Professional Documents
Culture Documents
FIDIC
FIDIC
FIDIC
Parikh
Dr. D. M. Parikh
1
Dr. D. M. Parikh
Topics
Introduction and Background of Contracts
Responsibilities of Main Parties
Management of Projects
Financial Clauses and Procedures
Risks, Force Majeure and Termination
Claims, Disputes and Arbitration
Scheduled Responsibilities
MDB-2010: FIDIC Pink Book
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 3
Dr. D. M. Parikh
2
Dr. D. M. Parikh
What is a Contract?
A contract is a legally binding exchange of promises or agreement
between parties that the law will enforce.
Dr. D. M. Parikh
What is a Contract?
All contracts in India are governed by Indian Contracts Act, 1872
3
Dr. D. M. Parikh
Types of Contracts
Lump Sum Contract
Unit Price Contract
Cost Plus Contract
Cost + Fixed Percentage Contract
Cost + Fixed Fee Contract
Incentive Contracts
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 7
Dr. D. M. Parikh
What is FIDIC?
Fédération Internationale des Ingénieurs Conseils (FIDIC)
International Federation of Consulting Engineers
Established in 1913 by 3 countries: Belgium, France & Switzerland
Remained Europe based till 1959 and Australia, Canada, South Africa, and
the USA joined to make it a Global Federation
FIDIC has Member Associations (MA) in each member countries – currently
99 MAs
4
Dr. D. M. Parikh
What is FIDIC?
Founding principles are Quality, Integrity, and Sustainability.
FIDIC publishes various standard forms of Contract conditions.
It encompasses most of the private practice consulting engineers.
Promotes and implements the consulting engineering industry’s strategic goals.
Members endorse FIDIC’s statutes and policy statements and comply with
FIDIC’s Code of Ethics.
Develops and promotes better business practices: Business Integrity
Management; Project Sustainability Management.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 9
Dr. D. M. Parikh
What is FIDIC?
FIDIC Organises:
Extensive programme of seminars and conferences.
International Training Programme (courses; workshops)
Capacity Development Programme (accredited trainers; training suppliers;
programmes and events).
Publishes
Business practice guides
Professional services agreements and guides
General Conditions of Contracts to implement almost all types of Works
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 10
5
Dr. D. M. Parikh
What is FIDIC?
Groups of Member Associations
African Union
GAMA Group of Africa Member Associations
www.fidic.org/gama
Dr. D. M. Parikh
What is FIDIC?
Regional Federations
NAFTA
FEPAC Panamerican Federation of Consultants
European Union
EFCA European Federation of Engineering
Consultancy Associations
6
Dr. D. M. Parikh
What is FIDIC?
What FIDIC does….
Represent globally the consulting engineering industry, >1 million professional
Enhance the image of consulting engineers
What FIDIC offers the industry….
Be the authority on issues relating to business practice
Promote the development of a global & viable consulting engineering industry
What are FIDIC’s governing principles….
Promote quality
Actively promote conformance to a code of ethics and integrity
Promote commitment to sustainable development
Dr. D. M. Parikh
What is FIDIC?
Holds Regular meetings as the industry’s voice with;
7
Dr. D. M. Parikh
What is FIDIC?
Forges Strategic partnerships with;
Dr. D. M. Parikh
8
Dr. D. M. Parikh
Dr. D. M. Parikh
9
Dr. D. M. Parikh
FIDIC Contracts
Standard Contracts and Agreements
Standard model agreements for Professional Services
Client - Consultant
Joint Venture
Sub-Consultant
Representative
Dr. D. M. Parikh
10
Dr. D. M. Parikh
Dr. D. M. Parikh
The FIDIC Books
11
Dr. D. M. Parikh
FIDIC Contracts
Advantages
Savings in time and cost on repetitive transactions.
Frequent use gives common understanding among stake holders.
Tenderers do not need to allow for unfamiliar contract conditions.
Fair to all parties = greater contractor confidence and lower risk
contingencies.
Uncertainties of meaning removed, either by decisions of courts or by
revisions; so they are predictable.
Dr. D. M. Parikh
FIDIC Contracts
Disadvantages
Tenderers often dispense with legal advice.
Widespread use of standard forms used as a gauge of market prices for a
certain construction items, products or processes, thus having a cartel-like
aspect.
Use of some standard forms is so widespread and common that it is as a
form of “private legislation”.
12
Dr. D. M. Parikh
FIDIC Contracts
Precautions
Amendments shall not be made to standard forms, because;
General Conditions of standard forms are copyrighted intellectual
property and shall not be modified by retyping.
Whatever the reason for amendments, the resulting document can be
disastrous and likely to have unintended results.
Construction of the Contract is a complex task with many interlinking and
inter-dependent clauses, and hence, contract/tender documentation shall
not be prepared in parts by different professionals/firms.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 25
Dr. D. M. Parikh
FIDIC Contracts
Departure from Standard Contract
Use of bespoke/modified contracts came about because:
Changed risk allocation was desired.
More project contracting routes and diverse project delivery methods:
standard forms did not keep up.
Major law firms developed in-house Particular Conditions and data on
the basis of unreported decisions.
13
Dr. D. M. Parikh
Stakeholders of Contracts
Dr. D. M. Parikh
FIDIC Definitions
Employer, means the person / entity who is the owner of the facility being
developed under the said Contract
Contractor, means the person / entity whose tender has been accepted by
the Employer and responsible to develop the facility under the said Contract
14
Dr. D. M. Parikh
FIDIC Definitions
If Employer or Contractor is called by another title such as ‘Owner’ or
‘Ministry’ or ‘Client’, or ‘Builder’ or ‘Constructor’, this revised terminology
MUST be explained in the Appendix to Tender or Contract Data (for the DBO
Contract) or elsewhere in the Contract.
Unless such explanation contains any revisions to the foreseen roles, such
Parties shall be deemed to have the roles of the Employer and the
Contractor, respectively assigned to them in the Contract.
Each Party to be a legal person or entity under the law of the country under
which it has been constituted (only legal persons or entities can enter into
contracts).
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 29
Dr. D. M. Parikh
15
Dr. D. M. Parikh
Dr. D. M. Parikh
16
Dr. D. M. Parikh
Dr. D. M. Parikh
17
Dr. D. M. Parikh
Dr. D. M. Parikh
18
Dr. D. M. Parikh
Dr. D. M. Parikh
19
Dr. D. M. Parikh
Dr. D. M. Parikh
20
Dr. D. M. Parikh
Dr. D. M. Parikh
21
Dr. D. M. Parikh
Dr. D. M. Parikh
22
Dr. D. M. Parikh
Dr. D. M. Parikh
23
Dr. D. M. Parikh
Dr. D. M. Parikh
24
Dr. D. M. Parikh
Dr. D. M. Parikh
25
Dr. D. M. Parikh
Dr. D. M. Parikh
26
Dr. D. M. Parikh
Dr. D. M. Parikh
27
Dr. D. M. Parikh
Dr. D. M. Parikh
28
Dr. D. M. Parikh
Legal Character
Dr. D. M. Parikh
Governing Law
Use of FIDIC contracts is common throughout the whole world.
What does it mean “to use FIDIC”?
FIDIC is a private organization having no legislative powers.
FIDIC standard contracts are simply general trade terms and are subject to
the Applicable Law [National Law of the Project country].
FIDIC conditions originated essentially are relying on Common Law regime.
29
Dr. D. M. Parikh
Governing Law
Common Law v/s Civil Law
Common Law, also known as Case Law is law developed though decisions
of courts rather than though legislative statutes or executive branch action –
India follows Common Law system
Civil Law, (inspired by Roman Law) is the legal system written into a
collection, codified and not determined by the courts (unlike Common Law)
Dr. D. M. Parikh
Governing Law
Common Law v/s Civil Law
Civil Law is followed in over 150 countries. The courts are usually
inquisitorial, unbound by precedents and with limited focus on interpretation
of law.
30
Dr. D. M. Parikh
Dr. D. M. Parikh
31
Dr. D. M. Parikh
Dr. D. M. Parikh
32
Dr. D. M. Parikh
Dr. D. M. Parikh
33
Dr. D. M. Parikh
Dr. D. M. Parikh
34
Dr. D. M. Parikh
Characteristics
Unification of Terms and Clauses
Contracts were prepared by a workgroup under the leadership of the
FIDIC Contract Committee. The clauses are under the same titles and
expressions, each consists of a total of 20 clauses.
More than 80% of the content is consistent, and 85% of definitions and
expressions are the same. It is of great help to users to understand
them completely, saving study time.
Dr. D. M. Parikh
Characteristics
Applicability: Project Delivery & Contracting System
The Red Book can be used in any kind on Engineering Construction
Contract
The Yellow Book applies to the Contracts, where the Contractor is
responsible for design also.
35
Dr. D. M. Parikh
Characteristics
Specific Provisions - Parties’ Obligations and Rights
Requirements for the Contractor
Quality Assurance System
Monthly Progress Reports
Dr. D. M. Parikh
Characteristics
Management Procedures
The FIDIC forms are dynamic. The procedures (e.g. claim procedure
2.5 & 20.1) are time related. The failure in respecting the procedure
leads to the cancelation of the right.
36
Dr. D. M. Parikh
Characteristics
Payments Procedures
The Employer is obliged to show his financial arrangements (Sub-
Clause 2.4).
