Professional Documents
Culture Documents
MS - Report
MS - Report
where:
t = estimate of expected activity time
a = optimistic time
m = most probable time
b = pessimistic time
𝜎 2 = variance
To understand on how the PERT is being implemented let us examine the next example.
Example: The AUS Company is planning to develop a new chemical process. They identified the
following activities:
Table 1.
Activity Description Immediate a m b
Predecessor
A Test method 1 for the process - 10 15 26
B Test method 2 for the process - 8 10 18
C Select the best method and refine the A,B 4 5 6
process
D Complete initial preparation of - 10 12 14
production facilities
E Train personnel D 1 2 3
F Develop final procedures manual D 1 3 11
G Run tests on the refined process C,E 1 2 3
H Adjust the production method F,G 1 2 3
I Set up complete production system F 3 4 5
J Run final tests H,I 1 2 3
A. Develop a project network and determine the expected project completion time.
B. What is the probability that project completion time will meet the 30 week deadline?
Solution:
Step 1: Compute for the expected times and variances.
Expected Times:
10+4(15)+26 96 1+4(3)+22 24
𝑡𝐴 = = = 16 𝑡𝐹 = = =4
6 6 6 6
8+4(10)+18 66 1+4(2)+3 12
𝑡𝐵 = = = 11 𝑡𝐺 = = =2
6 6 6 6
4+4(5)+6 30 1+4(2)+3 12
𝑡𝐶 = = =5 𝑡𝐻 = = =2
6 6 6 6
10+4(12)+14 72 3+4(4)+5 24
𝑡𝐷 = = = 12 𝑡𝐼 = = =4
6 6 6 6
1+4(2)+3 12 1+4(2)+3 12
𝑡𝐸 = = =2 𝑡𝐽 = = =2
6 6 6 6
Variances:
26−10 2 11−1 2
𝜎𝐴 2 = ( ) = 2.672 = 7.13 𝜎𝐹 2 = ( ) = 1.672 = 2.78
6 6
18−8 2 3−1 2
𝜎𝐵 2 = ( ) = 1.672 = 2.78 𝜎𝐺 2 = ( ) = 0.332 = 0.11
6 6
6−4 2 3−1 2
𝜎𝐶 2 = ( ) = 0.332 = 0.11 𝜎𝐻 2 = ( ) = 0.332 = 0.11
6 6
14−10 2 5−3 2
𝜎𝐷 2 = ( ) = 0.672 = 0.44 𝜎I 2 = ( ) = 0.332 = 0.11
6 6
3−1 2 3−1 2
𝜎𝐸 2 = ( ) = 0.332 = 0.11 𝜎𝐽 2 = ( ) = 0.332 = 0.11
6 6
Table 2 shows the summary table on the expected times and the variance of the activities for
AUS Company project.
Activity a m b t 𝝈2
A 10 15 26 16 7.13
B 8 10 18 11 2.78
C 4 5 6 5 0.11
D 10 12 14 12 0.44
E 1 2 3 2 0.11
F 1 3 11 4 2.78
G 1 2 3 2 0.11
H 1 2 3 2 0.11
I 3 4 5 4 0.11
J 1 2 3 2 0.11
Start B G
E H
D
J Finish
F I
A
16
C
5
B G
Start 2
11
E
2
D H
12 2 J
Finish
2
F I
4 4
Step 4: Determine the earliest start time and earliest finish time using forward pass and the formula
EF = ES+t. (See Figure 3)
A 0 16
16
C 16 21
5
B 0 11 G 21 23
Start 2
11
E 12 14
2
D 0 12 H 23 25
12 2 J 25 27
Finish
2
F 12 16 I 16 20
4 4
Step 5: Develop the latest finish time and latest start time using the backward pass. (See Figure 4)
Figure 3
A 0 16
16 0 16
C 16 21
5 16 21
B 0 11 G 21 23
Start 2 21 23
11 5 16
E 12 14
2 19 21
D 0 12 H 23 25
12 5 17 2 23 25
J 25 27
Finish
2 25 27
F 12 16 I 16 20
4 17 21 4 21 25
Step 6: Compute for the slack of all activities using the formula provided below and identify the
zero slack to identify the critical path.
Slack = LS-ES=LF-EF
Table 3
Activity ES LS EF LF Slack Critical
Path
A 0 0 16 16 0 Yes
B 0 5 11 16 5 No
C 16 16 21 21 0 Yes
D 0 7 12 19 7 No
E 12 19 14 21 7 No
F 12 19 16 23 7 No
G 21 21 23 23 0 Yes
H 23 23 25 25 0 Yes
I 16 21 20 25 5 No
J 25 25 27 27 0 yes
Figure 4
Critical Path: A C G H J
A 0 16
16 0 16
C 16 21
5 16 21
B 0 11 G 21 23
Start 2 21 23
11 5 16
E 12 14
2 19 21
D 0 12 H 23 25
12 5 17 2 23 25 J 25 27
Finish
2 25 27
F 12 16 I 16 20
4 17 21 4 21 25
E(t) = tA + tC + tG + tH + tJ = 16 + 5 + 2 + 2 + 2 = 27
Let us determine what probability thus the project will be done given a 30-week deadline. First is
to determine the variance of the critical activities. We will only consider all the variance of
activities A,C,G,H, and I.
𝜎 2 = 𝜎𝐴 2 + 𝜎𝑐 2 + 𝜎𝐺 2 + 𝜎𝐻 2 + 𝜎𝐽 2 = 7.13 + 0.11 + 0.11 + 0.11 + 0.11 = 7. 57
𝜎 2 = √𝜎 2 = √7.57 = 2.75
Using z = 1.09 and the table for normal distribution, we will find that the probability of the project
meeting 30 weeks deadline is 0.3621 + 0.5000 = 0.8621 or 86.81%. Thus, even though activity
time variability may cause the completion time to exceed 27 weeks, there is an excellent chance
that the project will be completed before 30-week deadline.
Figure 5
27 30
| 0.5000 | 0.3621 |
Probability of AUS Company to the 30-week Deadline
Submitted by:
Anilao, Elijah Joyce
Base, Crissa Mae
Comiso, Ricardo Jr.
Formarejo, Christine
Pagana, Fionalyn
Sagarino, Sandra
Villadiego, Jizelle
BSA – II CA2A1