Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 44

RELEVANCE OF PREFABRICATED CONSTRUCTION IN

RESIDENTIAL BUILDINGS OF KERALA


Amith Krishnan
Guided By;
Ar. Anjith Augustine
Assistant Professor

Abstract:

Pre-fabricated construction is now rapidly growing in Kerala’s context. People are attracted
towards steel and pre-fabricated structure mainly because of low budget and fast
construction. This research shows how the aspect of conceptual design is achieved when using
pre-fabricated material. The idea is to study the aspects like space optimization, aesthetics
and visual impacts, flexibility and use of space by using steel and gypsum in residential building
and comparing with the conventional residential buildings of Kerala. Through this research in
looking into only budgeted homes under 2500.00soft.The construction process is studied
through books and internet and two literature case studies are also conducted to understand
why steel and gypsum is rapidly used in construction industry. The primary and secondary data
collected from about literature case studies and literature review. For the final conclusion of
research is done by doing 4 live case studies which 2 project are under the pre-fabricated
construction method and 2 of them for conventional construction method. Each project for
the live case study is taken from the same location and each having the same design
requirement. After doing the live case study I come to conclusion by doing interviews with
designers, contactors and client and users. In interview I have prepared several questions, for
answers of each questions I have rated marks out of 5. This helped me to conclude answers
for my research question.

After visiting the buildings and interviewing the designers and the users of the buildings, I
came to a conclusion that gypsum and steel is a very good option to consider for the residential
buildings along the context of Kerala. For building owners if the construction is finished as fast
as possible it will be cost saving for them.

But when going through the other aspects of steel and gypsum which will be sometime not
space optimization, aesthetics and visual impacts, flexibility and use of space.

1
these currently faced issues to a certain
extend. (Why Build Modular, 10 Oct 2013)
INTRODUCTION Modular and prefabricated construction is a
The material cost and the construction costs new method introduced in Kerala in past 5
are increasing in Kerala these days and the years. Modular construction is commonly
availability of material is reducing. So there is known as pre-fabricated construction.
an increasing demand in the construction (Modular construction , 2 Jan 2014)
sector for an alternate method which solves
ERIALS RATE ON 2019 RATE O

Semi Wire cut brick 12.0 per piece 8.0 per piece
9”x 4”x3”
Solid concrete blocks 28.0 per piece 20.0 per piece
16”x8”x4”

Binding wire 16 gauge 66 per kg 55 per kg

Steel TMT Bars 53 per kg 46 per kg

M-Sand 14000.00 for 200 12000.00 for 200 CFT


CFT
Plastering sand river 28000.00 for 500 22000.00 for 500 CFT
sand CFT
Metal 4 mm 11000.00 for 200 6000.00 for 200 CFT
CFT
Cement 406.00 for 50kg 350.00 for 50kg

Table 1 Approximate material cost as per 2019 and2016


(From interview with contactor Mr.Mahesh and Mr.sanju from Thrissur)

MATERIAL COST CAMPARISON OF PAST


4 YEARS
Rate on 2019 Rate on 2016
140
110
70
66

60

55
54

53
46

40
35
30
28
20
12
8

1
Background and Context How these aspects can be compared with pre-
fabricated and conventional construction
Why pre-fabricated construction?
method?
Reduction in construction time: Either the
structure can be constructed cast in situ or
factory made. Commonly the pre-fabricated Research Sub questions
structures are made off site, by this can reduce,
1) How does steel and gypsum can
and save large amount of construction time in
site. (W; Why Build Modular, 10 Oct 2013) become a major construction material
for the residential scale?
This result in saving all around from inventory
to construction of temporary accommodation, 2) What are the merits and demerits of
and factors such as interruptions and dust are steel and gypsum over the
eliminated. conventional method?
With reduce construction the cost is 3) How does these materials help in
significantly reduced. Pre-fabricated structure Space optimization, Aesthetics and
have high level of automation which make cost Visual impacts, Flexibility and use of
effective than traditional construction
space? In comparison with the
methods. (Alatza, 1 jan 2014)
conventional method.
In case of durability and strength, the buildings
are durable and lightweight due to the large 4) What will be the difference in cost and
amount of use of steel, which is considered as time in these construction method?
strong building material. (Why Build Modular, study through comparing the cost of
10 Oct 2013) different materials and time taken for
These structures are against weather which the different works in these methods
leads to wind storm and rain, and commonly of construction
seen defect cracking also be reduced. (W)
(Alatza, 1 jan 2014)
Aim and objectives
Research
By doing a research I am aiming to study and
Questions understand how using steel and gypsum as a
major structural element in residential building
1) Understanding opportunities and helps in design flexibility, Space optimization,
constrains of prefabricated Aesthetics and Visual impacts, When
construction in Kerala? - A feasibility compared to the conventional structured
study on residential application in residential buildings. The study will be limited
context of Thrissur. to three factors on conceptual design stage,
2) which is space optimization, aesthetics and
 Space optimization visual impacts and flexibility of use and use of
space.
 Aesthetics and Visual impacts. The economical aspect is also a major factor
that
 Flexibility and use of space.

should be studied, but a brief study on the economic factors while the construction process is also
considered.
Objectives:

1
1) To find how steel and gypsum become construction type. Few architects in Kerala
as a major construction material in practice the particular construction methods
residential building over the and majorly civil engineers and contractors
conventional method. practice the method. Therefore, the data
2) To find the different advantages and produced is collected from contractors and
disadvantages this method of civil engineers.
construction
3) To find the efficient method of More than live case study I have interacted
construction by looking at the aspects with 5 architects in kerala to understand their
of Space optimization Aesthetics and opinion about the particular type of
Visual impacts. Flexibility and use of construction. As limitation to this my result and
space. conclusion for this interaction will be only
based on their opinion.
Even though the major attention of the paper
will be on the conceptual design analysis, the
Scope, limitations and significance
financial aspects during the construction
Pre-fabricated construction is a vast topic. In process will also be studied, in a scale, which
this particular type of construction there are will give a brief idea how steel, and gypsum
various methods. In addition, various factors residences differ from conventional typology
affect the particular type of construction. of residences. The study will be limited to a
Here I am studying how to prefabricate specific building typology, which are small
residential building with steel gypsum/ALC residences under 2000.00 sqft within the state.
panels. The particular type of contraction with
steel is now fully fledged in the commercial LITERATURE REVIEW
sector of Kerala. Gypsum and steel are now
widely available in Kerala form manufactures
like FACT, so the availability of material will not This chapter explores the current theories and
be limitation in this method. Here I am looking literature on the prefabricated construction. It
in to how these materials can change the begins with an overall understanding
typology of traditional construction method. prefabricated construction with in the world.
The study will be much of a qualitative analysis Further, the different types of prefabricated
and comparison of buildings, which is construction and their advantages and
constructed, in both traditional and disadvantages are explored and studied about
prefabricated method in all over Kerala.In GFRG panels, Steel structures and ALC panels.
addition, the study is dealing with use, types, The relevance of prefabricated construction in
Quality, time and the importance in future
residential buildings of Kerala is examined in
years
the background of the research context.
I am only looking through three factors, which
are space optimisation, aesthetics and visual Prefabricated structures
impact and flexibility of use and optimisation Prefabricated construction is a process in
of space, which are three factors that affect the which sections of modules of the edifice are
conceptual design analysis. In addition, the assembled at a remote location, and then
study will be on buildings, which come under transported to the building site. This particular
the residential buildings within the state. construction method is very cost-effective
As the limitation to the topic, am not dealing (Design in Modular Construction, 6 Mar 2017)
with the structural analysis of the particular and often makes it possible to complete

a building project in as much as half the time Mar 2017)Prefabricated construction is


required for methods that are more commonly employed with the construction of
traditional. (Design in Modular Construction, 6

