Operation of Precalciner

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

CALCINERS 31

Stratification: the hidden


menace to performance
The operating performance of calciners is affected by several factors, but flow
stratification presents a particular challenge for the cement plant. To successfully address
flow stratification and find low-cost solutions requires a combination of fundamental
process knowledge and problem-solving experience.
n by Tom Lowes, OPECS, UK, Joana Bretz and Mariana Pinheiro, Cinar, Brazil, Bernd Klarner,
PM Technologies, Austria, and Shan Raza, Cinar, UK

S ince their initial installation in the 1970s


in Japan, calciners have developed to
become a key part of every new cement
Figure 1: residence time for burn-out of 50mm SRF and 90µm petcoke at 900˚C

plant installation. While the largest calciner


is installed in a 12,500tpd kiln system, in
general calciners today are often part of
Residence time (s)

5000tpd kiln configurations and include a


five-stage preheater (PH).
With early models including oil firing
and <2s residence time (RT), modern
newly-built and existing calciners are
required to:
• operate to burn 100 per cent of high-
sulphur petcoke (up to seven per cent
sulphur)
Oxygen (%)
• use 100 per cent SRF in the fuel mix
with 80 per cent <50mm and a calorific
value (CV) of 3000kcal/kg Furthermore, it will introduce a new The general statement that the three
• have a CO <500ppm calciner developed by PM-Technologies Ts – temperature, turbulence and time
• keep NOx emissions < 500mg/Nm3 at with the help of Cinar. This calciner can – are required for good combustion,
10 per cent O2. burn 100 per cent SRF or tyre-derived fuel has two essential items missing: oxygen
To meet these operating requirements with a gas RT of only 0.7s, leading to a and mixing. While all calciners are in the
new plants are designed for RTs of up to significant reduction in capital cost. Reynolds Turbulent regime, this does not
8s. However, for a six-stage PH installation, guarantee the mixing required to achieve
this is a big blot on the landscape, which Flow stratification good combustion, and even good overall
can lead to problems obtaining building Flow stratification, which occurs to a mixing is inadequate without sufficient
permits for some cement producers. greater or less extent in all calciners, is local O2. It is essential to consider what
A key factor that negatively affects defined in terms of this article as a lack of happens on the microscale inside a
calciner performance is flow stratification. or poor mixing efficiency between gases calciner and not just look at it as a ‘black
This article examines the occurrence of (combustion products, pure air, volatiles box’.
flow stratification and how it causes issues from solid fuels) and particles (meal and So instead of the three Ts, the design
in the most common calciner types. In solid fuels). needs to embody TOM – temperature,
addition, it will discuss the method to Severe flow stratification leads to oxygen and mixing – where the mixing is
assess the performance of an existing insufficient local micro-mixing. Therefore, driven by jet mixing, like in a kiln burner.
calciner and find solutions in terms of: before being quenched by the meal, the Figure 1 shows the RT needed for the
• poor burn-out driving SO3 cycles fuel volatiles are not evolved into the complete burn-out of 50mm SRF and 90µm
• stratification producing high LOI required local O2 and temperature for petcoke at 900˚C as a function of O2: after
and CO, as well as increasing PH a sufficiently-long period to avoid CO. 3s the petcoke is burnt out at two per cent
temperatures and fuel consumption (in As a result, the meal is not adequately O2 and the SRF at three per cent O2.
kcal/kg) dispersed and mixed with the combustion This needs to be compared to the data
• low NOx emissions from reburn of kiln gases to ensure the expected calcination from MI-CFD simulations of the four main
gases and staging of the calciner fuel. for the calciner fuel input. calciner types.