Dr. D. M. Parikh
Characteristics
The Engineer
In the Red Book, Engineer’s role increased in solving the problems
during the Contract.
37
Dr. D. M. Parikh
Characteristics
The Engineer
In the Yellow Book the responsibilities of the Engineer remain the
same as in the Red Book except increased responsibility of review of
design.
In the Yellow Book any ‘consent’ to the design does not discharge the
Contractor of his obligations and any errors of the design are the
Contractor’s responsibility.
Dr. D. M. Parikh
Characteristics
Disputes Resolution
FIDIC stipulates the use of DAB.
Note that the DAB members are to be independently chosen by each
party and paid by each party.
In Red Book the Engineer is required to mediate the disputes.
[however, the general notion is that it is difficult to be impartial since
the Engineer is part of the Employer]
If the mediation fails then the dispute/s go to DAB.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 76
38
Dr. D. M. Parikh
Characteristics
User Friendliness
Common definitions for all defined terms.
Use of identical wording while considering the same topic.
Incorporate as much text as possible in General Conditions.
Elaborate Guidance notes are provided to prepare the Particular
Conditions (PC).
Some provisions not applicable to the Work, can readily be disabled by
deletion to be specified in PC.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 77
Dr. D. M. Parikh
Characteristics
User Friendliness
It incorporates a user-friendly check-list in the Appendix to Tender
(Contract Data) for the insertion of all essential data.
The Contract becomes effective when the Employer issues a Letter of
Acceptance. However, this condition may be suitably modified by the
Employer and/or by mutual consent during pre-contract negotiations.
39
Dr. D. M. Parikh
Features of 3 Contracts
10%
Dr. D. M. Parikh
Features of 3 Contracts
40
Dr. D. M. Parikh
Dr. D. M. Parikh
41
Dr. D. M. Parikh
Dr. D. M. Parikh
42
Dr. D. M. Parikh
Dr. D. M. Parikh
43
Dr. D. M. Parikh
Risk Sharing
Contractor’s Risk
Contract Price
Silver
Yellow Book
Red Book
Risk Analysis Book
involvement
Employer’s
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 87
Dr. D. M. Parikh
Structure of Contract
44
Dr. D. M. Parikh
Dr. D. M. Parikh
45
Dr. D. M. Parikh
Dr. D. M. Parikh
Particular Conditions of the Contract give the possibility to modify the existing clauses
in the Contract in order to make them more suitable to the actual conditions of the
project.
46
Dr. D. M. Parikh
In the preparation of the Particular Conditions there are Cross references with
Annexures and Tender Specifications and Appendices. It is obligatory to have no
contradiction in Contract clauses.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 93
Dr. D. M. Parikh
47
Dr. D. M. Parikh
Dr. D. M. Parikh
48
Dr. D. M. Parikh
Dr. D. M. Parikh
49
Dr. D. M. Parikh
Dr. D. M. Parikh
50
Dr. D. M. Parikh
Dr. D. M. Parikh
51
Dr. D. M. Parikh
Dr. D. M. Parikh
52
Dr. D. M. Parikh
Dr. D. M. Parikh
Quiz
NO QUESTION YES NO MAYBE
1 FIDIC Red, Yellow and Silver Books means a complete Contract for Works?
2 FIDIC conditions are tilted in favour of the Employers.
3 Nominated sub-contractor is the same as the sub-contractor?
4 Engineer being part of the Employer’s Personnel shall always act in favour of Employer?
5 Financing institutes are Party in the FIDIC Contracts.
6 Insurance companies are not required to be a Party to the Contract.
7 FIDIC conditions have priority over the national laws.
8 A total of 3 clauses are different between Red Book and Yellow Book.
9 If the Employer terminate the Contract for his convenience, the Contractor is eligible of
payment of Cost and Profit on the balance Works.
10 Defects Notification Period can not be extended beyond stipulated period in the Contract.
11 The Employer may appoint his staff as a DAB member on the 3 member board.
12 Bill of Quantities forms part of RB and YB based Contracts.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 106
53
Dr. D. M. Parikh
Dr. D. M. Parikh
54
Dr. D. M. Parikh
1. General Provisions
1.1.1 Definitions – The Contract
“Contract” means the Contract Agreement, the Letter of Acceptance, the Letter of Tender, these
Conditions, the Specifications, the Drawings, the Schedules, and the further documents (if any)
which are listed in the Contract Agreement or in the Letter of Acceptance.
“Contract Agreement” means the contract agreement (if any) referred to in Sub-Clause 1.6
[Contract Agreement].
“Letter of Acceptance” means the letter of formal acceptance, signed by the Employer, of the
Letter of Tender, including any annexed memoranda comprising agreements between and
signed by both Parties. If there is no such letter of acceptance, the expression “Letter of
Acceptance” means the Contract Agreement and the date of issuing or receiving the Letter of
Acceptance means the date of signing the Contract Agreement.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 109
Dr. D. M. Parikh
1. General Provisions
1.1.1 Definitions – The Contract
"Letter of Tender" means the document entitled letter of tender, which was completed by the
Contractor and includes the signed offer to the Employer for the Works.
"Schedules" means the document(s) entitled schedules, completed by the Contractor and
submitted with the Letter of Tender, as included in the Contract. Such document may include the
Bill of quantities, data, lists, and schedules of rates and/or prices.
"Tender" means the Letter of Tender and all other documents which the Contractor submitted
with the Letter of Tender, as included in the Contract.
"Appendix to Tender" means the completed pages entitled appendix to tender which are
appended to and form part of the Letter of Tender
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 110
55
Dr. D. M. Parikh
1. General Provisions
1.1.2 Definitions – Parties and Persons
"Party" means the Employer or the Contractor, as the context requires.
"Employer" means the person named as employer in the Appendix to Tender and the legal
successors in title to this person.
"Contractor" means the person(s) named as contractor in the Letter of Tender accepted by the
Employer and the legal successors in title to this person(s).
"Engineer" means the person appointed by the Employer to act as the Engineer for the purposes
of the Contract and named in the Appendix to Tender, or other person appointed the Employer
and notified to the Contractor under Sub-Clause 3.4 [Replacement of the Engineer]
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 111
Dr. D. M. Parikh
1. General Provisions
1.1.2 Definitions – Parties and Persons
"Contractor's Representative" means the person named by the Contractor in the Contract or
appointed from time to time by the Contractor under Sub-Clause 4.3 [Contractor's
Representative], who acts on behalf of the Contractor.
"Employer's Personnel" means the Engineer, the assistants referred to in Sub-Clause 3.2
[Delegation by the Engineer] and all other staff, labour and other employees of the Engineer and
of the Employer; and any other personnel notified to the Contractor, by the Employer or the
Engineer, as Employer's Personnel.
56
Dr. D. M. Parikh
1. General Provisions
1.1.2 Definitions – Parties and Persons
"Contractor's Personnel" means the Contractor's Representative and all personnel whom the
Contractor utilizes on Site, who may include the staff, labour and other employees of the
Contractor and of each Subcontractor; and any other personnel assisting the Contractor in the
execution of the Works.
"DAB" means the person or three persons so named in the Contract, or other person(s)
appointed under Sub-Clause 20.2 [Appointment of the Dispute Adjudication Board] or under Sub-
Clause 20.3 [Failure to Agree Dispute Adjudication Board].
Dr. D. M. Parikh
1. General Provisions
1.1.3 Definitions- Dates, Tests, Periods and Completion
"Base Date" means the date 28 days prior to the latest date for submission of the Tender.
"Commencement Date" means the date notified under Sub-Clause 8.1 [Commencement of
Works].
"Time for Completion" means the time for completing the Works or a Section (as the case may
be) under Sub-Clause 8.2 [Time for Completion], as stated in the Appendix to Tender (with any
extension under Sub-Clause 8.4 [Extension of Time for Completion]), calculated from the
Commencement Date.
"Tests on Completion" means the tests which are specified in the Contract or agreed by both
Parties or instructed as a Variation, and which are carried out under Clause 9 [Tests on
Completion] before the Works or a Section (as the case may be) are taken over by the Employer.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 114
57
Dr. D. M. Parikh
1. General Provisions
1.1.3 Definitions- Dates, Tests, Periods and Completion
“Taking Over Certificate" means a certificate issued under Clause 10 [Employer’s Taking-Over]
“Defects Notification Period" means the period for notifying defects in the Works or a Section (as
the case may be) under Sub-Clause 11.1 [Completion of Outstanding Work and Remedying
Defects], as stated in the Appendix to Tender (with any extension under Sub-Clause 11.3
[Extension of Defects Notification Period]), calculated from the date on which the Works or
Section is completed as certified under Sub-Clause 10.1 [Taking Over of the Works and
Sections].
Dr. D. M. Parikh
1. General Provisions
1.1.4 Definitions - Money and Payments
"Accepted Contract Amount" means the amount accepted in the Letter of Acceptance For the
execution and completion of the Works and the remedying of any defects.
"Contract Price" means the price defined in Sub-Clause 14.1 [The Contract Price], and includes
adjustments in accordance with the Contract.
"Cost" means all expenditure reasonably incurred (or to be incurred) by the Contractor, whether
on or off the Site, including overhead and similar charges, but does not include profit.
58
Dr. D. M. Parikh
1. General Provisions
1.1.4 Definitions - Money and Payments
"Provisional Sum" means a sum (if any) which is specified in the Contract as a provisional sum,
for the execution of any part of the Works or for the supply of Plant, Materials or services under
Sub-Clause 13.5 [Provisional Sums].
