BOQ FOR PROPOSED INDUSTRIAL BUILDING @ KALLAKAL

Sl No Description Unit Quantity


Rate Amount (RS) Remarks
Unit Material Labour Total
for manual
1 Excavation CUM 1974 CUM 0 100 100 197359
Rs.160/Cum
Including
2 Earth Filling CUM 3530 CUM 0 80 80 282419
Plinth Filling

3 READY MIX CONCRETE

M10 CUM 577 CUM 2800 450 3250 1873956 GST INCLUDED

M20 CUM 1239 CUM 3450 650 4100 5078752 GST INCLUDED

M25 CUM 55 CUM 3600 650 4250 235497 GST INCLUDED

4 VDF & GROOVE SQM 3827 SQM 0 120 120 459294

5 Cement Bags 859 Bags 320 0 320 274820 GST INCLUDED

6 Sand - Below PCC CUM 214 CUM 635 250 885 189801

7 M Sand - Block Work CUM 114 CUM 1058 0 1058 120333

8 M Sand - Plastering CUM 60 CUM 1764 0 1764 106518

9 Internal Plaster SQM 1493 SQM 0 170 170 253857

10 External Plaster SQM 2273 SQM 0 170 170 386337

11 8" Solid Blocks CUM 227 CUM 3000 900 3900 886304

12 RR Stones CUM 239 CUM 850 850 1700 406960

13 Through bond stones CUM 24 CUM 850 850 1700 40696

14 Shuttering SQM 1455 SQM 300 150 450 654692 GST INCLUDED

15 Reinforcement Steel MT 96 MT 38000 7000 45000 4322170

16 Binding Wire Kg 960 Kg 70 7 77 73957

17 Wall Putty Bags 90 SQM 56 25 81 7257

18 Primer - Internal 20 Ltr Can 4 SQM 7 4 11 49

19 Primer - External 20 Ltr Can 9 SQM 7 4 11 100

20 Paint- Internal 20 Ltr Can 12 SQM 22 17 39 472

21 Paint - External 20 Ltr Can 14 SQM 27 21 48 655

22 MS Work Kg 1980 Kg 45 30 75 148495

23 Rolling Shutter SQM 9 SQM 2000 450 2450 22050

24 uPVC Window SQM 103 SQM 3400 1500 4900 502826

25 Structural Steel MT 312 MT 42000 38000 80000 24960000


Roofing & Cladding Sheet
26 and Screws and other SQM 9300 SQM 433 170 603 5607900
accessories
27 Gutter, Flashes Etc Rmt 250 Rmt 275 100 375 93750
GRAND TOTAL Rs. 47,187,274.00
IN WORDS: RUPEES FOUR CRORE SEVENTY ONE LAKHS EIGHTY SEVEN THOUSAND TWO HUBDRED AND SEVENTY FOUR ONLY.

NOTE:
RMC RATE MAY VARY FROM PLANT TO PLANT. THIS RMC CONCRETE RATE HOLDS GOOD ONLY FOR 1 MONTH.