Professional Documents
Culture Documents
Precom & Commissioning Plan PDF
Precom & Commissioning Plan PDF
OWNER : Job No :
03-1202
Contract No. :
MALAYSIAN NPK FERTILIZER SDN BHD
MNFSB-01/03-MPP
PMC :
z
Doc No. :
REKAYASA REKMAL 1 of 14 0
PT REKAYASA INDUSTRI REKAYASA INDUSTRI MALAYSIA SDN BHD
SHEET 2 OF 14
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
DISTRIBUTION ORDER
Internal CONTRACTOR (by DDO): Internal CONTRACTOR (by Transmittal): External CONTRACTOR (by Transmittal):
DDO Attachment
Project Director KPO Copy(s) OWNER
Project Manager With Status for JPO 1 Copy(s)
Procurement Manager For Review SPO 1 Copy(s)
Project Control Manager For Info. H/O 1 Copy(s)
Construction Manager As a “CC”
QA/QC Manager
Engineering Manager SPO Copy(s) PMC
Project Engineer With Status for JPO 3 Copy(s)
Civil Lead Eng. For Review SPO 2 Copy(s)
Electrical Lead Eng. For Info. H/O 2 Copy(s)
Instrument Lead Eng. As a “CC”
Mechanical Lead Eng.
Piping Lead Eng.
Process Lead Eng.
SHEET 3 OF 14
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
TABLE OF CONTENT
1. SCOPE
2. ORGANIZATION
4. RESOURCES PLAN
APPENDIXES
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
1. SCOPE
The CONTRACTOR will perform and be responsible for all activities required during Pre-
Commissioning and COMMISSIONING. Procedures, organization, schedule, manpower
plan, tools and equipment, operating manuals, utility and power consumption plan will be
provided in details for the activities later.
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
2. ORGANIZATION
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
Pre-commissioning activities will be proceeded from Utility and Offsite FACILITIES, including
PFK Plant then Solid Raw Material Handling and Storage Area, Product Handling and
Storage, Main Process NPK Plant including Urea Evaporation Section, in-sequential. Raw
Water and Fire Water System will be the first energize/available FACILITIES. Then LP
Steam and Condensate System, Cooling Water System, HVAC System, and Compressed
Air System. These systems will be the most priority system for the whole Pre-commissioning
and COMMISSIONING activities. Raw Water will be as media for mechanical cleaning,
flushing, chemical cleaning, etc., Fire Water will be important FACILITIES to ensure safety
during Pre-commissioning, Cooling Water will be required for Main Process Equipments,
HVAC will be required for DCS installation and any instrument work in Central Control
Building/Room.
On the other hand, Pre-commissioning activities for Solid Raw Material Handling and
Storage will be executed in a little bit parallel with Utility & Offsite Facilities and Product
Handling and Storage.
The latest priority will be Urea Evaporation Section and Combustion Chamber Package
because the activities will require completion of other predecessor unit/system activity and
will be a little bit overlap with COMMISSIONING activities. Pre-commissioning activities for
the unit will be under supervision of PROCESS LICENSORS or Licensor’s specialist/
representative and their duty shall be extended until INNITIAL ACCEPTANCE.
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
As planned above, MECHANICAL COMPLETION will be are end of month 18th. At this time
Utility & Offsite FACILITIES including PFK FACILITIES, Solid Raw Material Handling and
Storage, Product Handling and Storage, and NPK Main Process Plant including Urea
Evaporation FACILITIES will be ready to operate as per defined design specification.
COMMISSIONING activities will be started from the beginning month 19 th and will be
completed on the end of month 20th. To avoid floating time, preparation for
COMMISSIONING is scheduled to be started from beginning of month 18th.
