FETUGA Abayomi Adebayo

Fetsb2000@yahoo.com, fetugaolamide@gmail.com
+2348026462629, +2349030125651
SYSTEMS COMPLETION/HANDOVER/PLANNING/CERTIFICATION/TURNOVER
CAREER SUMMARY
A versatile and experienced Systems Completion Lead with expert knowledge of Zenator Systems / GOC / ICAPS / WINPCS /
MCPLUS and its completion methodology process. With over 11 years of experience in the utilization of Zenator Systems /
GOC/ICAPS/WINPCS/MCPLUS/COCONSOLE application to solving completions problems in oil and gas design phases
including FEEDs, detailed design, construction, pre commissioning and commissioning using the database application to
track to completions each of the stage of EPC/EPCIC projects.
As a Systems Completion/turnover Lead, my role is providing technical coordination of the system turnover and acceptance
of the project from construction to commissioning and start-up interfacing with client, engineering, construction group and
contractors. My responsibilities are defining systems and boundary limit of system, developing and maintaining turnover
database, certification process, planning walk downs reviewing discipline packages and handover dossiers, punch list
management and categorization, generating reports and ensuring that the system is progressively transfer to
commissioning and start-up. Managing project preservation activities.

PROFILE KEY DATA


Last Name: FETUGA First Name: Adebayo

DOB: 02-07-1985 Gender: MALE


(dd-mm-yyyy) (M/F)

Nationality : NIGERIAN Point of Origin: LAGOS, NIGERIA


(Permanent Residence)

RELOCATION YES Availability: IMMEDIATELY / ASAP

Languages: ENGLISH... Computer Skills: MS OFFICE,ICAPS,ZENATOR,GOCOMPLETIONS,


FRENCH - BEGINNER... PRIMAVERA,MS
PROJECTS,CMMS,MCPLUS,WINPCS,AUTOCAD
Years of Experience with Oil & 11 YEARS Years of Experience with 10 YEARS
Gas E&P Operator

Years of Experience with Oil & 11 YEARS Overall Years of 10 YEARS


Gas EPC Contractor: Experience:

ACADEMIC QUALIFICATIONS (Post Secondary Education only, starting from the highest qualification to the lowest)
Graduation Date Graduating Institution Qualification
UNIVERSITY OF BENIN B.ENG MECHANICAL ENGINEERING

2007 FEDERAL POLYTECHNIC OFFA HND COMPUTER ENGINERRING

2004 FEDERAL POLYTECHNIC OFFA NATIONAL DIPLOMA IN COMPUTER ENGINEERING

COMPETENCY

Page 1 of 8
FETUGA Abayomi Adebayo
Fetsb2000@yahoo.com, fetugaolamide@gmail.com
+2348026462629, +2349030125651
SYSTEMS COMPLETION/HANDOVER/PLANNING/CERTIFICATION/TURNOVER
 Completions and Handover of both Greenfield and Brownfield facilities
 Mechanical Completions/Pre commissioning/commissioning/ Fabrication
 Turnaround maintenance planning / CMMS / Preservations
 Systems completions / Punch list categorization and management/CERTIFICATION
 Onshore/LNG/GTL/Offshore/Planning/Commissioning/Turnover/Start up,Project
Management/Certification/Handover/Punchlist management

SKILL / TOOLS
 Microsoft office application/Documentum/Prodom/EDMS/IDOCS
 GOC,ZENATOR,WINPCS,ICAPS,MCPLUS/coconsole
 2D AutoCAD
 CMMS/SAP/JDE/MARIAN
 Primevera/MS Projects / SAP Project Systems

TRAINING
 Facilities Engineering Maintenance and Operations Training
 Project Management Training
 Planning, Scheduling and Cost estimating Training - Chevron
 Zenator Training – Chevron
 ICAPS - SPIE
 OMEGA PIMS / FLOUR MCPLUS
 GOC – QEDI / SHELL NIGERIA
 COCONSOLE – CBI OMAN
 BOSIET

