Professional Documents
Culture Documents
Iii A - Cases
Iii A - Cases
BERSAMIN, J.:
82
An agreement to submit to voluntary arbitration for 82 SUPREME COURT REPORTS
purposes of vesting jurisdiction over a construction dispute ANNOTATED
in the Construction Industry Arbitration Commission Federal Builders, Inc. vs. Power Factors, Inc.
(CIAC) need not be contained in the construction contract, On February 19, 2008, Power sent a demand letter to
or be signed by the parties. It is enough that the agreement Federal claiming the unpaid amount of P11,444,658.97 for
be in writing. work done by Power for the Bullion Mall and the Precinct
Building. Federal replied that its outstanding balance
The Case under the original contract only amounted to
P1,641,513.94, and that the demand for payment for work
done by Power after June 21, 2005 should be addressed
directly to BIDC.4Nonetheless, Power made several
demands on Federal to no avail. 83
On October 29, 2009, Power filed a request for VOL. 820, MARCH 8, 2017 83
arbitration in the CIAC invoking the arbitration clause of Federal Builders, Inc. vs. Power Factors, Inc.
the Contract of Service reading as follows: agreement for arbitration, the CIAC had no jurisdiction to
ARBITRATION COMMITTEE — All disputes, hear and decide the case.7
controversies or differences, which may arise between the On February 8, 2010, the CIAC issued an order setting
parties herein, out of or in relation to or in connection with the case for hearing, and directing that Federal’s motion to
this Agreement, or for breach thereof shall be settled by the dismiss be resolved after the reception of evidence of the
Construction Industry Arbitration Commission (CIAC) parties.8
which shall have original and exclusive jurisdiction over the Federal did not thereafter participate in the proceedings
aforementioned disputes. 15.5 until the CIAC rendered the Final Award dated May 12,
2010,9disposing:
In summary: Respondent Federal Builders, Inc. is
On November 20, 2009, Atty. Vivencio Albano, the
hereby ordered to pay claimant Power Factors, Inc. the
counsel of Federal, submitted a letter to the CIAC
manifesting that Federal agreed to arbitration and sought following sums:
an extension of 15 days to file its answer, which request the The foregoing amount shall earn legal interest at the
rate of 6% per annum from the date of this Final Award
CIAC granted.
On December 16, 2009, Atty. Albano filed his until this award becomes final and executory, Claimant
withdrawal of appearance stating that Federal had shall then be entitled to 12% per annum until the entire
meanwhile engaged another counsel.6 amount is fully satisfied by Respondent.
Federal, represented by new counsel (Domingo, Dizon,
Leonardo and Rodillas Law Office), moved to dismiss the Federal appealed the award to the CA insisting that the
case on the ground that CIAC had no jurisdiction over the CIAC had no jurisdiction to hear and decide the case; and
case inasmuch as the Contract of Service between Federal that the amounts thereby awarded to Power lacked legal
and Power had been a mere draft that was never finalized and factual bases.
or signed by the parties. Federal contended that in the _______________
absence of the
_______________ 7 Id., at p. 35.
8 Id.
4 Id. 9 Id., at pp. 98-128.
5 Id., at p. 44.
6 Id., at pp. 34-35.
to arbitrate need not be signed by the parties; that the
84 consent to submit to voluntary arbitration was not
84 SUPREME COURT REPORTS necessary in view of the arbitration clause contained in the
ANNOTATED Contract of Service; and that Federal’s contention that its
Federal Builders, Inc. vs. Power Factors, Inc. former counsel’s act of manifesting its consent to the
arbitration stipulated in the draft Contract of Service did
On August 12, 2013, the CA affirmed the CIAC’s
not bind it was inconsequential on the issue of
decision with modification as to the amounts due to
jurisdiction.12
Power,10 viz.:
_______________
WHEREFORE, the CIAC Final Award dated 12 May
2010 in CIAC Case No. 31-2009 is
10 Id., at pp. 32-42.
hereby AFFIRMED withMODIFICATION. As modified,
11 Id., at pp. 44-45.
FEDERAL BUILDERS, INC. is ordered to pay POWER
12 Id., at p. 38.
FACTORS, INC. the following:
92
92 SUPREME COURT REPORTS
ANNOTATED
Federal Builders, Inc. vs. Power Factors, Inc.
Velasco, Jr. (Chairperson), Reyes,
Jardeleza and Caguioa,**JJ., concur.
Judgment affirmed.
G.R. No. 184295.July 30, 2014.* Same; Same; It is well-settled that findings of fact of
NATIONAL TRANSMISSION quasi-judicial bodies, which have acquired expertise because
CORPORATION, petitioner, vs. ALPHAOMEGA their jurisdiction is confined to specific matters, are
INTEGRATED CORPORATION, respondent. generally accorded not only respect, but also finality,
especially when affirmed by the Court of Appeals (CA).—The
Remedial Law; Civil Procedure; Section 1, Rule 45 of Court finds no reason to disturb the factual findings of the
the Rules of Court provides that a petition for review on CIAC Arbitral Tribunal on the matter of AIC’s entitlement
certiorari under the said rule, as in this case, “shall raise to damages which the CA affirmed as being well supported
only questions of law which must be distinctly set forth.”— by evidence and properly referred to in the record. It is well-
TRANSCO seeks through this petition a recalibration of settled that findings of fact of quasi-judicial bodies, which
the evidence presented before the CIAC Arbitral Tribunal, have acquired expertise because their jurisdiction is
insisting that AIC is not entitled to any damages not only confined to specific matters, are generally accorded not only
because it had previously waived all claims for standby fees respect, but also finality, especially when affirmed by the
in case of project delays but had eventually failed to CA. The CIAC possesses that required expertise in the field
perform the workable portions of the projects. This is of construction arbitration and the factual findings of its
evidently a factual question which cannot be the proper construction arbitrators are final and conclusive, not
subject of the present petition. Section 1, Rule 45 of the reviewable by this Court on appeal.
Rules of Court provides that a petition for review Same; Same; It is well-settled that no relief can be
on certiorari under the said rule, as in this case, “shall raise granted a party who does not appeal and that a party who
only questions of law which must be distinctly set forth.” did not appeal the decision may not obtain any affirmative
Thus, absent any of the existing exceptions impelling the relief from the appellate court other than what he had
contrary, the Court is, as a obtained from the lower court, if any, whose decision is
_______________ brought up on appeal.—It must be emphasized that the
* SECOND DIVISION. petition for review before the CA was filed by TRANSCO.