FEBRUARY 2018 INTERNATIONAL CEMENT REVIEW


34 CALCINERS

Figure 2: main inline calciner models Main calciner types


Figure 2 shows calciners produced by the
three main European plant manufacturers
where B, with a separate combustion
chamber, can be produced by the
manufacturer of A or C.
These four calciner models, with similar
sizes, have been modelled with Cinar
Ltd’s MI-CFD under the same operational
conditions: burning seven per cent-sulphur
petcoke at three per cent at 90µm, 50mm
SRF at 20 per cent thermal substitution
rate (TSR) and three per cent O2 at the
calciner exit.
Figure 3 shows the internal oxygen
concentration profile and the paths of the
petcoke particles in black lines. For all four
A. B. C. D. models, the effect of flow stratification
delaying petcoke combustion is observed.
Petcoke particles that cannot find local
Figure 3: oxygen concentration profile and petcoke particles trajectories inside calciners oxygen flow along their paths, with some
reaching the calciner exit without complete
burn-out.
In calciner type A, the high O2
stratification is easily seen as well as the
twisting route of the petcoke particles
which does not spread into gaseous flow.
This is a typical case where the issue is
not the calciner size, but how its volume is
being used by the particles.
In calciner B the gas flow from the
separate combustion chamber does not
mix with the gas riser flow up to the level
of half the vertical distance in the calciner
neck. On some plants with CC calciners this
mixing only is effective late up the calciner
neck, sometimes very close to the calciner
exit. There are cases where this type of
A. B. C. D. calciner, when operated with 2-3 per cent
O2 at exit and having all fuel injected at the
CC burner, becomes a high-NOx producer in
Figure 4: gas residence time (RT), petcoke and SRF burn-out (BO) the calciner as well as overall, as reburn of
the kiln gases is not possible.
In calciner C, special attention needs
to be paid to the angle of the top tertiary
air inlet and to the tertiary air distribution
between its three inlets. Although not
immediately apparent in Figure 3, these
calciner types can slope at an angle
soon after the tertiary air ducts. In these
cases, unless good mixing of the fuels,
O2 and meal has been achieved by then,
the mixing afterwards is very slow as is
evidenced by the high O2 mid-way up the
calciner.
In calciner D, the mixing between the
kiln riser duct gases and the tertiary air
A. B. C. D.
is often ineffective and good mixing only
occurs after the top bend. Therefore, to
guarantee the efficiency of this calciner
type, special care is needed to position

