25 01 2020

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

DATE : 25.01.

2020
OVERHAULING STATUS UNIT # 6
Description of work Start date Completion date

Erection of scaffolding 19.01.2020 25.01.2020


with sealing

Arrangement &
Removal of Economizer 19.01.2020 30.01.2020
coil
HP Jet cleaning in 1st 25.01.2020 31.01.2020
Boiler Pass

Physical inspection and


thickness survey of 2nd 25.01.2021 13.02.2020
pass and rectification
work
40/40 coal burners 21.01.2020 27.01.2020
removed
APH basket removal 20.01.2020 25.01.2020

Removal of insulation of 23.01.2020 25.01.2020


HP & IP Turbine
Turbine
Removal of pedestal
cover and bearing top 24.01.2020 25.01.2020
half
Exciter outer cover 24.01.2020 24.01.2020
Removal
Exciter inner cover 25.01.2020 25.01.2021
Removal
Generator
Removal of C&I
Mounting 25.01.2021 25.01.2022
Diodewheel cover ,PMG
Removal 25.01.2022 25.01.2023

1/20/2020 2/2/2020
ESP DFA 2/1/2020 2/10/2020
1/22/2020 2/10/2020
1/20/2020 2/3/2020
2/4/2020 2/10/2020
BAH
1/20/2020 2/1/2020
AHD 2/2/2020 2/10/2020
1/20/2020 2/5/2020
Ash slurry pump and 1/20/2020 1/23/2020
Ash water pump
2/1/2020 2/10/2020
1/20/2020 1/31/2020
Compressors
1/25/2020 2/5/2020
SILO 1/20/2020 2/10/2020
Cleaning of 11 Kv
Station Bus OBA
Electrical Cleaning of ID Fan
Motor 6A cooler
Overhauling of CEP 6C
Motor

Bowl Mill 6D, 6E, 6F, 6G, 1/18/2020


6H

RCF 6A, 6B 6C, 6D 1/19/2020

ID Fan 6A 1/18/2020

Milling
System
Division ID Fan 6B 1/18/2020

FD Fan 6B 1/18/2020

Ducts 1/19/2020
Status

90% completed

In Progress

In Progress

In Progress

In Progress

completed

completed

In Progress

Completed

Completed

Completed

Completed

40%

10%
35%

25%

35%
90%

80%
25%

Completed

Completed

Completed

B/m 6D, 6E airport assembly


installed; rollers serviced;
MPO/MDV installed.
B/m 6F, 6G, 6H work in
progress. (30% completed)

Work in progress (20%


completed)
Cone re-installed after DPT;
Lube oil skid servicing work in
progress (40% completed)

Cone dismantled for DPT;


decoupled from motor (20%
completed)

Rotor & blades installed;


Alignment completed; Lube oil
skid servicing work in progress
(50% completed)

Cleaning work in progress;


welding work in progress
Expansion joints repairing /
shielding work in progress (30%
completed)