AIC never elevated before the courts the matter concerning
300
the discrepancy between the amount of the award stated in
3 SUPREME COURT REPORTS the body of the Final Award and the total award shown in
its dispositive portion. The issue was touched upon by the
00 ANNOTATED
CA only after AIC raised the same through its Comment
National Transmission Corporation vs. (With Motion to Acknowledge Actual Amount of Award) to
Alphaomega Integrated Corporation TRANSCO’s petition for review. The CA should not have
general rule, precluded from delving on factual modified the amount of the award to favor AIC because it is
determinations, as what TRANSCO essentially seeks in well-settled that no relief can be granted a party who does
this case. not appeal and that a party who did not appeal the decision
may not obtain any affirmative relief from the appellate
court other than what he had obtained from the lower Reinforcement Project Schedule I (BTRP Schedule I
court, if any, whose decision is brought up on appeal. The Project); (c) Contract for the Construction, Erection &
disposition, as stated in the fallo of the CIAC Arbitral Installation of 230 KV and 69 KV S/S Equipment and
Tribunal’s Final Award, should therefore stand. Various Facilities for Makban Substation under the
_______________
PETITION for review on certiorari of the decision and [1] Rollo, pp. 10-82.
resolution of the Court of Appeals. [2] Id., at pp. 84-121. Penned by Associate Justice
301 Arcangelita M. Romilla-Lontok, with Associate Justices
Mariano C. Del Castillo (now member of the Court) and
VOL. 731, JULY 30, 2014 301 Ricardo R. Rosario, concurring.
National Transmission Corporation vs. [3] Id., at pp. 123-124.
Alphaomega Integrated Corporation [4] Id., at pp. 164-248.
The facts are stated in the opinion of the Court.
Office of the Government Corporate Counsel andNational 302
Transmission Corporation for petitioner. 302 SUPREME COURT REPORTS
Rivera, Santos and Maranan for respondent. ANNOTATED
National Transmission Corporation vs.
PERLAS-BERNABE, J.:
Alphaomega Integrated Corporation
Assailed in this petition for review on certiorari[1] are the
Batangas Transmission Reinforcement Project (Schedule II)
Decision[2] dated April 8, 2008 and the
(Makban Substation Project); (d) Contract for the
Resolution[3]dated August 27, 2008 of the Court of Appeals
Construction, Erection & Installation of 138 & 69 KV S/S
(CA) in C.A.-G.R. S.P. No. 99454 affirming with modification
Equipment for Bacolod Substation under the Negros III-
the Final Award[4] of the Construction Industry Arbitration
Commission (CIAC) Arbitral Tribunal in favor of respondent Panay III Substation Projects (Schedule II) (Bacolod
Substation Project); (e) Contract for the Construction,
Alphaomega Integrated Corporation (AIC) by increasing
Erection & Installation of 138 & 69 KV Substation
petitioner National Transmission Corporation’s (TRANSCO)
Equipment for the New Bunawan Switching Station Project
liability from P17,495,117.44 to P18,896,673.31.
The Facts (Bunawan Substation Project); and (f) Contract for the
AIC, a duly licensed transmission line contractor, Construction, Erection & Installation of 138 and 69 KV
Substation Equipment for Quiot Substation Project (Quiot
participated in the public biddings conducted by TRANSCO
Substation Project).[5]
and was awarded six (6) government construction projects,
namely: (a) Contract for the Construction & Erection of In the course of the performance of the contracts, AIC
Batangas Transmission Reinforcement Project Schedule encountered difficulties and incurred losses allegedly due to
III (BTRP Schedule III Project); (b) Contract for the TRANSCO’s breach of their contracts, prompting it to
Construction & Erection of Batangas Transmission surrender the projects to TRANSCO under protest. In
accordance with an express stipulation in the contracts that AIC prayed for judgment declaring all six (6) contracts
disagreements shall be settled by the parties through rescinded and ordering TRANSCO to pay, in addition to
arbitration before the CIAC, AIC submitted a request for what had already been paid under the contracts, moral
arbitration before the CIAC on August 28, 2006, and, damages, exemplary damages, and attorney’s fees at
thereafter, filed an Amended Complaint against TRANSCO P100,000.00 each, and a total of P40,201,467.19 as actual
alleging that the latter breached the contracts by its failure and compensatory damages.[8]
to: (a) furnish the required Detailed Engineering; (b) TRANSCO, for its part, contended that: (a) it had
arrange a well-established right-of-way to the project areas; conducted Detailed Engineering prior to the conduct of the
(c) secure the necessary permits and clearances from the bidding; and (b) it had obtained the necessary government
concerned local government units (LGUs); (d) ensure a permits and endorsements from the affected LGUs. It
continuous supply of construction materials; and (e) carry asserted that AIC was guilty of frontloading — that is,
out AIC’s requests for power shut down. The collecting the bulk of the contract price for work
aforementioned transgressions resulted in protracted accomplished at the early stages of the project and then
delays and contract suspensions for each project,[6] as abandoning the later stages of the project which has a lower
follows: contract price[9]— and that it disregarded the workable
_______________ portions of the projects not affected by the lack of supplies
[5] Id., at pp. 85-86. and drawings. TRANSCO further argued that AIC was
[6] Id., at pp. 87-89. estopped from asking for standby fees to cover its overhead
expenses during project suspensions considering that the
303 delays, such as the unresolved right-of-way
VOL. 731, JULY 30, 2014 303 _______________
National Transmission Corporation vs. [7] Id., at p. 87.
Alphaomega Integrated Corporation [8] Id., at pp. 95-96.
[9] Id., at p. 98.
304
304 SUPREME COURT REPORTS
ANNOTATED
National Transmission Corporation vs.
Alphaomega Integrated Corporation
issues and nonavailability of materials, were factors
already covered by the time extensions and suspensions of
work allowed under the contracts.[10]
On April 18, 2007, the CIAC Arbitral Tribunal rendered
its Final Award[11]in CIAC Case No. 21-2006 ordering the
payment of actual and compensatory damages which AIC VOL. 731, JULY 30, 2014 305
would not have suffered had it not been for the project National Transmission Corporation vs.
delays attributable to TRANSCO. It found ample evidence Alphaomega Integrated Corporation
to support the claim for the increase in subcontract cost in WHEREFORE, Respondent, National Transmission
BTRP Schedule I, as well as such items of cost as house and Corporation [TRANSCO] is hereby ordered to pay
yard rentals, electric bills, water bills, and maintained Claimant, Alphaomega Integrated Corporation, the
personnel, but disallowed the claims for communications following sums:
bills, maintenance costs for idle equipment, finance
charges, and materials cost increases.[12] According to the
Arbitral Tribunal, even if AIC itself made the requests for
contract time extensions, this did not bar its claim for
damages as a result of project delays since a contrary ruling
would allow TRANSCO to profit from its own negligence
and leave AIC to suffer serious material prejudice as a
direct consequence of that negligence leaving it without any
remedy at law.[13] The Arbitral Tribunal upheld AIC’s Each Party shall shoulder its own cost of arbitration.