"Retention Money" means the accumulated retention moneys which the Employer retains under
Sub-Clause 14.3 [Application for Interim Payment Certificates] and pays under Sub-Clause 14.9
[Payment of Retention Money].
Dr. D. M. Parikh
1. General Provisions
1.1.5 Definitions – Works and Goods
"Permanent Works" means the permanent works to be executed by the Contractor under the
Contract.
"Section" means a part of the Works specified in the Appendix to Tender as a Section (if any).
"Temporary Works" means all temporary works of every kind (other than Contractor's Equipment)
required on Site for the execution and completion of the Permanent Works and the remedying of
any defects.
"Works" mean the Permanent Works and the Temporary Works, or either of them as appropriate.
59
Dr. D. M. Parikh
1. General Provisions
1.1.6 Definitions – Other Definitions
"Country" means the country in which the Site (or most of it) is located, where the Permanent Works
are to be executed.
"Laws" means all national (or state) legislation, statutes, ordinances and other laws, and regulations
and by-laws of any legally constituted public authority.
"Performance Security" means the security under Sub-Clause 4.2 [Performance Security].
"Site" means the places where the Permanent Works are to be executed and to which Plant and
Materials are to be delivered, and any other places as may be specified in the Contract as forming part
of the Site
"Unforeseeable" means not reasonably foreseeable by an experienced contractor by the date for
submission of the Tender.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 119
Dr. D. M. Parikh
1. General Provisions
1.2 Interpretation
♦ Words indicating one gender include all genders;
♦ Words indicating the singular also include the plural and words indicating the plural
also include the singular;
60
Dr. D. M. Parikh
1. General Provisions
1.3 Communication
♦ In writing and delivered by hand (against receipt), sent by mail or courier, or transmitted
using any of the agreed systems of electronic transmission as stated in the Appendix to
Tender; and
♦ When a certificate is issued to a Party, the certifier shall send a copy to the other Party.
♦ When a notice is issued to a Party, by the other Party or the Engineer, a copy shall be sent to
the Engineer or the other Party, as the case may be.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 121
Dr. D. M. Parikh
1. General Provisions
1.4 Law and Language
♦ The Contract is governed by the law mentioned in Appendix to Tender.
♦ The Employer should check if there are discrepancies between the governing law and the
Contract. If there are some discrepancies these should be resolved through Particular
Condition/s.
♦ To be noted also that FIDIC allows for changes in legislation through Sub-clause 13.7.
♦ The ruling language is the one stated in Appendix to Tender and if not, the ruling language is
the one in which the majority of the documents have been written.
♦ The language for communication is the one stated in Appendix to Tender.
♦ It is important to avoid confusion and to define the ruling language and the language for
communication.
It is recommended to have the same ruling and communication language.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 122
61
Dr. D. M. Parikh
1. General Provisions
1.5 Priority of Documents
the Contract Agreement
the Letter of Acceptance
the Letter of Tender
the Particular Conditions
the General Conditions
the Specification
the Drawings
the Schedules and any other documents forming part of Contract
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 123
Dr. D. M. Parikh
1. General Provisions
1.6 Contract Agreement
Parties shall enter into the Contract Agreement within 28 days after the Contractor
receives the Letter of Acceptance, unless they agree otherwise.
1.7 Assignment
No assignment of part or whole of the Contract or benefit or interest in or under the
contract with out prior agreement
62
Dr. D. M. Parikh
1. General Provisions
1.8 Care and Supply of the Documents
This clause deals with the responsibility, custody and caring for the Documents
between the Parties.
Dr. D. M. Parikh
63
Dr. D. M. Parikh
2. Employer
2.1 Access to the Site
♦ The Employer has the responsibility to provide access to the site in the time stated in
Appendix to Tender.
♦ If there is no time stated in Appendix to Tender the access must be provided in a such
manner to not delay the Contractor and his program of Works (Sub-clause 8.3).
♦ Any default would attract claims under Sub Clause 20.1 – EOT + Cost + Profit
♦ Can the Employer withdraw the Site Access?
The Site Access can be withdrawn if the Contractor fails to provide a Performance Security
in accordance with the provisions of the Sub-clause 4.2.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 127
Dr. D. M. Parikh
2. Employer
2.2 Permits, Licenses and Approvals
The Employer shall reasonable assist the Contractor in obtaining permits, licenses and
approvals.
The Employer shall be responsible for the good co-operation of his personnel with the
Contractor and will take similar safety measures and environment protection as
required for the Contractor.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 128
64
Dr. D. M. Parikh
2. Employer
2.4 Employer’s Financial Arrangement
♦ The Employer shall submit, within 28 days after receiving any request from the
Contractor, reasonable evidence that financial arrangements have been made and
are being maintained, which will enable Employer to pay the Contract Price
(estimated at that time) in accordance with Clause 14 [Contract Price and Payments].
♦ If the Employer intends to make any material change to his financial arrangements,
the Employer shall give notice to the Contractor with detailed particulars.
♦ Any defaults from Employer will attract Contractor’s claims under 16.1, 16.2, 16.4,
and 19.6.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 129
Dr. D. M. Parikh
2. Employer
2.5 Employer’s Claims
♦ If the Employer considers himself to be entitled to any payment under any Clause of
these Conditions or otherwise in connection with the Contract, and/or to any
extension of the Defects Notification Period, the Employer or the Engineer shall give
notice and particulars to the Contractor.
♦ The notice shall be given as soon as practicable after the Employer became aware
of the event or circumstances giving rise to the claim. A notice relating to any
extension of the Defects Notification Period shall be given before the expiry of such
period.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 130
65
Dr. D. M. Parikh
2. Employer
2.5 Employer’s Claims
♦ The Employer shall only be entitled to set off against or make any deduction from
an amount certified in a Payment Certificate, or to otherwise claim against the
Contractor, in accordance with this Sub-Clause.
Dr. D. M. Parikh
2. Employer - Exercise
66
Dr. D. M. Parikh
Dr. D. M. Parikh
3. Engineer
3.1 Engineer’s Duties and Authority
♦ The Engineer is carrying out the duties assigned to him under the Contract.
♦ The Engineer deemed to obtain the Employer's specific approval for some issues
which have to be specified in Particular Conditions.
67
Dr. D. M. Parikh
3. Engineer
3.1 Engineer’s Duties and Authority..contd.
♦ However, whenever the Engineer exercises a specified authority for which the
Employer's approval is required, then (for the purposes of the Contract) the
Employer shall be deemed to have given approval.
♦ The Engineer has no authority to relieve either Party of any duties, obligations or
responsibilities.
♦ Any approval, consent, certificate, notice of the Engineer shall not relive the
Contractor from any responsibility under the Contract.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 135
Dr. D. M. Parikh
3. Engineer
3.2 Delegation by the Engineer
♦ The Engineer may time to time assign duties and delegate authority to assistants.
♦ Without the approval of the Parties he can not delegate the authority to make a
determination [sub-Clause 3.5].
68
Dr. D. M. Parikh
3. Engineer
3.3 Instructions of the Engineer
♦ The Engineer may issue to the Contractor (at any time) instructions and additional
or modified Drawings which may be necessary for the execution of the Works and
the remedying of any defects, all in accordance with the Contract.
♦ The Contractor shall only take instructions from the Engineer, or from an assistant
to whom the appropriate authority has been delegated under this Clause.
Dr. D. M. Parikh
3. Engineer
3.4 Replacement of the Engineer
♦ If the Employer intends to replace the Engineer, the Employer shall, not less than
42 days before the intended date of replacement, give notice to the Contractor of
the name, address and relevant experience of the intended replacement Engineer.
♦ The Employer shall not replace the Engineer with a person against whom the
Contractor raises reasonable objection by notice to the Employer, with supporting
particulars.
69
Dr. D. M. Parikh
3. Engineer
3.5 Determination
♦ The Engineer is required to act fairly in making a determination.
♦ There are 2 steps:
A consultative step in order to reach an agreement.
If the Parties cannot have an agreement the Engineer shall act fair and give a
determination.
♦ The determination shall be given to the Parties with supporting documents and justification.
♦ Each Party shall give effect to each agreement or determination unless and until revised by
DAB.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 139
Dr. D. M. Parikh
3. Engineer - Exercise
70
Dr. D. M. Parikh
Dr. D. M. Parikh
4. Contractor
4.1 Contractor’s General Obligations
♦ The Contractor shall design as per the scope specified in the Contract.
♦ The Contractor shall provide the equipment, plants, documents (whatever is needed) to
finalize the Works and remedy the defects.
♦ The Contractor shall be responsible for the safety and all operation on site, permanent or
temporary Works.
71
Dr. D. M. Parikh
4. Contractor
4.2 Performance Security
♦ Within 28 days after the receipt of the Letter of Acceptance the Contractor shall deliver to the Employer
and copy to the Engineer a Performance Security for the amount stated in Appendix to Tender and in the
format requested by the Employer.
♦ The Employer shall indemnify and hold Contractor harmless against and from all damages, losses and
expenses (including legal fees and expenses) resulting from a claim under the Performance Security.