1
new homes; the strategy can also be used with various quality checks from the factory itself
other buildings. (A, 1 Mar 2011) and thereby can create consistent quality. (A, 1
Mar 2011).
At the site, the modules are unloaded, with Reduce site disruption:
heavy machinery, and connected to form a Since many components of a building are done
single building. Along with the fast assembly, in the factory, so there is significantly less work
prefabricated construction can often save a in final construction site. This limits the
great deal of money. (Alatza, 1 jan 2014) By disruption of traditional jobsites that suffer
using normal patterns, the building materials from noise, pollution, waste and other
are pre-cut at the factory .This eliminates a common irritants. (A, 1 Mar 2011) This
great deal of the waste in materials that can approach to construction provides a far more
occur during the process of building. As a efficient productivity, and eliminates
result, a prefabricated house with three distractions and interference that are typical of
bedrooms have less cost than a three-bedroom construction sites. (Design in Modular
house that is constructed in conventional Construction, 6 Mar 2017)
method. (Alatza, 1 jan 2014). Shorter construction time:

One other benefit of prefabricated Since the construction materials and the pre-
fabricated materials are portable, it can reduce
construction is the energy efficiency of this
type of building typology . Because the sections the construction time. (A, 1 Mar 2011) The pre-
of a home are precut, and they are fit together, fabricated construction takes half the time of
traditional conventional methods. This due to
to form a complete home. This means less
better planning, elimination of site weather
effort to heat and cool the space, resulting in
factors, quicker fabrication as multiple units.
lower utility bills. (Design in Modular
(A, 1 Mar 2011)
Construction, 6 Mar 2017)
Safety in construction :
Prefabricated construction in Kerala:
Since the material availability and skilled labor Since most of the works are done from factory,
is reducing in the construction field of Kerala, there is less risk from moisture environmental
more advanced and budgeted constriction hazards and dirt. An indoor construction
methods wanted to be introduced in the environment presents considerably less risks
construction field of Kerala. By this can change for accidents and other problems. There are
the present scenario of construction and can strict factory processes and procedures that
improve the construction quality with in short protect the worker from on-the-job injury. At a
time period. (Why Build Modular, 10 Oct 2013) construction site, workers are subjected to
Flexibility in design: weather-related conditions, changing ground
Prefabricated construction can easily conditions, wind and other crewmembers will
demolished and shifted to other sites. This will create lot of problems for workers.
reduce the demand for materials and create
more energy saving and can reduce time
required for construction. Modular
construction create more flexibility in
architectural design and structural design. (A, 1
Mar 2011)
Consistent quality:
The quality will change according different
contractors. In pre-fabricated construction the
works are done form the factory and which are
executed in site. Machine do most of the works
so it is giving a consistent quality in work. The
pre-fabricated materials are carried out

2
Literature Review on Gypsum inside the enterprise, is the name given to a
new constructing panel product that is
Introduction
fabricated from gypsum plaster and
The glass fibre reinforced gypsum is GFRG. (S. strengthened with glass fibres. GFRG is of
Vishnu, 11 Nov 2018 ) It’s far the name of a specific relevance to India. There’s a
brand new building panel product extraordinary need for price-effective mass-
manufactured from gypsum plaster with glass scale low-priced housing wherein gypsum is
fibres and it's also referred to as fast wall in the amply available as an industrial derivative
industry. (Modular construction , 2 Jan 2014) waste. The product is not most effective green
This product is suitable for speedy mass-scale or inexperienced, however additionally
building creation, became at first evolved, and resistant to water and fireplace. (S. Vishnu, 11
was used in view that 1990 in Australia. Nov 2018 )
(Eldhose M Manjummekudiyil, March
2015)The product isn't best ecofriendly ,
however is likewise proof against water and
fireplace. (Modular construction , 2 Jan 2014)
(S. Vishnu, 11 Nov 2018 )
2.1.1 Glass fibre reinforced gypsum
GFRG panels are currently manufactured with
a thickness of 124 mm, a length of 12m and a
top of 3m. (Eldhose M Manjummekudiyil,
March 2015)Although its important
application is in the construction of wall, it
could additionally be used in ground, and roof
slabs in mixture with the bolstered concrete.
The panel includes cavities that can be packed
with concrete and reinforced with steel bars to Figure 1 load carrying capacity of GFRG panels(S.
provide electricity and ductility. The panels can Vishnu, 11 Nov 2018 )
be unfilled and partly filled or fully full of
reinforced concrete. (S. Vishnu, 11 Nov 2018 )
2.1.3 Project Details about GFRG
The principle distinction among dewatered A storey building in Kochi is chosen, carried out
and non-dewatered GRC is the difference in by using a Kerala based enterprise Sheghram
density and it has effects. First of all, even Nirman Pt. Ltd. the construction approaches
though the fibre content by way of weight is and strategies are determined, that are getting
the identical and higher density of the used for GFRG
dewatered board gives a higher fibre extent
fraction giving better strengths. Secondly, the
dewatered board has higher compaction and
reduced porosity, which offers higher
fibre/matrix bond electricity. (S. Vishnu, 11
Nov 2018 )
2.1.2 An overview of GFRG wall panel systems
Glass fibre reinforced gypsum, abbreviated as
GFRG, which is better referred to as rapid wall
panel’s construction, the complete cost and building. A detailed case study of contrast
estimation of constructing, applicable among the traditional constructing and GFRG
techniques used for panel manufacturing, panel constructing in the most important
analysis, and duration of the each detail of

3
factors is made.. (Why Build Modular, 10 Oct 5. Less building weight, thereby reduction in
2013) design for seismic forces and savings in
foundation in multi-storeyed buildings.
. Cost
6. 8 to 10 storied buildings can be designed
2. Time using GFRG panels and without the need of
3. Quality conventional RC beams and columns.

4. Quantity 7. Very good finishes of GFRG buildings: use of


factory made panels for all the walls, floors,
B. Type of Building: two Storey Building and staircases.
C. Type of Construction: Rapid wall 8. Less CO2 is emitted compared to other
construction with GFRG panels conventional building materials.
D. Area: 1500 Sq.ft 9. Better thermal comfort inside GFRG building
(Eldhose M Manjummekudiyil, March 2015) than conventional buildings.
10. Since gypsum is a hard material, there is no
creep in the GFRG panel, so it is major asset of
this type of construction.
2.1.4 Applications of GFRG 11. In this Rapid wall system, there is no
GFRG building panels are generally used in the volume change even at high temperature.
following ways.
12. The movement of moisture through
1. As load bearing walls in buildings, to resist concrete structures is dampness. There is no
the gravity load. dampness problem in GFRG panel wall system.

2. As partition or infill walls in multi-storeyed 13. The durability of this rapid wall system is
framed RC structures. same as the RCC construction.

3. as compound walls in combination with (Eldhose M Manjummekudiyil, March 2015)


minimum quantity of concrete. 2.1.6 Disadvantages of GFRG
4. As shear walls, resist both gravity load and 1. You do need some expertise in order to
lateral load from earthquakes and wind as make a house using this technology. The
walls of lift well and parapet walls. handing, fixing and equipment required for
these panels is different from conventional
5. As floor slabs / roof slabs, pitched roof slabs style. Although it is not very difficult to learn,
and staircase waist slabs and mid-landing the right techniques and it will eventually take
slabs. time for becoming and industry trend (Musa,
13 July 2016)
2.1.5 ADVANTAGES OF GFRG
1. High speed of construction. 2. The Panels are customized according to the
design and drawings of your house when
2. More carpet area for the same built-up area- manufactured. Unfortunately, you cannot
thickness of wall panels is only 124mm. make many changes during the fixing stage.
3. Less embodied energy and carbon footprint Hence planning is important. In addition, the
has significant reduction in use of steel, doors, windows and other openings are made
cement, sand, and water. by cutting through the panels, hence the
planning for placing doors and windows need
4. Less cost of construction and savings in to be extensive. (Eldhose M Manjummekudiyil,
materials and no cement plastering. March 2015)
3. In India, if you are looking to do a
construction in a normal populated area, it is

