Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 17

Subject : Triple Barrel Box Culvert

Owner : Prominence Properties, Inc.


Location : Paseo de San Roque, Bulacan
Date : Dec. 26, 2019

ITEM
DESCRIPTION/SPECIFICATION FACTORS QTY UNIT
NO.
1.00 EXCAVATION/HAULING 73.00 cu.m
1.10 Materials
1.20 Equipment
Excavator, PC30 (for cut & fill) 1.00 16.86 cu.m/hr 2.00 day(s)
Temporary Facility 1.00

1.30 Labor
Operator/Driver 1.00 2.00 day(s)
Laborer/Helper 3.00 2.00 day(s)

2.00 CONCRETE WORKS 209.89 cu.m


2.10 Materials
Lean Concrete/Slab 54.45 cu.m
Cement, Portland 40kg 9.00 bags/cu.m 491.00 bags
Crushed Gravel 3/4 1.00 cu.m/cu.m 54.45 cu.m
Sand (S-1) 0.50 cu.m/cu.m 27.23 cu.m

Barrel Box 89.40 cu.m


Cement, Portland 40kg 9.00 bags/cu.m 805.00 bags
Gravel 1.00 cu.m/cu.m 89.40 cu.m
Sand (S-1) 0.50 cu.m/cu.m 44.70 cu.m
Pipe PVC Series 600 x 75mm x 3000mm 3.02 pc(s)

Wingwall & Headwall 24.07 cu.m


Cement, Portland 40kg 9.00 bags/cu.m 217.00 bags
Gravel 1.00 cu.m/cu.m 24.07 cu.m
Sand (S-1) 0.50 cu.m/cu.m 12.03 cu.m

Aggregate Base Course 47.97 cu.m

2.20 Equipments
Concrete Mixer 1.00 25.00 cu.m/day 19.00 days

2.30 Labor
Foreman 1.00 19.00 days
Skilled Worker 3.00 19.00 days
Laborer/Helper 5.00 19.00 days

3.00 REBAR DETAILING


3.10 Materials
Slab
Deformed Bars, 12mm∅ x 6m 1.33 8m/sqm 599.68 pcs
GI Tie Wire #16 22.29 kgs

Barrel Box
Deformed Bars, 12mm∅ x 6m 79.20 pcs
Deformed Bars, 16mm∅ x 6m 171.60 pcs
Deformed Bars, 20mm∅ x 6m 394.53 pcs
Deformed Bars, 25mm∅ x 6m 52.80 pcs
GI Tie Wire #16 40.00 kgs
Wingwall & Headwall
Deformed Bars, 12mm∅ x 6m 175.54 pcs
Deformed Bars, 16mm∅ x 6m 61.60 pcs
GI Tie Wire #16 16.00 kgs

2.30 Labor
Foreman 1.00 Php 72.65/hr 12.00 days
Rebarman 3.00 Php 65.4/hr 12.00 days
Laborer/Helper 5.00 Php 46.87/hr 12.00 days

4.00 FORMWORKS
4.10 Materials
Good lumber 2"x4"x12' 335.45 bdf
CW Nails 4" 32.08 kgs
CW Nails 3" 35.24 kgs
Phenolic Board 1/2 x 4'x8' 132.05 pc(s)

4.20 Labor
Foreman 1.00 Php 72.65/hr 8.00 days
Skilled Worker 3.00 Php 65.4/hr 8.00 days
Laborer/Helper 5.00 Php 46.87/hr 8.00 days

Total Material Cost


Total Labor/Equipment Cost
Total Direct Cost
Indirect Cost, 5%
Mark-up Cost, 10%
Total Project Cost

Prepared by: Checked by:


___________ _______________
Ricky Calara Engr. Jay Russel Fajarito
UNIT AMOUNT
COST
484.82 35,392.20

32,200.00
1100.00 2,200.00
30000.00 30,000.00

3,192.20
546.10 1,092.20
350.00 2,100.00

5125.08 1,075,708.97
970,722.57

225.00 110,475.00
2100.00 114,345.00
2100.00 57,172.50

225.00 181,125.00
2100.00 187,733.70
2100.00 93,866.85
210.00 634.62

225.00 48,825.00
2100.00 50,538.60
2100.00 25,269.30

2100.00 100,737.00

28,500.00
1500.00 28,500.00

76,486.40
581.20 11,042.80
523.20 29,822.40
374.96 35,621.20

561,638.66
513,331.46

195.00 116,937.60
90.00 2,006.10

195.00 15,444.00
352.00 60,403.20
518.00 204,368.61
1007.94 53,219.23
90.00 3,600.00
195.00 34,229.52
352.00 21,683.20
90.00 1,440.00

