Professional Documents
Culture Documents
2015-07-09 - Item 5.8 - Attach 4
2015-07-09 - Item 5.8 - Attach 4
2015-07-09 - Item 5.8 - Attach 4
A detailed condition assessment was undertaken for both walls, as presented in Aurecon’s report
“Condition Assessment Report – Tully Heads Seawall”, recommending a series of short term and long
term considerations for management of the assets.
This report is aimed at presenting long term remediation options to address the issues identified in the
aforementioned Condition Assessment report.
Seawall 1
Various options exist to protect coastal foreshores. The selection of the most appropriate option
depends on the site and environmental conditions. Five options are proposed for the protection of
Tully Heads Foreshore. Indicative costs (exclusive of GST) associated with the construction of those
options are also estimated.
Seawall 2
Seawall 2 is believed to be mostly buried under the existing beach. The rocks that can be seen are
assumed to be the crest rocks. It is assumed that the rest of the seawall structure is complete under
the existing beach. Reconstructing Seawall 2 will imply large excavation and is not considered as
critical works at this time. Regular monitoring inspections are recommended to remediate any scouring
issue or crest damage, especially after storm event.
Project 243333 File OptionAssessmentReport.docx 4 June 2015 Revision 1 Page III Page III
Appendices
Appendix A
Document register
Appendix B
Option Assessment Drawings
Appendix C
Approved Plans of Development – existing Seawall 1 and Seawall 2
Figures
Figure 2-1 Locality plan of the existing seawalls at Tully Heads 2
Figure 2-2 Project site land tenure 3
Figure 2-3 Bathymetry in the vicinity of Tully Heads (AUS 829 chart) 7
Figure 4-1 Example of geocontainer seawall 20
Figure 4-2 Example of concrete stepped seawall 21
Tables
Table 2-1 Summary of land tenure within the Project footprint 3
Table 2-2 Tully Heads Seawall chronology 4
Table 2-3 Tidal planes at Clump Point published by Maritime Safety Queensland (MSQ), 2014 6
Table 3-1 Key standards used in seawall design 9
Table 3-2 Risk of encountering various ARI events in 20 and 50 year period 10
Table 3-3 Wind speed conversion from m/s to km/h and knots 11
Table 3-4 Extreme wind recurrences at Tully Heads (10 m above sea level) 11
Table 3-5 Storm tide levels at Tully Heads (including wave set-up) from JCU 12
Table 3-6 Peak inundation levels at Tully / Hull Heads from the Cardwell Inundation Study project 12
Table 3-7 Design water levels 13
Table 3-8 Earthquake parameters for Tully Heads 14
Table 4-1 Indicative material quantity associated with Option1 - Variant A 17
Table 4-2 Indicative material quantity associated with Option 1 - Variant B 18
Table 4-3 Indicative material quantity associated with Option 1 - Variant C 19
Table 4-4 Indicative material quantity associated with Option 2 20
Table 4-5 Material quantity associated with Option 3 22
Table 4-6 Assumed material rates 23
Table 4-7 Proposed contingencies 23
Table 4-8 Indicative cost estimate for Option 1 – Variant A 24
Table 4-9 Indicative cost estimate for Option 1 – Variant B 24
Table 4-10 Indicative cost estimate for Option 1 – Variant C 24
Table 4-11 Indicative cost estimate for Option 2 25
Table 4-12 Indicative cost estimate for Option 3 25
Table 5-1 Multi-criteria analysis 29
1.1 Purpose
Aurecon has been commissioned by Cassowary Coast Regional Council (CCRC) to complete Stage 1
of a preliminary design required for the replacement, extension and modification of the existing
seawalls at Tully Heads and Hull Heads. Stage 1 includes the development of risk management
solutions to manage both Tully Heads and Hull Heads seawalls in their existing conditions. Moreover
Stage 1 incorporates the review of permits and approvals for both seawalls and the preparation of a
preliminary design for the Tully Heads Seawall.
Tully Heads Seawall is an erosion protection structure but is not a flood control structure. Aurecon has
issued a condition assessment report for both Hull Heads and Tully Heads Seawall including risk
management solutions and review of existing permits and approvals.