2
very likely that your plot is already surrounded Literature review on steel
by built house. The GFRG technique needs
This is the maximum seen shape of creation for
empty spaces around the plot so that cranes
can be placed while fixing panels. In addition, steel buildings. it is so named for the reason
the panels need special care while storing that the profile of the metallic beam appear to
them and need more space as compared to be a letter "I", solid out of steel like a railroad
cement/blocks. These two factors make it (only tons bigger). This tool is likewise known
difficult for a full-scale implementation in India as "inflexible frame" or "pink iron" metallic
Empty space to store and move Panels is building. A metal main body truss is the help
needed. (J) for the constructing. Each truss includes four
sections: sidewall sections and roof sections.
4. The fact that panels are specifically made
for a design and is transported from factory, After assembly on the ground, every solid
the price of each type of panel goes done metallic "I" beam truss is raised after which
significantly only when used on a large scale. added down (or bolted) to the concrete basis.
Comparatively you can save 25–30% compared An everyday spacing among trusses is usually
to that of conventional building method and 25-30 ft (6-10 meters). (Pande, 5 May 2016)
more if used on large scale. 2.2.1 Advantages of steel i beam buildings
(Eldhose M Manjummekudiyil, March 2015) * Common type of building system, generally
readily available.
2.1.7 Conclusion about gypsum
From this, we finish that conventional buildings * A common building system to most in the
are extra high-priced when as compared to construction/contracting/steel building
panel gadget. The panels has properly business.
existence span as identical as concrete * Quick assembly and erection
systems. Nowadays using panels for creation is
evolving regularly. Still most people aren't * Wide variety of colours available
used to this form of creation practices for * Few width limitations, that is, you can do
residential homes. From this, able to deliver huge "monster" type buildings with clear span
some attention approximately the widths of 100 to 200+ feet (30-60 meters).
construction of panel systems approximately
the price, time control, useful resource * Can be cost effective
allocation and exceptional and amount of
* Can accommodate higher load requirements
GFRG. (A, 1 Mar 2011)
* Generally no interior support posts or
GFRG can be efficaciously used for the whole
columns needed.
superstructure of buildings, such as all walls,
slabs, staircases, parapets, and many others. * Low roof slope makes the profile less
This constructing system has many benefits obstructive
over traditional buildings. GFRG buildings have
the ability to satisfy the challenges of * Does not need a slab floor, can be installed
presenting fast cheap mass housing. This is an on foundation piers (for example, a riding ring
green and sustainable constructing device, that would not have a interior concrete slab
which uses recycled business waste gypsum or floor) (E, 11 Jan 2011)
natural gypsum and minimising using cement, 2.2.2 Disadvantages
steel, sand, water and labour enter. This
* Usually limited to a simple "box" shape with
technology is now gaining reputation in India
little or no roof pitch (slope) or unique
and all over other Asian nations. (E, 11 Jan
configurations beyond a square or rectangle,
2011)
and usually with no exterior options other than
steel sheeting (usually what we see around.)

3
* Usually requires a crane or heavy apparatus, * Some steel I-beam building systems aren't
and sometimes on-site welding, depending on really designed for the "do-it-yourself" market
the size of the building and the degree of pre- (especially large buildings), but are presented
engineering done by the builder. as such
* Some systems need that insulation be done * May be required to pre-drill all the holes in
only at the time the building is erected. If the exterior steel sheeting for the attachment
fiberglass bat insulation is used (this is the of the steel panels to the side girts and roof
most common method) then some of R-value purlins
of the insulation is lost at all the compression
points since the fiberglass insulation is * Many are sold through broker (which is
perfectly OK -- just make sure you know who
sandwiched between the trusses and the
outside sheeting. you are dealing with and exactly what you are
buying.) (E, 11 Jan 2011)

Figure 2 Forces experienced by structures(Pande, 5 May 2016)

Figure 3 Gravity and wind loads taken by steel structures (Pande, 5 May 2016)

4
2.3 Literature review on ALC panels thicknesses, are also utilized in load-bearing
ALC Panel – Autoclaved lightweight Concrete capacities and are commonplace in
Panel is the following technology flexible commercial and industrial applications. ALC
inexperienced constructing material of desire Panels, additionally known as “units” are
for constructing community, which comes with stacked the use of skinny-set mortar, as
a number of Technical and useful blessings that opposed to the conventional cement-based
trigger a love for this cloth among the creation mortar used in CMU construction. (E, 11 Jan
specialists and workers. (W) The fabric is 2011)
appropriate and proved to be a tremendous 2.3.1 ALC Panels
constructing fabric for structures consisting of
residential, commercial, and business and Due to ALC’s layout flexibility and mixed
warehouse buildings, inns, faculties and structural and insulation additives, a whole
hospitals, and so on. In any terrain and all shape can be constructed the usage of the only
climatic situations. it is used for each outside fabric. outside surfaces can be finished with
and internal partitions, load bearing and non- skim coat, conventional veneers or siding,
load bearing partitions, basement walls, infill while interior partitions may be skim coated,
partitions to framed structures, celebration painted, or left unfinished, similarly to
partitions, fire break partitions, etc. It’s also conventional sheet rock finishes. (E, 11 Jan
used as a precast ground/ decking / roof. (E, 11 2011)
Jan 2011)
Further, ALC is easy to use and can be cut and
manipulated with ordinary wooden-working
tools. ALC panels are made With cement, lime,
ALC Panel Product kinds: ALC, unlike traditional Silica Sand as raw materials, adopting -manner
concrete masonry units (“CMU”), is a solid and welded metallic reinforcement mesh
panel /cloth gadget with integrated insulation (reinforcing bar) processed through special
and structural components, and is to be had in anti-rust liquid, produced in high temperature,
a selection of products that can be utilized in high stress and steam curing, it’s a type of
each load and non-load-bearing programs. (E, porous silicate plate of high performance, and
11 Jan 2011) complete load bearing has many incomparable performances of good
applications, however, are confined to low- fire-resistance, fire prevention, sound
upward thrust creation, although cladding and insulation, heat insulation, thermal insulation
large panels are to be had to take advantage of and so forth.
ALC’s insulate, fireplace proofing, and other
advantages on mid- and excessive-upward (DLC Limited site) (Design in Modular
thrust initiatives. Moreover, the big wall, Construction, 6 Mar 2017)
ground, and roof panels, measuring up to ten
feet lengthy, 2 toes extensive, and in diverse

1
`
Figure 4 ALC panels ready for transportation in plant in Chennai (DLC Limited site) (Eldhose M
Manjummekudiyil, March 2015)
the constructing in the long run. (Eldhose M
Manjummekudiyil, March 2015)The products
2.3.2 Advantages of steel ALC panels are tested and authorized through the
The usage of the ALC, the construction work renowned laboratories like SGS, TUV, and
may be elevated to obtain a more quantity of SETSCO….and so on, which isn't the case in the
time performance. By using the proper tools traditional constructing fabric. (Ajay Patre and
the construction can be mechanized to growth Laxmikant Vairagade, 2014)
the labour efficiency and faster creation.
(Eldhose M Manjummekudiyil, March 2015) Accelerated comfort and capability

A higher hearth score of three-four hours can Massive size of the panels assist do away the
be done for the buildings constructed using construction with much less quantity of joints.
ALC. (The R cost is 1.2 in keeping with inch and Due to the mild weight nature, much less
as a result a four inch or 100mm thick ALC manpower and their attempt is required for
Panel wall could gain an R fee of four. Eight construction. (Eldhose M Manjummekudiyil,
whereas the identical 4inch Concrete wall has March 2015)
an R value of simplest 2. which results in an
True Workability – approach operating on
ideal thermal insulation, that is 6 to 10 times
conduits and fixing service lines etc becomes
better than normal concrete. This enables
easier with this product.
keep on the strength fee notably. (Ajay Patre
and Laxmikant Vairagade, 2014) The reinforcement with Galvanized steel mesh
gives additional power to the panels
Forty-forty eight dB of sounds are filtered by
means of the ALC panels, which makes it Long sturdiness: proof against rot or pest, and
certainly acoustic. Perfect for resorts, this material has been in use for over eighty
hospitals, classified ads and multifamily. years (Eldhose M Manjummekudiyil, March
2015)
The lightweight nature of this product helps
reduce the dead load of the building As this cloth has a high load-bearing electricity
considerably. The density of this material is – it becomes the selection for all sort of
1/4th of Concrete. partitions: external and internal, load bearing
and non-load-bearing, basement, and fireplace
No Air Cracks inside the completed homes,
ruin walls … and many others. (Ajay Patre and
which reduces the general protection costs for
Laxmikant Vairagade, 2014)

