MANUFACTURER'S NAME & ADRESS QUALITY ASSURANCE PLAN REF.

ATSPL/QAP/BFV-2020/19-20-0069-4
AQUAVARI TECHNICAL SOLUTIONS PVT LTD FOR DUAL PLATE CHECK VALVE (DPCV) DATE 29-01-2020
Gat No. 49 & 58, Industrial Estate, Palus, CLIENT CAUVERY NEERAVARI NIGAM LIMITED PO NO :- PO/ACPL/Valves/953
Maharashtra 416310 (INDIA) PROJECT SUTTUR STAGE - I & II
EPC CONTRACTORS AMRUTHA CONSTRUCTIONS PVT LTD
900 mm DPCV PN2.3 - 3 NOS REV 0
SIZE 900 mm DPCV PN3 - 3 NOS PAGE 1/1
1000 mm DPCV PN3 - 4 NOS SPACE FOR NOTES-
MANUFACTURER STANDARD API 594 MATERIAL - CAST STEEL (WCB)
REFERNCE DRG NO AQ/QUOAT/19-20/0069-4
SR NO COMPONENT AND OPERATION CATEGORY TYPE OF CHECK QANTUM OF CHECK REFERENCE DOCUMENT ACCEPTANCE STANDARD FORMAT OF RECORD AGENCY REMARKS
1 RAW MATERIAL P W R
Major MECHANICAL ONE PER HEAT RELEVANT MATERIAL SPECIFICATION / DATA SHEET DRG Foundary MTC 2 2 1,2
1.1 Body & Doors Casting
Major CHEMICAL ONE PER HEAT RELEVANT MATERIAL SPECIFICATION / DATA SHEET DRG Foundary MTC 2 2 1,2
Major MECHANICAL ONE PER HEAT RELEVANT MATERIAL SPECIFICATION Test Report 2 2 1,2
1.2 Hinge Pin / Stop Pin Major CHEMICAL ONE PER HEAT RELEVANT MATERIAL SPECIFICATION Test Report 2 2 1,2
Major UT for dia 50mm & above 100% ASTM A388 SEE NOTE -1 NDT Report 2 2 1,2
Major MECHANICAL ONE PER HEAT RELEVANT MATERIAL SPECIFICATION Test Report 2 2 1,2
1.3 Body Seat Ring
Major CHEMICAL ONE PER HEAT RELEVANT MATERIAL SPECIFICATION Test Report 2 2 1,2
2 IN-Process inspection
Body, Disc & Shaft
2.1 Major Visual & Dimension 100% Component Drg Component Drg Inspection Report 2 2 2
Casting
3 FINAL INSPECTION
Major Overall Dimensions & Visual 100% Approved GAD Approved GAD Inspection Report 2 1 2
100% 2 2 -
Major Body Hydro Test Approved GAD / Test Procedure No leakage Inspection Report
3.1 COMPLETE ASSEMBLED VALVE 10% 2 1 -
100% 2 2 -
Major Seat Hydro Test Approved GAD / Test Procedure No leakage Inspection Report
10% 2 1 -
Shed Verification & DFT
3.2 Painting Major 100% Approved GAD Approved GAD Inspection Report 2 2 -
Measurment
As per Packing Slip / BOM
3.3 Packing Major 100% Plant std Plant std Packing slip 2 2 2
Verification
LEGEND : 1 - CAUVERY NEERAVARI NIGAM LIMITED
P: PERFORM 2 - VALVE MANUFACTURER
R: REVIEW
W: WITNESS
FOR : CAUVERY NEERAVARI NIGAM LTD (CNNL) FOR : AQUAVARI TECHNICAL SOLUTIONS PVT LTD
Reviewed : Approved by : Prepared by : Approved by