Lab 8 - Part A
Lab 8 - Part A
Lab 8 - Part A
30 Days
2 - If task AD took 12 days instead of 6 would it affect the critical path? If so, how?
If the change results in a new critical path, please describe the new critical path.
It creates a new Critical Path of 31 days consisting of activities S-A, A-D, D-I and I-F.
3 - If task DG took 8 days instead of 2 would that change the critical path? If so,
please describe the new critical path.
No.
4 – How late could task FI be before it affected the overall delivery date of the
project?
13 days BEFORE it affected the overall delivery. After 14 days it WOULD affect
the delivery date of the project.
5 – How many days will it take to complete the project?
14 Days.
A, B, D, F, and I.
7 - If activity G was completed one day early, would the overall project be
completed any faster?
No.
8 - If activity F was delayed by two days what effect would that have on the
overall project completion date?
9 – Using a piece of scrap paper, please draw a network diagram, using the
second of the above formats, based on the following work-breakdown
structure (WBS).
12 – If activity 11 was done three days early, what impact would it have on the
critical path?