1
This is an environmental pleasant constructing of walls: outside and internal, load bearing and
material as it's miles non-poisonous. The non-load-bearing, basement, and fire break
wastage is minimal and negligible and the walls … and so on.
whole fabric is reusable and recyclable.
(Ajay Patre and Laxmikant Vairagade, 2014)
As this fabric has a excessive load-bearing
strength – it becomes the selection for all kind
and my personal observation I came to a
METHODOLOGY concluded the study.
The method I followed during this
Overview:
process is explained in this chapter. Firstly I
started with getting a brief idea on how steel 1. Secondary data collection
and gypsum/ALC structures are designed,  Literature case study about
fabricated and erected, and also various steel and gypsum residential
methods in constructing these structure. This building.
study was to build a base knowledge about my
 Finding how does the steel
topic so that all his homework will help me for
and gypsum work as a major
further study and interviews. This base study
construction material and its
was done from reading books, eBooks and
advantages and
construction videos on internet. The second
stage is doing case studies, in which literature disadvantages over
case studies comes first, I opted to finish the conventional method.
literature case studies first because all these 2. Primary data collection
work helped me to build a basic knowledge on  Questionnaire preparation
the construction techniques of steel from the inferences of
structures, which later helped me for easy literature review.
communication with designers and labours.  Interactive section with
After finishing the literature case studies contractors and engineers.
comes the live case studies. For that, first I  Live case studies of selected
identified the buildings which came under my
on both conventional and
scope and shortlisted it into three buildings. A
prefabricated method.
questionnaire was prepared for both the
 Online interaction with
designers and the occupants for the structure
which will ease the data collection. And by company managers of
schematically analysing and comparing the particular companies and
data collected from the designers, occupants practicing engineers.
 Interactions with occupants
of these case studies.

2
Table 2 Methodology
Data sources and data types pre-fabricated in which one
is a renovation project and
Secondary data collection
two case study for
 Literature cases studies
conventional method
1) Residence for
 One literature case
Mr.Rajagopalan
study is done on
Namboothiripad @
gypsum and steel
Guruvayoor
residence.
2) Residence for
SHUNYA, Sec-107,
Mr.sajeevan at
NOIDA
Thrissur
 SHUNYA well
3) Residence for Mr.shaji
maintained energy
at Perinjanam ,Thrissur
efficient building with
(Renovation )
structure made of
4) THE HOUSE OF NIVRITI
steel and internal and
THRISSUR(Convention
external partitions
al method )
with gypsum
5) BREEZE HOUSE
ALAPUZHA
Primary data collection
(Conventional method
 Questionnaire preparation )
from the inferences of
literature review and  Interactive section with
literature case studies. contractors and engineers
and architect of the
 Live case studies. selected projects.

 Five live case studies were - Conducted


done, three case study for Interview with two
contractors in

1
Kerala with more particular
than 20 years of products.
experience, with - The primary data
two engineers and was collected for
one young the research is
architect in Kerala. from interviews
- Conducted with to contractors
telephonic from Trissur who
interview with a have more than 20
managing yrs. of experience
directors and and two young
engineers of the engineers.

Table 3 Data sources and data types


Data sources and Data types
 From interviews with to contractors from Thrissur who have
more than 20 yrs. of experience and two young engineers .

 Literature review
Secondary data
collection  CRITERIA FOR SELECTION OF PREFAB IN INDIA- BY
P.K.ADHLAKHA & H.C.PURI

 PREFABRICATION IN DEVELOPING COUNTRIES: A CASE STUDY


OF INDIA, by Ryan E. Smith

 Literature case studies

 SHUNYA, Sec-107, NOIDA

 Questionnaire preparation
-For the interactive section with architects and structural
engineers and contractors.
-Conducted telephonic interview with managing directors and
engineers of the particular products.
 Live case studies

 Residence for Mr.Rajagopalan Namboothiripad @ Guruvayoor

 Residence for Mr.sajeevan at Manjeri


Primary data
collection  Residence for Mr.shaji at Perinjanam ,Thrissur (Renovation )

 THE HOUSE OF NIVRITI THRISSUR(Conventional method )

2
 BREEZE HOUSE ALAPUZHA (Conventional method )

 Interactive section
-with young architects in Kerala, with two young engineers in
Kerala and two contractors.

RESULT
Data collection
CASE STUDY– LITERATURE
 SHUNYA, Sec-107, NOIDA

Figure 5 Front view from the courtyard (P, 2017)


financial savings in electric energy in
comparison to a conventional building of the
SHUNYA is a 0 power prefab residence by
same climatic area; nearly forty% financial
means of the organization 3C. Its miles an
savings in electric energy is thru passive power
internet-0 power domestic is that which works
conservation strategies. It has additionally
on the principle of making use of maximum
included a courtyard that serves as a number
renewable strength, and is independent of any
one source of (electricity) mild and herbal
strength grid, and preserves the energy that it
ventilation and has sun shades with louvers
consumes. (P, 2017)
designed optimally for summer and wintry
SHUNYA is broadly speaking constructed with weather climate. (P, 2017)
old refurbished substances like antique
shipment packing containers, antique metallic
sections, GFRG panels packaged timber, and
vintage furniture. It achieves extra than 70%

2
Figure 6 Concept behind the design (W) (A, 1 Mar 2011)

It is constructed using four cargo containers, which are welded and bolted to each other .The doors,
windows have been cut through these containers.

Figure 7 The truss is covered with angled louvers, which let in ample amount of light and let us hot air
out . (P, 2017)
MATERIALS USED 3.2.2 Outcomes
 Local materials used including locally Prefabrication era has no longer transferred as
available materials and maximum without problems whilst as compared with
different technologies because it's miles a
materials are reused.
manufacturing technology or information
 steel and wood and GFRG Panels as primarily based and not a intake era or product
main materials primarily based. Technology switch of
 columns prefabrication isn't always as pertinent to
 frame architects as it is far to producers of
 truss constructing products, however we're
caretakers of way of life inside the AEC
 finishing material industry. in many cases, have been requested
• WOOD to help with among the transfers that are
happening by using way of worldwide exercise
 interior walls
or running for multi-countrywide companies
 finishing material which are generating prefabricated additives
 beams and complete buildings for India and
 GFRG Panels are used as main material elsewhere. Even though transfers will retain to
for partition of walls occur, especially in the place of prefabrication
in building, we need to be well aware of how
the selections of U.S. and western architects
may also have a62effect on the moral

2
dilemmas regarding less evolved international industrialization, residential desires,
locations’ development and subculture. settlements and lots of different factors of
transportation like bridges, towers, railways
the usage of prefab can help to achieve
calls for fast settlement and requirement for
outcomes for the society’s immediately needs buildings, places of work and industries, for
due to the fact the fast changing surroundings, this reason prefabrication is the solution for
commercial enterprise, economics, immediate and time saving production
Table 4 Comparison between prefabricated (GFRG) and conventional building
Materials/items Prefabricated building Conventional
building

Cement 16 tons 32.55 tons

Steel 1800 kg 2779 kg

Sand 20 cum 83.87 cum

Granite 38 cum 52.46 cum

Brick - 57200

GFRG panel 500 sum

Water 50000 liter 200000 liter

Labour 389 man days 1200 man days

Construction time 21 days 120 days

Wt. of superstructure 170 tons 490 ton


Construction cost

Rs. 13.25 lakhs 18.27 lakhs

Table 5 Comparison of construction time


S. No Item of work RCC (in days) GFRG(In
days)
1 EARTH WORK EXCAVATION 2-4 2-4
2 PCC 2-3 2-3

3 BRICK WORK IN FOUNDATION 5-7 5-7

2
4 DPC 2-4 2-4

5 COLOUMN 9-10 -

6 WALL 10-15 2-4

7 BEAMS 15-18 -
8 LINTEL /SUNSHADE 4-5 2-3

9 SLAB 28 14

10 PLASTERING 10-12 --

11 WHITE WASH 3-4 -

12 COLOUR WASH 2-3 2-3

13 FLOORING 3 3

TOTAL DURATION 98-120 35-45

(Prefabrication in Developing Countries: A Case Study of India)


