We are pleased to submit our quotation for the extension of the building
height from 3 meters to 3.5 meters and other additional works.
below is the scope of work.
I. MASONRY WORKS
CHB 4" 497 pcs 17 8,449.00
Cement (40kg) 54 bags 225 12,150.00
Screened Sand 2 cu.m 1450 2,900.00
Gravel 3/4 1 cu.m 1700 1,700.00
Fine Sand 2 cu.m 2000 4,000.00
Tie Wire #16 1 roll 2000 2,000.00
Ø10mm RSB X 6m 36 pcs 125 4,500.00
Material Cost 35,699.00
Labor Cost 14,279.60
I. Total Cost 49,978.60
II. PAINTING WORKS
Skim Coat 3 bags 450 1,350.00
Latex Paint Primer 1 pcs 1950 1,950.00
Gloss Latex Paint 1 pcs 2275 2,275.00
Sand Paper #120 50 pcs 15 750.00
Material Cost 6,325.00
Labor Cost 3,162.50
II. Total Cost 9,487.50
III. SLIDING DOOR AT MASTER BEDROOM
Sliding Door Glass 2.1 m x 2.4m 1 pc 15,000 15,000.00
Material Cost 15,000.00
Labor Cost 6,000.00
IV. Total Cost 21,000.00