SHREE BALAJI TEST HOUSE PVT. LTD.

DAILY PROGRESS REPORT OF GORAKHPUR LINK EXPRESSWAY PROJECT

Date of Reporting : 20.01.2020

Day Wise Total


Chainage Total BH
Date Machine No. Structure BH No. Running Running Northing Estaing
No. Depth
Depth Depth

20.11.2019 1 MNB 6+235 8 - - 40 mtr. 2951030.2648 727239.2248

21.11.2019 1 MNB 6+235 7 - - 20 mtr. 2950922.2131 727120.5563

24.11.2019 2 MNB 6+235 4 - - 40 mtr. 2951058.2361 727191.4909

24.11.2019 1 MNB 6+235 3 - - 40 mtr. 2951055.9425 727220.446

25.11.2019 2 MNB 6+235 1 - - 20 mtr. 2951159.8910 727280.402

25.11.2019 1 MNB 6+235 2 - - 20 mtr. 2951120.8250 727230.1464

27.11.2019 2 MNB 6+235 10 - - 40 mtr. 2950991.6142 727212.7423

27.11.2019 1 MNB 6+235 5 - - 40 mtr. 2951016.9442 727194.2178

29-11-19 1 MNB 6+235 9 - - 40 mtr. 2951010.8164 727226.1702

29-11-19 2 MNB 6+235 6 - - 20 mtr. 2950998.1684 727149.0372

1.12.2019 2 MNB 2+058 2 - - 20 mtr. 2955121.2342 728132.7995

1.12.2019 1 MNB 2+058 3 - - 40 mtr. 2955067.654 728161.0777

30.11.2019 1 MNB 2+058 1 - - 20 mtr. 2955187.4969 728154.9384

2.12.2019 2 MNB 2+058 5 - - 36 mtr. 2955038.6704 728162.5624

2.12.2019 1 MNB 2+058 8 - - 40 mtr. 2955063.4008 728191.0845


3.12.2019 1 MNB 2+058 6 - - 20 mtr. 2954988.7359 728165.1204

3.12.2019 2 MNB 2+058 10 - - 40 mtr. 2955034.4388 728192.5682

8.12.2019 1 MNB 2+058 7 _ _ 20 mtr. 2954922.4929 728142.9444

5.12.2019 2 MNB 2+058 13 _ _ 40 mtr. 2955046.5909 728106.8342

Prepared by Checked by Approved by

SHREE BALAJI TEST HOUSE PVT. LTD.


DAILY PROGRESS REPORT OF GORAKHPUR LINK EXPRESSWAY PROJECT

Date of Reporting : 20.01.2020

Day Wise Total


Chainage Total BH
Date Machine No. Structure BH No. Running Running Northing Estaing
No. Depth
Depth Depth

8.12.2019 1 FLYOVER 0 4 _ _ 20 mtr. 2957109.649 728030.938


8.12.2019 2 FLYOVER 30 5 _ _ 20 mtr. 2957080.992 728057.94
8.12.2019 1 FLYOVER 150 7 _ _ 20 mtr. 2956961.150 728064.079
9.12.2019 2 FLYOVER 80 6 _ _ 40 mtr. 2957029.753 728035.031
10.12.2019 1 MNB 17+477 2 _ _ 20 mtr. 2951120.8250 727230.1464
10.12.2019 2 MNB 17+477 3 _ _ 40 mtr. 2951055.9425 727220.4460
11.12.2019 1 MNB 17+477 1 _ _ 20 mtr. 2951159.8910 727280.4020
11.12.2019 2 MNB 17+477 4 _ _ 40 mtr. 2951058.2361 727191.4909
13.12.2019 1 MNB 17+477 5 _ _ 20 mtr. 2951016.9442 727194.2178
13.12.2019 2 MNB 17+477 6 _ _ 20 mtr. 2950998.1684 727149.0372
16.12.2019 1 MNB 17+477 7 _ _ 40 mtr. 2942502.4502 720363.5154
16.12.2019 2 MNB 17+477 8 _ _ 40 mtr. 2942477.7070 720358.6740
16.12.2019 1 FLYOVER 27+680 6 _ _ 20 mtr. 2932896.941 719715.5380
17.12.2019 2 LVUP 17+290 2 _ _ 20 mtr. 2942719.1556 720455.2215
17.12.2019 1 FLYOVER 27+630 5 _ _ 40 mtr. 2932920.352 719766.550
18.12.2019 2 LVUP 17+290 1 _ _ 20 mtr. 2942664.7108 720442.1155
18.12.2019 1 LVUP 17+290 3 _ _ 20 mtr. 2942610.1225 720429.6209
18.12.2019 _ FLYOVER 27+450 1 _ _ 20 mtr. 2933061.560 719878.176
19.12.2019 1 VUP 10+210 1 _ _ 20 mtr. 2947987.0562 724701.7304
19.12.2019 2 VUP 10+210 2 _ _ 20 mtr. 2948039.5735 724734.6839

Prepared by Checked by Approved by

SHREE BALAJI TEST HOUSE PVT. LTD.