right to rescind the contracts in accordance with Resolution The foregoing amount of P17,495,117.44 shall earn interest
No. 018-2004 of the Government Procurement Policy Board at the rate of six percent (6%) per annum from the date of
(GPPB), which explicitly gives the contractor the right to promulgation of this Final Award until it becomes final and
terminate the contract if the works are completely stopped executory. Thereafter, the Final Award, including accrued
for a continuous period of at least 60 calendar days, through interest, shall earn interest at the rate of 12% per
no fault of its own, due to the failure of the procuring entity annum until the entire amount due is fully
to deliver within a reasonable time, supplied materials, paid.[15] (Emphasis supplied)
right-of-way, or other items that it is obligated to furnish
Unconvinced, TRANSCO instituted a petition for
under the terms of the contract, among others.[14] The
review[16] with the CA.
dispositive portion of the Arbitral Tribunal’s Final Award
Before filing its comment[17] to the
reads:
petition, AIC moved for the issuance of a writ of
_______________
execution,[18] not for the amount of P17,495,117.44
[10] Id.
awarded in the Final Award, but for the increased
[11] Id., at pp. 164-248.
amount of P18,967,318.49.[19] It sought correction of the
[12] Id., at pp. 244-246.
discrepancies between the amount of the award appearing
[13] Id., at p. 229.
in the dispositive portion[20] and the body of the
[14] Id., at p. 227.
_______________
305 [15] Id., at p. 248.
[16] Id., at pp. 252-312. Dated June 12, 2007. signifying its satisfaction with AIC’s performance negate
[17] Id., at pp. 313-343. Comment (With Motion to such claim and, secondly, because all the orders issued by
Acknowledge Actual Amount of Award) Dated August 24, TRANSCO suspended the contracts not only in part but in
2007. their entirety, thus, permitting no work activity at all
[18] Id., at pp. 344-349. Motion for Issuance of Writ of during such periods.[25]
Execution for the Total Amount of P18,967,318.49 as The CA upheld the Arbitral Tribunal’s Final Award as
Embodied in the Final Award dated June 13, 2007. having been sufficiently established by evidence but
[19] Id., at p. 349. modified the total amount of the award after noting a
[20] Id., at p. 248. supposed mathematical error in the computation.
Setting aside
306 _______________
306 SUPREME COURT REPORTS [21] Id., at pp. 245-246.
ANNOTATED [22] Id., at pp. 350-352. Order dated June 18, 2007
National Transmission Corporation vs. issued by Chairman Custodio O. Parlade.
Alphaomega Integrated Corporation [23] Id., at pp. 84-121.
Final Award.[21] The Arbitral Tribunal, however, denied [24] Id., at pp. 112-113.
AIC’s motion, holding that while the CIAC Revised Rules of [25] Id., at pp. 117-118.
Procedure Governing Construction Arbitration (CIAC
307
Rules) would have allowed the correction of the Final
VOL. 731, JULY 30, 2014 307
Award for evident miscalculation of figures, typographical
or arithmetical errors, AIC failed to file its motion for National Transmission Corporation vs.
the purpose within the time limitation of 15 days Alphaomega Integrated Corporation
from its receipt of the Final Award.[22] TRANSCO’s objections, it ruled that when a case is brought
The CA’s Ruling to a superior court on appeal every aspect of the case is
In the Decision[23] dated April 8, 2008, the CA affirmed thrown open for review,[26] hence, the subject error could
the Arbitral Tribunal’s factual findings that TRANSCO be rectified. The CA held that the correct amount of the
failed to exercise due diligence in resolving the problems award should be P18,896,673.31, and not P17,495,117.44 as
regarding the right-of-way and the lack of materials before stated in the Arbitral Tribunal’s Final Award.[27]
undertaking the bidding process and entering into the Dissatisfied, TRANSCO moved for
contracts with AIC.[24] It found no merit in TRANSCO’s reconsideration[28]but was, however, denied by the CA in a
allegation that AIC refused to perform the remaining Resolution[29]dated August 27, 2008, hence, the instant
workable portions of the projects not affected by problems of petition.
right-of-way, shutdowns, supplies and drawings, firstly,
because the certificates of accomplishments issued by The Issues Before the Court
TRANSCO in the course of project implementation
The essential issues for the Court’s consideration are a petition for review on certiorari under the said rule, as in
whether or not the CA erred (a) in affirming the CIAC this case, “shall raise only questions of law which must be
Arbitral Tribunal’s findings that AIC was entitled to its distinctly set forth.” Thus, absent any of the existing
claims for damages as a result of project delays, and (b) in exceptions impelling the contrary, the Court is, as a general
increasing the total amount of compensation awarded in rule, precluded from delving on factual determinations, as
favor of AIC despite the latter’s failure to raise the allegedly what TRANSCO essentially seeks in this case. Similar to
erroneous computation of the award before the CIAC in a the foregoing is the Court’s ruling in Hanjin Heavy
timely manner, that is, within fifteen (15) days from receipt Industries and Construction Co., Ltd. v. Dynamic Planners
of the Final Award as provided under Section 17.1 of the and Construction Corp.,[30] the pertinent portions of which
CIAC Rules. are hereunder quoted:
Dynamic maintains that the issues Hanjin raised in its
The Court’s Ruling petitions are factual in nature and are, therefore, not
proper subject of review under Section 1 of Rule 45,
TRANSCO seeks through this petition a recalibration
prescribing that a petition under the said rule, like the one
of the evidence presented before the CIAC Arbitral
at bench, “shall raise only questions of law which must be
Tribunal, insisting that AIC is not entitled to any damages
distinctly set forth.”
not only because it had previously waived all claims for
Dynamic’s contention is valid to point as, indeed,
standby fees in case of project delays but had eventually
the matters raised by Hanjin are factual, revolving as
failed to perform the workable portions of the projects. This
they do on the entitlement of Dynamic to the awards
is evidently a factual question which cannot be the proper
granted and computed by the CIAC and the CA.
subject of the present petition. Section 1, Rule 45 of the
Generally, this would be a question of fact that this
Rules of Court provides that
Court would not delve upon. Imperial v.
_______________
Jaucian suggests as much. There, the Court ruled that the
[26] Id., at p. 119.
computation of outstanding obligation is a question of fact:
[27] Id., at pp. 119-120.
