingdom of Saudi Arabia
16.23.1.9 20 Watts Wall Mounted Speaker EA 1 459 459.00 - 0.00% - 1.00 100.00% 459.00
16.23.1.10 Audio Monitor Panel. Inter-M EA 3 4,436 13,308.00 - 0.00% - 3.00 100.00% 13,308.00
16.23.1.11 Switching Unit & Zone Selection System with Digital SET 3 3,282 9,846.00 - 0.00% - 3.00 100.00% 9,846.00
Control ( 8 ZONES )
16.23.1.13 Microphone Wall Outlet EA 1 266 266.00 - 0.00% - 1.00 100.00% 266.00
16.23.1.14 9 Inputs, 2 Outputs Pre - Amplifier & Mixer EA 1 5,706 5,706.00 - 0.00% - 1.00 100.00% 5,706.00
16.23.1.15 Digital Zone Selector Microphone EA 2 8,072 16,144.00 - 0.00% - 2.00 100.00% 16,144.00
16.23.1.16 120 Watts RMS power amplifier remove EA 1 2,127 2,127.00 - 0.00% - 1.00 100.00% 2,127.00
16.23.1.17 19" Metal Rack, powder coated with front Transparent Lockable Door & SET 3 27,246 81,738.00 - 0.00% - 3.00 100.00% 81,738.00
Rear Solid Lockable Door with Auto Blower and Power Distributor, Inter-
M
ADDENDUM -3( KIDNEY DIALYSIS ROOM &CSSD )
16.24.1.1.1 High Professional Live Sound Mixer 24 input, (from Allen & Heath) SET 1 19,896 19,896.00 - 0.00% - 1.00 100.00% 19,896.00
16.24.1.1.2 CD, USB, MP3 Player with Tuner (from RCF) EA 1 5,590 5,590.00 - 0.00% - 1.00 100.00% 5,590.00
16.24.1.1.2A Feedback Eliminator (from Ferret) EA 1 11,816 11,816.00 - 0.00% - 1.00 100.00% 11,816.00
16.24.1.1.3 Professional Audio Hi-Fi stereo amplifier 750 x 2 watts Each channel 750 SET 1 16,433 16,433.00 - 0.00% - 1.00 100.00% 16,433.00
watts with key control and indicators of the Medium Voice Protection
(from RCF)
16.24.1.1.4 120 watt power amplifier (from RCF) EA 1 5,592 5,592.00 - 0.00% - 1.00 100.00% 5,592.00
Procare Riaya Hospital Expansion Page 74 of 81
Al-Khobar, Kingdom of Saudi Arabia
16.24.1.1.5 19” Metal rack American standard with front transparent lockable door SET 1 21,263 21,263.00 - 0.00% - 1.00 100.00% 21,263.00
and rear solid lockable door with power distributor and auto blower
(from Inter-M)
16.24.1.1.6 Professional speaker 400 watts (from RCF) EA 4 1,955 7,820.00 - 0.00% - 4.00 100.00% 7,820.00
16.24.1.1.7 20 Watts Wall Mounted Speaker (from RCF) EA 1 744 744.00 - 0.00% - 1.00 100.00% 744.00
16.24.1.1.8 Volume Control Switch (from RCF) EA 1 686 686.00 - 0.00% - 1.00 100.00% 686.00
16.24.1.1.9 Handheld Wireless Microphone high sensitivity with a receiver to receive EA 14 9,508 133,112.00 - 0.00% - 14.00 100.00% 133,112.00
the signal UHF with the unity electrical feed the microphone and
microphone can be covered throughout the Hall (from DB).