Preparation work will be started from the time when process water introduced in to
Scrubbing Section and Final Washing Section. Then adjustment for any parameter will be
done as soon as possible after completion of water introducing. In parallel with water
introducing and adjustment, NPK granule will be loaded/introduced in to Granulation Loop,
totally around 40 ton and will circulate in Granulation Loop equipment. Water circulation
and air dust system will be operated while loading and circulation to avoid dust emission to
environment. During water and solid circulation operating, final check for actual interlock
system, start and shutdown sequence, emergency shutdown, and setting some parameters
will be done to ensure COMMISSIONING operation.
INNITIAL ACCEPTANCE will be expected to be received from OWNER at the end of month
20th.
SHEET 8 OF 14
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
4. RESOURCES PLAN
Required skill manpower, suitable tools, proper equipment and any resources will be
provided by Subcontractors as it being included within subcontracting package scopes.
Based on Pre-commissioning Schedule, the anticipated pre-commissioning crews structure
will be as shown in below Table 4.1 Pre-commissioning Manpower Loading Plan of which its
number can be expanded particularly during peak period. This Table 4.1 of crew structure
are excluding CONTRACTOR’s engineers/supervisors.
CONTRACTOR will source requirement of experienced operators from NPK Plant Gresik,
Indonesia to execute Pre-commissioning activities and to train OWNER’s Operation and
Maintenance personnel. The duty of operators can be extended to cover COMMISSIONING
activities.
Provision of maintenance staff will be introduced during Pre-commissioning period, this will
be arranged by each related CONSTRUCTION Superintendent. The staff will rectify
problems, which appear during Pre-Commissioning.
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
CONTRACTOR will assign special experience operators from NPK Plant Gresik for
supervising the operation of Granulation Loop Equipment and Laboratory to ensure quality of
NPK granulation and will also serve as instructor/job trainers for OWNER’s Operators.
Manpower loading plan for COMMISSIONING activities will be as shown in Table 4.2 below.
NPK Main Process Area 3 Granulation Loop Oprs 1 persons each shift
including Urea Evaporation 3 Scrubbing Section and 1 persons each shift
Section Combustion Chamber Oprs
Laboratory 1 Laboratory Head
1 Laboratory Operators
CONTRACTOR will also assign Safety, Health, and Environment (SHE) Coordinator to
manage and coordinate safety aspect to ensure Pre-commissioning and COMMISSIONING
activities are executed in a safe manner in accordance with PROJECT SHE requirements.
The SHE Coordinator will ensure to timely obtain all required special permits and approvals
from authorities prior to taken any activity within PFK Plan such as hot tapping, instrument
and electrical wiring, flushing and blowing. SHE Coordinator will be assisted by three (3)
SHE officers and three (3) SHE man. The Coordinator will join in daily Pre-commissioning
and COMMISSIONING meeting to know the highlighted time by time Pre-commissioning and
COMMISSIONING activities status. In order to comply with Government Regulations and
SHE Plan and Procedure, the coordinator will conduct, arrange, sign, and announce SHE
aspect to everybody involved in COMMISSIONING work under the coordination with
OWNER’s SHE Coordinator/Manager.
SHEET 10 OF 14
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
The following are the outlined basic structure of Pre-commissioning and commissioning
procedures and its detailed procedures will be provided by CONTRACTOR six (6) months
prior to commencement of activities.
The procedure covers general requirements for flushing and blowing out for piping as a
part of pre-commissioning stage. The main objective of the work is to clean the lines
and equipment and to remove foreign materials such as debris, grit, welding spatters,
which may enter into or remain inside the pipe and equipment during construction work.
b) Disinfecting Procedure
The procedure covers requirements for disinfecting work for sanitary water system.
This work shall be carried out to make the system sanitary clean and to certify it to be
ready for use and safe for mankind.
SHEET 11 OF 14
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
The procedure covers the mechanical running test for all rotating equipment, i.e.
pumps, fans/blowers, conveyors, screens, elevators, crushers, etc. The main objective
of this work is to make sure that the rotating equipment could operate smoothly
throughout its range and maximum vibration level corresponding with the shaft’s speed
when normal and maximum load test is conducted on the equipment after installation at
site.
