PROJECT: KALIKASAN HOMES ONE STOREY BUILDING WITH ROOFDECK

LOCATION: KALIKASAN HOMES


OWNER: SIR. AARON JANG

We are pleased to submit our quotation for the extension of the building
height from 3 meters to 3.5 meters and other additional works.
below is the scope of work.

DESCRIPTION QTY UNIT UNIT COST TOTAL COST


EXTENSION OF HEIGHT OF THE BUILDING FROM 3 METERS TO 3.5 METERS

I. MASONRY WORKS
CHB 4" 497 pcs 17 8,449.00
Cement (40kg) 54 bags 225 12,150.00
Screened Sand 2 cu.m 1450 2,900.00
Gravel 3/4 1 cu.m 1700 1,700.00
Fine Sand 2 cu.m 2000 4,000.00
Tie Wire #16 1 roll 2000 2,000.00
Ø10mm RSB X 6m 36 pcs 125 4,500.00
Material Cost 35,699.00
Labor Cost 14,279.60
I. Total Cost 49,978.60
II. PAINTING WORKS
Skim Coat 3 bags 450 1,350.00
Latex Paint Primer 1 pcs 1950 1,950.00
Gloss Latex Paint 1 pcs 2275 2,275.00
Sand Paper #120 50 pcs 15 750.00
Material Cost 6,325.00
Labor Cost 3,162.50
II. Total Cost 9,487.50
III. SLIDING DOOR AT MASTER BEDROOM
Sliding Door Glass 2.1 m x 2.4m 1 pc 15,000 15,000.00
Material Cost 15,000.00
Labor Cost 6,000.00
IV. Total Cost 21,000.00

TOTAL COST FOR EXTENSION ------------- 59,466.10


COST FOR SLIDING DOOR ------------- 21,000.00
Total Cost 80,466.10
Discounted Total Cost 70,000.00
FOR CANTILEVER AT ROOFDECK

DESCRIPTION QTY UNIT UNIT COST TOTAL COST


I. MASONRY WORKS
Cement (40kg) 32 bags 225 7,200.00
Screened Sand 1 cu.m 1450 1,450.00
Gravel 3/4 2 cu.m 1700 3,400.00
Fine Sand 0.5 cu.m 2000 1,000.00
Tie Wire #16 2 roll 2000 4,000.00
Ø10mm RSB X 6m 128 pcs 125 16,000.00
Material Cost 33,050.00
Labor Cost 13,881.00
I. Total Cost 46,931.00
II. PAINTING WORKS
Skim Coat 2 bags 450 900.00
Latex Paint Primer 0.5 pcs 1950 975.00
Gloss Latex Paint 0.5 pcs 2275 1,137.50
Sand Paper #120 20 pcs 15 300.00
Material Cost 3,312.50
Labor Cost 1,656.25
II. Total Cost 4,968.75

III. FORM WORKS


2"x2"x10' Cocolumber 72 bags 83 5,976.00
2"x3"x10' Cocolumber 50 pcs 125 6,250.00
CN Nail #4 10 kls 65 650.00
Plywood 1/4 7 pcs 470 3,290.00
Material Cost 16,166.00
Labor Cost 8,083.00
III. Total Cost 24,249.00

TOTAL COST FOR CANTILEVER ------------- 76,148.75


Discounted Total Cost 70,000.00

ENGR. ORNEL ASPERAS SIR. AARON JANG


CONTRACTOR OWNER