The idea is to study the following aspects in person to person , as to what they prefer to see
steel and gypsum residential buildings and through their eyes, the general finish of the
compare it with the conventional residential type of construction matters; whether it is neat
buildings, keeping the following areas as key , eye pleasing, availability of colours and
aspects. textures etc.
• Space optimization. – Land values are • Flexibility and use of space - A same
increasing at alarming rates each day in every space can be interpreted/ used in different
city undergoing the process of development ways, depending on its users. The intended
and Kerala is no exception. Thus in this present use, at the time of designing/construction, of a
scenario, optimization of whatever little space particular space can change over the years
available is of clear importance to save space, based on user demands, especially in today’s
money as well as resources. This can be fast growing era. Thus it is important for spaces
achieved in various ways like; inducing design to be open to changes over time or anytime in
strategies by minimalizing waste of space in future. Construction techniques supporting
the design or even by thoughtful use of these provision of future changes, by reducing
materials/ finishes/ furniture etc. In this time the demolition need / ease in installation etc.,
of decreasing land availability and the are recommended in today’s construction by
increasing demand for it, space optimization is many designers as well as clients.
now an essential tool for designing in whatever
limited spaces available. A conventional CASE STUDY – LIVE
method of construction may not always fulfil 1. Preparing questionnaires
the space requirements of the users/ Individual questionnaires were prepared for
designers, which demands for newer architects / designers and occupants. case
technologies/ materials/ installations that can studies will be done , on from pre-fabricated
withstand the crisis of space limitation. building and other from conventional building
• Aesthetics and Visual impacts – typology which will help me to compare the
Although the visual interests can vary from typologies in same locality and can come to a

2
better result. Two type of questionnaires are 4. Can you please explain the quality of
prepared for the designer. One is normal spaces in this residence?
interview questions and the other is for them
5. How did using of steel & ALC helped you in
to rate, this will ease in reviewing the results
too. optimisation of space?

Occupants will be having the ratting and yes or 6. How did using these materials affect the
no questions. Their opinion for the same elevation or aesthetics of the building?
questions is also noted. 7. How does the use of these materials affect
QUESTIONS FOR DESIGNER. the flexibility in use of space?
1. Can you give a brief idea on the project? 8. Would you choose again for further of
2. Why did you choose steel & ALC over your projects?
conventional RCC framed structure?
9. Can you please explain about the usability
3. What are the advantages of these and about client satisfaction?
materials over the conventional method?

DESIGNER

QUESTIONS
1. Did the use of steel help you in space
optimisation?
2. How would you rate the use of steel and
ALC in achieving the visual impact of your
building in others?

3. How would you rate the flexibility of use


of space you have created?
4.Advantage over conventional method

5. usability and client satisfaction

6. Quality of spaces provided

7. overall aesthetics of residence

*Noted opinion if any.

2
QUESTIONS FOR OCCUPANT/ USER.
Table 6: Rating Table / user
1. User 1

2. User 2

3. User 3

NO:
1 2 3
QUESTIONS
1. How will you rate the quality of
space of this building in 5 ?

2. How will you rate the building in


terms of aesthetics and visual
impact?

3. Have you felt any discomfort in


terms of discomfort and flexibility
of use of space?

4. Have you felt any kind of


discomfort because of the material
used for construction?

5. Would you recommend this


construction method and
technology to others?

6. What is the main objective for


choosing the particular
construction?

Electing appropriate buildings for optimisation, aesthetics and visual impact and
flexibility of use of space, and for comparing
case study the building I hav shortlisted 2 buildings which
By this reserch I am aiming to study and is in thrissur and which has all three factors
analyse the conceptual design factors and satisfied.
comparing the prefabricated residential
building with the conventional building of steel 4.3.1 Prefabricated residential building
and ALC structures in kerala , and unerstand 1) Residence for Mr.Rajagopalan
how these materials can solve the present Namboothiripad at Guruvayoor
problems in residential building construction . 2) Residence for Mr.sajeevan at Manjeri
As I am only looking to 3 factors that influence
the conceptual design which is space

2
3) Residence for Mr.shaji at Perinjanam
,Thrissur (Renovation )

4.2.2 Data collected from case studies.


1) RESIDENCE FOR MR.RAJAGOPALAN NAMBOOTHIRIPAD @ GURUVAYOOR

Figure 8 Residence for Mr.Rajagopalan Namboothiripad


(PHOTO TAKEN DURING SITE VISIT)

DESIGNER/ BUILDER Ans: This was the first prefabricated


residential building with ALC and Steel, in
Er.Pradeep Nair (GREEN LIFESTYLE CREATOR
Kerala. So my objective was to make it as
P.LTD CHENNAI )
unique as possible in a budget that the owner
OCCUPANTS would take. As it was the first residence in
Kerala we had to face many queries and ensure
1. Mr.Rajagopalan Namboothiripad (Owner) clarity of the methods to be followed, before
2. Mrs.Reeja Rajagopalan (wife) actually starting the construction. But despite
those challenges, we were able to successfully
3. Rajeev (son) complete the project within the intended
schedule.

Q2. Why did you choose steel ALC over


Interview with designer (Pradeep Nair)
conventional RCC framed structure?
Q1. Can you give a brief idea on the Ans: Ours is an established company in
project? India, which mainly focused on the

2
construction of commercial buildings with amount of columns and beams running inside
steel gypsum and ALC. The design the residence. So the flexibility of use of space
requirements of this project and its space is ensured to a great extent.
availability, lead me to choosing steel gypsum
Q6. Would you choose these
and ALC type of construction. Also,
prefabricated construction is fully fledged in construction again for further of your projects?
the commercial sector of Kerala and not so
much in the residential sector, so I consider Ans: Sure yeah, if the site conditions
this project as a stepping stone for more and the project requirements are
favourable. But since transportation of
designers and users to opt for alternate
prefabricated structures to the site are
practices rather than sticking on to the
involved the budget controlling was a
conventional methods of construction anytime problem. In my experience for a single
and anywhere. dwelling house, this type of construction is a
Q3. Did using steel and ALC help you in little bit expensive. It is more suitable for
large scale projects. Also the time of
optimisation of space?
construction and completion of the project
Ans: In conventional method, the wall was very less compared to conventional
sizes are normally 25 cm thick while using steel methods of construction.
and ALC it is only 15 cm thick, thus overall there Q7. Are there any long term goals for using
will be a considerable increase in usable space steel & ALC construction?
of the building. Also in prefabricated
structures, the columns used are less and this Ans: Changing the use of space over time is a
too helps in optimising the space available. challenge that needs to be addressed in
today’s designs and this type of construction
Q4. How did using these materials affect provides room for future alterations. In steel
the elevation or aesthetics of the building? & ALC construction the walls are installed as
panels and can be removed or demolished
Ans: Aesthetics is a subjective matter easily compared to conventional methods of
and there is no “correct” way of presenting it. construction. So a space can be
reinterpreted in the future years by making
In this design steel and ALC have given
slight alterations in the structure without
the external façade a simple look without creating much havoc or structural instability.
much experimentation or ornamentation
which satisfies the client as well. In general the Q.8. Do you feel using steel & ALC helped in
use steel and ALC may bring in a touch of considerably reducing the overall cost of
typicality in terms of visual appearance, which construction?
could be corrected through the choice of Ans: The wall sizes in this type of construction
colours or textures used for finishes. are just 15 cm and thus there will be a
considerable amount of reduction in the
Q5. How does the use of these affect the materials required for construction, compared
flexibility in use of space? to conventional methods. That being said,
Ans: In steel & ALC construction the while considering the overall picture there isn’t
much of a difference in cost as the
walls are installed as panels and can be
transportation and installation charges adds
removed or demolished easily compared to
up as extra in the end. Thus for large scale
conventional methods of construction. So a projects where a bulk amount of materials can
space can be reinterpreted in the future years be reduced, this type of construction is cost
by making slight alterations in the structure effective, but not so much for small scale
without creating much havoc or structural residential projects.
instability. Also, there are very minimal

2
Q.9. Does the use of Steel & ALC influenced Ans: The materials and prefabricated
the design of the building, during the primary units used in this project are from our industry
design stages? in Chennai, so they had to be transported to
the site in Kerala, which was one of the major
Ans: Steel & ALC type of construction was challenges faced in the project. Also reducing
fixed in the primary stages of design itself. the budget cost low was a big challenge for this
This helped in creating more room for usable scale of a building. In this project, one thing
spaces while keeping the total floor area that could have been bettered are the details
intact. Thus helping in reducing the waste of in the finishes which would have improved the
spaces and crating more spacious interiors. overall aesthetics of the building.
Q.10.Are there any challenges/limitations
you faced during the construction time?