The procedure describes the operational tightness procedure for all equipment and
connecting line-work. During pressure test and flushing and blowing work, some
connections of lines and equipment are disconnected/dismantled and rotated for
installing temporary spools and some instrumentations and valves is removed for
safety reason. After completion of the pressure tests and flushing and blowing works,
all item of equipment and connecting line-work to be pressurized during operation shall
be tested to check the tightness of the system by using nitrogen, plant air, instrument
air, process air, CO2 or own fluid (service test)
The procedure covers the requirements for purging and venting work for natural gas
lines and ammonia lines system before introducing the fluid. The main objective of this
work is to purge the gas or water remains inside the pipe, which is possible to react or
cause a fire or other dangerous gases or compounds or other side effect, before the
fluid is introduced into piping lines and equipments. The work is carried out after
completion of restoration work.
The procedure covers the requirements for cooling down of ammonia service lines.
This work shall be carried out to make sure the gas or water remains inside the pipe
that may cause or react to other dangerous gases or compounds or other side effect
already removed and to pressurize and cool down the lines with ammonia itself
gradually.
The procedure describes the water and solid running test for each section of the
system in this plant. The plant consists of liquid circulation system and solid handling
system. The main objective of this work is to make sure each section of the system
could start and run separately and/or integrated before start up. All instrumentations
could be operated manually or automatically by Programmable Logic Control (PLC)
and Distributed Control System (DCS) from Central Control Room (CCR). The water
SHEET 12 OF 14
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
run of liquid circulation system is carried out by using water and the solid run of solid
handling system by using the NPK product itself. Before water and solid running test all
interlocking systems and rotating equipments shall be already tested completely.
d) Start-up Procedure
This document describe start-up operation procedure for NPK Plant 310,000 MTPY in
NPK Fertilizer Project, including plant preparation and observation, for
PERFORMANCE Guarantee formula. There are 14 step operation for plant start up
operation that consist of 8 step for plant preparation operation and 6 step for plant start
up. Some specification, observing, and controlling work which are described, will be
followed.
Raw Material
o Phosphate Rock, approximately 9565 Tonne
o MOP, approximately 16447 Tonne
o Urea Granules approximately 3216 Tonne
o MAP/DAP 6334 Tonne
o Liquid Ammonia, approximately 634 Tonne
o Urea Solution, approximately 12977 Tonne
o Sulphuric Acid, approximately 1673 Tonne
o Liquid Coating Agent (LCA), approximately 238 Tonne
Utilities
o Raw Water, approximately 77064 Tonne
o Steam, approximately 16410 Tonne
o Natural Gas, approximately 656 MSm3
o Diesel Fuel, approximately 25600 Lt
o Cooling Water, approximately 842400 Tonne (Circulation)
o LP Condensate Flushing, approximately 2246 Tonne
o Compressed Air, approximately 1044 MS/m3
o Nitrogen, approximately 31 Bottle
o Power, approximately 9389160 kWh
Chemicals
o Cooling Water Dosing Chem., approximately 215 Lt (Liquid), 6 bottle (Cl)
o Disinfectant Chemicals, approximately 6 kg
Consumables
o Oxygen, approximately 6 bottles
o Nitrogen, approximately 7 bottles
o Natural Gas, approximately 4 bottles (portable)
SHEET 13 OF 14
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN
Total consumption is calculated based on three (3) months of Pre-commissioning period and
two (2) months of COMMISSIONING period.
Detail consumption schedule for Utility, Raw Material, and Consumable during Pre-
commissioning and COMMISSIONING are described in Appendix-4
Classroom and job training by PROCESS LICENSORS shall be required to train OWNER’s
Operation and maintenance personnel by highlighting operation and maintenance aspects.
SHEET 14 OF 14
00
NPK-C-00-000-PE-024
PRECOMMISSIONING AND COMMISSIONING PLAN