This option assessment report is part of the preliminary design phase relating to the Tully Heads
seawall. An Environmental Design Report (EDR) has been prepared concurrently for this site.
1.2 Methodology
In preparing this option assessment report for the Tully Heads seawall, it was necessary to:
Complete a desktop review of all existing information pertaining to the Tully Heads seawalls,
including previous designs, regulatory approvals, studies and investigations
The review and assessment undertaken, with respect to past works, design and investigations
completed to date in relation to the Tully Heads seawalls has been limited to those documents listed
in Appendix A which were provided to Aurecon by CCRC as part of this study.
In undertaking this assessment, Aurecon has made assumptions that the team could reasonably be
expected to make in accordance with sound professional practice.
2.4.3 Restoration of Tully Heads and South Mission Beach Seawalls - 2011
J T Smith and Associated Pty Ltd prepared a seawall restoration report detailing the nature and costs
of works required to reconstruct the seawalls along South Mission Beach and Tully Heads following
Tropical Cyclone Yasi. This report was compiled to assist CCRC to plan the reconstruction of the
seawalls.
Armour rock mass of approximately 3t on top of existing armour (from the private owners’
construction)
1v:2h slope
Crest level at 3.5 m AHD and toe at approximately 0.5 m below AHD.
It is noted that the seawall was reconstructed and reshaped following storm events, in particular
following TC Larry and TC Yasi.
2.5.2 Seawall 2
Tully Heads Seawall 2 was designed and approved in 2006 as a partially buried two layer rock
seawall, approximately 160 m in length, with the following attributes:
Table 2-3 Tidal planes at Clump Point published by Maritime Safety Queensland (MSQ), 2014
2.6.2 Bathymetry
Figure 2-3 indicates an approximate bathymetry in the vicinity of Tully Heads, sourced from the marine
chart AUS 829 – Brook Islands to Russell Island. Depths are referenced to Chart Datum,
approximately Indian Spring Low Water level (which is close to LAT).
It is understood that no bathymetric or topographic survey is available. Ground level data surveyed
during the existing seawall condition assessment at Tully Heads will be included in the concept
design.
Protect Carron Esplanade and adjacent residential properties from shoreline erosion;
Integrated Development Assessment System (IDAS) Code for Prescribed Tidal Work – Schedule
4A of the Coastal Protection and Management Regulation 2003
Relevant provisions of the Cardwell Shire Planning Scheme 2007 as called up by the Schedule 4A
code
Consideration of any proposed new provisions under the Draft Cassowary Coast Regional Council
Planning Scheme 2014
Regarding public access, there is no standard that provide requirements for pedestrian access
associated with a seawall construction. However the State Development Assessment Provisions
(SDAP) Code for Tidal Works makes reference to public access in Performance Outcome (PO) 10,
with the following conditions:
AO10.2 Development adjacent to state coastal land, including land under tidal water:
(1) is located and designed to:
(a) allow safe and unimpeded access to, over, under or around built structures located on, over
or along the foreshore
(b) ensure emergency vehicles can access the area near the development, or
(2) minimises and offsets any loss of access to and along the foreshore within two kilometres of the
existing access points, and the access is located and designed to be consistent with (1)(a) and
(b).
AS 1000 The International System of Units (SI) Units to be used on the Project.
and its application
AS 1170 (Parts 0 to 4) Minimum design loads on structures General loadings including wind load and
(SAA Loading Code – Australian earthquake loads
Standard)
Load combinations
AS 4997 Guidelines for the Design of Maritime General Design Requirements
Structures
Design Loads
Load combinations
Table 3-2 Risk of encountering various ARI events in 20 and 50 year period
Average Recurrence Interval (ARI) 50 year 100 year 500 year 1,000 year
Annual Exceedance Probability (AEP) 2% 1% 0.2% 0.1%
Probability of encounter over 20 years 33% 18% 4% 2%
Probability of encounter over 50 years 63% 39% 10% 5%
Table 3-3 Wind speed conversion from m/s to km/h and knots
Structural design wind conditions are given in from the AS/NZS 1170.2 standard. This wind code gives
3-second wind gust measured at 10 m above ground for all Australian regions. Tully Heads lies in
Cyclonic Region C. The Coastal Engineering Manual (CEM) Part II, Chapter 2, Figure II-2-1
relationship between a 3-second wind speed and an hourly averaged wind speed based on a large
sample of wind measurements 10 m above sea level was adopted to derive hourly winds. Table 3-4
presents the 3-second and hourly averaged wind speeds for a range of Average Recurrence Interval
(ARI) events for a Region C location.