48,307.20
581.20 6,974.40
523.20 18,835.20
374.96 22,497.60

298,458.61
266,253.81
198 66,418.11
85.00 2,726.80
85.00 2,995.40
1470.00 194,113.50

32,204.80
581.20 4,649.60
523.20 12,556.80
374.96 14,998.40

1,750,307.84
/Equipment Cost 192,390.60
1,942,698.44
97,134.92
194,269.84
2,234,103.21

ussel Fajarito
Subject : Triple Barrel Box Culvert
Owner : Prominence Properties, Inc.
Location : Paseo de San Roque, Bulacan
Date : Nov.7, 2019

ITEM
DESCRIPTION/SPECIFICATION FACTORS QTY UNIT
NO.
1.00 EXCAVATION/HAULING 73.00 cu.m
1.10 Materials
1.20 Equipment
Excavator, PC30 (for cut & fill) 1.00 16.86 cu.m/hr 2.00 day(s)

1.30 Labor
Operator/Driver 1.00 2.00 day(s)
Laborer/Helper 3.00 2.00 day(s)

2.00 CONCRETE WORKS 177.55 cu.m


2.10 Materials
Lean Concrete/Slab 54.45 cu.m
Cement, Portland 40kg 9.00 bags/cu.m 490.05 bags
Crushed Gravel 3/4 1.00 cu.m/cu.m 54.45 cu.m
Sand (S-1) 0.50 cu.m/cu.m 27.23 cu.m

Barrel Box 89.40 cu.m


Cement, Portland 40kg 9.00 bags/cu.m 804.57 bags
Gravel 1.00 cu.m/cu.m 89.40 cu.m
Sand (S-1) 0.50 cu.m/cu.m 44.70 cu.m
Pipe PVC Series 600 x 75mm x 3000mm 3.02 pc(s)

Wingwall & Headwall 24.07 cu.m


Cement, Portland 40kg 9.00 bags/cu.m 216.59 bags
Gravel 1.00 cu.m/cu.m 24.07 cu.m
Sand (S-1) 0.50 cu.m/cu.m 12.03 cu.m

Pavement 9.64 cu.m


Cement, Portland 40kg 9.00 bags/cu.m 86.75 bags
Gravel 1.00 cu.m/cu.m 9.64 cu.m
Sand (S-1) 0.50 cu.m/cu.m 4.82 cu.m
Aggregate Base Course 47.97 cu.m

2.20 Equipments
Concrete Mixer 1.00 25.00 cu.m/day 14.20 days

2.30 Labor
Skilled Worker 3.00 14.20 days
Laborer/Helper 5.00 14.20 days

3.00 REBAR DETAILING


3.10 Materials
Lean Concrete/Slab
Deformed Bars, 12mm∅ x 6m 1.33 8m/sqm 599.68 pcs
GI Tie Wire #16 22.29 kgs

Barrel Box
Deformed Bars, 12mm∅ x 6m 79.20 pcs
Deformed Bars, 16mm∅ x 6m 171.60 pcs
Deformed Bars, 20mm∅ x 6m 394.53 pcs
Deformed Bars, 25mm∅ x 6m 52.80 pcs
GI Tie Wire #16 40.00 kgs

Wingwall & Headwall


Deformed Bars, 12mm∅ x 6m 175.54 pcs
Deformed Bars, 16mm∅ x 6m 61.60 pcs
GI Tie Wire #16 16.00 kgs

2.30 Labor
Rebarman 3.00 10.00 days
Laborer/Helper 5.00 10.00 days

4.00 FORMWORKS
4.10 Materials
Good lumber 2"x3"x12' 335.45 bdf
Good lumber 2"x2"x12' 335.45 bdf
CW Nails 4" 32.08 kgs
CW Nails 3" 35.24 kgs
Plywood Ordinary 1/2 x 4'x8' 132.05 pc(s)

4.20 Labor
Skilled Worker 3.00 Php 65.4/hr 8.00 days
Laborer/Helper 5.00 Php 46.87/hr 8.00 days

5.00 PAINTING WORKS


5.10 Materials 117.88 sqm
Primer 12.38 4L
Paint, White (Wing wall) 77.08 sqm 4.05 4L
Paint, Black 6.19 4L

5.20 Labor
Painter 1.00 3.00 days
Helper 2.00 3.00 days

Total Material Cost


Total Labor Cost
Total Equipment Cost
Total Project Cost

Prepared by: Checked by:


