Mobilisation - access control, barricading, path ways and temporary facilities

works to complete before start of excavation

actual achieved
# Works Activity target date status Remarks
on
1 controlled access
Gate no 1 - Temporary closure by GI sheet or so
Gate no 2 - Boom barrier, barricading between boom barrier
& boundary wall
Gate no 3 - temporary closure by block masonry
Deployment of guard to restrict entry of workers without
PPE
spare hamlet etc to visitor - say 10 nos

2 Path ways & barricading


path ways as per logistic plan - Railings, raising of bottom
level by soil filling & GSB with moorum, painting of railing
etc.
hard barricading of excavation area, including painting of
pipe
hard barricading between construction area and yard,
including painting of pipe
hard barricading of 3 material yards - main yard near store,
near gate no 3 and near curing water tank
3 Drinking water
arrangement of drinking water for workers at 3 locations
with proper drainage (ensure no water accumulating near
this area)

4 Toilets
Functional toilets for workers with water supply, drainage
and septic tank (with arrangement of taking out of sewer by
tanker)

5 stores & site office


general store
medical room - in ready to use condition with first aid box,
cot, table, one chair, fan etc.)
site office
functional toilet

6 General lighting
source of power (DG) with earthing and distribution panel
(with elcb)
Lights at various location (near - gates, store, drinking water
area, toilets etc.)

7 Water
arranging source of water and send for testing

works to complete before start of next activity post excavation

# Works Activity target date status Remarks


1 Controlled access
Temp gate at gate no 2 and gate no 1
2 water network
curing water tank, arrangement for filling water in this tank,
booster pump, distribution netwrok/ ring, out lets at various
location for curing the concrete
3 Drinking water
filling water with water network (pipe), connected at both
end (drinking water side and source side), no manual
loading of water
4 Toilets
filling water with water network (pipe), connected at both
end (toilet water tank side and source side), no manual
loading of water in water tank near these toilets
5 stores & site office
cement store
Lab with all equipment's (as per tender doc)
shed for workers to take rest/ lunch
others
6 electricity/ illumination
power from grid
proper incomming connections from grid & DG with change
over facility
distribution panel

distribution network with feeder panels at various locations


general lighting (illumination of path ways, gate, yards,
worker's shed, toilets, drinking water locations etc.)