FACULTY OF CIVIL AND ENVIRONMENTAL ENGINEERING

UNIVERSITI TUN HUSSEIN ONN MALAYSIA

INDIVIDUAL ASSIGNMENT
(10% marks)
BFC 43201 - Civil Engineering Software (Microsoft Project)
SEM I, 2019/2020

Instruction:

Construct a precedence diagram for activities listed in table 1 below and answer the following
questions:

1. The duration requires to complete the project is _____________ days.


2. The critical activities for the project are: ___________________________________________.
3. If the project starts on 1st October 2019, the completion date for the project is
_________________________. (Assume Monday to Friday is working day and no Public
holiday).
4. Show the critical path in your diagram.

Table 1

Activity Duration (days) Predecessor(s)


A 6 -
B 2 A
C 3 B
D 6 B
E 5 B
F 5 C (FS+4), D
G 5 D, E (FS+2)
H 4 F
J 8 F
K 5 G
L 1 H (FS+2), J, K (FS+2)
M 1 L

*Submit your report with a cover page consists of your details and picture*

*Don’t forget to write your section number*

*Submit your assignment on 18 December 2019, 5.00 pm