Arguing that she had already fully paid the loan x x x,
[28] See Motion for Reconsideration dated April 29,
petitioner alleges that the two lower courts misappreciated
2008; id., at pp. 125-155
the facts when they ruled that she still had an outstanding
[29] Id., at pp. 123-124.
balance of P208,430.
308 This issue involves a question of fact. Such question
308 SUPREME COURT REPORTS exists when a doubt or difference arises as to the truth or
the falsehood of alleged facts; and when there is need for
ANNOTATED
a calibration of the evidence, considering mainly the
National Transmission Corporation vs. credibility of witnesses and the existence
Alphaomega Integrated Corporation _______________
[30] 576 Phil. 502; 553 SCRA 541 (2008).
309 (6) when the judgment of the [CA] is
premised on a misapprehension of
VOL. 731, JULY 30, 2014 309 facts;
National Transmission Corporation vs. (7) when the [CA] fails to notice
Alphaomega Integrated Corporation certain relevant facts which, if
and the relevancy of specific surrounding circumstances, properly considered, will justify a
their relation to each other and to the whole, and the different conclusion;
probabilities of the situation. (G.R. No. 149004, April 14, (8) when the findings of fact are
2004, 427 SCRA 517, 523-524.) themselves conflicting;
The rule, however, precluding the Court from delving on (9) when the findings of fact are
the factual determinations of the CA, admits of several conclusions without citation of the
exceptions. In Fuentes v. Court of Appeals, we held that the specific evidence on which they are
findings of facts of the CA, which are generally deemed based; and
conclusive, may admit review by the Court in any of the (10) when the findings of fact of the
following instances, among others: [CA] are premised on the absence of
(1) when the factual findings of the evidence but such findings are
[CA] and the trial court are contradicted by the
contradictory; 310
(2) when the findings are grounded
310 SUPREME COURT REPORTS
entirely on speculation, surmises, or
ANNOTATED
conjectures;
National Transmission Corporation vs.
(3) when the inference made by the
Alphaomega Integrated Corporation
[CA] from its findings of fact is
manifestly mistaken, absurd, or evidence on record. (G.R. No. 109849,
impossible; February 26, 1997, 268 SCRA 703,
(4) when there is grave abuse of 709.)
discretion in the appreciation of Significantly, jurisprudence teaches that
facts; mathematical computations as well as the propriety
of the arbitral awards are factual determinations.
(5) when the [CA], in making its And just as significant is that the factual findings of the
findings, goes beyond the issues of CIAC and CA — in each separate appealed decisions —
the case, and such findings are practically dovetail with each other. The perceptible
contrary to the admissions of both essential difference, at least insofar as the CIAC’s Final
appellant and appellee;
Award and the CA Decision in C.A.-G.R. S.P. No. 86641 are VOL. 731, JULY 30, 2014 311
concerned, rests merely on mathematical computations or National Transmission Corporation vs.
adjustments of baseline amounts which the CIAC may have Alphaomega Integrated Corporation
inadvertently utilized.[31] (Emphases and underscoring cation did not observe the proper procedure for the
supplied) correction of an evident miscalculation of figures,
In any case, the Court finds no reason to disturb the including typographical or arithmetical errors, in
factual findings of the CIAC Arbitral Tribunal on the the arbitral award. Section 17.1 of the CIAC Rules
matter of AIC’s entitlement to damages which the CA mandates the filing of a motion for the foregoing purpose
affirmed as being well supported by evidence and properly within fifteen (15) days from receipt thereof, viz.:
referred to in the record. It is well-settled that findings of 17.1 Section Motion for correction of final award.—Any of
fact of quasi-judicial bodies, which have acquired expertise the parties may file a motion for correction of the Final
because their jurisdiction is confined to specific matters, are Award within fifteen (15) days from receipt thereof upon
generally accorded not only respect, but also finality, any of the following grounds:
especially when affirmed by the CA.[32] The CIAC a.An evident miscalculation of figures, a
possesses that required expertise in the field of construction typographical or arithmetical error; (Emphasis
arbitration and the factual findings of its construction supplied)
arbitrators are final and conclusive, not reviewable by this xxxx
Court on appeal.[33]
Failure to file said motion would consequently render
While the CA correctly affirmed in full the CIAC the award final and executory under Section 18. 1 of the
Arbitral Tribunal’s factual determinations, it improperly same rules, viz.:
modified the amount of the award in favor of AIC,
18.1 Section Execution of Award.—A final arbitral
which modifi- award shall become executory upon the lapse of fifteen (15)
_______________ days from receipt thereof by the parties.
[31] Id., at pp. 519-520.
[32] Public Estates Authority v. Uy, 423 Phil. 407, 416; AIC admitted that it had ample time to file a motion
372 SCRA 180, 189 (2001). for correction of the Final Award but claimed to have
[33] Shinryo (Philippines) Company, Inc. v. RRN purposely sat on its right to seek correction supposedly as a
Incorporated, G.R. No. 172525, October 20, 2010, 634 SCRA strategic move against TRANSCO[34]and, instead, filed
123, 130, citing IBEX International, Inc. v. Government with the CIAC Arbitral Tribunal on June 13, 2007 a
Service Insurance System, 618 Phil. 306, 312; 603 SCRA “Motion for Issuance of Writ of Execution for the Total
306, 314 (2009). Amount of P18,967,318.49 as Embodied in the Final
Award.”[35] The Arbitral Tribunal eventually denied AIC’s
aforesaid motion for execution because, despite its merit,
311 the Arbitral Tribunal could not disregard the time-
limitation under the CIAC Rules.[36] Clearly, having failed modified the amount of the award to favor AIC because it is
to move for the correction of the Final Award and, well-settled that no relief can be granted a party who does
_______________ not appeal[41] and that a party who did not appeal the
[34] See Rollo, p. 348. decision may not obtain any affirmative relief from the
[35] Id., at pp. 344-349. appellate court other than what he had obtained from the
[36] Id., at p. 250. lower court, if any, whose decision is
_______________
312 [37] Soler v. Bastida, No. L-22822, March 19, 1925, 47
312 SUPREME COURT REPORTS Phil. 676. See also National Bank v. De la Viña, 46 Phil. 63
ANNOTATED (1924).
National Transmission Corporation vs. [38] Office of the Ombudsman v. Chavez, G.R. No.