INTERNATIONAL CEMENT REVIEW FEBRUARY 2018


CALCINERS 35

increased CO and loss either reducing conditions in the flame


Table 1: Case 1 – one week’s hot meal and clinker data
of output once they aim and/or the hot meal.
Compound Hot meal Clinker VF
for TSRs of more than 50 Two quick checks are needed to
per cent. In these cases a establish the SO3 cycles drivers:
combination of process • hot meal carbon via a Leco or visual
SO3 2.55 0.90 2.84 knowledge and MI-CFD inspection or counting
Na2O 0.67 0.45 1.50 modelling is required to • insoluble alkalis in the clinker.
find a suitable solution. For this plant, the maximum insoluble
K2O 4.89 1.12 4.35
There are many alkali level for these data is 0.49 and a
Cl 1.97 0.05 41.65 calciners in operation ORC3A of 6.18 and both were found to be
SF 10.08 with RTs much lower than in this range. Hence, the kiln burner is not
MR 0.58 0 6s, some even lower than the main driver of SO3 cycles. However,
3s, which run into issues the hot meal carbon (HMC) was above the
with 100 per cent petcoke recommended maximum of 0.1, at 0.2 per
fuel and alternative fuels injection in the and SRF at a much earlier stage. Below cent, as well as whole tyres being put on
correct locations. This step is often more is a process methodology that has been the feedshelf. This results in the SF being
important than determining the size of the successfully used by the authors. above the recommended maximum level
calciner. of 8. Figure 5, which compares hot meal
Flow stratification delays not only Poor fuel burn-out driving SO3 cycles chlorine (HMCl) and SO3, shows the extent
combustion but also meal calcination. It Firstly, find the magnitude of the issue by of this issue.
is important to emphasise that while it comparing the expected and actual SO3 in The recommended short-term solution
may lead to the need for large calciners the clinker. If this is more than 0.2 per cent is to reduce stratification in the calciner
when aiming for good burn-out levels, below the predicted daily value, there are by installing JAMS (Jet Air Mixing System)
increasing gas RTs does not necessarily not only build-up issues, but also potential sleeves – optimised via MI-CFD – on the
mean an increase in fuel/meal particle ring issues. calciner burners and run at one per cent
RT within the calciner. As a solution to Secondly, look at the sulphur trioxide more kiln and calciner O2. In the longer
calciner performance issues, extending volatisation factor (VFSO3), sticky factor (SF)1 term, and with the aim of increasing
the calciner’s length at the cold end is and Cl vs SO3 (Table 1). petcoke and AFR use, it is recommend to
not an optimal solution. A better and less Table 1 shows a week’s data of a current install a Cl by-pass.
expensive way to improve performance investigation – Case 1: a 5500tpd calciner The importance of unburnt carbon
is to make the heart of the calciner work with 3.5s RT, which is currently running at in the hot meal from the tyres on the
better. a 50/50 petcoke-coal mix and 35 per cent feedshelf driving the excess SO3 over alkalis
Figure 4 compares the gas RTs for the TSR. The plant management wants to in the form of CaSO4 in the after-calcination
four calciner models showing the burn-out change the fuel mix to a 50 per cent TSR zone cannot be stressed enough. Figure
of petcoke and SRF at 3s, and at calciner and no longer use coal but is experiencing 6 shows that, based on plant data, the
exit, all in the same conditions shown in both build-up and CO issues. higher VFSO3 values are estimates from
Figure 3. The balance of SO3 in to out is at an whole tyres on the feedshelf of calciner
The effect of flow stratification in terms acceptable level. However, it should be kilns at a TSR of 10 per cent. As a guideline,
of combustion efficiency is shown by the noted that the VF SO3 is close to 3 and the at 100 per cent petcoke the burn-out needs
inability of the 3s RT to achieve complete clinker molar ratio (MR) is <<1, while the to reach 99 per cent to have a HMC <0.1 per
petcoke burn-out in any of the four calciner clinker MR should be at 1.5. This indicates cent.
models. However, at a TSR of 20 per cent
SRF and following some optimisation on Figure 5: Case 1 – hot meal Cl vs SO3
its injection location via MI-CFD modelling,
a good level of burn-out is possible with The conventional limit is shown by the red line above which there
gas RTs of >6s. are severe build-up issues. It has been found that on plants with
many blasters, focussed shift cleaning and good kiln control, good
As both methods are complementary operation is possible up to the crimson line. At least 50% of the
to each other, a process evaluation in data lies above this line. A drop of Cl input or increased bypass is
needed to get below the crimson line. To move from 3% to 1%
addition to MI-CFD modelling is essential HMCl is a drop in Cl input of 400mg Cl/kg clinker, or 3.5% more
to ensure that the calciner is operating at bypass
Cl in hot meal (%)

its maximum efficiency, irrespective of the


output of the calciner model.

Calciner performance
assessment
Examining data can help to assess calciner
performance and find ways to improve this
at low cost.
Even calciners with the RTs >6s
previously simulated have issues in terms SO3 in hot meal (%)
of increased SO3 cycle/build-up as well as

FEBRUARY 2018 INTERNATIONAL CEMENT REVIEW


36 CALCINERS

Figure 6: VF SO3 vs unburnt carbon in hot meal In addition, it should be noted that VFSO3
values of >10 have been found in PH plants
without riser or feedshelf firing, when
there is a low-momentum burner and/or
flame impingement in the burning zone. In
these circumstances there is no mistaking
the very brown clinker. Green clinker can
even be found from unburnt petcoke
VF SO3 (HMSO3/ClkSO3)

impingement.