Figure 9 Conventional stair (interior )


PHOTO TAKEN DURING SITE VISIT

Figure 10 Residence for Mr.Rajagopalan Namboothiripad (interior )PHOTO TAKEN DURING SITE VISIT

3
Figure 11Modular kitchen
PHOTO TAKEN DURING SITE VISIT
Table 6 RATING TABLE (DESIGNER)
Er.Pradeep Nair (GREEN LIFESTYLE CREATOR P.LTD CHENNAI )

DESIGNER

QUESTIONS

1. Did the use of steel help you in space 3


optimisation?

2. How would you rate the use of steel and ALC 4


in achieving the visual impact of your building
in others?

3. How would you rate the flexibility of use of 4


space you have created?

4.Advantage over conventional method 4

5. usability and client satisfaction 5

2
6. Quality of spaces provided 3

7. overall aesthetics of residence 3

* The detail is poor, some of the design elements have very less perfection. I propably should
have took the factor perfection more seriously.

Table 7 RATING TABLE (OCCUPANTS/ USERS)


Occupants

1. Mr.Rajagopalan Namboothiripad (Owner)

2. Mrs.Reeja Rajagopalan (wife)

3. Rajeev (son)

NO:
1 2 3
QUESTIONS
1. How will you rate the quality of 3 3 2
space of this building in 5 ?

2. How will you rate the building in 3 3 2


terms of aesthetics and visual
impact?

3. Have you felt any discomfort in NO NO NO


terms of discomfort and flexibility
of use of space?

4. Have you felt any kind of YES YES YES


discomfort because of the material *bescause of the
used for construction? using of steel tress
in first floor ,
feeling hot in first
floor
5. Would you recommend this YES YES NO
construction method and
technology to others?

6. What is the main objective for Cost effective and Cost effective
choosing the particular faster construction and faster
construction? time construction
time

3
*No Air condition are used , although there is no problem in ground floor ,but feeling hot in first floor
because of the using of trussed roof. More compromises are done in the filed Aesthetics.

2) RESIDENCE FOR MR.SAJEEVAN AT MANJERI

Figure 12 On site execution of precast steel and columns


PHOTO TAKEN DURING SITE VISIT

Figure 13At the stage of structure finishing * external walls are made of concrete blocks and internal
pration with gypsum boards.(Photo taken during site visit)
DESIGNER/ BUILDER/ ENGINEER 1. Mr. Sajeevan (Owner)
Er. Anand P( MECHANICAL ) 2. Mrs.Seema (wife)
Er.Najeeb ( CIVIL ) 3. sooryanath (son)
An engineering consortium Manjeri
OCCUPANTS

4
Interview with designer Q6. Would you choose these
construction again for further of your projects?
Q1. Can you give a brief idea on the
project?
Ans: Sure yeah, we are promoting this
Ans: Actually the project is a budgeted method to other areas also. As cost of
home .so we decide to use these prefabricated materials are increasing day by day this will
be a good method for people whose looking
materials as main material. Were we can
into budgeted homes.
reduce so much of cost?
Q7. Are there any long term goals for using
Q2. Why did you choose steel ALC over
steel & gypsum construction?
conventional RCC framed structure?
Ans: the renovation in future years will be
Ans: As the client wanted to finish the more easy in this method because each walls
project as fast as possible. And also steel can and columns are modules and con easily
load more weight than that of concrete for modified . Also at time of renovation the
large scale. waste will be less compared to the
conventional method
Q3. Did using steel and gypsum help you
in optimisation of space? .

Ans: Actually we are used gypsum panels Q.8. Do you feel using steel & gypsum helped
for internal walls and concrete blocks for the in considerably reducing the overall cost of
external walls. Internals walls have less construction?
thickness compared with the normal brick Ans: almost 5 lacks we saved in the structural
walls so maximum carpet area can be utilized. stage when comparing with conventional
method. When coming to finishing stage it is
Q4. How did using these materials affect dependable accordingly to the products we are
the elevation or aesthetics of the building? using.
Ans: Actually we are using concrete Q.9. Does the use of Steel & gypsum
blocks for the external walls. so the elevation influenced the design of the building, during
can be designed as normal as conventional the primary design stages?
method
Ans: No. At first stage discussion itself we are
Q5. How does the use of these affect the fixed with this method.
flexibility in use of space?
Q.10.Are there any challenges/limitations
Ans: all the structure elements are made you faced during the construction time?
from our factory and only site level execution Ans: security was the main concern for
is done from site and which take only 2 days for the client so we are used concrete blocks for
the execution in site. Each columns and beams the external walls.
are individual blocks and each can be easily
dismantled

Table 8 RATING TABLE (DESIGNER)


DESIGNER/ BUILDER/ ENGINEER
Er. Anand P( MECHANICAL )
Er.Najeeb ( CIVIL )
An engineering consortium Manjeri

2
DESIGNER

QUESTIONS

1. Did the use of steel help you in space 4


optimisation?

2. How would you rate the use of steel and 4


gypsum in achieving the visual impact of
your building in others?

3. How would you rate the flexibility of use of 4


space you have created?

4.Advantage over conventional method 4

5. usability and client satisfaction 5

6. Quality of spaces provided 3

7. overall aesthetics of residence 3

Table 9 RATING TABLE (DESIGNER)


OCCUPANTS

1. Mr. Sajeevan (Owner)

2. Mrs.Seema (wife)

3. sooryanath (son

NO:

1 2 3

QUESTIONS

1. How will you rate the quality 5 5 4


of space of this building in 5 ?

2
2. How will you rate the 4 4 3
building in terms of aesthetics
and visual impact?

3. Have you felt any discomfort NO NO NO


in terms of discomfort and
flexibility of use of space?

4. Have you felt any kind of NO NO NO


discomfort because of the
material used for
construction?

5. Would you recommend this YES YES NO


construction method and
technology to others?

6. What is the main objective We wanted to


for choosing the particular complete the
construction? project as fast as
possible

3) RESIDENCE FOR MR.SHAJI AT PERINJANAM


PREFABRICATED RESIDENTIAL BUILDING/ RENOVATION

Figure 14On site execution of precast steel and columns


PHOTO TAKEN DURING SITE VISIT
Table 10 RATING TABLE (DESIGNER)
BUILDER/ ENGINEER

3
Er. Jos Kattukkaran Er.Najeeb ( CIVIL )

Kattukkaran Architectural Solutions Thrissur

DESIGNER

QUESTIONS

1. Did the use of steel help you in space 4


optimisation?

2. How would you rate the use of steel and 4


gypsum in achieving the visual impact of
your building in others?

3. How would you rate the flexibility of use 4


of space you have created?

4.Advantage over conventional method 4

5. usability and client satisfaction 5

6. Quality of spaces provided 4

7. overall aesthetics of residence 4

Table 11 RATING TABLE (OCCUPANTS/ USERS)


OCCUPANTS

1. Mr. Shaji (Owner)

2. Mrs.Mini (wife)

NO:

1 2

QUESTIONS

1. How will you rate the quality 4 4


of space of this building in 5 ?

2. How will you rate the 4 4


building in terms of aesthetics
and visual impact?