16.24.1.1.10 Clip Type Wireless Microphone high sensitivity with a receiver to receive EA 2 11,816 23,632.00 - 0.00% - 2.00 100.00% 23,632.00
the signal UHF with the unity electrical feed the microphone and
microphone can be covered throughout the Hall (from DB)
16.24.1.1.11 Condenser Gooseneck microphone with phantom unit (from RCF). EA 3 1,206 3,618.00 - 0.00% - 3.00 100.00% 3,618.00
16.24.1.1.12 Professional Floor Mount Outlet Microphone resister distress consisting EA 3 801 2,403.00 - 0.00% - 3.00 100.00% 2,403.00
of a packet of metal size ground 8x8cm covered under the cover of copper
casting high quality (from MCB).
16.24.1.1.13 Wooden Lecturn with Gooseneck Microphone and Reading Lamp EA 1 11,816 11,816.00 - 0.00% - 1.00 100.00% 11,816.00
16.24.1.1.14 Audio Cables SET 1 11,816 11,816.00 - 0.00% - 1.00 100.00% 11,816.00
16.24.1.2.1 6500 ANIS Lumens 3 Chip DLP, projector with HDMI input (M- Series) SET 1 90,062 90,062.00 - 0.00% - 1.00 100.00% 90,062.00
with Lense (from CHRISTIE).
16.24.1.2.2 Electrical Screen HDTV FORMAT (119" x 212") 243"Diagonal (302 x SET 1 16,145 16,145.00 - 0.00% - 1.00 100.00% 16,145.00
538cm), from DA- LITE.
16.24.1.2.3 22" LCD with HDMI inputs (from SONY) EA 3 4,497 13,491.00 - 0.00% - 3.00 100.00% 13,491.00
16.24.1.2.4 Projector Elevator Lift (from SVS) EA 1 25,667 25,667.00 - 0.00% - 1.00 100.00% 25,667.00
16.24.1.2.5 Floor Box with one HDMI Female socket type (from CRESTRON). EA 1 6,744 6,744.00 - 0.00% - 1.00 100.00% 6,744.00
16.24.1.2.6 Fiber Optics Transmitter for HDMI by Crestron. EA 1 12,970 12,970.00 - 0.00% - 1.00 100.00% 12,970.00
16.24.1.2.7 Fiber Optics Receiver for HDMI (from CRESTRON). EA 1 12,970 12,970.00 - 0.00% - 1.00 100.00% 12,970.00
16.24.1.2.8 8" x 8" Multimedia Matrix Switcher (from CRESTRON). EA 1 30,861 30,861.00 - 0.00% - 1.00 100.00% 30,861.00
16.24.1.2.9 SDI Pan/ Tilt/ Zoom Camera System (from SONY). EA 3 4,891 14,673.00 - 0.00% - 3.00 100.00% 14,673.00
16.24.1.2.10 Pan/ Tilt/ Zoom Camera Controller System (from SONY). EA 1 4,891 4,891.00 - 0.00% - 1.00 100.00% 4,891.00
Procare Riaya Hospital Expansion Page 75 of 81
Al-Khobar, Kingdom of Saudi Arabia
16.24.1.2.11 Video Cables SET 1 13,760 13,760.00 - 0.00% - 1.00 100.00% 13,760.00
16.24.1.3.1 Main Processor Dual Bus Control System six built- in can port eight IR/ LOT 1 71,989 71,989.00 - 0.00% - 1.00 100.00% 71,989.00
serial ports, eight 1/0 versa ports and eight isolated relays, 32-bit
microprocessor 257MIPS, 4MB flash, 32 SDRAM, 256KBNVRAM w/
Power supply.
16.24.1.3.3 9” Wired Touch Screen for Control Room. EA 1 20,944 20,944.00 - 0.00% - 1.00 100.00% 20,944.00
16.24.1.3.4 5.7" Wireless Touch Screen for Podium Area. EA 1 18,636 18,636.00 - 0.00% - 1.00 100.00% 18,636.00
16.24.1.3.5 Volume Control Unit EA 1 5,651 5,651.00 - 0.00% - 1.00 100.00% 5,651.00
16.24.1.4 LIGHTING & DIIMMER SYSTEM FOR LECTURE HALL (FROM LSC):
16.24.1.4.1 24 Faders, 512 DMX Channel console with MIDI, VGA output and USB In/ SET 1 85,050 85,050.00 - 0.00% - 1.00 100.00% 85,050.00
Out.