Stratification producing high LOI and


CO and raised PH temperatures and
fuel consumption
When the fuel volatiles do not mix
well with local micro-mixed O2 and a
temperature of at least 1000˚C is reached,
then CO is produced ex calciner and only
loses about 20 per cent of its quantity (in
ppm) by further combustion up the PH
Unburnt carbon in hot meal (%) tower. This combustion up the PH tower
raises the exit temperature and increases
fuel consumption (in kcals/kg) in addition
Figure 7: Case 2 – calciner exit CO and PH exit temperature vs time to the final CO emissions.
Figure 7 shows Case 2, a five-stage
PH calciner that is running with a fuel
Calciner CO PH exit temperature demand of 795kcal/kg, which is 70kcal/
Average values: kg greater than a normal well-run five-
PH exit temperature – 377˚C stage calciner PH system. The average PH
Calciner exit CO – 5000ppm exit temperature is 377˚C and calciner
exit average CO is 5000ppm. These two
PH exit temperature (˚C)

factors combined account for the poor


Calciner exit CO (ppm)

performance of the plant against the


benchmark.
Table 2 shows the simulation of
a benchmark five-stage PH calciner
temperatures and LOI compared to the
plant data. It should also be noted that the
ex-calciner LOI of the plant is lower than
simulated. This shows that the heat in the
calciner is not being transferred well to the
meal and goes up the PH, increasing the
Time exit temperature.
On detailed scrutiny is was found that
the SRF feed was above the splash boxes
and introduced via a double flap valve with
Table 2: Case 2 – calciner and preheater simulation the calciner operating at less than one per
cent O2. While any one of these factors will
Simulation Plant data
produce CO, in combination these three
factors have serious consequences. Figure
No of stages 5 5
8 shows the calciner CO vs O2 where simply
running at below two per cent O2 would go
Parameters Efficiency Temperature LOI Temperature LOI
(˚C) (˚C) a long way to reduce fuel consumption.
The low calciner O2 can be attributed
C1 0.9 314 35.1 378
to the plant being operated at maximum
C2 0.8 487 34.5 568 capacity. Therefore, a more complex
C3 0.8 653 33.0 708 solution is required to reduce the PH tower
C4 0.8 809 27.2 809 pressure by overcoming the severe build-
C5 0.7 896 1.2 889 4.4 up issues that are occurring driven by the
poor burn-out. As a result, modifications to
Fuel consumption the SRF feeding system and its location as
728 775
(kcal/kg)
well as modifying the calciner burners to

ICR FEBRUARY 2018


38 CALCINERS

Figure 8: calciner exit CO vs O2 reduce stratification will be needed to be


able to lower the fuel consumption at the
same calciner O2.

Reburn of kiln gases and staging of


the calciner fuel
NOx emissions from calciner kilns fired
Calciner CO (ppm)

on coal without any special NOx-reducing


Average calciner O2 – 0.9%
provisions built into the design are
Stay >2% O2 , and eliminate CO issues and between 800-1200mg/Nm3 at 10 per cent
reduce fuel consumption (kcals/l) O2. When coal is replaced by 100 per cent
petcoke, depending on the calciner, the
NOx will range between 1000-1600mg/Nm3
at 10 per cent O2.
To reduce the NOx, kiln gases first need
to be reburnt with the calciner fuel and
then fuel N in the calciner fuel needs to
Calciner SO2 (%) be staged to minimise NOx generation
and achieve <500mg/Nm3.2 For coal, a hot
reburn of 0.15s is needed, followed by 0.5s
Figure 9: Case 3 – stack NOx vs kiln back end (KBE) NOx RT for the gases to allow the hydrocyanide
(HCN) to go to N2 before the tertiary air
Stack NOx = 0.35*KBE NOx + 155 is mixed in. For SRF, which due to its
structure produces ketenyl (HCCO) radicals
which are 35 times more effective than
Stack NOx (mg/Nm3 at 10% O2)

methylidyne (CH) radicals in the reburn


reactions, plant data has shown that a hot
reburn stage is not needed. With only 0.5s
RT with SRF up to 100 per cent reburn of
the kiln gases is possible.
The way to assess the current level of
reburn and staging of a plant is to look at
the stack NOx vs Kiln Back End (KBE) NOx –
as shown in Figure 9.
For a 35/65 split of kiln/calciner fuel,
KBE NOx without any reburn will be diluted
to 39 per cent when expressed as mg NO2
KBE NOx (ppm) and 10 per cent O2. Total reburn will show
no impact of KBE NOx on stack NOx. Figure
9 shows this plant for Case 3 which has
Figure 10: low-RT calciner a type B calciner. The figure shows little
reburn as stated earlier in the paper with a
slope of 0.35. However, the NOx generated
in the calciner is only 155 at the stack,
which is contrary to the earlier statement
in which the combustion chambers
produce high NOx. Approximately 750
would be expected from the volatile fuel
nitrogen (N) of a 1.5 per cent N coal with
30 per cent volatiles. However, the plant
runs at an average of 8000ppm at the exit
calciner and 2.2 per cent O2 at the end of
the calciner riser. As the KBE O2 average is
seven per cent, this means the combustion
chamber is running under reducing
conditions and therefore, producing high
CO and low calciner NOx.
The high KBE O2 is due to a low-
momentum burner producing stratified
KBE O2 that does not burn out the HMC
from the calciner fuels. The plant aims

