Professional Documents
Culture Documents
Underground Cable Temperature Monitoring in The Real World
Underground Cable Temperature Monitoring in The Real World
Temperature Monitoring in
the Real World
Executive Summary
Background
Brain Storming Possible Causes to Duct Bank
Over Heating
Mitigating Duct Bank Overheating
DTS Installation for Duct Bank Temperature
Monitoring
October Heat Storm
Wrap-Up
Background
• (Jan 2014) Hot conditions were first noticed by Troublemen
performing switching operations during early morning hours.
• A new circuit was needed at the substation, so the ductbank was
split in two.
• (May 2014) While work was being performed, elevated
temperatures were again observed.
• A temperature of 183F was measured in an empty conduit.
1. Neutral Imbalance
2. Load Factor
3. Vault Blower
4. Soil Conditions
5. Over Crowding
Possible Causes
1. Neutral Imbalance
West Wall inside M5586490 from Sub (Line Side)
• Panther 12kv - Gnd 9 amps
• Gazelle 12kv - Gnd 16 amps
• Cougar 12kv - Gnd 12.5 amps
• Elephant 12kv - Gnd 14.8 amps
• Jaguar 12kv - Gnd 6 amps
• Bison 12kv - Gnd 3 amps
East Wall inside M5586490 (Load Side)
• Panther 12kv - Gnd 13 amps
• Elephant 12kv - Gnd 11.5 amps
• Gazelle12kv - Gnd 14.7amps
• Bison12kv - Gnd 14amps
• Cougar 12kv - Gnd 4.4amps
• Jaguar 12kv - Gnd 10.7amps
Possible Causes
2. Load Factor
Monthly load factor was calculated for all phases of each circuit. The highest
load factor from the three phases was then used as that respective circuit’s
load factor during simulations.
January July
• Issue
Transition
Duct Bank
Possible Causes
5. Over Crowding of Duct Banks
• In the transition design, 6 circuits were together in one duct bank.
– High temperature of 195.4C
– Issue 2: Over Crowding of Duct Banks
Solution 1: Soil Mitigation with Slurry Backfill
Trees Removed
New
Vault
Solution 2: Re-Routing of Duct Bank
• New duct banks were routed towards the outside, furthest away
from the trees and other duct banks.
Validation of Solutions
DTS
MEER
FIBER WELL
No. 1
CAP BK
12kV SWITCHRACK
No. 2
CAP BK
FIBER
SPLICE
SUBSTATION
FENCE
Benefits of Distributed Temperature
Sensor (DTS) System
• Thermal Study are an estimate of the thermal characteristics of the
cable, ductbank, ambient temperature, soil conditions and loading.
• Soil thermal properties cannot be known throughout a duct bank run,
without taking multiple measurements throughout the run.
• No other method of determining the actual cable temperature in the
middle of the duct bank.
• Knowing the temperature of the cable:
– Make better, more accurate decisions in real time.
– Extend the life of cable by monitoring the cables
temperature.
– Possible increase of current capacity, by loading the cable
up to the actual loading limits, rather than an estimate.
Duct Bank Performance Monitoring (DTS)
• The DTS system was implemented to monitor cable temperatures inside
the duct banks.
• Utilizes a fiber optic cable to monitor temperatures along the entire length
of the duct bank.
DTS and Computer Rack
Measured
Calculated
DTS Temperature was as expected. (63 deg. C measured & 65 deg.C calculated.)
Improved duct bank design, slurry back fill & tree removal prevent duct bank
overheating (Conductor Temperature ~ 68.8*C during heat wave at 103 deg. F)
24
Wrap – Up - Conclusion
• Predominant causal factors in the Lampson overheated duct bank
condition are the high soil thermal resistivity and the overcrowding
of the duct banks.
• The corrective actions implemented have mitigated both causal
factors:
– Splitting the circuits into two paths (4 circuits and 3 circuits) and cable
placement in the duct arrangement to address the circuit density.
– Adding slurry to address the soil thermal resistivity issue.
• The DTS system has proven that the integrated solution of splitting
the duct bank and adding slurry backfill prevented overheating
during the October heat wave.
Wrap Up – Lessons Learned / Challenges
• Installing the fiber cable in the same duct as power cables.
– Damage may occur during installation.
– Small clearances in duct.
– Communication fiber cable requirements / standards are higher
than needed for monitoring cable temperature.
– Paying more attention to the contractors, they work fast and may
not have the same goals as you do.
– Cost was small to add fiber cable to an existing power cable pull.
• Fiber splicing
– Coordinating non electrical crews.
• Fiber cables are normal treated as separate installations
• Setting up computer for DTS
– Cost is of the project is in the DTS unit.
Wrap Up – Future Needs
• Possible installation of fiber cable in highly
loaded circuit sections (ie. Substation
getaways, highly loaded customers, etc.)
• Installing fiber cable at the same time as
power cable is reasonably low cost.
References
• CYMCAP 6.2, rev2 – Duct Bank Modeling Software
• IEEE 442- Guide for Soil Thermal Resistivity Measurements
• SENSA-Distributed Temperature Sensor
• SCE Circuit Loading Data
• Thermal Images Provided by SCE Troubleman – Santa Ana,CA
• AEIC CG6-2005, Section 6.1 Guide for Establishing The Maximum Operating
Temperatures of Extruded Dielectric Insulated Shielded Power Cables
• IEEE 835 IEEE Standard Power Cable Ampacity Tables
• ICEA P-53-426 (WC-50) Ampacities Including Effect of Shield Losses for Single
Conductor Solid Dielectric Power Cable 15 kV through 69 kV