Appendix 3 Schedule of Work - R03

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Work 2019 2020 2021

System Quantity Start Finish Dur.


Scope 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2

GT/G #21(GTB #2) Conduit 1900m 11-Dec-19 28-Jan-20 48


910 990

GT/G #22(GTB #2) Conduit 1900m 07-Jan-20 18-Feb-20 42


910 990

Cable Tray 498m 10-Dec-19 25-Mar-20 106


90 150 150 108
HRSG #11
Conduit 2918m 13-Feb-20 30-Jun-20 138
386 576 700 700 576

Cable Tray 498m 10-Dec-19 25-Mar-20 106


90 150 150 108
HRSG #12
Conduit 2918m 13-Feb-20 30-Jun-20 138
386 576 700 700 576

Cable Tray 840m 12-Dec-19 22-Feb-20 72


190 400 250

LEB #10 Conduit 446m 01-Feb-20 30-May-20 119


108 108 144 86

SWGR 88 PNL 01-Jan-19 28-Feb-19 58


50 38

PIPE RACK B1 Cable Tray 2109m 15-Dec-19 30-Apr-20 137


238 418 468 518 468