♦ The Employer shall return the Performance Security to the Contractor within 21 days after receiving a
copy of the Performance Certificate.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 143
Dr. D. M. Parikh
4. Contractor
4.2 Performance Security….contd.
♦ The Employer shall not make a claim under the Performance Security, except for amounts to which the
Employer is entitled under the Contract in the event of:
failure by the Contractor to extend the validity of the Performance Security in which event the
Employer may claim the full amount of the Performance Security,
failure by the Contractor to pay the Employer an amount due, as either agreed by the Contractor or
determined under Sub-Clause 3.5 within 42 days after this agreement or determination,
failure by the Contractor to remedy a default within 42 days after receiving the Employer’s notice, or,
72
Dr. D. M. Parikh
4. Contractor
4.3 Contractor’s Representative
♦ The Contractor shall appoint the Contractor's Representative and shall give him all authority
necessary to act on behalf of the Contractors under the Contract.
♦ if the Contractor's Representative was not nominated in the Contractor's offer then the
consent of the Engineer is needed.
♦ The Contractor's Representative is the one who is receiving instructions on behalf of the
Contractor from the Engineer.
♦ The Contractor's Representative must be fluent in the language of contract (Sub-Clause 1.4).
♦ The Contractor's Representative may delegate tasks.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 145
Dr. D. M. Parikh
4. Contractor
4.4 Subcontractors
♦ The Contractor shall not sub-contract the whole of the Works.
♦ The Contractor shall give 28 days' notice of the intended date of commencement by each
sub-contractor for the Engineer's consent.
73
Dr. D. M. Parikh
4. Contractor
4.5 Assignment of Benefit of Subcontract
♦ If a Subcontractor's obligations extend beyond the expiry date of the relevant Defects
Notification Period and the Engineer, prior to this date, instructs the Contractor to assign the
benefit of such obligations to the Employer, then the Contractor shall do so.
♦ Unless otherwise stated in the assignment, the Contractor then shall have no liability to the
Employer for the work carried out by the Subcontractor after the assignment takes effect.
4.6 Co-operation
♦ The Contractor shall ensure the co-operation with the Employer's personnel [Sub-Clause 2.3]
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 147
Dr. D. M. Parikh
4. Contractor
4.7 Setting Out
♦ The Employer is responsible for any errors in these specified or notified items of reference and
the Contractor may claim under Sub-Clause 20.1.
♦ The Contractor is responsible for the positioning of the Works.
74
Dr. D. M. Parikh
4. Contractor
4.9 Quality Assurance
♦ The Contractor shall institute a quality assurance system to demonstrate compliance with the
requirements of the Contract.
♦ Details of all procedures and compliance documents shall be submitted to the Engineer for
information before each design and execution stage is commenced.
♦ Compliance with the quality assurance system shall not relieve the Contractor of any of his
duties, obligations or responsibilities under the Contract.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 149
Dr. D. M. Parikh
4. Contractor
4.10 Site Data
♦ The Employer has the obligation to make available all site data available in his possession
before Base Date.
75
Dr. D. M. Parikh
4. Contractor
4.12 Unforeseeable Physical Conditions
♦ "physical conditions" means natural physical conditions and man-made and other physical obstructions;
which Contractor encounters at the Site while executing Works, including sub-surface and hydrological
conditions but excluding climatic conditions.
♦ The Contractor is entitled to an EOT+ recovery of the costs occurred.
♦ However, the Engineer may also review whether other physical conditions in this parts of the Works (if any)
were more favourable than could reasonably have been foreseen when the Contractor submitted the Tender.
♦ If and to the extent that these more favourable conditions were encountered, Engineer may proceed in
accordance with Sub-Clause 3.5 to agree or determine reductions in Cost which were due to these
conditions, which may be included (as deductions) in Contract Price and Payment Certificates, but shall not
result in a net reduction in Contract Price.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 151
Dr. D. M. Parikh
4. Contractor
4.13 Rights of Way and Facilities
♦ The Contractor shall bear all costs for the temporary Works which may be required, including
the ones for access to the site.
♦ The Contractor shall obtain at his risk and costs all facilities necessary outside the site which
may be required for the execution of the Works.
76
Dr. D. M. Parikh
4. Contractor
4.15 Access Routes
♦ Contractor is deemed to have satisfied himself with the availability of the access routes to the
Site and shall use reasonable efforts to prevent the damage of roads & bridges due to his traffic.
♦ shall be responsible for maintenance that may be required for his use of access routes.
♦ shall provide all necessary signs or directions along access routes, and shall obtain any
permission which may be required from the relevant authorities far his use of routes.
♦ The Employer shall not be responsible for any claims which may arise from the use or otherwise
of any access route; does not guarantee the suitability or availability of particular access routes,
and the Costs due to non-suitability or non-availability, for the use required by the Contractor, of
access routes shall be borne by the Contractor.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 153
Dr. D. M. Parikh
4. Contractor
4.16 Transport of Goods
♦ the Contractor shall give the Engineer not less than 21 days' notice of the date on which any
Plant or a major item of other Goods will be delivered to the Site;
♦ the Contractor shall be responsible for packing, loading, transporting, receiving, unloading,
storing and protecting' all Goods and other things required for the Works; and
♦ the Contractor shall indemnify and hold the Employer harmless against and from all damages,
losses and expenses (including legal fees and expenses) resulting from the transport of Goods,
and shall negotiate and pay all claims arising from their transport.
77
Dr. D. M. Parikh
4. Contractor
4.17 Contractor's Equipment
♦ The Contractor shall be responsible for all Contractor's Equipment.
♦ When brought on to the Site, Contractor's Equipment shall be deemed to be exclusively intended for the
execution of the Works.
♦ The Contractor shall not remove from Site any major items of Equipment without the consent of Engineer.
Consent, however, is not required for vehicles transporting Goods or Contractor's Personnel off Site.
Dr. D. M. Parikh
4. Contractor
4.19 Electricity, Water and Gas
♦ The Contractor shall be responsible for the provision of all power, water and other services he
may require.
♦ The Contractor shall be entitled to use for the purposes of the Works such supplies of
electricity, water, gas and other services as may be available on the Site. The Contractor shall,
at his risk and cost, provide any apparatus necessary for his use of these services and for
measuring the quantities consumed.
♦ The quantities consumed and the amounts due (at these prices) for such services shall be
agreed or determined by the Engineer in accordance with Sub-Clause 2.5 [Employer's Claims]
and Sub-Clause 3.5 [Determinations]. The Contractor shall pay these amounts to the Employer.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 156
78
Dr. D. M. Parikh
4. Contractor
4.20 Employer's Equipment and Free-Issue Material
♦ The Employer shall make the Employer's Equipment (if any) available for the use of the
Contractor in the execution of the Works in accordance with the details, arrangements and
prices stated in the Specification. Unless otherwise stated in the Specification:
the Employer shall be responsible for the Employer's Equipment, except that
the Contractor shall be responsible for each item of Employer's Equipment whilst any of
Contractor's Personnel is operating it, driving it, directing it or in possession or in control.
♦ The appropriate quantities and the amounts due (at such stated prices) for the use of
Employer's Equipment shall be agreed or determined by the Engineer in accordance with Sub-
Clause 2.5 [Employer's Claims] and Sub-Clause 3.5 [Determinations]. The Contractor shall pay
these amounts to the Employer.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 157
Dr. D. M. Parikh
4. Contractor
4.20 Employer's Equipment and Free-Issue Material….contd.
♦ The Employer shall supply, free of charge, the "free-issue materials" (if any) in accordance with
the details stated in the Specification. The Employer shall, at his risk and cost, provide these
materials at the time and place specified in the Contract. The Contractor shall then visually
inspect them, and shall promptly give notice to the Engineer of any shortage, defect or default
in these materials, Unless otherwise agreed by both Parties, the Employer shall immediately
rectify the notified shortage, defect or default.
♦ After this visual inspection, the free-issue materials shall come under the care, custody and
control of the Contractor. The Contractor's obligations of Inspection, care, custody and control
shall not relieve the Employer of liability for any shortage, defect or default not apparent from a
visual Inspection.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 158
79
Dr. D. M. Parikh
4. Contractor
4.21 Progress Reports
The Contractor to submit Progress Reports it within 7 day of end of month & to continue to submit
till outstanding works at Taking over Certificate are completed. Each report shall include:
♦ Charts and detailed description of progress, including each stage of design (if any),
Contractor’s Documents, procurement, manufacture, delivery at site, construction, erection and
testing; [Add for RB: including these stages of work by each nominated Subcontractor] [Add for
YB: commissioning and trial operation]
♦ for the manufacture of each main item of Plant and Materials, the name of the manufacturer,
location, percentage progress, and the actual or expected dates of commencement, inspection,
tests and shipment & arrival at Site.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 159
Dr. D. M. Parikh
4. Contractor
Required for Period of
4.21 Progress Reports….contd. certification of Payment under
IPC [14.3] 14.7 doesn’t
Each report shall include…contd. commence
♦ photographs showing the status of manufacture and of progress on the Site
♦ records of Contractor’s Personnel and Equipment (6.1)
♦ QA documents, test results and certificates of Materials
♦ list of variations [YB only] and notices under 2.5 and 20.1
♦ safety statistics including incidents & activities related to environmental aspects
♦ comparison of actual and planned progress, with details of event(s) which may hinder the
completion as per Contract and mitigation measures to overcome delays
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 160
80
Dr. D. M. Parikh
4. Contractor
4.22 Security of the Site
♦ The Contractor is responsible for the Site security
4.24 Fossils
♦ When founded shall be placed on the care and authority of the Employer. Subject to
Sub-Clause 20.1 the Contractor may be entitled to an EOT + Costs occurred.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 161
Dr. D. M. Parikh
4. Contractor - Exercise
81
Dr. D. M. Parikh
Dr. D. M. Parikh
5. Nominated Subcontractor
5.1 Definition of Nominated Sub-contractors
♦ in the Contract, "nominated Subcontractor" means a Subcontractor:
whom the Engineer, under Clause 13 [Variations and Adjustments], instructs the
Contractor to employ as a Subcontractor.
