Professional Documents
Culture Documents
Selecting Flare Gas Recovery System For A Greenfield Refinery
Selecting Flare Gas Recovery System For A Greenfield Refinery
Selecting Flare Gas Recovery System For A Greenfield Refinery
and Safety
S. CHAUDHURI and S. SENGUPTA,
Process Technology, Fluor Daniel India Pvt. Ltd.,
Gurgaon, India
it is not practically possible to calculate capability, which often makes them un- • Ability to handle gas containing
the normal flaring rate for the sizing of acceptable for an FGRS. A sliding vane condensate and particulates,
an FGRS. The capacities of the FGRS compressor can also be an option for flare as well as toxic and corrosive gases
in such cases are primarily determined gas application, if the pressure is too high • Works without lubricants
based on the FGRS capacities of existing for a roots blower but too low to justify a • System is significantly
refineries of similar scale under operation. reciprocating compressor. tolerant for sudden gas
If the gas is always dry (which is sel- and condensate surges
Compressor selection. Insights into dom the case for a refinery flare), then • The intensive contact between
optimum compressor type selection a screw compressor is another choice. It the gas being conveyed and the
and sparing, as well as positive pressure caters to higher turndown, lower power operating fluid leads to only
requirements in the flare header, are dis- draw and low cooling water consumption, a slight rise in the temperature
cussed here. The selection of compres- and has no need for water makeup and a of the gas being conveyed
sor for an FGRS is a critical decision, as discharge separator/cooler, such as a liq- • Since the compression is
its service involves long stretches of con- uid ring compressor. However, a screw- achieved with contact-free
tinuous operation, variable flowrates, a type compressor is not really tolerant for components, any local rise in
range of molecular weight of gases to be liquid and particulate carryover and the temperature is eliminated
handled, potential liquid carryover and handling of corrosive gases. • No metal parts that move
the existence of corrosive components in Considering all operating variables, against each other; therefore,
the recovered gas. a liquid ring compressor is the popular a high level of reliability in
A roots-type blower is the simplest, choice for this service, as it can handle service exists with a minimum
least expensive option for compression. the variable molecular weights and liq- of required maintenance.
However, the use of these blowers is uid carryover, in addition to the follow- The FGRS design using a liquid ring
constrained by limited casing pressure ing advantages: compressor was selected for the case study.
Cooker flare
KO drum
68 AUGUST 2018 | HydrocarbonProcessing.com
Environment and Safety
Positive pressure requirements. stallation of a water seal between the flare be accepted, alternate methods are
Introducing a compressor into a flare knockout drum and the flare tip. The seal implemented using a fail-open pressure
collection network always poses the risk provides a relatively constant, low back- control valve and a high-capacity, pilot-
of sucking in air from the atmosphere, pressure on the flare header and a narrow, operated pressure relief valve, rupture
and the formation of an explosive but usually adequate, control range (ap- disk or buckling pin around the control
mixture within the flare network. proximately 1,000-mm water column) for valve. This is illustrated in Figure 14 of
Provisions must be made to prevent the the flare gas recovery control system. The API Standard 521.1 However, this option
backflow of air from the flare into the water seal should be designed to func- is not considered for the purpose of this
flare gas recovery system. tion over the pressure range in which the case study, as conventional water seal-
All compressors should be equipped FGRS is designed to operate. At higher based systems are proven to function
with a highly reliable, low-suction pres- release rates, flare gas flows through the adequately for refining applications.
sure shutdown system. water seal and to the flare.
The most positive and preferred meth- Where process requirements Case study system configuration. The
od for preventing air ingress from the flare dictate that the narrow operating refining complex under study had four in-
back into the collection system is the in- ranges afforded by water seals cannot dependent hydrocarbon flare systems.
Option 1
Design press: kg/cm2g/ Material
Equipment item Capacity/size Temp, °C of construction
Flare gas recovery compressor, liquid ring— Capacity: 15 tpd; Differential pressure, Casing: SS;
2 × 50% kg/cm2: 7.4; mol wt: 19.3; power: 92.3 kW Rotor: SS
Separator (two phases, 1 × 100%) Diameter × T/T length, mm: 1,900 x 4,600 9/70 Killed CS
Cooler: Shell and tube, 2 × 50% Duty: 33 kW; area: 6 m2 Shell: 9/70 Shell: KCS;
Tube: 10/80 Tube: CS
Line from FGRS to sat gas plant Nominal pipe size = 6 in.; length = 1,360 m 9/70 CS
Line from HP flare header to FGRS Nominal pipe size = 12 in.; length = 70 m 3.5/400 KCS
Line from LP flare header to FGRS Nominal pipe size = 20 in.; length = 70 m 3.5/400 KCS
Line from COK flare header to FGRS Nominal pipe size = 20 in.; length = 70 m 3.5/400 KCS
Line from ALK flare header to FGRS Nominal pipe size = 12 in.; length = 70 m 3.5/400 KCS
Flare header take-off line control valve 2 × 20 in.