WORK EXPERIENCE
Dates: OCTOBER 2017 – MAY 2019 Project ORPIC LIWA PROJECTS - STEAM
CRACKER UNIT / UTILITIES
Company: CBI / CTCI JV / ORPIC Business Activity EPCIC –

Status: CONTRACTED Job Location (city/country): SOHAR/ OMAN


(Staff or Contracted)

Job Title: SYSTEMS COMPLETION LEAD – CO CONSOLE/MCPLUS PuOWER USER- LEAD

Reporting to: COMMISSIONING MANAGER / COMPLETIONS MANAGER


Tasks & Achievements: ONSHORE – STEAM CRACKER UNIT AND OTHER UTILITIES
 Responsible to coordinate all activities oriented to the final turnover of the
project in accordance with project schedule and milestones from the mechanical
completion until the full operability of the plant Interfacing with discipline leads,
QA/QC Manager and commissioning leads as regards system completions.
 Following up and expediting the progress of the COCONSOLE database
preparation and population for pre-commissioning/commissioning activities
including task-sheets forms, matrix of task-sheets, status index, punch-list forms,
relevant engineering documents (PID with mark-up, in-tools database, list of
tags, basic functions, loop dossiers, etc.)
 Producing daily reports and status to monitor the progress (tasks, man-hours,
punch, subsystems completed or ready to sign) of preparation and execution of
pre-commissioning and commissioning.
 Ensuring that all safety and precautionary requirements and procedures are
followed during the completion and handover process in line with the
commissioning schedule.
 Holding regular review meetings with the Completion Team, subcontractors, and

Page 2 of 8
FETUGA Abayomi Adebayo
Fetsb2000@yahoo.com, fetugaolamide@gmail.com
+2348026462629, +2349030125651
SYSTEMS COMPLETION/HANDOVER/PLANNING/CERTIFICATION/TURNOVER
other contractors on issues such as HSE conformance and completion and
handover progress as well as meetings with the vendors to resolve any
equipment related problems
 Responsible for core procedures preparation such as System Completion & Work
Package Completion and Turnover Procedure, and Punch listing Procedure
 Coordinate and lead walk down inspections at site to guide client personnel
(PMT, Manufacturing, Operations) in order to identify and record any deficiencies
found.
 Ensuring that system completion methodology and CO CONSOLE database
software are well understood and applied by all the people involved in the
Project, Contractors and Company personnel
 Preservation Activities control and tracking

Dates: MARCH 2016 – AUG 2017 Project SHELL PETROLEUM NIGERIA

Company: SAIPEM / NESTOIL Business Activity: EPCIC

Status: CONTRACT Job Location (city/country): BAYELSA / RIVERS STATE


(Staff or Contracted)

Job Title: COMPLETIONS AND HANDOVER LEAD– GOCOMPLETIONS LEAD

Reporting to: COMPLETIONS MANAGER / PROJECT MANAGER


Tasks & Achievements: ONSHORE / BROWNFIELD / PIPELINE
 Responsible to coordinate all activities oriented to the final turnover of the
project in accordance with project schedule and milestones from the mechanical
completion until the full operability of the plant Interfacing with discipline leads,
QA/QC Manager and commissioning leads as regards system completions.
 Following up and expediting the progress of the go completions database
preparation and population for pre-commissioning/commissioning activities
including task-sheets forms, matrix of task-sheets, status index, punch-list forms,
relevant engineering documents (PID with mark-up, in-tools database, list of
tags, basic functions, loop dossiers, etc.)
 Producing daily reports and status to monitor the progress (tasks, man-hours,
punch, subsystems completed or ready to sign) of preparation and execution of
pre-commissioning and commissioning.
 Ensuring that all safety and precautionary requirements and procedures are
followed during the completion and handover process in line with the
commissioning schedule.
 Holding regular review meetings with the Completion Team, subcontractors, and
other contractors on issues such as HSE conformance and completion and
handover progress as well as meetings with the vendors to resolve any
equipment related problems
 Responsible for core procedures preparation such as System Completion & Work
Package Completion and Turnover Procedure, and Punch listing Procedure
 Coordinate and lead walk down inspections at site to guide client personnel
(PMT, Manufacturing, Operations) in order to identify and record any deficiencies
found.
 Ensuring that system completion methodology and go completions database
software are well understood and applied by all the people involved in the
Project, Contractors and Company personnel