82
Dr. D. M. Parikh
5. Nominated Subcontractor
5.2 Objection to Nomination
The Contractor is not under any obligation to employ a nominated Subcontractor
against whom he raises reasonable objection, including but not limited to;
♦ If there are reasons to believe that the Subcontractor does not have sufficient
competence, resources or financial strength.
♦ If the subcontract does not specify that the nominated Subcontractor shall indemnify
the Contractor against and from any negligence or misuse of Goods by the
nominated Subcontractor, his agents and employees.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 165
Dr. D. M. Parikh
5. Nominated Subcontractor
5.2 Objection to Nomination
The Contractor is not under any obligation to employ a nominated Subcontractor
against whom he raises reasonable objection…..contd.
♦ If the subcontract does not specify that, for the subcontracted work (including
design, if any), the nominated Subcontractor shall:
Undertake to the Contractor such obligations and liabilities as will enable the Contractor
to discharge his obligations and liabilities under the Contract, and
Indemnify the Contractor against an from all obligations and labilities arising under or in
connection with the Contract and from the consequences of any failure by the
Subcontractor to perform these obligations or to fulfil these liabilities.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 166
83
Dr. D. M. Parikh
5. Nominated Subcontractor
5.3 Payments to Nominated Subcontractors
♦ The Contractor shall pay to the nominated Subcontractor the amounts which the Engineer
certifies to be due in accordance with the subcontract.
♦ The Employer may (at his sole discretion) pay, direct to the nominated Subcontractor, part or
all of such amounts previously certified (less applicable deductions) as are due to the
nominated Subcontractor and for which the Contractor failed to submit the evidence.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 167
Dr. D. M. Parikh
Clause 5: Design
84
Dr. D. M. Parikh
5. Design
5.1 General Design Obligations
♦ The Contractor shall carry out and be responsible for the design of the Works.
♦ The Contractor warrants that he, his designers, his design Sub-contractor has the
experience and capability necessary for the design.
Dr. D. M. Parikh
5. Design
5.3 Contractor's Undertaking
5.4 Technical Standards and Regulations
♦ The Contractor shall prepare the design in accordance with the laws in the Country and shall
comply with the Country's standards and regulation and the standards mentioned in the
Employer's requirements.
85
Dr. D. M. Parikh
5. Design
Engineer to
Design Procedure
give Consent
Engineer to
International Federation of Consulting Engineers review in 21
The Global Voice of Consulting Engineers days 171
Dr. D. M. Parikh
Quiz
NO QUESTION YES NO MAYBE
1 How many Main Clauses are in the Red/Yellow Book? Provide no.
2 How many Main Clauses are different in the Red/Yellow Book? Provide no.
3 Is the Engineer an independent entity in the Contract?
4 In the Red Book: does the BOQ take precedence to the Specifications?
5 Does FIDIC measures the time in working days?
6 In Red Book: can the designer directly instruct the Contractor?
7 Does the term 'Works' in FIDIC means the permanent works?
8 The written communication can be done by e-mail?
9 The ruling language and the language for communications has to be the same?
10 The Engineer has to nominate a person who acts as “the Engineer”?
11 Can Contractor at any time request for the Employer's financial arrangements?
12 Can the Engineer delegate all his authorities to his Resident Engineer?
13 Can the Engineer be changed?
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 172
86
Dr. D. M. Parikh
Quiz
NO QUESTION YES NO MAYBE
14 Can Contractor request the change of a person from the Engineer's team?
15 Can the Engineer request change of a person from the Contractor's team?
16 A Sub-contractor mentioned in the Contractor's offer has to be approved?
17 The Engineer has to approve the Contractor's Monthly Progress Report?
18 Is there a time limit for the Engineer to issue a determination under 3.5?
19 Is the Engineer required to consult the Contractor before issuing a determination in
accordance with 3.5?
20 Can the Engineer be changed with another one if the Contractor reasonably objected to
the new Engineer?
21 The Contractor has to visit the Site during the Tender period.
22 Is the Contractor obliged to employ a nominated Sub-contractor?
23 YB. if the Engineer approve the Contractor's design then the Engineer remain responsible
for the errors found in the Design?
Dr. D. M. Parikh
Management of Projects
87
Dr. D. M. Parikh
Dr. D. M. Parikh
88
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ In collaboration with local health authorities, the Contractor shall ensure that medical staff, first
aid facilities, sick bay and ambulance service are available at all times at the Site and at any
accommodation for Contractor's and Employer's Personnel.
♦ The Contractor shall appoint an accident prevention officer at the Site, responsible for
maintaining safety and protection against accidents.
89
Dr. D. M. Parikh
Dr. D. M. Parikh
90
Dr. D. M. Parikh
Dr. D. M. Parikh
91
Dr. D. M. Parikh
7.2 Samples
♦ The Contractor shall submit samples of Materials, and relevant information, to the Engineer for
consent prior to using the Materials in or for the Works.
♦ Manufacturer's standard samples of Materials and samples specified in the Contract, all at the
Contractor's cost, and;
♦ Additional samples instructed by the Engineer as a Variation.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 183
Dr. D. M. Parikh
have full access to all parts of Site and to all places from which natural Materials are
being obtained, and;
during production, manufacture and construction (at Site and elsewhere), be entitled to
examine, inspect, measure and test the materials and workmanship, and to check the
progress of manufacture of Plant and production and manufacture of Materials.
92
Dr. D. M. Parikh
♦ Engineer shall then either carry out the examination, or testing without unreasonable delay,
or promptly give notice to the Contractor that he does not require to do so.
♦ If the Contractor fails to give the notice, he shall, if and when required by the Engineer,
uncover the work and thereafter reinstate and make good, all at the Contractor's cost.
Dr. D. M. Parikh
93
Dr. D. M. Parikh
♦ If the Engineer requires this Plant, Materials or workmanship to be retested, the tests shall be
repeated under the same terms and conditions.
♦ If the rejection and retesting cause the Employer to incur additional costs, the Contractor shall
subject to Sub-Clause 2.5 and pay these costs to the Employer.
Dr. D. M. Parikh
94
Dr. D. M. Parikh
7.8 Royalties
♦ Contractor shall pay all royalties and other payments for; Natural materials obtained outside
Site, and, responsible for disposal of materials from demolition, excavation or other surplus.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 189
Dr. D. M. Parikh
95
Dr. D. M. Parikh
Dr. D. M. Parikh
the order in which the Contractor intends to carry out the Works
each of the stages for work being carried out by each nominated Subcontractor
the sequence and timing of inspections and tests
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 192
96
Dr. D. M. Parikh
Dr. D. M. Parikh
42 days 28 days
28 days
Performance
Security 4.2
97
Dr. D. M. Parikh
Dr. D. M. Parikh
Contractor Contractor advises Engineer with (within 42 days of receipt consult with
considers Engineer within 28 detailed particulars of claim or particulars) on Employer and
himself days of occurrence within 42 days. the principles of the claim Contractor to
entitled to yes of event yes For continuing event with approval or rejection reach agreement
EOT interim particulars at with detailed comments on EOT and
intervals of not more and proceed in accordance additional
than 28 days with Clause 3.5 payment, if any
no no
Clause 20.1 Clause 20.1
2nd Paragraph-No EOT claim may be
EOT may be given restricted if
and Employer Contractor’s failure
discharged from has prevented or
liability prejudiced proper
International Federation of Consulting Engineers investigation
The Global Voice of Consulting Engineers 196
98
Dr. D. M. Parikh
Then this delay or disruption will be considered as a cause of delay in Sub-Clause 8.4.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 197
Dr. D. M. Parikh
99
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ If with in 28 days he does not receive the permission, the Contractor may (by notifying the
Engineer) treat the suspension as an omission under Clause 13.
♦ If the suspension is for the whole Work then the Contractor may terminate the Contract in
accordance with Sub-Clause 16.2.
100
Dr. D. M. Parikh
Dr. D. M. Parikh
9. Tests on Completion
9.1 Contractor's Obligations
♦ The Contractor shall give to the Engineer not less than 21 days' notice of the date after which
the Contractor will be ready to carry out each of the Tests on Completion.
♦ Unless otherwise agreed, Tests on Completion' shall be carried out within 14 days after this
date, on such day or days as the Engineer shall instruct.
♦ As soon as the Works, or a Section, have passed any Tests on Completion, the Contractor shall
submit a certified report of the results of these Tests to the Engineer.
101
Dr. D. M. Parikh
9. Tests on Completion
9.2 Delayed Tests
♦ If the Tests on Completion are being unduly delayed by the Employer, the Contractor is
entitled to E0T+COST+PROFIT after following the procedure of Sub-Clause 20.1.
♦ If delays are caused by the Contractor, then Employer's personnel may proceed with the
tests at the Contractor's risk and costs.
