Now undertake the JSA and record in the table below. Use prompts on JSA Prompt Sheet and Hazard Checklist PA-HSEC-02-040-002-F03.
Part 3: Contingency Plans. Standard PPE,S : First aid kit must be present at the area and the HSE personnel is the first response in case of
emergency
Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? Any practices
that need to be captured in the OMS? List action items, changes, and transfer any changes to the Change Management system.
File: 10.30
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
1 Mobilization of equipment & Unauthorised equipment/tools brought out to Before mobilizing any equipment/tools make sure
workers site that the E &P Personnel got inspected the
equipment. Checklist must be present in equipment
Ensure that all personnel prior to start the have
Unskilled and uninducted personnel starting been inducted and oriented about the hazard in the
the job job site.
All personnel not fit to work shall not be allowed
to work at the project site.
Workers starting the job unfit to work
JSA must be in place prior to work. Ensure all the
persons take part in the toolbox meeting
Workers starting the job without permit discussion. Persons signed at the back of JSA
Ensure that adequate rest or shade must be
Heat exhaustion provided and water must be present at the area
Ensure that workers and drivers adhere the traffic
Possible road accident plan following the right pathway and pedestrian,
speed limit is only 10km/hr while accessing the
area
Ensure that workers are wearing hi vest all the
SIMOPS times. No unauthorised workers shall be allowed to
stay at the working area
2 Clearing/grubbing using Grader Personnel and equipment interface Ensure that a banks man shall be present at every
equipment all the times
Equipment failure Ensure E &P Personnel got inspected the
equipment. Checklist must be present in equipment
Equipment fall over/overturn Ensure that the tractor shall not go for maximum
slope of 30 degree/open edge
4. Soil clearing and levelling Grader Personnel and equipment interface Ensure that a banks man shall be present at every
equipment all the times
Equipment failure Ensure E &P Personnel got inspected the
equipment. Checklist must be present in equipment
Ensure that the equipment shall not go for
maximum slope of 30 degree/open edge
Equipment fall over/overturn
Exposure of workers to various hazard like Ensure workers are complying with the min. PPE
hand injury, dust, eye injury req..Safety shoes, helmet, safety glass, dust mask,
reflective vest, Note: Scarf/Loose cloth is not
allowed
SIMOPS Ensure that workers are wearing hi vest all the
times. No unauthorised workers shall be allowed to
stay at the working area Other personnel shall be
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
informed about the equipment operation on the
area
If works shall be done at night ensure provision of
Poor lighting sufficient light and full supervision are in place
Ensure that flashing light is in place
Hi-vest is necessary
Ensure buddy system
No night work shall commence if there is poor
lighting
6. Stone Laying-using tractor with Personnel and equipment interface Ensure that a banks man shall be present at every
trolley/manually equipment all the times
Equipment failure Ensure E &P Personnel got inspected the
equipment. Checklist must be present in equipment
Equipment fall over/overturn Ensure that the equipment shall not go for
maximum slope of 30 degree/open
JSA No: JOB TITLE:
Step Describe Job Step Potential Hazards Hazard Controls
No (Copy from part 2 of form) (Use Hazard Checklist)
edge/uncompacted soil
Workers will be oriented about the proper posture
Back injury and positioning during the execution of the job
Ensure workers are complying with the min. PPE
Dust req..Safety shoes, helmet, safety glass, dust mask,
reflective vest, Note: Scarf/Loose cloth is not
allowed
Ensure workers/opt. are wearing dust mask
Ensure frequent wetting of soil to eliminate
accumulation of dust in the area
Ensure workers are aware about the presence of
snake at the area. No killing of snake.
Snake bite Ensure proper supervision are in place adhering the
Poor supervision drawing for road construction
Ensure that the area was properly secured and
manage
Ensure that the tractor shall not go for maximum
slope of 30 degree/open edge
7. Personnel and equipment interface Ensure that a banks man shall be present at every
Concreting/Asphalting works equipment all the times
Ensure E &P Personnel got inspected the
equipment. Checklist must be present in equipment
Equipment failure
Unskilled and uninducted personnel starting Ensure that toolbox meeting was regularly
conducted and people are aware of the job and the
the job
hazard enclosed in the job they are performing
.JSA was discussed and signed at the back by all
workers. JSA valid for one week
8. Demobilization Poor Hosukeeping Ensure area was left clean and tidy