Alphaomega Integrated Corporation 172206, July 3, 2013, 700 SCRA 409.
thereafter, having opted to file instead a motion for [39] Rollo, pp. 252-312.
execution of the arbitral tribunal’s unopposed and [40] Id., at pp. 318-343.
uncorrected Final Award, AIC cannot now question against [41] Pascual v. Ramos, G.R. No. 144712, July 4, 2002,
the correctness of the CIAC’s disposition. Notably, while 384 SCRA 105, 116.
there is jurisprudential authority stating that “[a] clerical
313
error in the judgment appealed from may be corrected by
VOL. 731, JULY 30, 2014 313
the appellate court,”[37] the application of that rule cannot
be made in this case considering that the CIAC Rules National Transmission Corporation vs.
provides for a specific procedure to deal with particular Alphaomega Integrated Corporation
errors involving “[a]n evident miscalculation of figures, a brought up on appeal.[42]The disposition, as stated in
typographical or arithmetical error.” Indeed, the rule is well the fallo of the CIAC Arbitral Tribunal’s Final Award,
entrenched: Specialis derogat generali. When two rules should therefore stand.[43]
apply to a particular case, that which was specially WHEREFORE, the petition is PARTLY
designed for the said case must prevail over the other.[38] GRANTED. The Decision dated April 8, 2008 of the Court
Furthermore, it must be emphasized that the petition for of Appeals in C.A.-G.R. S.P. No. 99454 is
review before the CA was filed by TRANSCO.[39] AIC hereby AFFIRMED with MODIFICATION. The
never elevated before the courts the matter concerning the compensation awarded in favor of Alphaomega Integrated
discrepancy between the amount of the award stated in the Corporation in the amount of P17,495,117.44, as shown in
body of the Final Award and the total award shown in its the fallo of the construction Industry Arbitration
dispositive portion. The issue was touched upon by the CA Commission’s Final Award dated April 18, 2007, stands.
only after AIC raised the same through its Comment (With SO ORDERED.
Motion to Acknowledge Actual Amount of Award)[40]to Carpio (Chairperson), Brion,
TRANSCO’s petition for review. The CA should not have Perez and Reyes,** JJ.,concur.
Petition partly granted, judgment and resolution Gaming Corporation [PAGCOR] vs. Marquez, 698 SCRA
affirmed with modification. 709 [2013])
——o0o——
Notes.—It is axiomatic that a party who does not
appeal, or file a petition for certiorari, is not entitled to any
affirmative relief. (Unilever Philippines, Inc. vs. Rivera, 697
SCRA 136 [2013]) © Copyright 2019 Central Book Supply, Inc. All rights
_______________ reserved.
[42] Daabay v. Coca-Cola Bottlers Phils., Inc., G.R. No.
199890, August 19, 2013, 384 SCRA 105, 116.
[43] “The resolution of the court in a given issue
embodied in the fallo or dispositive part of a decision or
order is the controlling factor as to settlement of rights of
the parties. Thus, where there is a conflict between
the fallo and the ratio decidendi or body of the decision,
the fallo controls. This rule rests on the theory that
the fallo is the final order while the opinion in the body is
merely a statement ordering nothing. The rule applies
when the dispositive part of a final decision or order is
definite, clear, and unequivocal, and can wholly be given
effect without need of interpretation or construction.” (Obra
v. Spouses Badua, 556 Phil. 456, 461; 529 SCRA 621, 629
[2007]; citations omitted)
** Designated additional member in lieu of Justice
Mariano C. Del Castillo per Raffle dated July 23, 2014.
314
_______________
188
188 SUPREME COURT REPORTS 10 Id., at p. 6373, ACI’s Memorandum.
ANNOTATED 11 Id.
12 Id., at p. 6374, Conditions of Contract, Clause 6.0.
CE Construction Corporation vs. Araneta Center,
Reproduced in ACI’s Memorandum.
Inc.
the Works known as Package 4 of the Araneta Center
Redevelopment Project.”10
As part of its invitation to prospective contractors, ACI 189
furnished bidders with Tender Documents, consisting of: VOL. 836, AUGUST 9, 2017 189
Tender Invitation, Project Description, Instructions to CE Construction Corporation vs. Araneta Center,
Tenderers, Form of Tender, Dayworks, Preliminaries and
Inc.
General Requirements, and Conditions of Contract; I:
TENDER AND CONTRACT
Volume
Fixed Price Contract
Technical Specifications for the Architectural,
1. The Contract Sum payable to the Contactor is a Lump
Structural, Mechanical, Plumbing, Fire Protection and
Electrical Works; and II: Volume Sum Fixed Price and will not be subject to adjustment,
save only where expressly provided for within the
Addenda Nos. 1, 2, 3, and 4 relating to modifications to
Contract Documents and the Form of Agreement.
portions of the Tender Documents.11
2. The Contract Sum shall not be subject to any adjustment
The Tender Documents described the project’s contract
“in respect of rise and fall in the cost of materials[,]
sum to be a “lump sum” or “lump sum fixed price” and
restricted cost adjustments, as follows: labor, plant, equipment, exchange rates or any other
matters affecting the cost of execution of Contract, save
TYPE OF CONTRACT 6
only where expressly provided for within the Contract
6.1. This is a Lump Sum Contract and the price is a fixed
Documents or the Form of Agreement.
price not subject to measurement or recalculation should
3. The Contract Sum shall further not be subject to any
the actual quantities of work and materials differ from
change in subsequent legislation, which causes
any estimate available at the time of contracting, except
additional or reduced costs to the Contractor.13
in regard to Cost-Bearing Changes which may be
ordered by the Owner which shall be valued under the
terms of the Contract in accordance with the Schedule of
The bidders’ proposals for the project were submitted on ACI, however, was unable to deliver to CECON the entire
August 30, 2002. These were based on “design and project site. Only half, identified as the Malvar-to-Roxas
construct” bidding.14 portion, was immediately available. The other half,
CECON submitted its bid, indicating a tender amount of identified as the Roxas to-Coliseum portion, was delivered
P1,449,089,174.00. This amount was inclusive of “both the only about five (5) months later.17
act of designing the building and executing its As the details of the project had yet to be finalized, ACI
construction.” Its bid and tender were based on schematic and CECON pursued further negotiations. ACI and
drawings, i.e., conceptual designs and suppositions culled CECON subsequently agreed to include in the project the
from ACI’s Tender Documents. CECON’s proposal construction of an office tower atop the portion identified as
“specifically stated that its bid was valid for only ninety (90) Part A of the project. This escalated CECON’s project cost
days, or only until 29 November 2002.” This tender to P1,582,810,525.00.18
proposed a total of 400 days, or until January 10, 2004, for After further negotiations, the project cost was again
the implementation and completion of the project.15 adjusted to P1,613,615,244.00. Still later, CECON extended
_______________ to ACI a P73,615,244.00 discount, thereby reducing its
offered project cost to P1,540,000,000.00.19
13 Id. Preliminaries and General Requirements, Section Despite these developments, ACI still failed to formally
4.0. Reproduced in ACI’s Memorandum. award the project to CECON. The parties had yet to execute
14 Id., at p. 3773. a formal contract. This prompted CECON to write a letter
15 Id., at p. 6222, CECON’s Memorandum. to ACI, dated December 27, 2002,20emphasizing that the
project cost quoted to ACI was “based upon the prices
prevailing at December 26, 2002” price levels.21
_______________
190
190 SUPREME COURT REPORTS 16 Id., at p. 6223, CECON’s Memorandum.
ANNOTATED 17 Id.