___________ _______________
Ricky Calara Engr. Jay Russel Fajarito
UNIT AMOUNT
COST
73.87 5,392.20

2,200.00
1100.00 2,200.00

3,192.20
546.10 1,092.20
350.00 2,100.00

6681.49 1,186,312.35
1,116,081.30

285.00 139,664.25
2100.00 114,345.00
2100.00 57,172.50

285.00 229,303.31
2100.00 187,733.70
2100.00 93,866.85
210.00 634.62

285.00 61,729.29
2100.00 50,538.60
2100.00 25,269.30

285.00 24,724.04
2100.00 20,241.90
2100.00 10,120.95
2100.00 100,737.00

21,306.24
1500.00 21,306.24

48,924.81
523.20 22,294.85
374.96 26,629.96

645,792.86
611,348.86

234.43 140,582.98
90.00 2,006.10

234.43 18,566.86
412.8 70,836.48
645.11 254,517.83
1007.94 53,219.23
90.00 3,600.00

234.43 41,150.90
412.8 25,428.48
90.00 1,440.00

34,444.00
523.20 15,696.00
374.96 18,748.00

230,599.05
203,043.85
198 66,418.11
132 44,278.74
85.00 2,726.80
85.00 2,995.40
656.00 86,624.80

27,555.20
523.20 12,556.80
374.96 14,998.40

14,587.41
11,137.41
445.00 5,507.94
550.00 2,225.69
550.00 3,403.79

3,450.00
450.00 1,350.00
350.00 2,100.00

1,941,611.43
117,566.21
23,506.24
2,082,683.88

ussel Fajarito
Subject : Triple Barrel Box Culvert
Owner : Prominence Properties, Inc.
Location : Paseo de San Roque, Bulacan
Date : Nov.7, 2019

ITEM UNIT
DESCRIPTION/SPECIFICATION FACTORS QTY UNIT
NO. COST
1.00 EXCAVATION/HAULING 73.00 cu.m 270.91
1.10 Materials
1.20 Equipment
Excavator, PC30 1.00 4hr/day 3.00 days 2600.00
Dump Truck (3 cu.m capacity) 1.00 3.00 days 1500.00

1.30 Labor
Operator/Driver 2.00 3.00 days 546.10
Laborer/Helper 4.00 3.00 days 350.00

2.00 CONCRETE WORKS 177.55 cu.m 5365.87


2.10 Materials
Lean Concrete/Slab 54.45 cu.m
Cement, Portland 40kg 9.00 bags/cu.m 490.05 bags 215.00
Gravel 1.00 cu.m/cu.m 54.45 cu.m 700.00
Sand 0.50 cu.m/cu.m 27.23 cu.m 700.00
Deformed Bars, 12mm∅ x 6m 1.33 8m/sqm 599.68 pcs 106.56
GI Tie Wire #16 22.29 kgs 90.00

Barrel Box 89.40 cu.m


Cement, Portland 40kg 9.00 bags/cu.m 804.57 bags 215.00
Gravel 1.00 cu.m/cu.m 89.40 cu.m 700.00
Sand 0.50 cu.m/cu.m 44.70 cu.m 700.00
Grade 40 Steel bars dapat gamitin
Deformed Bars, 12mm∅ x 6m 79.20 pcs 106.56
Deformed Bars, 16mm∅ x 6m 171.60 pcs 189.36
Deformed Bars, 20mm∅ x 6m 394.53 pcs 295.92
Deformed Bars, 25mm∅ x 6m 52.80 pcs 462.36
GI Tie Wire #16 40.00 kgs 90.00
Pipe PVC Series 600 x 75mm x 3000mm 3.02 pc(s) 210.00

Wingwall & Headwall 24.07 cu.m


Cement, Portland 40kg 9.00 bags/cu.m 216.59 bags 215.00
Gravel 1.00 cu.m/cu.m 24.07 cu.m 700.00
Sand 0.50 cu.m/cu.m 12.03 cu.m 700.00
Deformed Bars, 12mm∅ x 6m 175.54 pcs 106.56
Deformed Bars, 16mm∅ x 6m 61.60 pcs 189.36
GI Tie Wire #16 16.00 kgs 90.00

Pavement 9.64 cu.m


Cement, Portland 40kg 9.00 bags/cu.m 86.75 bags 215.00
Gravel 1.00 cu.m/cu.m 9.64 cu.m 700.00
Sand 0.50 cu.m/cu.m 4.82 cu.m 700.00
Aggregate Base Course 47.97 cu.m 700.00