INTERNATIONAL CEMENT REVIEW FEBRUARY 2018


40 CALCINERS

Figure 11: X5 calciner to be built in Egypt therefore final burn-out and HMCl <0.1
per cent. It should also be noted that
the longer RT for the larger SRF particles
will drive more of fuel N off under sub-
stoichiometric conditions and produce a
lower NOx than the more conventional air-
staged calciner.

Conclusions
All calciners are different and complex
with even those built by the same
supplier having subtle differences. To
meet the challenges of operating the
calciner at maximum output, 100 per
cent petcoke and SRF TSRs, low NOxand
Novel combustion chamber with 1s fuel consumption, a fundamental process
RT for staged combustion and 10s knowledge combined with real plant
problem-solving experience is needed
RT for 100 * 100 * 2.5mm SRF to recognise and overcome stratification
issues.
MI-CFD and process knowledge and
experience is an unbeatable combination
in this task for low-cost solutions to the
issues which normally involve, in order of
application:
• setting and maintaining clinker SO3,
SF, VF SO3, KBE and calciner O2 targets
• significantly reducing stratification
by designing and installing a novel
JAMS system3 – either as sleeves to the
calciner burner or as injectors in the
regions of the tertiary air inlets, or for
type D calciners, at the convergence of
the tertiary air duct and kiln riser duct
to move to higher-sulphur petcoke and largest SRF particle. (KRD)
a higher AFR TSR. To achieve this the This type is also available in an air- • improving the kiln burner’s
calciner’s combustion chamber needs through (AT) calciner and has potential momentum to twice the burning zone
to be optimised and the kiln burner’s application to large PH kilns where calciner thermal load in terms of N/MW
momentum increased by some 4N/MW. TSRs of up to 35 per cent and up to 100mm • improving and relocating the feeding
SRF could be achieved. system of alternative fuels, such as SRF,
Novel low-RT calciner to keep the STIFF at the required level
As the issue is associated with X5 inline calciner • modifying the design of splash boxes
increasingly-high PH tower and capital The concept of recirculating fuel or their location to make better usage
costs to encompass bigger RT calciners, particles was further developed to an of the heat released in combustion
the collaboration between Cinar and integrated approach for inline calciners. process
PM-technologies to develop a small In this concept coarse fuel particles • helping in the design of novel calciners
calciner with ‘a big heart’ was a positive are recirculated in the customised hot that maximise the use of TOM. n
step. The new, patented calciner can combustion zone. In addition, the calciner
achieve a 100 per cent TSR with coarse SRF. top chamber is designed as a horizontal
REFERENCES
The calciner is tilted to the side by some cyclone swirl chamber in the style of the
1
LOWES, T AND BRETZ DE SOUZA, J (2017)
15˚ which produces a cyclonic motion previously-mentioned low-RT calciner. ‘Preventing build-ups and rings’ in: ICR, July,
of the SRF. This allows a TSR of 100 per The X5 inline calciner is currently being p78-83.
cent with up to 100*100 * 2.5mm SRF in a installed in an Egyptian cement plant to 2
LOWES, T AND BRETZ, J (2016) ‘Keeping NOx
calciner with only 0.7s gas RT, by spinning accommodate up to 100 per cent SRF, air- under control’ in: ICR, July, p64-69.
the SRF inside the calciner until it is staged combustion, with optimised mixing 3
NANCE, G, ABBAS, T, LOWES, T AND BRETZ
sufficiently small to exit the cyclone. designed by MI-CFD for opposed tertiary DE SOUZA, J (2011) ‘Optimum Calciner Design
for Lower CO and NOx’ in: Proceedings of 53rd
Figure 10 shows the general layout of air inlets. The calciner swirl chamber Cement Industry Technical Conference, IEEE-IAS/
the calciner, with fuel, meal and tertiary design at the calciner top is based on the PCA, 22-26 May, St Louis (MI), USA.
air inlets, with a MI-CFD simulation of the concept in Figure 10 to ensure that the
SRF flow and burn-out, which shows SRF larger SRF does not leave the chamber
burn-out of 97 per cent and a 10s RT for the until it has achieved good burn-out and

