Actual

No List Building Start Finish


1 GT CCWH Exchanger
Foundation Work 15-Oct-18 14-Nov-18
2 N2 Gas Storage Area
Foundation Work 4-Jan-19 12-Jan-19
SS Erection 21-Mar-19 23-Mar-19
Architecture Work 15-Jun-19 On Progress
3 H2 Plant House
Foundation Work 28-Oct-18 21-Nov-18
SS Erection 21-Feb-19 24-Mar-19
Architecture Work 24-Mar-19 On Progress
4 Auxiliary Boiler
Foundation Work 5-Dec-18 20-Jan-19
5 HRSG
Foundation Work 10-Oct-18 1-Dec-18
6 By Pass Stack & Exhaust Duct
Foundation Work 26-Sep-18 27-Oct-18
7 GT Foundation
Foundation Work 15-Sep-18 14-Oct-18
Pedestal & Column 3-Nov-18 4-Nov-18
Top Deck 8-Nov-18 4-Dec-18
8 Fuel Gas Treatment Plant
Foundation Work 2-Sep-18 17-Sep-18
9 GT Electrical Building
Foundation Work 4-Oct-18 8-Nov-18
SS Erection 19-Nov-18 7-Mar-19
Architecture Work 6-Feb-19 On Progress
10 Administration Building
Foundation Work 16-Nov-18 5-Dec-18
Upper Structure Work 25-Nov-18 4-Mar-19
Architecture Work 14-Feb-19 On Progress
11 Central Control Building
Foundation Work 17-Sep-18 19-Nov-18
SS Erection 15-Dec-18 7-Mar-19
Architecture Work 29-Jan-19 On Progress
12 BONNA Pipe
Road Crossing to Condenser Area 1-Dec-18 23-Jun-19
Road crossing to Outfall 2-May-19 On Progress
Intake Area to Road Crossing 26-May-19 On Progress
13 Condensate Pump Pit
Foundation Work 4-Feb-19 20-Mar-19
14 Chlorination Building
Foundation Work 16-Oct-18 16-Jan-19
SS Erection 18-Apr-19 1-Jul-19
Architecture Work 22-Apr-19 On Progress
15 CW Intake Pit
Foundation Work 28-Oct-18 6-Dec-18
Wall Work 19-Nov-19 29-Mar-19
Top Slab 7-Mar-19 29-Mar-19
16 CW Outfall
Foundation Work 12-Feb-19 7-Apr-19
Wall Work 24-Feb-19 16-May-19
17 ST Transformer
Foundation Work 8-May-19 On Progress
Wall Work 15-May-19 On Progress
18 Water Tank
Foundation Work 22-Nov-18 5-Feb-19
19 Waste Water Pit
Construction Work 16-Oct-18 21-Nov-18
20 ST Foundation
Foundation Work 17-Sep-18 19-Dec-18
Pedestal & Column 5-Dec-19 16-Jan-19
Top Deck 23-Jan-19 26-Feb-19
21 Waste Water Treatment Plant
Construction Work 12-Jan-19 20-Jun-19
22 TG Building
Foundation Work 13-Sep-18 22-Jan-19
SS Erection 28-Dec-18 20-Apr-19
Architecture Work 24-Feb-19 On Progress
23 Cable Trench
Construction Work 16-Oct-18 8-Jul-19
24 Soundproof wall
Foundation Work 12-Sep-18 6-Oct-18
SS Erection 6-Dec-18 4-Mar-19
25 GT Transformer
Foundation Work 8-Dec-18 5-Jan-19
Wall Work 2-Jan-19 13-Mar-19
Remark

Will be Finished on 31 July 2019

Will be Finished on 15 Sept 2019

Will be Finished on 31 July 2019

Will be Finished on 15 Nov 2019

Will be Finished on 15 Sept 2019

Will be Finished on 13 Aug 2019


Will be Finished on 15 Oct 2019

Will be Finished on 15 Nov 2019


Will be Finished on 1 Aug 2019
Will be Finished on 30 Nov 2019

Will be Finished on 15 Nov 2019


No List Building Percentage
1 HRSG
Concrete Structure 100%
2 TG Building
Concrete Structure 100%
SS Erection 100%
Architecture Work 55%
3 CW Intake Pit & Pump House
Concrete Structure 100%
SS Erection 100%
Architecture Work 20%
4 Water Pump Shed
Concrete Structure 100%
SS Erection 100%
5 Chlorination Building
Concrete Structure 100%
SS Erection 100%
Architecture Work 5%
6 Water Treatment Electrical Building
Concrete Structure 100%
SS Erection 100%
Architecture Work 80%
7 GT Transformer
Concrete Structure 100%
8 Fuel Gas Treatment Plant
Concrete Structure 100%
9 CW Outfall
Concrete Structure 100%
10 Underground Bonna Pipe
Concrete Structure 60%
Bonna Pipe Installation 60%
11 Central Control Building
Concrete Structure 100%
SS Erection 100%
Architecture Work 60%
12 Administration Building
Concrete Structure 100%
Architecture Work 55%
13 ST Transformer
Concrete Structure 40%
14 ST Common Electrical Building
Concrete Structure 100%
SS Erection 100%
Architecture Work 15%