Table 3-4 Extreme wind recurrences at Tully Heads (10 m above sea level)
Table 3-5 Storm tide levels at Tully Heads (including wave set-up) from JCU
In addition, BMT WBM carried out a coastal inundation investigation in 2007 during the Cardwell
Inundation Study project focusing on Tully and Hull Heads area. Table 3-6 provides peak inundation
levels for return period events greater than 100 year ARI assessed by BMT WBM.
Table 3-6 Peak inundation levels at Tully / Hull Heads from the Cardwell Inundation Study project
By extrapolation, a 50 year ARI peak inundation level is approximately 2.25 m AHD. It is understood
that no sea level rise or climate change effects were considered in the peak inundation levels given in
Table 3-6.
The Cardwell Inundation Study levels have been derived locally and seem slightly higher than the JCU
numbers. A storm tide level of 2.25 m AHD will be taken as the 50 year ARI design storm tide level for
the project.
4.1.1 Seawall 1
Seawall 1 is approximately 400m long and has been damaged during past severe storm events. It is
proposed to upgrade or replace Seawall 1. Conceptual options for this work are presented in the
following sections.
4.1.2 Seawall 2
Seawall 2 is believed to be mostly buried under the existing beach. The rocks that can be seen are
assumed to be the crest rocks. Those crest rocks have been displaced following storm and cyclone
events. It is proposed to relocate those rocks in an orderly manner and to add large 6,000kg rocks as
well to increase the crest stability. However it is assumed that the rest of the seawall structure is
complete under the existing beach. Therefore no other works is considered in this option assessment
report regarding Seawall 2. Reconstructing Seawall 2 will imply large excavation and is not considered
as critical works. Regular monitoring inspections are recommended to remediate any scouring issue or
crest damage, especially after storm event.
No detailed survey was undertaken to obtain the dimensions of the existing seawall, therefore the
actual volume of material required may increase once the detailed design and a survey is carried
out.
The concept design options are designed to a 50 year ARI event and would be damaged in severe
weather events that would be similar to TC Yasi.
The seawall is not intended for pedestrian access. However consideration should be given to
inclusion of a Building Code of Australia (BCA) compliant public access stair to provide a safe
access to the beach, or alternate means of deterring unauthorised access on the wall. Such
measures have been excluded from the quantity estimate but a unit cost has been included in the
contingency table.
Warning signs, fencing and other public safety features have not been detailed in this assessment
but are recommended to be implemented in the detailed design phase
Regular monitoring and maintenance is critical with any type of coastal protection revetment
Potential community concerns over visual amenity (although as the existing seawall is a rock
structure, this may be minimal)
Beach access restricted to stairways – the top of seawall should be fenced off for safety reasons
Structure shape
The existing rock armour shall be shaped to form a layer of at least 1m thick. Any gaps in the armour
shall be filled. A minimum 2.1 m thick armour layer of rocks of M50=3,000 kg shall be installed once the
layer of existing rocks is shaped.
To limit average overtopping rates lower than 200 L/s/m in the design event for a 50 year period, a
crest at 4m AHD is suitable. This is approximately 0.5 m higher than the existing foreshore level. It is
understood that Tully Heads community desires keeping the visual aspect of the current foreshore. A
crest at 3.5m AHD would be suitable for current climatic conditions but would eventually have to be
raised when sea level rises. It is proposed to increase the seawall height at a later date, therefore
keeping the current visual amenity at this stage.