INTERNATIONAL CEMENT REVIEW FEBRUARY 2018 ©Copyright Tradeship Publications Ltd 2018
301988-2018
YE ARS

SUBSCRIPTION PACKAGE INCLUDES: THE WORLD’S LEADING MONTHLY CEMENT JOURNAL


12
 ISSUES OF INTERNATIONAL CEMENT
REVIEW (ICR) – the cement industry’s leading
monthly publication, delivered direct to your desk
by First Class Airmail with early access to the
digital magazine via CemNet.com. Each issue of
ICR includes news and market reports, technical
articles and recent case studies, informed
commentary and much more...
EE
 FR HANDBOOK! Choose either the
Cement Plant Environmental Handbook, A COMBINED
2nd Edition or The Cement Plant Operations PRINT AND
Handbook, 6th Edition (fully-revised). DIGITAL
ICR SUBSCRIBER DISCOUNTS on all other
SUBSCRIPTION
reference works published by ICR.

Building
 bulletin newsletter Monthly
newsletter covering the latest developments in Annual subscription to ICR (12 issues):
the building materials sector – complimentary
to all ICR subscribers. GBP 205 / USD 315 / EUR 260
This is a combined print and digital
subscription package
PLUS UNLIMITED ACCESS TO CEMNET.COM
THE LEADING INDUSTRY WEBSITE
n Full
 digital issues of ICR available in
advance of the print edition
n Over
 five years of online back issues CHOICE OF FREE HANDBOOK
n Daily
 news service and 15-year The monthly news OCTOBER 2017
letter covering n ISSUE 238

searchable ICR news database


the building mate
rials sector
Ferguson growth
driven by favourable
FERGUSON PLC
HAS recorded US markets
for the year ending
revenue to GBP14,8
a six per cent increase
31 July 2017. The
increase, at constan
in revenue for
its ongoing business
es
Contents
78m (US$19,765m) t exchange rates,
last year. Trading for FY17, compare takes the group’s

n Access to Corporate Watch and


profit in the ongoing d to GBP12,146m Ashtead Group revenue
per cent ahead
of last year at constan
businesses over
the same period
in the same period up 25%
Strong quarter


points ahead at t exchange rates, was GBP1032m, of organic growth
6.9 per cent. Trading while the trading 8.7
versus GBP30m profit from the margin was 10 and bolt-on acquisi
in the same period non-ongoing business basis tions
came in at GBP1059 last year, while trading es was GBP27m 2
m. Trading profit profit from continui , Tarmac targets asset
According to Ferguso from discontinued ng operations management
n, the results were operatio ns was GBP63m New service to improv
commercial markets

Market Reports section
driven by favourab . e local road
, which account le US residential network efficien
markets, which for the majority and cy
represent seven of the group’s
although recovere per cent of US revenue. Industria 2
d in the second revenue, were
weak in the first l Scandinavian markets
the Canadian markets half. In the UK
the heating market half of the year level off
improved progress also remained Norway and Sweden
In the US, which ively throughout flat while slow, as
accounts for 89 the year. Denmark enjoys
revenue increase per cent of the “upswing”
by seven per cent group’s trading
cent, mainly due on a like-for-like profit, the business 2
to falling commod basis, includin saw its Vulcan acquires
g price deflation Polaris Materials