16.24.1.4.2 Dimmer Pack consist of 12 module 13A each DMX512 Control Command SET 1 73,508 73,508.00 - 0.00% - 1.00 100.00% 73,508.00
16.24.1.4.3 Rack for Dimmer System SET 1 85,050 85,050.00 - 0.00% - 1.00 100.00% 85,050.00
16.24.1.4.4 Stage Area Spot light, 500 watts, can be flood and spot with 771 lux at EA 16 3,282 52,512.00 - 0.00% - 16.00 100.00% 52,512.00
10m with 1.22m spot including Color filter frame, 4-door rotatable barn
doors and Safety bond (from SPOTLIGHT)
16.24.1.4.5 Ceiling Aluminum Trussing Structural System,10 meter (from SPAIN) EA 2 21,263 42,526.00 - 0.00% - 2.00 100.00% 42,526.00
16.24.1.4.6 Ceiling Down Light, 100 watts (from LUCIFEROS). EA 88 1,068 93,984.00 - 0.00% - 88.00 100.00% 93,984.00
16.24.1.4.7 Wooden Console to put devices on it at Control Room. EA 1 17,516 17,516.00 - 0.00% - 1.00 100.00% 17,516.00
16.24.1.5 VIDEO CONFERENCE SYSTEM FOR LECTURE HALL (FROM TANDBURG): LOT 1 366,323 366,323.00 - 0.00% - 1.00 100.00% 366,323.00
16.24.1.5.2 Service
16.24.1.5.6 VC Proxy
16.24.1.6.1 Master Unit Forum Congress System. SET 1 31,728 31,728.00 - 0.00% - 1.00 100.00% 31,728.00
16.24.1.6.2 4 Channel UHF Digital Transmitter for Simultaneous Translation. SET 1 57,236 57,236.00 - 0.00% - 1.00 100.00% 57,236.00
16.24.1.6.3 Kit for 3 additional Language Modules. EA 1 19,319 19,319.00 - 0.00% - 1.00 100.00% 19,319.00
16.24.1.6.4 Interpreter Set. EA 6 11,239 67,434.00 - 0.00% - 6.00 100.00% 67,434.00
16.24.1.6.6 Simultaneous Translation Pocket Receiver 99 Channels. EA 100 1,955 195,500.00 - 0.00% - 100.00 100.00% 195,500.00
16.24.1.6.7 Stethoscopic Headphones. EA 100 595 59,500.00 - 0.00% - 100.00 100.00% 59,500.00
16.24.1.6.8 Recharging Encrypting and Transport Case for up to 56 pockets. EA 2 20,398 40,796.00 - 0.00% - 2.00 100.00% 40,796.00
16.25.1 Supply and Installation of complete queuing system including conduits, LOT 1 136,080 136,080.00 - 0.00% - 1.00 100.00% 136,080.00
wires, termination box, pull box, PC work station, and other fixation.
16.25.1.1 Main display 948 red color, English & Arabic alphanumeric Included
16.25.1.2 Counter display 924 red color, English & Arabic alphanumeric Included
16.26.1 Complete supply , install, testing and commissioning of Grounding System LOT 1 89,303 89,303 - 0.00% - 1.00 100.00% 89,303.00
including grounding cables, conduit, earth pit and copper bus bars, as per
requirement of the project and NEC code. Grounding System shall be
FURSE or approved equal.