The toe of the rock revetment shall be buried to LAT to mitigate scour issues. This assumes that the
existing seawall is also buried. This will have to be confirmed from a survey carried out to identify any
buried material at the site. Secondary armour rocks of M50=300 kg will have to be added to construct
the toe. The seawall toe will require monitoring and additional stones may be required to maintain the
seawall if and when scour develops.
Quantity estimate
Table 4-1 presents an indicative quantity estimate of material associated with this option.
This quantity estimate excludes any additional material that may be required to repair and reshape the
existing rock layer.
Conclusion
The main advantages of the rock revetment upgrade with buried toe are:
Scour mitigation
Quantity estimate
Table 4-2 presents an indicative quantity estimate of material associated with this option.
This quantity estimate excludes any additional material that may be required to repair and reshape the
existing rock layer.
Conclusion
The main advantages of the rock revetment upgrade with a toe on the existing surface are:
Limited excavation
Structure shape
The existing rock armour shall be demolished and a new profile of 1v:1.5h prepared. A geotextile
equivalent to 600R Elcomax geotextile shall be laid on the shaped profile. A secondary layer of
M50=300kg rock and a primary layer of rocks of M50=3,000kg shall be placed on the geotextile layer.
Quantity estimate
Table 4-3 presents an indicative quantity estimate of material associated with this option.
Conclusion
The main advantages of the total rock revetment reconstruction are:
Scour mitigation
The principal disadvantages associated with this option are:
Beach access friendly – the smooth, sloping wall would not require hand railing and may enable
direct access to the beach
Limited trucking requirement if the sand can be sourced from the local beach(es)
Reduction of beach or foreshore space – sloping wall reduces flat foreshore space
Reduced erosion protection compared to the rock revetment in higher wave climate
4.2.2.3 Conclusion
The main advantages of the geocontainer seawall are:
Scour mitigation
Easily removed (bags can be cut open and the sand distributed on the beach)
The principal disadvantages associated with this option are:
Not appropriate for higher wave climate – containers will have to be replaced during the seawall
design life
Low maintenance
Reflection of large portion of the wave energy due to low porosity of the structure which may cause
reduction in beach amenity
Beach access restricted to stairways - the top of seawall should be fenced off for safety reasons
More difficult to repair as compared to rock revetment, if damage occurs during a storm event
Stability of this type of construction is sensitive to toe erosion (toe sheetpiling may be required for
Tully Heads site conditions)
4.2.3.3 Conclusion
The main advantages of the concrete stepped seawall are:
Scour mitigation
Wave reflection
Estimate is preliminary only, and requires confirmation from Council’s preferred suppliers.
Detailed site survey (including buried material) and geotechnical investigation would also be
required to confirm estimated quantities.
4.3.2 Contingencies
Table 4-7 indicates contingencies proposed for the project.
(*) Detailed design escalation covers features which may become required during the consultation and
detailed design process.
A risk assessment is recommended to be developed at the onset of the detailed design phase to
reduce the range of uncertainties on these contingencies.
4.3.3.2 Option 1 - Variant B - Rock revetment repair with toe on existing surface
Table 4-9 Indicative cost estimate for Option 1 – Variant B
A Multi Criteria Analysis has been undertaken to compare a range of options plausible to mitigate the
erosion problem at Tully Heads.
Multi Criteria Analysis is a tool that can be used for complex problems where multiple criteria need to
be assessed in the process of making decisions about proposals for future action. Multi Criteria
Assessments (MCAs) attempt to incorporate all criteria simultaneously within the analysis, to arrive at
a single conclusion or ranking. As such, those assessments can consider a range of complex issues,
impacts and opportunities and can therefore be applied to more complex situations than a Cost
Benefit Analysis. For these reasons, an MCA process is used to inform the selection of a preferred
seawall option at Tully Heads.
5.1.1 Impact
The impact or influence of a proposed option is a key consideration and generally relates to the
degree to which an option may change conditions from the status quo (perceived or otherwise
defined). Impacts can occur to the environment and to the community.