CE Construction Corporation vs. Araneta Center, 18 Id.
Inc. 19 Id., at p. 6224, CECON’s Memorandum.
CECON offered the lowest tender amount. However, 20 Id., at pp. 549-553, Annex D to CECON’s Petition.
ACI did not award the project to any bidder, even as the 21 Id., at p. 549.
validity of CECON’s proposal lapsed on November 29, 2002.
ACI only subsequently informed CECON that the contract
was being awarded to it. ACI elected to inform CECON
191
verbally and not in writing.16
VOL. 836, AUGUST 9, 2017 191
In a phone call on December 7, 2002, ACI instructed
CECON to proceed with excavation works on the project. CE Construction Corporation vs. Araneta Center,
Inc. 22 Id., at pp. 554-555, Annex E to CECON’s Petition.
By January 2003 and with the project yet to be formally 23 Id., at pp. 556-557, Annex F to CECON’s Petition.
awarded, the prices of steel products had increased by 5% 24 Id., at p. 556.
and of cement by P5.00 per bag. On January 8, 2003, 25 Id., at pp. 3786 and 6225.
CECON again wrote ACI notifying it of these increasing 26 Id., at p. 6225.
costs and specifically stating that further delays may affect
the contract sum.22
Still without a formal award, CECON again wrote to
ACI on January 21, 200323 indicating cost and time 192
adjustments to its original proposal. Specifically, it referred 192 SUPREME COURT REPORTS
to an 11.52% increase for the cost of steel products, totalling ANNOTATED
P24,921,418.00 for the project; a P5.00 increase per bag of CE Construction Corporation vs. Araneta Center,
cement, totalling P3,698,540.00 for the project; and costs Inc.
incurred because of changes to the project’s structural On June 2, 2003, ACI finally wrote a letter27 to CECON
framing, totalling P26,011,460.00. The contract sum, indicating its acceptance of CECON’s August 30, 2002
therefore, needed to be increased to P1,594,631,418.00. tender for an adjusted contract sum of P1,540,000.00 only:
CECON also specifically stated that its tender relating to Araneta Center, Inc. (ACI) hereby accepts the C-E
these adjusted prices were valid only until January 31, Construction Corporation (CEC) tender dated August 30,
2003, as further price changes may be forthcoming. CECON 2002, submitted to ACI in the adjusted sum of One Billion
emphasized that its steel supplier had actually already Five Hundred Forty Million Pesos Only
advised it of a forthcoming 10% increase in steel prices by (P1,540,000,000.00), which sum includes all additionally
the first week of February 2003. CECON further impressed quoted and accepted items within this acceptance letter and
upon ACI the need to adjust the 400 days allotted for the attachments, Appendix A, consisting of one (1) page, and
completion of the project.24 Appendix B, consisting of seven (7) pages plus attachments,
On February 4, 2003, ACI delivered to CECON the which sum of One Billion Five Hundred Forty Million Pesos
initial tranche of its down payment for the project. By then, Only (P1,540,000,000.00) is inclusive of any Government
prices of steel had been noted to have increased by 24% Customs Duty and Taxes including Value Added Tax (VAT)
from December 2002 prices. This increase was validated by and Expanded Value-Added Tax (EVAD), and which sum is
ACI.25 hereinafter referred to as the Contract Sum.28
Subsequently, ACI informed CECON that it was taking
upon itself the design component of the project, removing
from CECON’s scope of work the task of coming up with Item 4, Appendix B of this acceptance letter explicitly
designs.26 recognized that “all design except support to excavation
_______________ sites, is now by ACI.”29 It thereby confirmed that the parties
were not bound by a design-and-construct agreement, as
initially contemplated in ACI’s June 2002 invitation, but by frequently pertained to revisions of prior items of work.35 Of
a construct-only agreement. The letter stated that these drawings, more than 600 were issued by ACI well
“[CECON] acknowledge[s] that a binding contract is now after the intended completion date of January 10, 2004:
existing.”30 However, consistent with ACI’s admitted Drawing No. 1040 was issued on January 12, 2004, and the
changes, it also expressed ACI’s corresponding undertaking: latest, Drawing No. 1675, was issued on November 26,
“This notwithstanding, formal contract documents 2004.36
embodying these positions will shortly be prepared and Apart from shifting its arrangement with CECON from
forwarded to you for execution.”31 design-and-construct to construct-only, ACI introduced
_______________ other changes to its arrangements with CECON. CECON
underscored two (2) of the most notable of these changes
27 Id., at pp. 558-560, Annex G of CECON’s Petition. which impelled it to seek legal relief.
28 Id., at p. 558. First, on January 30, 2003, ACI issued Change Order
29 Id., at p. 641. No. 11,37 which shifted the portion identified as Part B of
30 Id., at p. 560, Annex G to CECON’s Petition. the project from reinforced concrete framing to structural
31 Id. steel framing. Deleting the cost for reinforced concrete
framing meant removing P380,560,300.00 from the contract
sum. Nevertheless, replacing reinforced concrete framing
with structural
193 _______________
VOL. 836, AUGUST 9, 2017 193
CE Construction Corporation vs. Araneta Center, 32 Id., at p. 6227, CECON’s Memorandum.
Inc. 33 Id.
Despite ACI’s undertaking, no formal contract 34 Id.
documents were delivered to CECON or otherwise executed 35 Id.
between ACI and CECON.32 36 Id., at p. 6228, CECON’s Memorandum.
As it assumed the design aspect of the project, ACI 37 Id., at pp. 663-669, Annex H to CECON’s Petition;
issued to CECON the construction drawings for the project. and, p. 6228, CECON’s Memorandum.