* Contractor shall verify on site if there will be any changes during execution
of the lightning protection system as to satisfy the project requirements
without any additional cost. Any changes shall be documented by providing
shop drawing and to be submitted to the Consultant for approval prior to
implementation
16.27.1.1 Down Conductor 1C-70mm2 LM 558 50 27,900.00 558.00 100.00% 27,900.00 - 0.00% -
16.27.1.2 Busbar Copper (mech'l bonding of equip't.) EA 16 999 15,984.00 - 0.00% - 16.00 100.00% 15,984.00
16.27.1.3 Air Terminal 20mm dia x 1000mm long EA 18 496 8,928.00 - 0.00% - 18.00 100.00% 8,928.00
16.28.1 Complete supply, installation, Testing & Commissioning of required L.S 1 1,316,756 1,316,756.00 - 0.00% - 1.00 100.00% 1,316,756.00
Building Management System complete with MCC Panels, DDC Panels,
wirings, conduiting, cable trays, sensors, motorized valves, motorized
dampers, control valves and all accessories needed for a full functional
system from SIEMENS or HONEYWELL. The system shall control and/ or
monitored as follows:
16.29.1 Complete supply and installation of cable duct banks All raceways for
medium voltage cable run underground shall be installed with spacers
and encased with concrete as mentioned in APPLICABLE CODES &
STANDARDS.
PVC Type 40, Underwriters’ Laboratories, Inc. (UL) Standard 651,
National Electrical Manufacturers
16.29.1.2 PVC Conduit for concrete encased duct bank shall be sch. 80,
gray in color, NEMA TC-8 or approved equal.
MECHANICAL- HVAC
Procare Riaya Hospital Expansion Page 79 of 81
Al-Khobar, Kingdom of Saudi Arabia
Sub- Total:
Division ( 15 & 16) Total
Page (39) Subtotal 314,215.00 0.00% 0.00 100.00% 314,215.00
Page (40) Subtotal 980,359.00 0.00% 0.00 100.00% 980,359.00
Page (41) Subtotal 97,128.00 0.00% 0.00 100.00% 97,128.00
Page (42) Subtotal 112,796.00 0.00% 0.00 100.00% 112,796.00
Page (43) Subtotal 121,993.00 0.00% 0.00 100.00% 121,993.00
Page (44) Subtotal 160,345.00 0.00% 0.00 100.00% 160,345.00
Page (45) Subtotal 138,209.00 0.00% 0.00 100.00% 138,209.00
Page (46) Subtotal 151,800.00 0.00% 0.00 100.00% 151,800.00
Page (47) Subtotal 148,181.00 0.00% 0.00 100.00% 148,181.00
Page (48) Subtotal 128,345.00 0.00% 0.00 100.00% 128,345.00
Page (49) Subtotal 154,235.00 0.00% 0.00 100.00% 154,235.00
Page (50) Subtotal 211,438.00 0.00% 0.00 100.00% 211,438.00
Page (51) Subtotal 740,830.00 71.39% 528,855.12 28.61% 211,974.88
Page (52) Subtotal 1,077,081.00 26.26% 282,874.00 73.74% 794,207.00
Page (53) Subtotal 4,260,045.00 68.88% 2,934,301.92 31.12% 1,325,743.08
Page (54) Subtotal 607,408.00 0.00% 0.00 100.00% 607,408.00
Page (55) Subtotal 119,002.00 0.00% 0.00 100.00% 119,002.00
Page (56) Subtotal 38,631.00 0.00% 0.00 100.00% 38,631.00
Page (57) Subtotal 335,350.00 0.00% 0.00 100.00% 335,350.00
Page (58) Subtotal 30,539.00 0.00% 0.00 100.00% 30,539.00
Page (59) Subtotal 45,565.00 0.00% 0.00 100.00% 45,565.00
Page (60) Subtotal 126,857.00 0.00% 0.00 100.00% 126,857.00