Dates: OCT 2015 – MARCH 2016 Project CHEVRON SONAM FIELD


DEVELOPMENT PROJECT

Page 3 of 8
FETUGA Abayomi Adebayo
Fetsb2000@yahoo.com, fetugaolamide@gmail.com
+2348026462629, +2349030125651
SYSTEMS COMPLETION/HANDOVER/PLANNING/CERTIFICATION/TURNOVER
Company: CHEVRON Business Activity: EPCIC

Status: CONTRACTED Job Location (city/country): DELTA / NIGERIA


(Staff or Contracted)

Job Title: SYSTEMS COMPLETIONS LEAD / SCDB LEAD - MCPLUS

Reporting to: COMMISSIONING MANAGER


Tasks & Achievements: OFFSHORE
 Following up and expediting the progress of the completions database
preparation and population for pre-commissioning/commissioning activities
including task-sheets forms, matrix of task-sheets, status index, punch-list forms,
relevant engineering documents (PID with mark-up, in-tools database, list of
tags, basic functions, loop dossiers, etc.)
 Responsible for Project System Completion for all discipline (Civil, Structural,
Arch, Electrical. Instrumentation, HVAC, Piping, fire protection and Mechanical)
 Producing daily reports and status to monitor the progress (tasks, man-hours,
punch, subsystems completed or ready to sign) of preparation and execution of
pre-commissioning and commissioning.
 Ensuring that all safety and precautionary requirements and procedures are
followed during the completion and handover process in line with the
commissioning schedule.
 Holding regular review meetings with the Completion Team, subcontractors, and
other contractors on issues such as HSE conformance and completion and
handover progress as well as meetings with the vendors to resolve any
equipment related problems
 Ensured that tests related to Pre-commissioning, Commissioning, Start-up, and
Performance Testing activities are witnessed and the required documents signed
by appropriate EPC, Company, Regulatory Inspectors and Equipment Suppliers /
Process Licensor representatives in accordance with the requirements of the
Handover Plan
 Ensuring all punch lists from Factory Acceptance Tests (FAT's) are cleared before
Ready For Commissioning (RFC) walk down
 Providing adequate reporting as per project requirements and customized SCD
data as and when required/requested: Commissioning and Punch List activities
either on System /Sub-System basis or on the Task basis such as Loop checks,
Functional tests, Item, Packs, Process Functions, Punch lists
 Verifying the correct completion of all punch items with construction,
subcontractors, vendor, licensor quality and commissioning groups

Dates: OCT 2014 – OCT 2015 Project MEREN GGCP PROJECT

Company: CHEVRON NIGERIA LIMITED Business Activity: EPCIC

Status: CONTRACTED Job Location (city/country): KOREA / NIGERIA


(Staff or Contracted)