9.3 Retesting
♦ If the Works, or a Section, fail to pass the Tests on Completion, Sub-Clause 7.5 shall apply,
and the Engineer or the Contractor may require the failed Tests, and Tests on Completion on
any related work, to be repeated under the same terms and conditions.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 203
Dr. D. M. Parikh
9. Tests on Completion
9.4 Failure to Pass Tests at Completion
♦ lf the failure prejudice the Employer of the benefit of the Work then the Employer is entitled to
recover all the sums paid + financing costs and the costs of dismantling, clearing the site and
returning Plant and Materials – applies to part of Work of whole Work.
♦ Issue a Taking Over for the remaining Work/section and the Contract Price shall be reduced
after procedures in line with Sub-Clauses 2.5 and 3.5.
102
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ If the Contractor incurs delay or costs the he may claim under 20.1 – EOT + Cost + Profit
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 206
103
Dr. D. M. Parikh
Dr. D. M. Parikh
104
Dr. D. M. Parikh
♦ complete any work which is outstanding on the date stated in a Taking-Over Certificate,
within such reasonable time as is instructed by the Engineer, and
♦ execute all work required to remedy defects or damage, as may be notified by (or on behalf
of) the Employer on or before the expiry date of the Defects Notification Period for the Works
or Section (as the case may be).
Dr. D. M. Parikh
♦ When the defects are attributable to other cause/s –Variation Procedure (Sub-Clause 13.3)
shall apply.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 210
105
Dr. D. M. Parikh
Dr. D. M. Parikh
106
Dr. D. M. Parikh
♦ Unless the defect is to be remedied at the cost of the Contractor under Sub-Clause 11.2, the Cost of the
search plus reasonable profit shall be agreed or determined by the Engineer in accordance with Sub-
Clause 3.5 and shall be included in the Contract Price.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 213
Dr. D. M. Parikh
107
Dr. D. M. Parikh
♦ If all these items have not been removed within 28 days after the Employer receives a copy
of the Performance Certificate, the Employer may sell or otherwise dispose of any remaining
items.
Dr. D. M. Parikh
108
Dr. D. M. Parikh
Quiz
NO QUESTION YES NO MAYBE
1 Is the Contractor obliged to have permanent on-site medical aid?
2 If the Engineer changes the location of the Tests, is the Contractor entitled to an EOT +
Costs + Profit?
3 Is the Tender Program of Works the same as the one submitted in accordance with Sub-
Clause 8.3?
4 Is the Engineer obliged to approve the Contractor's Program of Works?
5 The Costs of Remedying defects after Completion are Contractor's risk?
6 The Contractor must complete all the Works before the Taking-Over Certificate is issued?
7 If the Contractor fails to remedy the defects, can the Engineer instruct another Contractor to
remedy them?
8 The Performance Certificate constitute the acceptance of the works?
9 After Performance Certificate is issued- Are the Parties any more liable?
10 Is the Contractor entitled to Costs if the Engineer suspends the Works?
Dr. D. M. Parikh
109
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ Wherever any Permanent Works are to be measured from records of construction, these shall
be prepared by the Engineer. The Contractor shall, as and when requested, attend to examine
and agree the records with the Engineer, and shall sign the same when agreed.
♦ If the Contractor examines and disagrees the records, and/or does not sign them as agreed then
the Contractor shall give notice to the Engineer of the respects in which the records are asserted
to be inaccurate.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 220
110
Dr. D. M. Parikh
♦ If the Contractor does not give notice to the Engineer within 14 days after being requested to
examine the records, they shall be accepted as accurate.
♦ The method of measurement shall be in accordance with the Bill of Quantities or other
applicable Schedules.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 221
Dr. D. M. Parikh
111
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ If no rates or prices are relevant for the derivation of a new rate or price, it shall be derived
from the reasonable Cost of executing the work, together with reasonable profit, taking
account of any other relevant matters.
♦ Until such time as an appropriate rate or price is agreed or determined, the Engineer shall
determine a provisional rate or price for the purposes of Interim Payment Certificates.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 224
112
Dr. D. M. Parikh
Upon receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5
[Determinations] to agree or determine this cost, which shall be included in the Contract Price.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 225
Dr. D. M. Parikh
113
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ If, for reasons not attributable to the Contractor, a Test after Completion on the Works or any
Section cannot be completed during the Defects Notification Period then the Works or
Section shall be deemed to have passed this Test after Completion.
114
Dr. D. M. Parikh
The Contractor is responsible for remedying Work under Sub-Clause 11.1, and
♦ If the Employer incurs additional costs, the Contractor shall be subjected to Sub-Clause 2.5
and may need to pay these costs to the Employer.
Dr. D. M. Parikh
the relevant sum payable as non-performance damages for this failure is stated in the
Contract, and
the Contractor pays this relevant sum to the Employer during DNP
115
Dr. D. M. Parikh
♦ If the Contractor incurs additional Cost as a result of any unreasonable delay by the
Employer in permitting access, the Contractor may claim under 20.1 Cost + reasonable
profit. the Engineer to determine under 3.5.
Dr. D. M. Parikh
116
Dr. D. M. Parikh
Dr. D. M. Parikh
117
Dr. D. M. Parikh
Dr. D. M. Parikh
118
Dr. D. M. Parikh
𝑃 =𝑎+𝑏 +𝑐 +𝑑 +⋯ , a+b+c+d+…=1
Lo", "Eo", "Mo", ... are the base cost indices (in relevant currency of payment) on Base Date.
“Ln", “En", “Mn", ... are the current cost indices on the date 49 d prior to the last day of period of
particular Payment Certificate relates
♦ For cost variation during Contract period, this formulae to be used to adjust for changes in
the cost of labour and materials (addition or deduction).
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 237
Dr. D. M. Parikh
each index or price applicable on the date 49 days prior to the expiry of Time for Completion,
OR, the current index or price: whichever is more favourable to the Employer
♦ Employers who currently use different procedures for evaluation of inflation costs may prefer to
continue to use their own procedures and make the appropriate provisions in Particular
Conditions.
119
Dr. D. M. Parikh
Dr. D. M. Parikh
120
Dr. D. M. Parikh
♦ The quantities are estimates and are not to be taken as the actual and correct quantities.
♦ In the Yellow Book it is mentioned that the quantities in the schedule are only for the purpose
stated in the schedule for the Works and may be not applicable for other purposes.
Dr. D. M. Parikh
♦ If Advance payment is not mentioned in the Appendix to Tender then this sub-clause is N.A.
♦ Deduction will start when 10% of the Accepted Contract Price minus Provisional Sums has
been reached. It will be in tranches of 25% of the amount in each IPC.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 242
121
Dr. D. M. Parikh
Dr. D. M. Parikh
no no no
Unspecified Amount need Unspecified Schedule of Payment
not be certified Sub-Clause 14.4, may be
written into the Contract.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 244
122
Dr. D. M. Parikh
yes
50% of retention
released Schedule of Payment
Sub-Clause 14.4, may be
written into the Contract.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 245
Dr. D. M. Parikh
♦ If actual progress is slower than that upon which the schedule was based, the Engineer
becomes entitled to propose or determine (under Sub-Clause 3.5) revised instalments.
♦ If schedule is not defined in the Contract, then Contractor shall submit non binding estimates of
payment/s for each quarterly period. The first estimate must be submitted within 42 days after
the Commencement Date.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 246
123
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ In 28 days after receiving the Statement with particulars the Engineer shall issue IPC with
supporting particulars which shall state the amount due to the Contractor.
♦ The Engineer may at any time make corrections in any IPC or any previous Certificate.
124
Dr. D. M. Parikh
if supplied items/s or work done by the Contractor is not in accordance with the Contract,
the cost of rectification or replacement may be withheld until rectification or replacement
is completed; and/or
if the Contractor was or is failing to perform any work or obligation in accordance with the
Contract, and had been so notified by the Engineer, the value of this work or obligation
may be withheld until the work or obligation has been performed.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 249
Dr. D. M. Parikh
♦ the amount to be certified in each Interim Payment Certificate within 56 days after the
Engineer receives the Statement and supporting documents; and
♦ the amount to be certified in the Final Payment Certificate within 56 days after the Employer
receives this Payment Certificate.
125
Dr. D. M. Parikh
♦ The entitlement is without being necessary to notify or claim under Sub-Clause 20.1.
Dr. D. M. Parikh
♦ When calculating these provisions no account shall be taken for Adjustments under Sub-Clause
13.7 [Changes in legislation] and Sub-Clause 13.8 [Changes in costs].
126
Dr. D. M. Parikh
Value of the Works done up to the date stated in the Taking Over Certificate,
Dr. D. M. Parikh
127
Dr. D. M. Parikh
Dr. D. M. Parikh
128
Dr. D. M. Parikh
Dr. D. M. Parikh
Final Statement
Final Payment 56 Days
after DNP
Certificate 28 days
Payment delay 56 Days
129
Dr. D. M. Parikh
Quiz
NO QUESTION YES NO MAYBE
1. Does the Contractor has to agree on result of measurement of Works by the Engineer?
2. Should the method of measurement be mentioned in Contract?
3. Can the Engineer request the breakdown of prices from the Contractor?
4. Does the Cost include financing charges?
5. RB: Is the Contract Price fixed form the beginning of the Contract?
6. Can the Engineer make corrections in the previous Payment Certificates?
7. Do the Provisional Sums have to be spent within the Time for Completion?
8. If there are arithmetic errors in an IPC, is the Employer obliged to pay?
9. Must the Contractor put all financial claims in the next statement after the Employer took
over the Works?