Page (61) Subtotal 1,050,495.00 0.00% 0.00 100.00% 1,050,495.00
Page (62) Subtotal 605,760.00 100.00% 605,760.00 0.00% 0.00
Page (63) Subtotal 1,588,901.00 0.00% 0.00 100.00% 1,588,901.00
Page (64) Subtotal 324,541.00 0.00% 0.00 100.00% 324,541.00
Page (65) Subtotal 150,000.00 0.00% 0.00 100.00% 150,000.00
Page (66) Subtotal 81,484.00 0.00% 0.00 100.00% 81,484.00
Page (67) Subtotal 493,676.00 76.39% 377,108.00 23.61% 116,568.00
Page (68) Subtotal 293,112.00 26.54% 77,786.00 73.46% 215,326.00
Page (69) Subtotal 306,534.00 0.00% 0.00 100.00% 306,534.00
Page (70) Subtotal 73,422.00 0.00% 0.00 100.00% 73,422.00
Page (71) Subtotal 324,479.00 0.00% 0.00 100.00% 324,479.00
Page (72) Subtotal 114,957.00 0.00% 0.00 100.00% 114,957.00
Page (73) Subtotal 60,877.00 0.00% 0.00 100.00% 60,877.00
Page (74) Subtotal 75,614.00 0.00% 0.00 100.00% 75,614.00
Page (75) Subtotal 80,548.00 0.00% 0.00 100.00% 80,548.00
Page (76) Subtotal 332,212.00 0.00% 0.00 100.00% 332,212.00
Page (77) Subtotal 272,575.00 0.00% 0.00 100.00% 272,575.00
Page (78) Subtotal 27,407.00 0.00% 0.00 100.00% 27,407.00
Page (79) Subtotal 130,748.00 0.00% 0.00 100.00% 130,748.00
Sub- Total:
Division ( 15 & 16) Total
Page (80) Subtotal 39,232.00 0.00% 0.00 100.00% 39,232.00
Page (81) Subtotal 88,531.00 0.00% 0.00 100.00% 88,531.00
Page (82) Subtotal 224,845.00 0.00% 0.00 100.00% 224,845.00
Page (83) Subtotal 1,275,624.00 0.00% 0.00 100.00% 1,275,624.00
Procare Riaya Hospital Expansion Page 81 of 81
Al-Khobar, Kingdom of Saudi Arabia
1.2 The Contractor shall submit Full detailed working shop drawings showing all materials Lump Sum 1.00 150,000.00 150,000.00
dimensions, fixing system and all required data to Engineer approval.
Flooring Works:-
1 3 Marble Tiling
Supplied and Installed; Including associated grouting; and polishing, adhesive; expansion
joints; accessories as necessary
1.1 & 4.1 3.1.1 Supply & Install Crema Marfil tiles 60*60*2 cm. According to the approved Sample. m2 2,898.00 830.33 2,406,306.00
1.2 & 4.2 3.3.1 Supply & Install Light Emperador Turkey tiles 60*60*2 cm. According to the approved m2 418.50 487.17 203,879.25
Sample.
1.3 & 4.3 3.2.1 Supply & Install Dark Emperador tiles Cut to Size According to the approved Sample. m2 750.00 819.83 614,875.00
1.7 Supply & Install Marble Border from Dark and Light Emperador Marble size = 30*80 cm LM 124.00 350.00 43,400.00
4.1 Supply & Install Marble Border from Light Emperador Turkey marble size = 10*80 cm LM 289.00 350.00 101,150.00
3.8 Supply and Install Marble cladding 3 cm thickness for rectangular columns by light and dark No 4.00 16,560.00 66,240.00
Emperador + Crema Marfil with decorative border on top, dimensions: 0.80*0.80, height 3.0
m
1.8 4.1.1 Supply & Install Dark Beige Porcelain Tiles 60*60*0.6 cm with adhesives for pharmacy m2 42.00 199.83 8,393.00
approved Sample.
1.9 4.2.1 Supply & Install Light Beige Porcelain Tiles 60*60*0.6 cm with adhesives for pharmacy m2 260.00 201.50 52,390.00
approved Sample.