Marine biodiversity – the degree to which the option may impact marine biodiversity at Tully
Heads, considering the benthic species associated with the beach, intertidal flats and the sub-tidal
areas
Beach/dune biodiversity – the degree to which the option may impact beach and dune
biodiversity (those areas typically above high tide mark), considering suitability to promote dune
vegetation (re-vegetation) and the opportunity for re-colonisation by dune animal species
Environmental impacts beyond Carron Esplanade – the impact of the option on areas farther
afield, including the impact on materials source areas, and up/down coast impacts due to changes
in sand supply or generation of plumes etc.
Construction impact – in relative terms, the area directly affected by the proposed option, both in
terms of option footprint as well as construction impacts for the materials sourcing areas. This
criteria may also capture issues relating to the degree to which construction works may interfere
with beach use
Construction timing – the time and flexibility taken to undertake construction (i.e. the degree to
which external influences may restrict the timing of works)
5.1.2 Effectiveness
The effectiveness of the option to address the erosion problem is assessed via a range of criteria.
Consideration is given to both the upside (addressing the problem) and downside risks (failure
consequence) of each option as well as to specific uncertainties.
Longevity of design – consideration of design life under typical conditions
Incident wave problem – degree to which a solution directly attenuates incident waves, creating
a reduced wave energy condition at the beach
Sand budget imbalance – degree to which a solution ameliorates the recognized imbalance
between longshore supply and storm sediment transport
Shoreline recession – degree to which a solution reduces or eliminates beach recession
Failure consequence – the downside risk of failure of the proposed option, perhaps due to
exposure to conditions beyond design criteria, where consequences could include potential loss of
life or damage to public/private property and/or infrastructure
Technology challenges – measure of the uncertainty associated with proven versus new
technology, and considers options proven/suitable for conditions at Tully Heads through to new
technology unproven along the Cassowary Coast
Integration/compatibility with existing – measure of the difficulty to integrate the proposed
option with the existing infrastructure
Adaptation to short term cyclic variations – degree to which the option can accommodate
short term (seasonal, storm) cycles in sand supply, wave climate, water levels
Adaptation to long term changes – degree to which the option can accommodate long term
(annual, climate change, ENSO) cycles in sand supply, wave climate, water levels
5.1.5 Economics
Cost is a major factor in any infrastructure project. Once completed, the seawall will become part of
the Cassowary Coast Regional Council portfolio of coastal assets and accordingly, capital cost is not
the only consideration.
Capital Cost – in relative dollar terms the up-front cost of the option, including material costs, site
construction activities, and any environmental (or other) monitoring linked to the option
Maintenance Cost – the cost of periodic routine maintenance
Lifecycle cost – the total cost of the asset each year, over its design life
Project 243333 File Appendix A - Document Register.docx 24 October 2014 Revision 1 Page 1
Title Description Prepared by Date