Job Title: SYSTEMS COMPLETION LEAD – ZENATOR LEAD

Page 4 of 8
FETUGA Abayomi Adebayo
Fetsb2000@yahoo.com, fetugaolamide@gmail.com
+2348026462629, +2349030125651
SYSTEMS COMPLETION/HANDOVER/PLANNING/CERTIFICATION/TURNOVER
Reporting to: COMMISSIONING MANAGER
Tasks & Achievements: KOREA YARD / OFFSHORE NIGERIA
 Assisting and supporting the Commissioning Leader in his daily activities;
 Operating and maintaining the project SC database in compliance with the
project requirements.
 Review of Engineering deliverables and launching into project SC database
 Defining adequate reporting to follow up and control status and progress of Pre-
commissioning and Commissioning preparation activities related to SC database.
PRE COMMISSIONING AND COMMISSIONING EXECUTION PHASE (AT YARD AND
OFFSHORE):
 Management of multidiscipline staff and contractors for commissioning
preparation
 Ensures that the EPCC Contractor instruct and obtain the various Vendors to
prepare and use correctly the forms and database for future compilation into the
SCD master database, including punch-list.
 Producing daily reports and status to monitor the progress (tasks, man-hours,
punch, subsystems completed or ready to sign) of preparation and execution of
pre-commissioning and commissioning.
 Identifying any activities to be done in order to reach RFC and RFSU stage as per
the priorities defined within the planning (Skyline tools).
 Ensuring that pre-commissioning and commissioning activities, including punch-
list are recorded in the database within 24 hours. Spot checks that closed punch
items are actually validated by Company authorized persons
 Ensuring that SC database, as prepared and managed by Contractor, is well
parameterised and populated for pre commissioning/commissioning activities.
 Providing adequate reporting as per project requirements and customized MC
data as and when required/requested: Commissioning and Punch List activities
either on System /Sub-System basis or on the Task basis such as Loop checks,
Functional tests, Item, Packs, Process Functions, Punch lists
 Ensured that each subsystem dossier has reached the “Ready for
Commissioning” status with associated punch list
 Ensured that each subsystem dossier has reached the “Achievement of
Commissioning” status with associated punch list
 Monitoring and follow up the execution of commissioning schedule as per
Project objective and in order to achieve a smooth hand over to Operator
 Ensuring that system completion methodology and MC database software are
well understood and applied by all the people involved in the Project,
Contractors and Company personnel

Page 5 of 8
FETUGA Abayomi Adebayo
Fetsb2000@yahoo.com, fetugaolamide@gmail.com
+2348026462629, +2349030125651
SYSTEMS COMPLETION/HANDOVER/PLANNING/CERTIFICATION/TURNOVER
Dates: JULY 2011 – OCTOBER 2014 Project CHEVRON ESCRAVOS GAS TO
LIQUIDS PROJECT
Company: CHEVRON NIGERIA LIMITED Business Activity: COMMISSIONING

Status: CONTRACTED Job Location (city/country): DELTA / NIGERIA


(Staff or Contracted)

Job Title: SYSTEMS COMPLETION COORDINATOR – ZENATOR POWER USER

Reporting to: COMMISSIONING MANAGER


Tasks & Achievements: GREENFIELD / ONSHORE
 Interfacing with discipline leads, QA/QC Manager and commissioning leads as
regards system completions.
 Operating and maintaining the project system completions database in
compliance with the project requirements.
 Review of Engineering deliverables and launching into project system
completions database
 Management of multidiscipline staff and contractors for commissioning
preparation
 Compiling and imputing engineering data by System and Subsystem itemize basic
functions, equipment checks, etc.
 Preparation and packaging of all handover deliverables like Commissioning
procedures, RFSU and RFO documents
 Planning of walk downs at various stages of the project.

 Punch list management, categorization, tracking and close out.

 Ensuring any punch items identified during the construction completion


Inspection and Test reports (ITRS) are included in the master punch list

 Carried out the system completions planning process with planning tool.

 Making available the current status of the punch list dataset as required to
complete works to the parties involved in punch list clearance work

 Ensuring the categorization of punch items into completion priority is maintained

 Ensuring regular reports (daily as a minimum) on the status of punch item


closeout

 Coordinates and making sure all specific punch lists associated with the delivered
materials are being tracked, cross referenced and cleared

Page 6 of 8
FETUGA Abayomi Adebayo
Fetsb2000@yahoo.com, fetugaolamide@gmail.com
+2348026462629, +2349030125651
SYSTEMS COMPLETION/HANDOVER/PLANNING/CERTIFICATION/TURNOVER
 Actively involved in construction, pre-commissioning & commissioning activities
identified for specific systems and sub systems in the work packages to achieve
RFC & RFSU, line walking of systems with Supervisors for punch entry / closure.

