Engineering Cost Estimate

Project:

PNEUMATIC CONVEYING
SYSTEM BUILDING
Client:
UNILEVER PAKISTAN FCL FACTORY
Consultants:
ans associates

Mechnical Works
S. No. Description Qty Unit Rate Rs. Amount Rs.
1 Safety Measures
Providing and fixing in position temporary scaffolding and corrugated sheets all around the site before start of
1.00 Job. 38,291.44 38,291.44
work. The arrangement shall remain at site till handing over of the site to the client.
2 Setting, Layout and Documentations -
Setting and layout in detail as per drawings, of the building with respect to its boundaries including maintaining
the desired levels, fixing the grids with PCC peg and maintaining them till they are required all to the satisfaction 1.00 Job. 28,718.58 28,718.58
of the Engineer.
3 Structural Steel
Providing and fixing in position MS Steel ASTM A36 Wide Flange, channel and box sections of sizes, as shown in
the drawings, including the cost of two coats of painting with red oxide anti-corrosion paint and then with Three
Coats Of Epoxy paint of ICI or approved company after fixing, welding, cutting and bolting, complete in all
respects as shown in the drawings and as approved by the engineer.
3-1 CS 50x100x9.84kg/m 922 kg 299.63 276,259.31
3-2 CS 63x125x11.48kg/m 300 kg 302.50 90,750.70
3-3 Cold Formed Purlin/Girts CS 75x150x4.4kg/m 2535 kg 302.50 766,843.44
3-4 HS 100X100X19.7 kg/m 2415 kg 329.31 795,274.83
3-5 HS 150x150x32.8kg/m 1104 kg 326.43 360,383.68
3-6 HS 200x200x50.4kg/m 5187 kg 329.31 1,708,112.03
3-7 HS 250x250x75.5kg/m 3045 kg 329.31 1,002,737.83
3-8 IS 100x200x26.2kg/m 1428 kg 290.06 414,202.29
3-9 IS 125x250x39.4kg/m 1386 kg 298.67 413,961.06
3-10 IS 125x300x49kg/m 1072 kg 295.80 317,099.04
3-11 IS 150x300x52.5kg/m 790 kg 296.76 234,439.32
3-12 IS 50x100x9.8kg/m 2073 kg 299.63 621,134.00
3-13 IS 75x150x17.3kg/m 2162 kg 293.89 635,383.20
3-14 L63x63x6mm 296 kg 296.76 87,840.55
3-15 L50x50x3mm 326 kg 296.76 96,743.31
3-16 L75x75x6mm 777 kg 295.80 229,837.64
3-17 Connecting Plates, Stiffners and Angles 6mm,8mm,10mm,12mm thick 1380 kg 282.40 389,711.09
3-18 Sag Rod 16mm dia 1,955.00 kg 409.72 800,999.40
3-19 Column Splicing Plate 3/4" Thick 1,610.00 kg 335.05 539,430.60
3-20 A325 pretensioned Bolts 3/4" dia 299.00 Nos 239.32 71,557.12
4 Checkered Plates - -

Placing and fixing in position Mild Steel ASTM A36 Checquered plates 6mm thick including the cost of cutting, bending,
bolting and welding as well as the cost of secondary members supporting floor plate and their end connections, 98.00 sq.m 11,998.62 1,175,864.90
complete in all respects as shown in the drawings and as approved by the engineer.
5 Safety Railings
Placing and fixing in position Mild Steel ASTM A36 Steel Safety Railings including the cost of pipes, channels, cleats,
cutting, bending, bolting and welding as well as the cost of secondary members such as bolts etc., complete in all
respects as shown in the drawings and as approved by the engineer. 127.00 r.m 3,819.57 485,085.48
(Note:- Railing locations around platform and equipment as Approved by Client to be, detailed in shop
drawings and implemented at site)
6 Metal-Roofing Sheets
Providing & Fixing 20 gauge Trapezoidal corrugated galvanized iron sheets with G.I. bolts, nuts, limpet and
a) bitumen washers, wind ties, without valleys and ridges, inclusive of Rock wool or other approved insulation/filler 642.00 sqm 2,393.21 1,536,443.87
and silicone

Providing, fabrication and fixing in position MS Sheet Gage 22 Gutter (150x225), inclusive the cost of rawal bolts,
b) 70.00 R.M. 790.72 55,350.27
PVC down spouts, complete in all respect as per specifications and as shown in the drawings.

TOTAL 13,172,455.00