Correspondence from International Coastal ICM November
Management (ICM) to the Environmental 2004
Protection Agency (EPA) submitting
application for assessment – extension of
existing rock wall at Tully Heads
Officer Report DA 146/06 Report Number W655 John Pettigrew November
(Deputy Director 2006
Officer’s Recommendation Report –
Engineering
Development Application for Prescribed
Services)
Tidal Works
Contract T01/06-07 Correspondence –Cardwell Shire Council 22 June
Construction of a to Jenkins Earthmoving 2007
Seawall at Tully
Heads
Construction of Rock Correspondence – Condition A1C3 – 1 February
wall, Taylor Street, Results of Site Inspection undertaken by 2008
Tully Heads, at and EPA officer on Thursday 17 January 2008
adjacent to Lot 10
CWL802853
Reference
Report on Stability of - GHD 1992
Seawall, Tully Heads
Seawall
Post Yasi Cylcone Section of report GHD 2011
Inspections, Tully
Heads Rock Seawall
Restoration of - J T Smith and March
Seawalls and other Associates Pty Ltd 2011
Works, South Mission
Beach and Tully
Heads
Tully Heads and Hull Final Report BMT WBM April 2009
Heads Shoreline
Erosion Management
Plan
Other Documents Received (Outside Scope)
Drawing BP97.02 Installation of a Trial Groyne at Tully Heads Cardwell Shire 1997
Council
Project 243333 File Appendix A - Document Register.docx 24 October 2014 Revision 1 Page 2
Appendix B
Option Assessment
Drawings
CONCEPT DESIGN
TULLY HEADS SEAWALL
DESIGN PARAMETERS
AVERAGE RECURRENCE WATER LEVEL WIND SPEED SIGNIFICANT WAVE DESIGN WAVE PEAK
INTERVAL (A.R.I. YEAR) (m AHD) (m/s) # HEIGHT Hs (m) PERIOD Tp (s)
50 2.55 34.7 2.75 5 to 7
GALMAHRA ST
2AP5889
1AP5889
37T9482 36T9482 35T9482 25T9486 24T9486 22RP846516 12T9486 11T9486 10T9486 9T9486 8T9486 7T9486 6T9486 5T9486 1RP738155 2T9486 1T9486
38T9482
642T9484 39T9482 TAYLOR ST
4RP736730
26T9482 25T9482 24T9482 23T9482 22T9482 16T9482 912T9482 911T9482 910T9482 909T9482 908T9482 907T9482 906T9482 905T9482 904T9482 903T9482 902T9482 901T9482 9T9483 2RP865399 1RP865399 2T9483 1T9483
27T9482
28T9482
3RP736730 BEACH12T9485
ACCESS 11T9485 10T9485 9T9485 8T9485 7T9485
(PRIVATELY BUILT)
TOP OF
EXISTING
SEAWALL
CARRON ESP
CARRON ESP
HAT 10CWL802853
HAT
MHWS
TOE OF MHWS
EXISTING TOE OF
LOCATION OF EXISTING
SEAWALL PROPOSED CREST EXISTING
SURFACE FOR CROSS
Filename: P:\MRN\243333_CASSOWARYCOASTSEAWALLS\3 PROJECT DELIVERY\CADD\DRAWINGS\243333-0000-DRG-LA-0002.DWG
SEAWALL 1 SEAWALL 2
LEGEND NOTES
Office: AUBNE
RL 2.55 RL 2.55
DESIGN WATER LEVEL DESIGN
1.5 WATER LEVEL
3200 (MIN.) RL 1.94 (HAT)
1
RL 1.04 (MHWS)
ADDITIONAL ROCKS
EXISTING ROCK
M 50 = 300kg
PROTECTION/SEAWALL TO BE
CONFIRMED BY SURVEY THICKNESS = 1000mm (MIN.)
CREST ROCKS
M 50 = 6000kg APPROX.
PATTERN PLACED
RL 2.55
3200 (MIN.) DESIGN WATER LEVEL
RL 1.94 (HAT)
1.5
1
Filename: P:\MRN\243333_CASSOWARYCOASTSEAWALLS\3 PROJECT DELIVERY\CADD\DRAWINGS\243333-0000-DRG-LA-0003.DWG
GEOTEXTILE
ELCOMAX 600R RL 1.04 (MHWS)
(OR EQUIVALENT)
EXISTING SURFACE
(REF. NOTE 2)
RL 0.05 (MSL)
RL 0.00 (AHD)
NEW PROFILE
NOTES:
Office: AUBNE
TYP.
RL 3.50
380
RL 3.50 (APPROX.)
(APPROX.) GEOCONTAINERS
RL 2.55 RL 2.55
DESIGN WATER LEVEL DESIGN WATER LEVEL
1.5
RL 1.94 (HAT)
1
REINFORCED CONCRETE
RL 1.04 (MHWS) SEAWALL
ROCK SCOUR
EXISTING SURFACE
EXISTING SURFACE PROTECTION (REF. NOTE 2)
(REF. NOTE 2)
RL 0.05 (MSL)
ENGINEERED RL 0.00 (AHD) ENGINEERED
1.5
FILL FILL
RL -0.89 (MLWS) 1 1
MOISTURE
1 BARRIER 1
RL -1.68 (LAT)
1
NEW PROFILE
2400
GEOTEXTILE ELCOMAX PRECAST REINFORCED ARMOUR ROCKS
600R (OR EQUIVALENT) CONCRETE TOE M 50 = 3000kg
ROCK SIZE TO BE
00
CONFIRMED PENDING
600
GEOTECHNICAL
INVESTIGATION.