10. Does the Contractor have to produce a Monthly Cash Flow?
Dr. D. M. Parikh
130
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ If the Contractor fails to carry out any obligation under the Contract, the Engineer may by
notice require the Contractor to make good the failure and to remedy it within a specified
reasonable time.
131
Dr. D. M. Parikh
Dr. D. M. Parikh
132
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ The Contractor shall proceed in accordance Sub-Clause 16.3 [Cessation of Work and Removal
of the Contractor's Equipment].
♦ The Contractor shall be paid in accordance with Sub-Clause 19.6 (Optional Termination,
Payment and Release].
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 266
133
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ If due to the suspension the Contractor suffers delays and/or costs then Sub-Clause 20.1
applies – EOT+Cost+profit.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 268
134
Dr. D. M. Parikh
Dr. D. M. Parikh
cease all further work, except for such work as may have been instructed by the Engineer
for the protection of life or property or for the safety of the Works,
hand over Contractor's Documents, Plant, Materials and other work, for which the
Contractor has received payment, and;
remove all other Goods from the Site, except as necessary for safety, and leave the Site.
135
Dr. D. M. Parikh
Dr. D. M. Parikh
136
Dr. D. M. Parikh
The Contractor shall indemnify and hold harmless the Employer, the Employer's personnel,
and their agents.
The Employer shall indemnify and hold harmless the Contractor, the Contractor's personnel
and their agents.
Dr. D. M. Parikh
♦ Before TOC: If loss or damages occur from a cause which is not listed in the Employer's risk
the Contractor shall remedy the defects on his own cost and risk.
♦ After TOC: The Contractor is responsible for the Works after the Taking-Over Certificate is
issued for damages caused by any actions done by the Contractor.
137
Dr. D. M. Parikh
Dr. D. M. Parikh
138
Dr. D. M. Parikh
♦ The total liability of the Contractor to the Employer, under or in connection with the Contract
shall not exceed the sum stated in the Particular Conditions or (if a sum is not so stated) the
Accepted Contract Amount.
♦ This Sub Clause shall not limit liability in any case of fraud, deliberate default or reckless
misconduct by the defaulting party.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 277
Dr. D. M. Parikh
139
Dr. D. M. Parikh
18. Insurance
18.1 General Requirements for Insurances
♦ Wherever the Contractor is the insuring Party, each insurance shall be effected with insurers
and in terms approved by the Employer.
♦ Wherever the Employer is the insuring Party, each insurance shall be effected with insurers
and in terms consistent with the details annexed to the Particular Conditions.
♦ The relevant insuring Party shall, submit to the other Party evidence that the insurances
have been effected, evidence of insurance – and copies of the policies.
♦ Neither Party shall make any alteration to the terms of any insurance without the prior
approval of the other Party.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 279
Dr. D. M. Parikh
18. Insurance
18.2 Insurance for Works and Contractor's Equipment
♦ The insuring Party shall insure the Works, Plant, Materials and Contractor's Documents for not
less than the full reinstatement cost.
♦ This insurance shall be effective from the date by which the evidence is to be submitted under
sub-paragraph (a) of Sub-Clause 18.1 [General Requirements for Insurances], until the date of
issue of the Taking-Over Certificate for the Works.
♦ The insuring Party shall maintain this insurance to provide cover until the date of issue of the
Performance Certificate, for loss or damage for which the Contractor is liable.
♦ The insuring Party shall insure the Contractor's Equipment for not less than the full replacement
value, including delivery to Site.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 280
140
Dr. D. M. Parikh
18. Insurance
18.3 Insurance against injury to Persons & Damage to Property
♦ This is third party insurance with limit per event as stated in Appendix to Tender.
Dr. D. M. Parikh
141
Dr. D. M. Parikh
which such Party could not reasonably have provided against before entering into the
Contract,
which, having arisen, such Party could not reasonably have avoided or overcome, and
Dr. D. M. Parikh
♦ The Party shall, having given notice, be excused from performance of such obligations for so
long as such Force Majeure prevents it from performing them.
♦ Force Majeure shall not apply to obligations of either Party to make payments to the other
Party under the Contract.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 284
142
Dr. D. M. Parikh
♦ A Party shall give notice to the other Party when it ceases to be affected by the Force
Majeure
Dr. D. M. Parikh
143
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ The termination shall take effect 7 days after the notice is given, and the Contractor shall
proceed in accordance with Sub-Clause 16.3.
144
Dr. D. M. Parikh
Dr. D. M. Parikh
the sum payable by the Employer to the Contractor shall be the same as would have
been payable under Sub-Clause 19.6.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 290
145
Dr. D. M. Parikh
Quiz
NO QUESTION YES NO MAYBE
1. Is the Employer entitled to terminate the Contract if the Contractor does not submit a
Performance Security under Sub-Clause 4.2?
2. Is the Employer entitled to terminate the Contract if the Contractor subcontracts all the
Works?
3. Is the Employer entitled to terminate the Contract at his own discretion?
4. If the Contractor does not receive his payment, is he entitled to terminate the Contract?
5. If at the Contractor's request the Employer does not share his financial arrangements; is
the Contractor entitled to terminate the Contract?
6. Any operation of the forces of nature, which is Unforeseeable or against which an
experienced contractor could not reasonably have taken adequate preventative
precautions; is this Employer's risk?
Dr. D. M. Parikh
146
Dr. D. M. Parikh
Employer’s Claims
2.5 Employer’s Claims
If the Employer considers himself to be entitled to any payment under or in connection with the
contract, and/or to any extension of the Defects Notification Period, the Employer or the Engineer
must give 'notice and particulars' to the contractor. The particulars must 'specify the Clause or
other basis of the claim ....
The notice must be given as soon as practicable (no time limit) after the employer became aware
of the event or circumstance giving rise to the claim. The employer is expressly denied the right
to set off against or make any deduction from a certified amount or otherwise claim against the
contractor, except in accordance with this provision.
Dr. D. M. Parikh
147
Dr. D. M. Parikh
Dr. D. M. Parikh
148
Dr. D. M. Parikh
Dr. D. M. Parikh
Contractor’s Claims
20.1 Contractor’s Claims: Notice [Conditional Precedent]
If the Contractor considers himself to be entitled to any extension of time for Completion and/or
any additional payment under any clause of these conditions or otherwise in connection with the
contract, the Contractor shall give notice to the Engineer, describing the event or circumstance
giving rise to the claim.
The notice shall be given as soon as practicable, and not later than 28 days after the Contractor
became aware, or should have became aware of the event or circumstance.
If the Contractor fails to give notice to the engineer of any claim not later than 28 days after the
Contractor became aware, or should have become aware, of the event or circumstance' giving
rise to a claim, the employer is discharged from all liability in connection with the claim.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 298
149
Dr. D. M. Parikh
Contractor’s Claims
20.1 Contractor’s Claims: [Contemporary Records]
The Contractor shall keep such contemporary records as may be necessary to substantiate any
claim, either on the Site or at another location acceptable to the Engineer. Without admitting the
Employer’s liability, the Engineer may, after receiving any notice under this Sub-Clause, monitor
the record-keeping and/or instruct the Contractor to keep further contemporary records….. and
shall (if instructed) submit copies to the Engineer [Employer]
Dr. D. M. Parikh
Contractor’s Claims
Contemporary records typically include:
Site diaries, with details of weather conditions, status of progress & causes of delays encountered
Construction progress charts, which include records of subsoil strata, water levels, etc.
Programmes of future work + a copy of each revision of the programme
Details of plant, materials & labour
Details of site costs: supervisory + non-productive labour, office costs (telephone, water supply, transport,
insurances, watching and lighting …)
All correspondences with Employer, Engineer and Engineer's representative- reg. variations, instructions,
amended drawings, contractor's confirmation of oral instructions and contractor's notifications to Engineer of
information required or of any matter causing or likely to cause delay to the progress of the works
Correspondence with other parties, such as subcontractors, suppliers and any other organizations or
services required in connection with the works
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 300
150
Dr. D. M. Parikh
Contractor’s Claims
Cl. 20.1 Claims Cl. 20.1 (a) Cl. 20.1 (b) Cl.20.1 (c) Details
in connection Notices to the Contemporary and Particulars-
with Contract Engineer Records basis of claims
Contractor considers to be describing the even or Contractor shall keep within 42 d the Contractor
entitled to any extension of circumstances giving rise to contemporary records on shall send a fully detailed
the Time for Completion and the claim not later than 28 d Site to substantiate the claim which includes full
/ or any additional payment claim supporting particulars of the
basis of the claim
Contractor became or
should have become aware if Contractor fails to give to be kept on Site, visit for If the contractor fails to
of the event notice within 28 d, then no the Representative establish the principles of the
entitlement claim within 42 d, the notice
< 28 d given shall be deemed to have
< 42 d lapsed and no longer
considered as a valid notice
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 301
Dr. D. M. Parikh
Contractor’s Claims
Cl.20.1 (c) Details Cl. 20.1 (d) Engineer
and Particulars- Respond
basis of claims
within 42 d the contractor within 42 d Engineer shall the Determinations shall be binding until
shall send a fully detailed respond with approval or revised under § 20 Claims, Disputes and
claim including full disapproval and detailed Arbitration
supporting particulars of comments and shall proceed in (notice of dissatisfaction within 28 d and
basis of claim accordance with § 3.5 thereafter proceed in accordance in writing to
the DAB for its decision)
151
Dr. D. M. Parikh
Contractor’s Claims
Sub-Clause 20.1 and Sub-Clause 3.5
Time Line
Contemporary
sub-clause 20.1 Records on Site
Dr. D. M. Parikh
Contractor’s Claim
(Under Sub-Clause 20.1)
Engineer’s Examination
No Dispute DAB / Arbitration
(Under Sub-Clause 3.5)
Yes
152
Dr. D. M. Parikh
Contractor’s Claims
20.1 Contractor’s Claims: [Contemporary Records]
The Contractor shall keep such contemporary records as may be necessary to substantiate any
claim, either on the Site or at another location acceptable to the Engineer. Without admitting the
Employer’s liability, the Engineer may, after receiving any notice under this Sub-Clause, monitor
the record-keeping and/or instruct the Contractor to keep further contemporary records….. and
shall (if instructed) submit copies to the Engineer [Employer]
Dr. D. M. Parikh
Contractor’s Claims
Clauses Requiring Notice
153
Dr. D. M. Parikh
Contractor’s Claims
Clauses Entitling Compensation
Dr. D. M. Parikh
Contractor’s Claims
Clauses Entitling Compensation….contd.