Unlike schematics, these drawings specified “the kind of
work to be done and the kind of material to be
used.”33CECON laments, however, that “ACI issued the
construction drawings in piece-meal fashion at times of its 194
own choosing.”34 From the commencement of CECON’s 194 SUPREME COURT REPORTS
engagement until its turnover of the project to ACI, ACI ANNOTATED
issued some 1,675 construction drawings. CECON CE Construction Corporation vs. Araneta Center,
emphasized that many of these drawings were partial and Inc.
steel framing “entailed substitute cost of P217,585,000, an 38 Id., at p. 6229, CECON’s Memorandum.
additional P44,281,100 for the additional steel frames due 39 Id.
to revisions, and another P1,950,000 for the additional 40 Id.
pylon.”38
Second, instead of leaving it to CECON, ACI opted to
purchase on its own certain pieces of equipment —
elevators, escalators, chillers, generator sets, indoor 195
substations, cooling towers, pumps, and tanks — which VOL. 836, AUGUST 9, 2017 195
were to be installed in the project. This entailed “takeout CE Construction Corporation vs. Araneta Center,
costs”; that is, the value of these pieces of equipment Inc.
needed to be removed from the total amount due to claimed P26,892,019.00 by way of compensation for the
CECON. ACI considered a sum totalling P251,443,749.00 to work that it rendered.41
have been removed from the contract sum due to CECON. With many changes to the project and ACI’s delays in
This amount of P251,443,749.00 was broken down, as delivering drawings and specifications, CECON
follows: increasingly found itself unable to complete the project on
For Elevators/escalators, P106,000,000; (a) January 10, 2004. It noted that it had to file a total of 15
For Chillers, P41,152,900; (b) Requests for Time Extension from June 10, 2003 to
For Generator Sets, P53,040,000; (c) December 15, 2003, all of which ACI failed to timely act
For Indoor Substation, P23,024,150; (d) on.42
For Cooling Towers, P5,472,809; and (e) Exasperated, CECON served notice upon ACI that it
For Pumps and Tanks, P22,753,890. (f) 39 would avail of arbitration. On January 29, 2004, it filed
with the CIAC its Request for Adjudication.43 It prayed that
a total sum of P183,910,176.92 representing adjusted
CECON avers that in removing the sum of
project costs be awarded in its favor.44
P251,443,749.00, ACI “simply deleted the amount in the
On March 31, 2004, CECON and ACI filed before the
cost breakdown corresponding to each of the items taken
CIAC a Joint Manifestation45 indicating that some issues
out in the contract documents.”40 ACI thereby disregarded
between them had already been settled. Proceedings before
that the corresponding stipulated costs pertained not only
the CIAC were then suspended to enable CECON and ACI
to the acquisition cost of these pieces of equipment but also
to arrive at an amicable settlement.46 On October 14, 2004,
to so-called “builder’s works” and other costs relating to
ACI filed a motion before the CIAC noting that it has
their preparation for and installation in the project. Finding
validated P85,000,000.00 of the total amount claimed by
it unjust to be performing auxiliary services practically for
CECON. It prayed for more time to arrive at a settlement.47
free, CECON proposed a reduction in the takeout costs
In the meantime, CECON completed the project and
claimed by ACI. It instead
turned over Gateway Mall to ACI.48 It had its blessing on
_______________
November 26, 2004.49
_______________ was to be composed of Dr. Ernesto S. De Castro, who acted
as Chairperson with Engr. Reynaldo T. Viray and Atty.
41 Id., at p. 6230, CECON’s Memorandum. James S. Villafranca as members.54
42 Id. ACI filed a Motion for Reconsideration of the CIAC’s
43 Id., at pp. 670-673, Annex I to CECON’s Petition. March 16, 2005 Order. This was denied in the Order dated
44 Id., at p. 673. March 30, 2005.55
45 Id., at p. 3763. In the Order dated April 1, 2005, the CIAC Arbitral
46 Id., at p. 6231, CECON’s Memorandum. Tribunal set the preliminary conference on April 13, 2005.56
47 Id., at p. 3764. At the preliminary conference, CECON indicated that,
48 Id., at p. 6231. the total sum it was entitled to recover from ACI needed to
49 Id., at p. 3764. be adjusted to P324,113,410.08. The CIAC Arbitral
Tribunal,
_______________
202 _______________
202 SUPREME COURT REPORTS
ANNOTATED 85 Id., at p. 69.
CE Construction Corporation vs. Araneta Center, 86 Id., at pp. 42-45.
87 Id., at pp. 62-63.
Inc.
88 Id., at p. 83.
Regarding attendance fees, the Court of Appeals
proffered that the work attributed to subcontractors was
merely work done by CECON itself, thereby negating the
need for attendance fees.85 203
Concerning takeout costs, the Court of Appeals stated VOL. 836, AUGUST 9, 2017 203
that CECON was in no position to propose its own takeout
CE Construction Corporation vs. Araneta Center,
costs as the tender documents issued along with ACI’s
Inc.
invitation to bidders stated that takeout costs must be
based exclusively on the rates provided in the Contract Cost AWARD TO ARANETA b.
Breakdown. Nevertheless, as ACI had previously
NO. ISSUE Pesos (PHP)
undertaken to pay the variance in takeout costs amounting
[5] Liquidated Damages 15,400,000.00
NO. ISSUE Pesos (PHP) The dispositive portion of the assailed Court of Appeals’
Defective and Incomplete July 1, 2010 Amended Decision read:
[6] 3,000,000.00
Works WHEREFORE, Our Decisiondated 28 April 2008 is
Bookmarking Granite Tiles 6,980,000.00 hereby modified as follows:
Permits, Licenses and Other I – AWARD:
[7] 6,186,246.23
Advances AWARD TO CE CONSTRUCTION, INC. a.
31,566,246.20
Total NO. ISSUE PESOS (PhP)
(sic)
In addition, CECON is directed to submit all required 1
Additional costs spent on
10,266,628.00
closeout documents within thirty (30) days from receipt of rebars.
this Decision. Increase in the costs of cement
The parties shall bear their own costs of arbitration and 2 and formworks falling under 5,205,004.02
litigation. cost-bearing change.
SO ORDERED.89 Representing undervaluation of
respondent’s works in the
3 1,209,782.50
_______________ supply and installation of G.I.
sheets.
89 Id., at pp. 84-85. 4
Representing Miscellaneous
27,601,469.32
Change Orders
5 Drilling of Holes 4,543,450.00
[Schematic Drawings] to
6 80,108,761.60
204 [Construction Drawings]
204 SUPREME COURT REPORTS Installation of equipment
[7] 1,127,486.50
ANNOTATED supplied by owner
CE Construction Corporation vs. Araneta Center, TOTAL 130,062,581.94
Inc.