NOTES:
Office: AUBNE
RL 4.65 NOM.
RL 3.50
(APPROX.)
RL 2.55
DESIGN WATER LEVEL
RL 1.94 (HAT)
RL 1.04 (MHWS)
EXISTING SURFACE
(REF. NOTE 2)
RL 0.05 (MSL)
RL 0.00 (AHD)
REFER SECTION D ON
DRG. LA-0003 FOR TYPICAL
ROCK SEAWALL DETAILS.
NOTES:
Office: AUBNE
C2 – Sanctioned Plans under Section 86 of the Harbours Act 1955 (repealed) prepared
by the former Cardwell Shire Council, dated 1996 – Extension of Seawall 1
C3 – Sanctioned Plans under Development Permit for Operational Works that are
Prescribed Tidal Works prepared by International Coastal Management, dated
December 2006 (Permit IPCC00419906C11) – Seawall 2
416348:JWP/tn
15 December 2006
Decision Notice
APPROVAL
Integrated Planning Act 1997 S 3.5.15
D/A146/06
John Pettigrew (Deputy Director, Engineering Services)
07 40439101
Dear Sir
I wish to advise that, on 14 December 2006, the above development application was -
approved in full;
OR
approved in part;
OR
approved in full with conditions. The conditions relevant to this approval are attached.
These conditions are clearly identified to indicate whether the assessment manager or
a concurrence agency imposed them;
OR
approved in part with conditions.
Page 1
the standard relevancy periods stated in section 3.5.21 of IPA apply to each aspect of
development in this approval;
Page 2
OR
An alternative relevant period.
OPERATIONAL WORK
Page 3
Operational work… Name of agency Status Address
3. That allows taking or Dept. of Natural Concurrence
interfering with water Resources & Mines
under the Water Act 2000
4. Controlling the flow of Dept. of Natural Concurrence
water in drainage and Resources & Mines
embankment areas
5. For a referable dam or that Dept. of Natural Concurrence
will increase the storage of Resources, Mines &
a referable dam by more than Energy
10%
6. That is tidal work other than Environmental Cairns District Office
Concurrence
Prescribed Tidal Work in a Protection Agency (EPA)
Canal. PO Box 2066
CAIRNS QLD 4870
7. Within a coastal Environmental Concurrence
management district, that Protection Agency &
is the disposing of dredge Qld Transport
spoil or other solid waste
material in tidal water, other
than under an allocation
notice under the Coastal
Protection and Management
Act 1995
8. Within a coastal Environmental Concurrence
management district, for Protection Agency
draining or allowing drainage
or flow of water or other
matter across State coastal
lands above high water mark
9. Within a coastal Environmental Concurrence
management district, in a Protection Agency
watercourse and not
assessable under schedule 8,
part 3, items 3B and 3C of
the IPA
10. Within a coastal management Environmental Concurrence
district, that is reclaiming Protection Agency
land under tidal water and Qld Transport
11. Within a coastal Environmental Concurrence
management district, that Protection Agency
is constructing an artificial and Qld Transport
waterway associated with
reconfiguration
Page 4
Operational work… Name of agency Status Address
12. Within a coastal Environmental Concurrence
management district, that Protection Agency
is constructing an artificial
waterway not associated with
reconfiguration, on land other
than State coastal land,
above high water mark if the
surface area of water in the
waterway is at lease 5 000m2
13. Within a coastal Environmental Concurrence
management district, that Protection Agency
is constructing a bank or
bund wall to establish a
ponded pasture on land,
other than State coastal land,
above high water mark
14. Within a coastal Environmental Concurrence
management district, that Protection Agency
is removing or interfering
with coastal dunes on land
other than State coastal land,
that is in an erosion prone
area and above high water
mark.
15. That is tidal work that Queensland Fire and Advice
involves a marina with Rescue Service
more than 6 vessel berths
Page 5
9. Submissions -
The application was not subject to public notification and therefore no submissions were
received.
OR
• when the submitter’s appeal period ends, if there is a submitter and the applicant
does not appeal the decision to the court
OR
• subject to the decision of the court, when the appeal is finally decided, if an appeal is
made to the court.