4
3. Have you felt any discomfort NO NO
in terms of discomfort and
flexibility of use of space?

4. Have you felt any kind of NO NO


discomfort because of the
material used for
construction?

5. Would you recommend this YES YES


construction method and
technology to others?

6. What is the main objective As we are


for choosing the particular renovating the old
construction? house we have
concern about the
structural stability

4.3.2 Conventional residential building


 1) Rsidence for Mr.Sujith at Thrissur

 2) Rsidence for Mr.Shyne at Alappuzha

4.3.2 Data collected from case studies.


1) Rsidence for Mr.Sujith at Thrissur

Figure 15 Residence for Mr.Sujith @ Arimboor , Thrissur


Architect Ar. Manuraj CR (i2a Architects Studio)

5
Occupants Ans: The concept of the building rooted back
to the traditional Kerala construction and the
1. Mr.Venu (Owner) conventional method of construction was
2. Mrs.Hema (wife) the ideal option for the project. The mixture
of exposed bricks and cement finished walls
3. Mr.Sujith ( son) in the exterior , together blended with the
traditional clay tiles on the roof pulled of a
Interview with designer (Ar. Manuraj rustic traditional look for the house.
CR) Q5. Was flexibility in use of space considered
while designing the project?
Q1. Can you give a brief idea on the
project? Ans: As the walls are all load bearing, future
alterations or extensions in the design may
Ans: “HOUSE OF NIVRITI” means the house of affect the structural stability of the building
bliss, which was designed to provide joy and and would be a great risk to do so. Only
happiness for its residents. The main concept adaptive reuses of space like the change in
was to create a connection between the interior furniture or partition walls may can
building and nature .So it is designed in such a be made to make the spaces flexible.
way that it responds to the aspects of site
Q6. Would you choose this approach again
context and climate.. The abundance of natural for further of your projects?
light inside & proper ventilation brings in fresh
flow of air and enhance living experience of the Ans: It will depend on its locality context,
habitat. The design was approached to project requirements and its scale. For
incorporate traditional aspects as much as constructing a normal residence in Kerala
possible, as per the client’s requirements. context, conventional RCC framed structures
would be ideal, considering the
Q2. Why did you choose conventional RCC transportation and labour charges required
framed structure? for other alternative methods like steel &
ALC construction.
Ans: The design was an attempt to bring in
maximum traditional elements possible, as Q7. Are there any long term goals for using
per the client’s requirements. Thus conventional method of construction?
conventional RCC structure was the best
Ans: The building will have a strong life
option which would easily blend in with the
expectancy for many years and many
building’s concepts. Any other alternative
columns and RCC framed structures are used
ways like prefabricated structures would’ve
in this conventional method of construction.
been a misfit to the theme of design.
Although future building alterations would
Q3. How did this affect the optimisation of be a difficult task as it can affect the
space inside the house? building’s structural stability.

Ans: All the walls are load bearing walls and Q.8. Has this method in any way helped in
hence are 25 cm thick. There were considerably reducing the overall cost of
challenges while designing certain spaces construction?
inside the house, to increase the usable
Ans: The project was completed within the
space. But by designing spaces linked to one
client’s targeted budget and no extra
another, without completely dividing them
expenses were made. Transportation
with a wall, openness was achieved in the
charges and other installation charges
design.
associated with prefabricated type of
Q4. How did using this conventional method construction were reduced here, as most of
affect the elevation or aesthetics of the the construction materials and labour came
building? from nearby distance of the site.

2
Q.9. Have this method affected the design of Q.10.Are there any challenges/limitations
the building, during primary design stages? you faced during the construction time?
Ans: During the design stages, increasing Ans: There weren’t any big challenges, but
usable spaces in the design with minimum preserving the existing vegetation of the site
wall partitions was a challenge, as the was an essential challenge which I was able
structural stability was to be taken care as to overcome successfully.
well. The spaces were designed keeping the
wall thickness 25 cm everywhere and was
able to successfully render the client’s
requirements.
Table 12 RATING TABLE (ARCHITECT)
ARCHITECT

Ar. Manuraj CR (i2a Architects Studio )

QUESTIONS DESIGNER

1. How you zoned residence to this small plot? 2

2. What about the space optimisation in this 3


project ?

3. How would you rate the flexibility of use of 3


space you have created?

4. Why don’t you recommend other methods? 2

Advantage over prefabricated method

5. usability and client satisfaction 4

6. Quality of spaces provided 4

7. overall aesthetics of residence 4

RATING TABLE (OCCUPANTS/ USERS)

OCCUPANTS

1. Mr.Venugopalan (Owner)

2. Mrs.Hema (wife)

3. Mr.Sujith (son)

3
Interview with users older generations, keeping the traditions intact
and that is exactly what we got.
Occupants
Q3. Does this method of construction chosen
1. Mr.Venu (Owner) by the designer affect your desired aesthetical
quality of the building in any way?
2. Mrs.Hema (wife)
Ans: The conventional style of construction
3. Mr.Sujith ( son) have added to the beauty of the traditional
themed elevation and design of the building,
Q1. Was there any demands from your side on which the designer has successfully rendered.
space optimisation while discussing with the
designer? Q4. Do you feel the spaces of your home are
capable of adaptive reuse?
Ans: We wanted spaces that could enhance the
family bonding like in traditional buildings and Ans: We haven’t planned of any future
we are happy be the design of the house – alterations or extensions as of now, although if
keeping the central courtyard connected to the needed an extra room could be added in the
dining as the energy core of house. present open terrace area of the house.

Q2. Now that the project is complete, do you Q5. Are there any challenges/ discomfort you
feel your needs have been fulfilled in a face as dwellers?
thoughtful way? Ans: we don’t face any challenges/ discomfort,
Ans: Absolutely. We wanted a house that in fact we feel living a step closer to the nature
would help us connect with nature and the now.

Figure 16 Dining space of Residence for Mr.Sujith @ Arimboor , ThrissurTable 14:RATING TABLE
(OCCUPANTS/ USERS)

QUESTIONS USER1 USER2 USER3

1. How will you rate the quality of 4 5 5


space of this building in 5?

2
2. How will you rate the building in 5 5 5
terms of aesthetics and visual
impact?

3. Have you felt any discomfort in NO NO NO


terms of discomfort and flexibility
of use of space?

4. Have you felt any kind of NO* NO NO


discomfort because of the material
used for construction?

2) Rsidence for Mr.Shyne at Alappuzha

Figure 17 Residence for Mr.Shyne at Alappuzha


Architect

Ar. Arjun KJ (i2a Architects Studio )

Occupants

1. Mr.Shyne (Owner)

2. Mrs.Soniya (wife)

3. Father

4. Mother

Table 13 RATING TABLE (DESIGNER)


ARCHITECT

Ar. Arjun KJ (i2a Architects Studio

2
DESIGNER

QUESTIONS

1. How you zoned residence to this small plot? 3

2. What about the space optimisation in this 3


project ?

3. How would you rate the flexibility of use of 3


space you have created?

4.Why don’t you recommend other methods? 4

Advantage over prefabricated method

5. usability and client satisfaction 3

6. Quality of spaces provided 4

7. overall aesthetics of residence 4

Table 14 RATING TABLE (OCCUPANTS/ USERS)


OCCUPANTS

1. Mr.Shyne (Owner)

2. Mrs.Soniya (wife)

3. Father

4. Mother

NO:

1 2

QUESTIONS

3
1. How will you rate the quality of space of 4 4
this building in 5 ?

2. How will you rate the building in terms of 4 4


aesthetics and visual impact?

3. Have you felt any discomfort in terms of YES YES


discomfort and flexibility of use of space?

4. Have you felt any kind of discomfort YES YES


because of the material used for
construction?

5. Would you recommend this construction YES YES


method and technology to others?

DISCUSSION
Based on live case study on pre-fabricated residences
Table 15 Based on live case study on pre-fabricated residences

DESIGNER 1 DESIGNER 2 DESIGNER 3 TOTAL( 15)

QUESTIONS

1. Did the use of steel help you in space 3 4 4 11


optimisation?