1.10 4.2.2 Porcelain skirting, type 100mm high*, 20mm thick LM 324.00 93.00 30,132.00
1.11 4.5.1 Supply & Install Light Beige Ceramic Tiles 33*33*0.6 cm for Public Toilets approved Sample. m2 48.00 147.17 7,064.00
5.1 4.6.1 Supply & Install Dark Beige Ceramic Tiles 33*33*0.6 cm for W.C According to the approved m2 42.00 149.83 6,293.00
Sample
5.2 4.7.1 Supply & Install Light Beige Ceramic Tiles 33*33*0.6 cm for W.C According to the approved m2 192.00 149.83 28,768.00
Sample
2.1 & 7.1 5.1.1 Supply & Install Jotun Light Beige Paint According to the approved Sample m2 5,015.00 34.83 174,689.17
2.2 & 7.2 3.1.2 Supply & Install Crema Marfil Cut to Size 20 mm, polished finish According to the approved m2 1,409.00 1,130.17 1,592,404.83
Sample
2.3 & 7.3 3.3.2 Supply & Install Light Emperador Turkey Cut to Size 20 mm, polished finish According to the m2 451.00 655.00 295,405.00
approved Sample
2.4 3.2.2 Supply & Install Dark Emperador Cut to Size 20 mm, polished finish According to the m2 235.00 797.50 187,412.50
approved Sample
2.6 4.3.1 Supply & Install Ceramic 50*20 Light for Public Toilet Code: 3152/KJIONABEL RAK m2 50.00 147.00 7,350.00
2.7 3.2.3 Dark Emperador Marble skirting, type 100 mm high*, 200 mm thick LM 2,834.00 103.83 294,263.67
2.8 4.4.1 Supply & Install Ceramic 50*20 Dark for Public Toilet Code: 3152/KJCRSLBR RAK m2 20.00 147.00 2,940.00
7.4 4.10.1 Light Beige Ceramic Tiles 50*20*0.6 cm for VIP Toilet Code: 3152/KJIONABE RAK with m2 720.00 145.33 104,640.00
adhesives According to the approved Sample
7.5 4.11.1 Dark Ceramic Tiles 50*20*0.6 cm for VIP Toilet Code: 3152/KJAZULLBR RAK with adhesives m2 136.00 145.33 19,765.33
According to the approved Sample
Procare Riaya Hospital Expansion
Al-Khobar, Kingdom of Saudi Arabia
7.7 4.11.1 Dark Ceramic Tiles 50*20*0.6 cm for Patient Room Toilet Code: 3110000ALICADG RAK with m2 102.00 142.83 14,569.00
adhesives According to the approved Sample
3 Ceiling Works
Suspended Ceiling Works
3.1 & 8.1 7.1 Supply & Install Gypsum board 120*240*1.2 cm system, including anchors, rods, channels, m2 5,430.00 160.17 869,705.00
girders, rails and any other accessories required for fixation, joints, corners and edges, all
metal work to be hot dip galvanized steel, Gypsum board to be fire rated 90 min. System
mock up and Samples to be approved by Owner Representative and to be referenced to
ASTM & Industrial assets
3.2 & 8.2 5.1.1 Supply & Install Jotun Light Beige Paint According to the approved Sample m2 5,008.00 34.83 174,445.33
6 Vinyl
6.1 9.1.1 Spaghetti Vinyl Code: 4551 005 for Patient Room Flooring m2 512.00 232.33 118,954.67
6.2 Spaghetti Vinyl Code: 4551 004 for Patient Room Flooring m2 202.00 232.33 46,931.33
6.3 9.1.2 Spaghetti Vinyl Code: 4551 004 for skirting LM 682.00 92.83 63,312.33
1.5 3.5 Supply & Install Waterjet Detail no 5 3.5 DEM No 1.00 35,533.33 35,533.33
1.6 3.7 Supply & Install Waterjet Diameter = 2.00 m Dark and Light Emperador Marble for columns No 12.00 1,675.00 20,100.00
9 2 Handrail
9.1 2.1 Supply & Install Stainless Steel Handrail; 40 mm diameter with steel anchors fixed to LM 18.00 3,043.33 54,780.00
concrete, and all the necessary fitting and fixing accessories all in Accordance with drawings
and relevant specifications
10 Columns Cladding
Option 1