This approval will lapse unless substantially started within the above stated currency periods
(refer to sections 3.5.19 and 3.5.20 of IPA for further details).
If you wish to discuss this matter further, please contact Council’s Deputy Director,
Engineering Services, Mr John Pettigrew, on the above telephone number.
Yours faithfully
MARK KELLEHER
CHIEF EXECUTIVE OFFICER
Page 6
ASSESSMENT MANAGER’S CONDITIONS:
Development Description
Property Lot/Plan Aspect of Development
(A1C2) Record, compile and keep all monitoring results required by this
document and present this information to the Environmental Protection
Agency upon request.
Page 7
be undertaken to cover the rock revetment must be to a minimum level of
RL2.0 metres (Australian Height Datum), and maintained to this level, with
a profile slope 1 on 4.
(A1C4) If the erosion scarp at the pocket beach adjacent to the Public
Park Reserve (Lot 9 on T9483) advances onto this Reserve, sand
nourishment must be immediately undertaken and maintained to the
profile as shown on Cardwell Shire Council drawing 3811, Sh. 2 of 2, and
be completed within thirty (30) days. The end walls (wings) of the rock
revetment must be covered with sand at all times to ensure erosion does
not progress in behind the rock revetment.
(A1C9) All organically enriched sand removed from the top layer
(topsoil) within the proposed development area must be stockpiled
separately prior to excavation and used landward of the crest of the
revetment wall. On completion of the works any excess organically
enriched sand material may be removed from the site. The area landward
from the crest of the revetment wall must be maintained as a pedestrian
and maintenance access.
(A1C10) Acid sulfate soils must be managed such that contaminants are
not directly or indirectly released from the works to any waters.
Page 8
(A1C11) The sand being placed on the beach shall be clean and free of silt,
clay, organic material or any other deleterious substance and must be of a
grain size compatible with the existing beach sand.
(A1C12) The Cardwell Shire Council shall be responsible for the ongoing
maintenance of the revetment wall and the removal of any debris from the
beach as a result of any damage to the wall.
DEFINITIONS:
Words and phrases used throughout this permit are defined below. Where a
definition for a term used in this permit is sought and the term is not defied within
this permit the definitions provided in the relevant legislation shall be used.
“approved plans” means the plans and documents listed in the approved plans
section in the notice attached to this development approval.
“coastal dune” means a ridge or hillock of sand or other material on the coast and
built up by the wind.
“dredge spoil” means material taken from the bed or banks of waters by using
dredging equipment or other equipment designed for use in extraction of earthen
material.
“erosion prone area” means an area declared to be an erosion prone area under
section 70(1) of the Coastal Protection and Management Act 1995.
“high water mark” means the ordinary high water mark at spring tides.
Page 9
“ponded pasture” means the ordinary high water mark at spring tides.
“quarry material” means material on State coastal land, other than a mineral
within the meaning of any Act relating to mining. Material includes for example
stone, gravel, rock, clay, mud, silt and soil, unless it is removed from a culvert,
stormwater drain or other drainage infrastructure as waste material.
“site” means land or tidal waters on or in which it is proposed to carry out the
development approved under this development approval.
“tidal water” means the sea and any part of a harbour or watercourse ordinarily
within the ebb and flow of the tide at spring tides.
“waters” includes river, stream, lake, lagoon, pond, swamp, wetland, unconfined
surface water, unconfined water natural or artificial watercourse, bed and bank of
any waters, dams, non-tidal or tidal waters (including the sea), stormwater
channel, stormwater drain, roadside gutter, stormwater run-off, and groundwater
and any part thereof.
“you” means the holder of this development approval or owner/occupier of the land
which is the subject of this development approval.
APPROVED PLANS:
End of Conditions.
Page 10
Aurecon Australasia Pty Ltd
ABN 54 005 139 873
Level 1, 242 Mulgrave Road
Cairns QLD 4870
PO Box 7625
Cairns QLD 4870
Australia
T +61 7 4019 6400
F +61 7 4051 2540
E cairns@aurecongroup.com
W aurecongroup.com