n Cement Plant Directory


Waterworks, HVAC, ity prices in the of 0.5 per
Fire and Fabricat first half of the Consolidates leading
gained market ion, and Facilities year. Blended
share. Build.co Branches, position in


m, its B2C e-comm Supply all generate Californian market
throughout the erce business, d good growth
year and e-comm and
in the USA. Acquisit erce now accounts continue d to grow strongly 2
ions contributed for over 22 per Saint-Gobain launche
acquisitions were 2.7 per cent of
additional revenue
cent of group revenue s new glazing
completed with
total annualised in the year. Nine
Focus on energy and
the group has daylight
acquired two more revenue of GBP267m 3
generate GBP86m B2C businesses . Since the year Sika continues to
of annualised – AC Wholesalers end, expand

n Video presentations
In the UK like-for-l revenue. and Supply.com
ike revenue was – which Czech Republic
cent. While the ahead by one and El Salvado
r


new residential per 3
and improvements construction markets cent including price inflation UK construction
markets , where saw growth, the
repairs, mainten
of 2.2 per in reverse gear
remained flat. the group generate ance Fastest decline
Good growth in s the majority since July 2016
in the large custome the small custome of its trading profit,
r segment. The r segmen 3
traded well and Pipe and Climate,
t was offset by
declining revenue NWH delivers double-
gained market
share, while the
and Infrastructure digit growth
challenging. The Plumbing and businesses Celebrates 50th
group continue Heating markets anniversary
well and achieved d to invest in its remained 3
good growth,” B2C business – Teko Mining boosts
according to Ferguso soak.com – which
GBP2m ahead
of last year. n. UK trading profit “traded quarry production
Canada and central of GBP76m was Serbia welcom
es new equipm
saw like-for-like
Europe, which
represents four ent 3
revenue growth per cent of the Siwertell supplies
of 3.6 per cent. group’s trading Güzey Bazalt

DAILY AND WEEKLY NEWSLETTERS


cent. Acquisitions This profit,
contributed 0.9 included price 4
Netherlands also
made very good
per cent of addition
al growth. Canada
inflation of 1.7
per Metso business reorgan
between Ferguso progress. April grew well and The
isation
n’s Tobler business marked the complet New structure
owns 39.2 per and Switzerland-bas ion of the merger to drive growth
cent of the combine ed Walter Meier. 4
three more business d business. Since Ferguson now Cemex supplies key
es – Aircovent the year end, the projects
Tackaberry, both in The Netherla group has acquired Airport and Constit
in Canada. nds, and Plomber ution Square
ium Pierrefonds 4
and CASE appoints new
CRH and Summit VP for EMEA
enter potential bidd
4
AfriSam scoops SARMA
A NEW BID for
Ash Grove Cement
CRH plc and Summit Company has ing war Poraver expands
awards 4
Materials. CRH led to a potentia
l bidding war between German sales team
US cement manufac had agreed to
acquire Ash Grove
4
turer, for US$3.5b Cement
2017. However, n with the deal
a new bid of US$3.8b expected to complet , a leading
submitted and n from US cement e at the end of Building Bulletin
is now under consider maker Summit is published monthly
Cement is currentl ation by the Ash Material International by:
y the Grove board. Kansas- s has been Old King’s Head Cement Review
eight cement plants, leading privately-owned cement based Ash Grove Court,

Subscribe to International Cement Review


extraction sites.
two import termina
ls, 52 ready-m
producer in the
USA and operate Dorking, Surrey, 15 High Street,
In 2016 the compan ixed batching s RH4 1AR, UK.
y registered a plants and 45 Tel: +44 (0) 1306
7.4Mt of cement. pretax aggregate 740363/383
CRH is its largest profit of US$215m Fax: +44 (0) 1306
customer. and shipped Email: info@Ce 740660
ICR BUILDING BULLETI mNet.com
N n OCTOBER www.CemNet.co
2017 m

Pay online at www.CemNet.com/subscribe

www.CemNet.com Payments by credit card receive a 5% discount


and instant access to CemNet.com
Alternatively, you may request an invoice.

Delivering business insight, market knowledge and technical expertise to the global cement industry

You might also like