2.20 Equipments
Concrete Mixer 2.00 30.00 days 150.00

2.30 Labor
Skilled Worker 3.00 31.00 days 450.00
Laborer/Helper 5.00 31.00 days 350.00

3.00 FORMWORKS
3.10 Materials
Cocolumber 2"x3"x12' 335.45 bdf 80
Cocolumber 2"x2"x12' 335.45 bdf 65
CW Nails 4" 32.08 kgs 85.00
CW Nails 3" 35.24 kgs 85.00
Plywood Ordinary 1/2 x 4'x8' 132.05 pc(s) 750.00

3.20 Labor
Skilled Worker 3.00 8.00 days 450.00
Laborer/Helper 5.00 8.00 days 350.00

4.00 PAINTING WORKS


4.10 Materials 117.88 sqm
Primer 12.38 4L 445.00
Paint, White (Wing wall) 77.08 sqm 4.05 4L 550.00
Paint, Black 6.19 4L 550.00

3.20 Labor
Painter 1.00 3.00 days 450.00
Helper 2.00 3.00 days 350.00

Total Material Cost


Total Labor Cost
Total Project Cost

Prepared by: Checked by:


___________ _______________
Ricky Calara Engr. Jay Russel Fajarito
NOTES/Comments

AMOUNT

19,776.60

12,300.00
7,800.00 Capability of PC30 Excavator = cum/hr?
4,500.00 Saan ang Disposal Site? Dba kailngan natin ng Panambak,

7,476.60
3,276.60 Please update labor rates of HE Operators
4,200.00

952,720.87
847,620.87 PAKIHIWALAY ITEM NG CONCRETE WORKS AT REBAR WORKS

105,360.75
38,115.00
19,057.50
63,901.90 Update price of Steel Bars Grade 40
2,006.10

172,983.20
62,577.90
31,288.95

8,439.55
32,494.18
116,750.50
24,412.61
3,600.00
634.62

46,567.71
16,846.20
8,423.10
18,705.12
11,664.58
1,440.00

18,651.47
6,747.30
3,373.65
33,579.00

9,000.00
9,000.00

96,100.00 Capability Output of Laborer


41,850.00
54,250.00

178,199.23
153,399.23
26,835.60 Good Lumber
21,803.93
2,726.80
2,995.40
99,037.50 Marine Plywood or

24,800.00
10,800.00
14,000.00

14,587.41
11,137.41
5,507.94
2,225.69
3,403.79

3,450.00
1,350.00
2,100.00

1,012,157.51
131,826.60
1,165,284.11
ITEM III - CONCRETE WORKS

Quantity: 4.00 cu.m

A) Quantity Take Off:


for Concrete Flooring:

Length= 36 m
Width= 1 m
Thickness= 0.10 m
Volume= 4 cu.m

Steel Reinforcement:
Main Bars, 10mmǾ Spaced @ 0.40m O.C.
for 36m
No. of Lines = 36/0.40 = 90lines
No. of Full L = 1x90= 90m.
No. of 6mL = 90/6=15 pcs
Provide: 15 pcs - 10mmǾx6m RSB

for 1m
No. of Lines = 1/0.40 = 2.5lines
No. of Full L = 36x2.5=90m
No. of 6mL = 90/6=15 pcs
Provide: 15pcs - 10mmǾx6m RSB

B) Materials:
Quantity= 4 cu.m
Concrete Strength= 1:2:4

Portland Cement= 4 x 9 32.40


Sand S-1= 4 x 0.5 1.80
Gravel 3/4= 4 x 1 3.60

Material Description Qty Unit Unit Cost


Portland Cement 32 bags 285.00
Sand (S-1) 2 cu.m 2,000.00
Crushed Gravel 3/4 4 cu.m 2,100.00
10mm dia. X 6m RSB Std. 30 pcs. 200.00
G.I Tire Wire 5 kgs. 100.00

C.) Equipment
Equipment Discription Qty Rate/day Duration
One(1) Bagger Concrete Mixer 1 1,500 2

D.) Labor
Manpower Description Qty Rate/day Duration
Foreman 1 600 2
Mason 2 450 2
Laborers 6 350 2
Amount
9,120.00
4,000.00
8,400.00
6,000.00
500.00
28,020.00

Amount
3,000.00
3,000.00

Amount
1,200.00
1,800.00
4,200.00
7,200.00

You might also like