Lab 8 - Part A

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 3

BUS1500 – Business Information Systems – Winter 2019

Lab Assignment EIGHT – Answer Key


Project Management - III

1 – The current critical path is shown in RED. How long is it?

30 Days

2 - If task AD took 12 days instead of 6 would it affect the critical path? If so, how?
If the change results in a new critical path, please describe the new critical path.

It creates a new Critical Path of 31 days consisting of activities S-A, A-D, D-I and I-F.

3 - If task DG took 8 days instead of 2 would that change the critical path? If so,
please describe the new critical path.

No.

4 – How late could task FI be before it affected the overall delivery date of the
project?

13 days BEFORE it affected the overall delivery. After 14 days it WOULD affect
the delivery date of the project.
5 – How many days will it take to complete the project?

14 Days.

6 - What activities are on the critical path?

A, B, D, F, and I.

7 - If activity G was completed one day early, would the overall project be
completed any faster?

No.

8 - If activity F was delayed by two days what effect would that have on the
overall project completion date?

The project completion date would also be delayed by two days.

9 – Using a piece of scrap paper, please draw a network diagram, using the
second of the above formats, based on the following work-breakdown
structure (WBS).

Activity What? How Long? What has to be done first?


ID (Task) (Duration in days) (Predecessors)
1 Start 0
2 A 5 Activity 1
3 B 7 Activity 1
4 C 4 Activity 2
5 D 8 Activity 2
6 E 3 Activity 4
7 F 4 Activity 5
8 G 2 Activities 6,7
9 H 4 Activity 3
10 I 5 Activity 8
11 J 6 Activity 9
12 K 4 Activities 10, 11
13 End 0 Activity 12

After studying this diagram …

10 – How long will it take to complete the project?

11 – What activities are on the critical path?

12 – If activity 11 was done three days early, what impact would it have on the
critical path?

See attached file

You might also like