2. How would you rate the use of steel 4 4 4 12


and gypsum in achieving the visual
impact of your building in others?

3. How would you rate the flexibility of 4 4 4 12


use of space you have created?

4.Advantage over conventional method 4 4 4 12

4
5. usability and client satisfaction 5 5 5 15

6. Quality of spaces provided 3 3 3 9

7. overall aesthetics of residence 3 3 3 9

Table 16 Comparison

CASESTUDY 01
Space
optimization 3 4
Aesthetics

Flexibility
4 3
use of space

CASESTUDY 02
Space
optimization 5 4
Aesthetics

Flexibility

3
use of space 4

5
CASESTUDY 03
Space
optimization 4 4
Aesthetics

Flexibility

use of space 4 3

• Flexibility
and use of
OVERALL CONCLUSION
space AGE ABOVE 50
40% 14%
AGE BELOW
30
14%

Aesthetics
• Space 20%
optimization
36%
• Space optimization • Flexibility and use of space
• Aesthetics and Visual impacts. AGE ABOVE 50
AGE BELOW 30

Based on live case study on conventional residences


Table 17 Based on live case study on conventional residences

6
CASESTUDY 01
Space
optimization 4
3
Aesthetics

Flexibility

3
use of space 2

CASESTUDY 02
Space 5
optimization 3
Aesthetics

Flexibility
2
use of space 4

OVERALL CONCLUSION
AGE ABOVE 50
• Space optimization
40%
• Flexibility and
use of space • Flexibility and use of
20% space
• Aesthetics and Visual
impacts.
Aesthetics AGE ABOVE 50
• Space 60%
optimization
20% AGE BELOW 30
AGE BELOW 30
20%

7
5.3 Based on interactions with practicing architects in kerala

1. Ar. Manuraj CR (i2a Architects Studio )

2. Ar. Arjun KJ (i2a Architects Studio )

3. Ar. Levin P Joy (Finder studio )

4. Ar. Josaph Josaph Chalisery (Dream infinite studio)

5. Ar. CS Menon ( CS MENON Associates )

Table 18 Based on interactions with practicing architects in kerala


QUESTIONS 1 2 3 4 5

1. Have you done any project with pre NO YES NO NO NO


fabricated construction method ? If NO why
don’t you prefer these types methods.

2. Your opinion about the construction with pre 2 3 2 2 3


fabricated method ?

3. Is this method have more advantages with 2 2 2 2 3


the conventional method ?

4.When we looking into aspects like 3 3 2 3 3

• Space optimization

• Aesthetics and Visual impacts.

• Flexibility and use of space.

Which method is more suitable to the context


of kerala?

No one are done a fully-fledged Prefabricated building*


Looking into space optimisation and flexibility it is ok

8
But aspects like aesthetics visual impacts and use of spaces conventional method is more
feasible to the context of kerala. *

• Drastic increase in cost of


BACKGROUND construction materials
STUDY FROM • An alternative method want to be
INTERVIEW introduced in the construction sector
of residence.

• Steel, gypsum and ALC panels have


LITERATURE more advantages as compared with
REVIEW the conventional method.
• There is drastic difference in time and
cost

• The energy efficiency of these


LITERATURE CASE buildings are high.
STUDY • Building is more flexible
• Increase in carpet and thereby have
more space inside.

9
Inference from live case study Space optimization: From the case studies it is
clear that the use of steel gypsum & ALC
5.4.1 Prefabricated residences
construction provides room for optimising
 Have more advantages when looking
whatever the space available, over
into the aspects of space optimization conventional RCC framed structure. : In
and flexibility conventional method, the wall sizes are
 Visual interests can vary from person normally 25 cm thick while using steel and ALC
to person. it is only 15 cm thick, thus overall there will be
 Construction techniques supporting a considerable increase in usable space of the
these provision of future changes, by building. Also in prefabricated structures, the
reducing the demolition need / ease in columns used are less and this too helps in
installation etc., optimising the space available. This helps in
 Time and cost are the other aspects creating more room for usable spaces while
attracting to the technology of keeping the total floor area intact. Thus
helping in reducing the waste of spaces and
prefabricated construction
creating more spacious interiors.
 When looking into clients they are
more satisfied about the quality of So to conclude, in this present scenario of
space inside, usability and living increasing land value and decreasing land
atmosphere inside availability, optimization of whatever little
space available is of clear importance to save
5.4.2 Conventional residences space, money as well as resources. A
When looking into aspect of aesthetics this conventional method of construction may not
method is more aesthetically pleasing. always fulfil the space requirements of the
Although the idea of aesthetics can vary from users/ designers which demands for newer
person to person, as to what they prefer to see methods, like prefabricated construction, that
through their eyes, the general finish of the can withstand the crisis of space limitation.
type of construction matters; whether it is
Aesthetics and Visual impacts: As we all know,
neat, eye pleasing, availability of colours and
aesthetics is a very subjective matter and there
textures etc.
is no “correct” way of presenting it. That being
5.4.3 Live interactions said, from the above case studies as well as
Most of the architects not interested with the from discussions with the architects and
method of prefabrication. It all about the lack designers, it is evident that prefabricated
of understanding about the particular method structures create a touch of typicality in
of construction. Architects wanted promote designs especially in external facades. There is
more about these method and also want to put very less to experiment with, in this type of
forward more design ideas with these construction. But conventional RCC framed
methods. method of construction provides more room
for experimentation by allowing the use of
different materials, finishes etc.

CONCLUSION Flexibility and use of space: In steel &


From the above live casestudies certain gypsum/ ALC construction the walls are
conclusions can be drawn, based on the three installed as panels and can be removed or
key factors for comparison : Space demolished easily compared to conventional
optimization, Aesthetics and Visual impacts, methods of construction. So a space can be
Flexibility and use of space, all in the Kerala reinterpreted in the future years by making
context. slight alterations in the structure without

1
creating much havoc or structural instability. in interior furniture or partition walls may can
Also, there are very minimal amount of be made to make the spaces flexible.
columns and beams running inside the
The intended use, at the time of
residence. So the flexibility in use of space is
designing/construction, of a particular space
ensured to a great extent. In conventional
can change over the years based on user
method, as the walls are all load bearing,
demands, especially in today’s fast growing
future alterations or extensions in the design
era. Thus to conclude, steel & ALC method of
may affect the structural stability of the
construction would be more successful in
building and would be a great risk to do so.
achieving flexibility in design for the future.
Only adaptive reuses of space like the change

References
1. A, M. M. (1 Mar 2011). Design in Modular Construction. CRC Press.

2. Ajay Patre and Laxmikant Vairagade. (2014). Comparative Analysis and Design of High Rise.
International Journal of Trend in Research and Development.

3. Alatza, D. R. (1 jan 2014). Pre fabricated structures. Sree Kamalamani Publications.

4. Design in Modular Construction. (6 Mar 2017). Journal of Architectural Education.

5. E, S. R. (11 Jan 2011). Factory Design For Modular Homebuilding .

6. Eldhose M Manjummekudiyil, B. P. (March 2015). study on GFRG Panels. International Journal of


Civil and Structural Engineering Research.

7. J, Q. (n.d.). design of modular construction. journal Of architectural education.

8. Modular construction . (2 Jan 2014). Steel construction.

9. Musa, M. F. (13 July 2016). Towards the adoption of modular construction. Journal of Engineering
and Applied Science.

10. O, M. L. (24 Feb 2014). Technical Handbook ,Kirby Building systums.

11. P, B. (2017). Prefabrication-concept,Components and Advantages. Presentation on Prefabricated


structures.

12. Pande, P. ( 5 May 2016). study of prefabricated modular and steel. SSRG Internationbal Jouranal
of Civil Engineering.

13. S. Vishnu, R. S. (11 Nov 2018 ). LITERATURE STUDY ON GFRG BUILDING AND LEAN CONSTRUCTION.
International Research Journal of Engineering and Technology (IRJET) .

14. W, W. R. (n.d.). Prefabricated construction systems. Division of Building Science & Technology.

15. Why Build Modular. (10 Oct 2013). Modular construction.

You might also like