Professional Documents
Culture Documents
Calculation For Short Circuit Current Calculation Using IEC IEEE Standard PDF
Calculation For Short Circuit Current Calculation Using IEC IEEE Standard PDF
Abstract: For the interruption of a large UAT, (3) from the generator itself. However,
generator source-short-circuit current, a current the generator breaker sees only the component
zero may not be obtained at the contact parting (3) contributed by the generator. Similarly for
time of the circuit breaker. Large generators fault at F1, the generator breaker sees the sum
which have high X/R ratio, and depending upon
of the utility source and auxiliary distribution
the relative impedances and time constants the dc
component can be higher than the ac decaying system short-circuits current contributions, but
component delaying the occurrence of current not the contribution from the generator itself.
zero well beyond contact parting time of the While selecting a generator breaker, higher of
circuit breaker. The subject is well addressed in these two fault currents at F1 and F2 should
the current literature, though not the calculations be considered. Generally, the generator
of it. This paper presents calculations of a large contribution for fault at F2 gives rise to higher
practical generator using ANSI/IEEE and IEC asymmetry than the fault at F1,because large
standards with verifications of results using generators have a higher X/R ratio compared
EMTP. It demonstrates large differences which to the short-circuit X/R ratios in the utility
impact the selection of generator circuit breaker
interrupting duties.
systems.
Fig. 2 shows a bus connected
Key terms: generator source asymmetrical generator in an industrial distribution system
short-circuit current, degree of asymmetry, running in synchronism with utility. Again the
lack of current zero at contact separation. faults at F1 and F2 can be considered and the
generator breaker sees only the generator
I. INTRODUCTION contribution for a fault at F1.
Consider system configurations shown in ANSI/IEEE Std. C37.010 [1] cautions
Fig. 1 and Fig.2. Fig.1 shows a generating that the longer dc time constants could cause a
station, the generation voltage is stepped up to problem with SF6 type puffer circuit breakers.
500 kV, the ratings of generators and The interrupting window, which is the time
transformers are not shown for generality of difference between the minimum and
the discussions. Generators 2 and 3 have a maximum arcing times, may be exceeded
generator breaker, while generators 1 and 4 do because of delayed current zero, and arc
not. Provision of a generator breaker makes it energy and interruption window are of
possible to use the generator step up concern. The calculation methods described in
transformer as step down transformer during this standard are qualified that the E/Z method
start-up. (The relative merits of providing a of calculation with adjustments of ac and dc
generator breaker are not discussed. In-line decrements can be used provided the X/R does
generators breakers rated at 50 kA continuous not exceed 45 at 60 Hz, i.e., the dc time
current and short-circuit interrupting current constant is not more than 120 ms. Yet, the
up to 250 kA are available.) Consider fault commercial software available in the USA is
locations F1 and F2 in Fig.1. The generator based upon the empirical calculations of the
breaker short-circuit duties are of interest. For short-circuit currents according to ANSI/IEEE
a fault at F2, there are three contributions of standard [1], and unfortunately the industry
the short-circuit currents; which are: (1) from ignores the qualifying statement of dc time
the utility source, (2) from the auxiliary constant with respect to short-circuit
distribution system rotating loads through calculations.
IEEE std. C37.013 [2] for generator from generator source short-circuit current
circuit breakers, states that any combination may exceed 110% in the large generators
of ac symmetrical and dc components of being manufactured today. Ref. [2] recognizes
short-circuit currents are permissible provided this asymmetry and states that at the time of
the following conditions are met at the current interruption, the arc fault resistance
primary contact parting time: will add to the generator armature resistance.
This reduces the time constant of the dc
1. The symmetrical component does not
component and forces it to decay faster:
exceed required generator source
symmetrical capability. X d"
Ta = (1)
2. The degree of asymmetry from 2πf (Ra + Radd )
generator source does not exceed
110%. Where Ta is the armature time constant, Ra
is the armature resistance, Radd is the added arc
3. The total source current does not resistance and X”d is the subtransient
exceed the required generator-source reactance and f is the system frequency.
asymmetrical capability.
It is the second condition that is discussed
in this paper, which shows that asymmetry
52 52 52 52 52 52
52 52 52 52 52 52
F2
52 52
G G
UAT2
F1 UAT1
G1 G2 52 52 G3 G4
Interlocks and auto switching
52 52 52
Aux Transf. 1 Aux. Transf. 2
Generation Medium-voltage
auxiliary loads
Third standby
source of power
Interlocks and auto switching
0.48 kV Bus 1 0.48 kV Bus 2
Generation Low-voltage
auxiliary loads
Where φrG is the load power factor angle prior VI. EMTP SIMULATION
to the generator fault and factor pG considers
generator voltage regulation. For the purpose of Short-circuit calculations are conducted
this calculation, it is ignored as ANSI/IEEE using EMTP program, with detail modeling and
methods and EMTP simulations are made with Park’s transformations. EMTP uses Park’s
rated generator voltage. Also the generator is transformation, which is a powerful analytical
considered at no-load, i.e., φrG =0. Substituting all transformation for the study of synchronous
the values, KG,SO=1.10 machine behavior. Conceptually this
ZG is the generator impedance, given by: transformation is shown in Fig. 4. The inductance
matrix of a synchronous machine reactance in the
Z G = RGf + jX d" (9) stator frame of reference is not constant and varies
with the position of the rotor with respect to the
"
Then, from (7), I kG = 49.97 kA . Generator stator coils. Consider that the field winding is co-
peak current is given by: phasial with the direct axis and also that the direct
axis carries a damper winding. The q-axis also has
i pG = χ 2 I kG
"
a damper winding. The field flux is directed along
(10) d-axis; therefore, the machine generated voltage is
Where ipG is the peak short-circuit current at right angles to it, along q-axis. Consider phase
(equivalent ANSI /IEEE close and latch current). ‘a’ inductance, which is a combination of its own
The factor χ can be ascertained from the X/R self inductance, and its mutual inductance with
curves in [3] or from analytical expression in [3]. respect to phases b an c. All these inductances
This gives i pG = 131.6 peak . vary with the position of the rotor with respect to
the stator.
Park’s transformation describes a new set of
variables, such as currents, voltages and flux
linkages in 0dq axes. The stator parameters are
transferred to the rotor parameters.
Using matrix notation:
i0 dq = P iabc
v0 dq = P v abc (13)
λ0 dq = P λabc
IX. CONCLUSIONS