154
Dr. D. M. Parikh
Contractor’s Claims
Clauses Entitling Compensation [Cost + Profit]
Clause 1.9 Delayed drawings or instructions [RB] / Errors in
Employer’s Requirements [YB]
Clause 2.1 Right of access to site
Clause 4.7 Setting out
Clause 7.4 Testing
Clause 10.2 Taking over parts of the works
Clause 11.8 Contractor to search
Clause 16.1 Contractor’s entitlement to suspend work
Clause 16.4 Payment on termination
Clause 17.4 Consequences of Employers risks
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 309
Dr. D. M. Parikh
Notices by Contractor
Sub-Clause Title Adjustment To
1.8 Care & supply of documents - EM
1.9 Delayed drawings or instructions T+C+P EN
2.1 Right of Access to the Site T+C+P EN
4.7 Co-operation T+C+P EN
4.12 Unforeseeable physical conditions T+C EN
4.24 Fossils T+C EN
7.4 Testing T+C+P EN
8.4 Extension of time for completion T EN
8.9 Consequences of suspension T+C EN
8.11 Prolonged suspension Termination EN
10.1 Taking Over the Works & Sections - EN
155
Dr. D. M. Parikh
Notices by Contractor
Sub-Clause Title Adjustment To
10.2 Taking Over parts of the Works C+P EN
10.3 Interference with Tests on Completion T+C+P EN
11.8 Contractor to search C+P EN
13.7 Adjustments for changes in legislation T+C EN
16.1 Entitlement to suspend work T + C +P EN
17.4 Consequences of Employer’s risks T+C EN
19.2 Notice of force majeure - EM
19.3 Duty to minimise delay - EM
19.4 Consequences of force majeure T+C EN
20.1 Contractor’s claims - EN
20.4 Dissatisfaction of DAB’s decision - EM
Dr. D. M. Parikh
156
Dr. D. M. Parikh
♦ However, quite often its unique aim is to avoid disputes, meaning that it will take actions
before a dispute arises.
♦ There is a choice between a three member board or a one member board – It is normally
defined at Tender stage.
Dr. D. M. Parikh
All procedures are same in both All procedures are same in both
FIDIC books FIDIC books
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 314
157
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ A model form of a Dispute Adjudication Agreement is part of the FIDIC Books. This
Agreement is governed by law of contract.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 316
158
Dr. D. M. Parikh
♦ Contractor and Employer shall give notice that the Agreement to become effective within a
period of six months, if not the Agreement becomes null and void.
♦ The fees are subject to negotiations, FIDIC has not published any recommendations.
Dr. D. M. Parikh
159
Dr. D. M. Parikh
♦ When appointing the Member, the Employer and the Contractor relied upon the Member's
representations that he/she is:
experienced in the work which the Contractor is to carry out under the Contract,
experienced in the interpretation of contract documentation, and;
fluent in the language for communications defined in the contract.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 319
Dr. D. M. Parikh
♦ comply with the procedural rules and with Sub-Clause 20.4 of the Conditions of Contract.
♦ shall ensure his/her availability for any site visit and hearings as are necessary.
♦ shall treat the details of the Contract and all the DAB's activities and hearings as private and
confidential.
160
Dr. D. M. Parikh
♦ If 3 members then each party nominates one for approval from other party. Two members
and parties shall agree to the Third member.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 321
Dr. D. M. Parikh
Then, appointing entity mentioned in the Appendix to Tender will nominate DAB and that shall be
binding.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 322
161
Dr. D. M. Parikh
Dr. D. M. Parikh
♦ If DAB fails to give decision in 84 days then either party can give notice of dissatisfaction to
other party.
162
Dr. D. M. Parikh
DAB Procedure
Notice of intention to
Appointment DAB
28 d
112 days
Submission of additional Access to
Experts
84 days
Dr. D. M. Parikh
163
Dr. D. M. Parikh
Arbitration
20.6 Arbitration
♦ Unless settled amicably, any dispute in respect of which the DAB's decision (if any) has not
become final and binding shall be finally settled by international arbitration. Unless otherwise
agreed by both Parties:
the dispute shall be finally settled under the Rules of Arbitration of the International
Chamber of Commerce,
the dispute shall be settled by three arbitrators appointed in accordance with these
Rules, and
the arbitration shall be conducted in the language for communications defined in Sub-
Clause 1.4 [Law and Language].
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 327
Dr. D. M. Parikh
Arbitration
20.6 Arbitration….contd.
♦ The arbitrator(s) shall have full power to open up, review and revise any certificate,
determination, instruction, opinion or valuation of the Engineer, and any decision of the
DAB, relevant to the dispute. Nothing shall disqualify the Engineer from being called as a
witness and giving evidence before the arbitrator(s) on any matter whatsoever relevant to the
dispute.
164
Dr. D. M. Parikh
Arbitration
In Summary…….Arbitration as per FIDIC
♦ Sub-clause 20.6 stipulates Arbitration to be conducted under Rules of Arbitration of ICC
Dr. D. M. Parikh
Arbitration
In Summary…….Arbitration as per Indian Act
♦ Arbitration to be conducted under the Arbitration and Conciliation Act, 1996/2015.
♦ Very few ground under which the Award can be challenged in the court of law.
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 330
165
Dr. D. M. Parikh
Referral &
RB: 8.1: Commencement submission to DAB
(20.4)
Notice of
Appointment of DAB DAB decision
DAB dissatisfaction within
within 28 d (20.2) within 84 d
28 d
YB & SB: Notice of Referral to
intention to refer dispute Arbitration (20.6)
to DAB
Notice of dissatisfaction Arbitration to Attempt
within 28 d, if no decision commence after Amicable
in 84 d 56 d settlement
during 56 d
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 331
Dr. D. M. Parikh
Parties present
submissions to Amicable
the DAB settlement
166
Dr. D. M. Parikh
Dispute
Referral to DAB
Arbitration Enforcement
International Federation of Consulting Engineers
The Global Voice of Consulting Engineers 333
Dr. D. M. Parikh
Scheduled Responsibilities
167
Dr. D. M. Parikh
Dr. D. M. Parikh
168
Dr. D. M. Parikh
Dr. D. M. Parikh
169
Dr. D. M. Parikh
Dr. D. M. Parikh
170
Dr. D. M. Parikh
Dr. D. M. Parikh
171
Dr. D. M. Parikh
Dr. D. M. Parikh
172
Dr. D. M. Parikh
Dr. D. M. Parikh
If a project is financed by an MDB but the Employer will not carry out the design
(i.e. Where the 1999 Red Book is not applied), the parties should not use the Pink
Book without suitable amendments
173
Dr. D. M. Parikh
Dr. D. M. Parikh
174
Dr. D. M. Parikh
Dr. D. M. Parikh
175
Dr. D. M. Parikh
Dr. D. M. Parikh
176
Dr. D. M. Parikh
Dr. D. M. Parikh
177
Dr. D. M. Parikh
Dr. D. M. Parikh
178
Dr. D. M. Parikh
Dr. D. M. Parikh
179
Dr. D. M. Parikh
Dr. D. M. Parikh
Become the property of the Employer: Become the property of the Employer:
- When delivered to the Site; - When incorporated in the Works;
- When the Contractor is entitled to payment - When the Contractor is paid their
of their value corresponding value
180
Dr. D. M. Parikh
Dr. D. M. Parikh
181
Dr. D. M. Parikh
Dr. D. M. Parikh
182
Dr. D. M. Parikh
Dr. D. M. Parikh
183
Dr. D. M. Parikh
Dr. D. M. Parikh
184
Dr. D. M. Parikh
Dr. D. M. Parikh
185
Dr. D. M. Parikh
Dr. D. M. Parikh
186
Dr. D. M. Parikh
Dr. D. M. Parikh
187
Dr. D. M. Parikh
Dr. D. M. Parikh
188
Dr. D. M. Parikh
Dr. D. M. Parikh
189
Dr. D. M. Parikh
Dr. D. M. Parikh
190
Dr. D. M. Parikh
Dr. D. M. Parikh
191