2 × 12 in.
Control valve in the line from FGRS 6 in.
to sat gas plant
Analyzer O2, N2
Option 2
Design press: kg/cm2g/ Material
Equipment item Capacity/size Temp, °C of construction
Flare gas recovery compressor, Capacity: 30 tpd; differential pressure, Casing: SS;
liquid ring—2 × 100% kg/cm2: 7.4; mol wt: 19.3; power: 178 kW Rotor: SS
Separator (two phases, 1 × 100%) Diameter × T/T length, mm: 1,900 × 4,600 9/70 Killed CS
Cooler: Shell and tube, 2 × 100% Duty: 62.3 kW; area: 11 m2 Shell: 9/70 Shell: KCS;
Tube: 10/80 tube: CS
Line from FGRS to sat gas plant Nominal pipe size: 6 in.; length: 1,360 m 9/70 CS
Line from HP flare header to FGRS Nominal pipe size: 12 in.; length: 70 m 3.5/400 KCS
Line from LP flare header to FGRS Nominal pipe size: 20 in.; length: 70 m 3.5/400 KCS
Line from COK flare header to FGRS Nominal pipe size: 20 in.; length: 70 m 3.5/400 KCS
Line from ALK flare header to FGRS Nominal pipe size: 12 in.; length: 70 m 3.5/400 KCS
Flare header take-off line 2 × 20 in.
control valve 2 × 12 in.
Control valve in the line from FGRS 6 in.
to sat gas plant
Analyzer O2, N2
In addition to the high-pressure [(HP), The compressed gas is separated from • High nitrogen content in
catering to relief from sources with a set the liquid in the separator. The liquid flare header (measured by
pressure of 7 kg/cm2g and higher)] and from the separator is cooled in a cooler to an N2 analyzer at FGRS inlet)
low-pressure [(LP), catering to relief from remove the heat absorbed by the motive • High temperature in flare header.
sources with a set pressure of 3.5 kg/cm2g– fluid, and then recycled back to the liquid Considering the composition of the
7 kg/cm2g] systems, there were dedicated ring compressor. gases to be handled, the refinery operating
flare systems for the delayed coker unit The seal liquid is considered to have philosophy and capital/operating costs,
(DCU) and alkylation (ALK) unit due to enough pressure head for circulation and the decision was made to have 2 × 100%
high governing relief rates. transfer to an SWS unit in case of turn- or 2 × 50% spare for the FGRS compres-
The FGRS for the case study was de- around operation. For the purpose of this sor and other associated equipment. The
signed to recover gases from all four flare case study, the seal liquid recycle pumps study covers both of these options to pro-
headers. The flare gases withdrawn from and seal liquid transfer pumps to the SWS vide high-level guidance (FIG. 1).
the HP, LP, coker (COK) and ALK flare unit were not considered.
headers under pressure control are routed The compressed gas, free from liquid, Arriving at the sizing basis. An FGRS
to a set of liquid ring compressors. is routed to a gas treatment and recovery is economically viable in existing refiner-
Stripped phenolic sour water from a system (sat gas) for amine treatment to ies, and the implementation decision is
sour water stripper (SWS) unit is used as remove sour impurities, if any. The gas made after executing an economic viability
the motive liquid for liquid ring compres- is then finally routed to the refinery fuel study. FGRS capacity is selected by con-
sors. Alternatively, service water can be gas system. tinuously measuring and monitoring the
used as motive fluid. The liquid is routed The compressor train is provided with overall flare gas loss in the refinery for a
to an SWS (phenolic) unit under level 100% recycle. Safety interlocks are pro- considerable period of time.
control while emptying the separator dur- vided to isolate the FGRS from the flare As no method exists to calculate this
ing maintenance. header and trip compressor on the follow- potential flare gas loss figure for a green-
Liquid levels in the seal drums of the ing conditions: field refinery during the basic engineer-
HP, LP, COK and ALK flares are suitably • Low flare header pressure ing phase, historical data and the preva-
selected to maintain a constant pressure • High flare header velocity lent practices in operating refineries are
of 1.1 kg/cm2 (abs) in the flare headers, (high flow) utilized to determine FGRS capacity
thereby ensuring a constant suction pres- • High oxygen content in flare (TABLE 1).