10.1 3.7 Supply & Install Marfil Cladding for Columns as shown on the drawings and in Accordance to No 16.00 22,516.67 360,266.67
the specifications
Option 2
10.2 Supply & Install Painting and Gypsum for Columns as shown on drawings and in Accordance No
to the specifications
Wall Works:-
2.5 & 7.8 6.1.1 Supply & Install Mahogany Wood Veneer Cladding According to the approved Sample m2 135.00 931.33 125,730.00
& 7.9
m2 369.00 914.67 337,512.00
m2 250.00 914.67 228,666.67
Leather Works
Ceiling Works:-
3.3 & 8.3 6.1.2 Supply & Install Mahogany Wood Veneer Cladding According to the Approved Sample m2 45.00 1,301.83 58,582.50
m2 550.00 900.00 495,000.00
7.2 Supply & Install Decorative Gypsum board at Ground Floor Ceiling, Reception area with m2 36.00 377.00 13,572.00
decorative elements
11 Counter
Supply and Install Custom-Made Wooden Counter with Light Emperador Top for Reception
as shown on the drawings and in Accordance to the specifications
11.1 11.1 Ground Floor Reception as shown on drawings and in accordance to Specification No 1.00 35,216.67 35,216.67
11.2 First Floor Reception as shown on drawings and in accordance to Specification No 1.00 17,420.00 17,420.00
Procare Riaya Hospital Expansion
Al-Khobar, Kingdom of Saudi Arabia
11.3 Second Floor Reception as shown on drawings and in accordance to Specification No 1.00 17,420.00 17,420.00
11.2 Custom made wooden cabinet with wooden shelves with Hardwood support, including
fittings, fixings, and accessories, carpentry to complete with proper job
11.2.3 For Patient Rooms - 0.70 H * 1.60 W + 2 Wooden decorative columns 2.00 Height No 30.00 32,850.00 985,500.00
13 Wooden Partition
Supply & Install Solid Wood partition Mahogany Wood Veneer Finish to
13.1 6.3.1 Sitting Area between Male and Female m2 95.00 2,306.00 219,070.00
14 Glass Works
Supply & Install glass partition 6 mm thick Sandblasted to
14.1 8.1.1 Sitting Area between Male and Female m2 120.00 477.67 57,320.00
14.3 3.6 Vanity Top complete with Cut-out to receive Hand Wash Basin with 30 mm thick Light No 2.00 6,328.33 12,656.67
Emperador Turkey 3*0.6 m, with framed mirror including fittings, fixings & accessories,
complete all as on drawing
3- All required floor leveling and all bending materials as per the manufacturer's instructions
and location condition
4- Preperation of floor prior to installation
15.3 6.2.3 Wooden Skirting darker than color, 100 mm height LM 180.00 177.00 31,860.00
16 Ceiling Works
Suspended Ceiling Works
16.1 2.1 Supply and install gypsum board 120x240x1.2 cm system including anchors, rods, channels, m2 290.00 200.17 58,048.33
girders, rails and any other accessories required for fixation, joints, corners and edges, all
metal work to be hot dip galvanized steel
16.2 Supply and install Jotun light beige Paint according to the approved sample m2 290.00 35.50 10,295.00
Procare Riaya Hospital Expansion
Al-Khobar, Kingdom of Saudi Arabia
17.1 1.1.1 Supply and install Mahogany Wood Veneer cladding including Germany leather and all m2 344.00 931.33 320,378.67
accessories as shown on drawings
Leather Works
Wooden Cabinet
Custom made wooden cabinet with wooden shelves with Hardwood support, including
fittings, fixings, and accessories, carpentry to complete with proper job
COLLECTION
PAGE 01 3,868,890.25
PAGE 02 4,011,352.17
PAGE 03 1,865,263.17
PAGE 04 3,295,214.17
PAGE 05 972,359.50
7 Site Photos
7.1 Basement Photos