DAILY PROGRESS REPORT OF GORAKHPUR LINK EXPRESSWAY PROJECT

Date of Reporting : 20.01.2020

Day Wise Total


Chainage Total BH
Date Machine No. Structure BH No. Running Running Northing Estaing
No. Depth
Depth Depth

19.12.2019 3 FLYOVER 27+570 3 _ _ 40 mtr. 2932967.421 719803.758


20.12.2019 1 VUP 10+210 3 _ _ 20 mtr. 2947934.5390 724668.7769
20.12.2019 2 VUP 9+218 3 _ _ 20 mtr. 2948774.7306 725207.2967
20.12.2019 3 FLYOVER 27+520 2 _ _ 20 mtr. 2933022.459 719814.761
20.12.2019 4 FLYOVER 27+600 4 _ _ 40 mtr. 2932959.700 719765.150
21.12.2019 1 VUP 9+218 1 _ _ 20 mtr. 2948821.5295 725238.0516
21.12.2019 2 VUP 9+218 2 _ _ 20 mtr. 2948868.3284 725268.8065
21.12.2019 3 FLYOVER 27+750 7 _ _ 20 mtr. 2932826.214 719692.132
23.12.2019 1 LVUP 8+792 2 _ _ 20 mtr. 2949224.3343 725502.7634
23.12.2019 2 LVUP 8+792 3 _ _ 20 mtr. 2949130.7365 725441.2536
23.12.2019 3 PUP 4+045 A1 _ _ 20 mtr. 2953185.6436 727589.5628
23.12.2019 4 PUP 2+753 A1 _ _ 20 mtr. 2954372.9947 728062.8200
24.12.2019 1 LVUP 8+792 1 _ _ 20 mtr. 2949177.5354 725472.0085
24.12.2019 2 LVUP 1+650 2 _ _ 20 mtr. 2955518.3882 728125.2211
24.12.2019 3 LVUP 1+650 3 _ _ 20 mtr. 2955406.5349 728130.9510
25.12.2019 1 PUP 8+245 A1 _ _ 20 mtr. 2949632.6725 725775.3050
26.12.2019 1 FLYOVER -150 1 _ _ 20 mtr. 2957260.757 728048.731
27.12.2019 2 PUP 0+500 A1 _ _ 20 mtr. 2956610.9556 728069.2518

Prepared by Checked by Approved by

SHREE BALAJI TEST HOUSE PVT. LTD.


DAILY PROGRESS REPORT OF GORAKHPUR LINK EXPRESSWAY PROJECT

Date of Reporting : 20.01.2020

Day Wise Total


Chainage Total BH
Date Machine No. Structure BH No. Running Running Northing Estaing
No. Depth
Depth Depth

28.12.2019 3 FLYOVER -80 2 _ _ 40 mtr. 2957189.544 728026.846


10.01.2020 1 VUP 22+715 3 _ _ 20 mtr. 2937251.1871 720399.1066
12.01.2020 2 VUP 22+715 1 _ _ 20 mtr. 2937307.2014 720372.5286
13.01.2020 1 VUP 22+715 2 _ _ 20 mtr. 2937364.0139 720347.7024
14.01.2020 2 PUP 24+010 2 _ _ 20 mtr. 720984.9680 2936227.5961
15.01.2020 1 PUP 24+010 1 _ _ 20 mtr. 721008.9109 2936179.7527
16.01.2020 1 LVUP 24+625 1 _ _ 20 mtr. 721121.0552 2935581.8880

17.01.2020 _ _ _ _ _ _ _ _ _

18.01.2020 1 LVUP 24+625 2 _ _ 20 mtr. 721123.7122 2935637.8249

19.01.2020 2 LVUP 24+625 3 _ _ 20 mtr. 721115.7881 2935526.1363

Note: 1. Total Sixty Six (66 nos.) Bore Holes are completed.
2. Site work is being stopped by the farmer ( water lodged ) and due to land issue problem from date 28.12.2019 to 8.01.2020

Prepared by Checked by Approved by


Remarks

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed
Completed

Completed

Completed

Completed

Remarks

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed
Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Remarks

Completed
Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Completed
Remarks

Completed

Completed

Completed

Completed

Completed

Completed

Completed
Work not done due to
heavy rain

Completed

Completed