sure for the compressor system in absence header (measured by an O2 During the engineering phase, a rea-
of significant relief. analyzer at FGRS inlet) sonable estimate of total flare system leak-
age can be achieved by assuming a per-
centage of leakage for the control/relief
TABLE 3. Economic evaluation—the CAPEX/OPEX values presented valves once all relief valves, control valves
are for comparison only1 and continuous/intermittent/machinery
Option 1 Option 2 Differential vents connected to the flare system are
CAPEX, $MM/yr 2.64 2.76 0.12 identified. Conservative leakage values
for pressure relief devices can be obtained
Product, utility and power load
from API Standard 527. The total fuel
Service Units Option 1 Option 2 Differential gas purge quantity can be accurately cal-
Recovered fuel gas Tpd 10 10 0 culated based on an estimated velocity of
Seal water cooler MMkCal/hr 0.0284 0.0536 0.252 purge gas through the flare header that is
OPEX estimation
The amount of purge gas used for thereby ensuring high availability and re- a strong function of refinery housekeeping
purging the hydrocarbon flare headers is liability of the FGRS (TABLE 3). practices, the outcome of the techno-eco-
estimated as 10 tpd. nomic analysis was positive.
Takeaway. For the case study, FGRS
Installation options. For installation installation (both Options 1 and 2) are NOTE
Option 1, 30 tpd of compression capac- observed to recoup their capital cost The conclusions presented here are solely those of
ity is installed in two trains of 15 tpd around the first planned refinery-wide the authors and cannot be ascribed to Fluor Corp., nor
to any of its subsidiaries.
each. It is assumed that for the first 4 yr, maintenance operation, which is typically
flare loss gases are essentially only purge in the first 4 yr of production. This is very LITERATURE CITED
gases; therefore, one of the 15-tpd com- encouraging in view of an overall refinery 1
API Standard 521, “Pressure relieving and depres-
pressors will operate while the other acts design life of 20 yr. suring systems,” 6th Ed., 2014.
as a standby. After 4 yr, when leakages Between the two options presented,
from relief and control valves increase, it is observed that the capital investment, SUSHREE CHAUDHURI is a
the second 15-tpd compressor will also as well as variable costs, are higher in the Process Engineer with Fluor
New Delhi. She has 17 yr of
start operating continuously. case of Option 2, with only a 0.6-yr incre- experience in petroleum refining,
For this installation option, it is as- mental payback period. The incremental petrochemicals, offshore oil and gas
sumed that the refinery can sustain op- capital cost and payback period for Op- and flare systems, and front-end
and detailed design. Ms. Chaudhuri
eration without the FGRS for a limited tion 2 are offset by the increased operat- earned BS degrees in chemistry and chemical
period of time without any significant ing flexibility and reliability in terms of engineering from the University of Calcutta.
impact. In Option 1, the FGRS operates 100% sparing capacity.
without a spare after the first 4 yr of refin- As an outcome of the case study, the in- SAUMYA SENGUPTA is a Principal
Specialty Engineer with Fluor New
ery operation. stallation of an FGRS was recommended Delhi. He has 25 yr of experience in
For installation Option 2, it is sug- for the new NA refinery. While it is dif- petroleum refining, petrochemical
gested to install 30 tpd of compressing ficult to quantify the economic viability complex and utilities/offsites, and
front-end and detailed design.
capacity with 100% spare. The FGRS of an FGRS due to the uncertainty in the Mr. Sengupta earned BS degrees
compressor should always have installed amount of gas that can be recovered and the in chemistry and chemical technology (petroleum
spare capacity in the case of Option 2, variable nature of recovered gases, which is refinery engineering) from the University of Calcutta.
11th ANNUAL
NATIONAL ABOVEGROUND STORAGE TANK
•
•
F REE T RA DE S HOW
Conference Sessions
Free Trade Show
CONFERENCE & TRADE SHOW • Welcome Reception
September 12-13, 2018 • Cocktail Mixer on the
Trade Show Floor
Moody Gardens | Galveston, Texas
• Golf Tournament
NISTM
NATIONAL INSTITUTE FOR STORAGE TANK MANAGEMENT
www.NISTM.org | 800.827.3515
International 011.813.600.4024