Dates: JULY 2010 – JULY 2011 Project CHEVRON DIBI LONG TERM
PROJECT
Company: CHEVRON NIGERIA LIMITED Business Activity: CONSTRUCTION
/COMMISSIONING
Status: CONTRACTED Job Location (city/country): DELTA / NIGERIA
(Staff or Contracted)

Job Title: MECHANICAL COMPLETION ENGINEER – ZENATOR ADMINISTRATOR

Reporting to: COMMISSIONING MANAGER


Tasks & Achievements: GREENFIELD / OFFSHORE
 Monitoring of PMC completion (inspection test record) and Follow up for closure
of PMC related and commissioning punch item by coordinating with client.
 Monitoring of Construction Quality record (Inspection Test record) and PMC
Quality Record for system completion.
 Monitoring of Punch item category and coordinating & follow up with discipline
for the punch closing and inform company for verification
 Compiling of System Definition Drawing, System Component List, Punch List, and
Document required for operation, HAZOP Action & Inspection test record for
system Mechanical Completion package.
 Responsible for core procedures preparation such as System Completion & Work
Package Completion and Turnover Procedure, and Punch listing Procedure
 Coordinating the achievement of the plant piping test circuits completion as
defined in the project plans and schedules by commissioning team
 Coordinating with Eng/QC/Construction/Hydro test group and Client for Material
& Manpower Schedule prior for testing
 Managing test pack documentation flow from Contractor to client for review and
approval and back to Contractor for execution
 Following up test pack documentation flow from multiple internal parties for
review and ensures timely review and return to Contractor
 Monitoring Status and controlling of all official document System Mechanical
Completion Package Transmitting to client

Dates: APRIL 2008 – JUNE 2010 Project CHEVRON ONSHORE / OFFSHORE


ASSET GAS MANAGEMENT
PROJECT
Company: CHEVRON NIGERIA Business Activity: EPCIC

Page 7 of 8
FETUGA Abayomi Adebayo
Fetsb2000@yahoo.com, fetugaolamide@gmail.com
+2348026462629, +2349030125651
SYSTEMS COMPLETION/HANDOVER/PLANNING/CERTIFICATION/TURNOVER
Status: CONTRACTED Job Location (city/country): DELTA / NIGERIA
(Staff or Contracted)

Job Title: HANDOVER / PUNCHLIST COORDINATOR – WINPCS POWER USER

Reporting to: COMMISSIONING MANAGER


Tasks & Achievements: ONSHORE / OFFSHORE
 Monitoring completions with regards to the completion status and organize joint
party punch listing between construction and commissioning
 Responsible for the compilation and indexing of Work Dossiers which shall
provide a complete record of the
 Work and Facilities including, Procurement, Construction, Certification,
Installation, Mechanical Completion and Hand-over.
 Ensuring that all required Engineering, Vendor, Operations Related,
Safety/Environmental, Fabrication / Construction, Mechanical Completion, As-
Built, Project, Supplier, Warranties & Guarantees’, Maintenance and Regulatory
Approval Documents and Certification are identified and suitably endorsed as
per Contract where required for final Hand Over
 Scheduling and coordinating turnover walk-downs.
 Supervises and provides technical direction to subordinate engineers and
assigned personnel
 Receiving operational surveillance, administrative supervision and technical
guidance from the Handover Manager
 Reviewing as-built documentation and red-line change records
 Reviewing registers of certified test equipment, authorized signatures and
engineering queries
 Informing Project Management Team of multi-discipline percentage completions
for mechanical completion, pre-commissioning and commissioning
 Reviewing and acceptance of vendor documentation to enable population of
completions database
Co-ordinate punch-out of systems post commissioning and prior to handover to
Operations. Manage and distribute details of punch items to facilitate close out

Page 8 of 8