_______________
Acting on CECON’s Motion for Reconsideration, the
Court of Appeals issued its Amended Decision on July 1,
90 Id., at pp. 87-137.
2010.90 This Amended Decision increased the award for
91 Id., at pp. 105-106.
miscellaneous change orders to P27,601,469.32; reinstated
92 Id., at p. 107.
awards for undervalued works in supplying and installing
93 Id., at p. 104.
G.I. sheets worth P1,209,782.5091 and for the drilling of
holes and application of epoxy worth P4,543,456.00;92 and
deleted the award for takeout costs.93
205
VOL. 836, AUGUST 9, 2017 205 offer to bid. It cites specific provisions of these documents
CE Construction Corporation vs. Araneta Center, such as valuation rules
Inc. _______________
AWARD TO ARANETA CENTER, INC. b.
94 Id., at pp. 136-137.
1 Liquidated Damage (sic) 20,000,000.00 95 Id., at pp. 153-268.
2 Defective and Incomplete Works 3,000,000.00 96 Id., at pp. 263-264.
3 Bookmarking Granite Tiles 6,980,000.00 97 Id., at p. 6098.
Permits, Licenses and other
4 6,186,246.23
Advances
TOTAL 36,166,246.23
206
II – COMPUTATION:
206 SUPREME COURT REPORTS
AWARD TO CE ANNOTATED
130,062,581.94
CONSTRUCTION, INC. CE Construction Corporation vs. Araneta Center,
LESS Inc.
AWARD TO ARANETA CENTER,
36,166,246.23 and required notices for extensions and changes, reckoning
INC. of losses and expenses, the ensuing liquidated damages for
BALANCE PAYABLE BY
93,896,335.71 defects, cost-bearing changes and provisional sums,98which
ARANETA TO CECON define parameters for permissible changes and for
SO ORDERED.94 reckoning corresponding costs and liabilities. However, it
did not attach any of these documents to its Comment or
Memorandum. It also cites statutory provisions — Articles
Aggrieved at the Court of Appeals’ ruling, CECON filed
171599and 1724100 of the Civil Code — on CECON’s
the present Petition insisting on the propriety of the CIAC
liabilities and the primacy of stipulated contract prices.101
Arbitral Tribunal’s conclusions and findings.95 It prays that
By the inviolability of their agreement, ACI insists on
the assailed Court of Appeals’ decisions be reversed and
the supposed immutability of the stipulated contract sum
that the CIAC Arbitral Tribunal’s October 25, 2006
and on the impropriety of the CIAC Arbitral Tribunal in
Decision, as modified by its December 28, 2006 Order, be
writing its own terms for ACI and CECON to follow.102 It
reinstated.96
faults the CIAC
ACI counters that the Court of Appeals’ July 1, 2010
_______________
Amended Decision must be upheld.97
ACI insists on the inviolability of its supposed 98 Id., at pp. 5914-5929 and 5934-5936.
agreement with CECON, as embodied in the contract 99 CIVIL CODE, Art. 1715 provides:
documents delivered to contractors alongside the original
The contractor shall execute the work in such a manner that run afoul of contractual stipulations and on bases such
that it has the qualities agreed upon and has no defects as industry practices and standards, which supposedly
which destroy or lessen its value or fitness for its ordinary should not have even been considered as the parties have
or stipulated use. Should the work be not of such quality, already adduced their respective evidence.103 It insists upon
the employer may require that the contractor remove the CECON’s fault for delays and defects, making it liable for
defect or execute another work. If the contractor fails or liquidated damages.104
refuses to comply with this obligation, the employer may Though nominally modifying the CIAC Arbitral
have the defect removed or another work executed, at the Tribunal’s October 25, 2006 Decision, the Court of Appeals
contractor’s cost. 1715. Article actually reversed it on the pivotal matter of the
100 CIVIL CODE, Art. 1724 provides: characterization of the contract between CECON and ACI.
The contractor who undertakes to build a structure or Upon its characterization of the contract as one for a lump
any other work for a stipulated price, in conformity with sum fixed price, the Court of Appeals deleted much of the
plans and specifications agreed upon with the landowner, CIAC Arbitral Tribunal’s monetary awards to CECON and
can neither withdraw from the contract nor demand an awarded liquidated damages to ACI.
increase in the price on account of the higher cost of labor On initial impression, what demands resolution is the
or materials, save when there has been a change in the issue of whether or not the Court of Appeals erred in
plans and specifications, provided: 1724. Article characterizing the contractual arrangement between
Such change has been authorized by the proprietor in petitioner CE Construction Corporation and respondent
writing; and (1) Araneta Center, Inc. as immutably one for a lump sum
The additional price to be paid to the contractor has fixed price.
been determined in writing by both parties. (2) However, this is not merely a matter of applying and
101 Rollo, pp. 5930-5933. deriving conclusions from cut and dried contractual
102 Id., at p. 5893. ACI’s Comment states, “the Arbitral provisions. More accurately, what is on issue is whether or
Tribunal significantly modified and amended the clear not the Court of Appeals correctly held that the CIAC
terms of the parties’ contract documents by rewriting their Arbitral Tribunal acted beyond its jurisdiction in holding
construction agreement and that the price of P1,540,000,000.00 did not bind the parties
as an immutable lump sum. Subsumed in this issue is the
matter of whether or not the Court of Appeals correctly
ruled that CECON was rightfully entitled to time
207 extensions and that intervening circumstances had made
VOL. 836, AUGUST 9, 2017 207 ACI liable for cost adjustments, increases borne by change
CE Construction Corporation vs. Araneta Center, orders, additional overhead costs,
Inc. _______________
Arbitral Tribunal for erroneously reckoning the sums due to
CECON, particularly in relying on factual considerations
unilaterally imposing upon ACI newly-created obligations, the Construction Industry Arbitration Law.105 At inception,
notwithstanding that there was no issue on the exact terms it was
of the contract documents and the intent of the parties in _______________
executing the same.”
103 Id., at pp. 5894-5895. 105 Though nominally an “executive order” the
104 Id., at pp. 5897-5898. Construction Industry Arbitration Law is a statute.
Jurisprudence has clarified that, in exercising legislative
powers, then President Marcos did not only use the
modality of presidential decrees, but also of executive
208 orders and letters of instruction. Though, this is not to say
208 SUPREME COURT REPORTS that all executive orders and letters of intruction issued by
ANNOTATED him are statutes.
CE Construction Corporation vs. Araneta Center, In Garcia-Padilla v. Enrile, 206 Phil. 392, 428; 121 SCRA
Inc. 472, 499 (1983) [Per J. De Castro, En Banc]:
extended contractor’s all risk insurance coverage, increased To form part of the law of the land, the decree, order or
attendance fees vis-à-vis subcontractors, and arbitration [letter of instruction] must be issued by the President in the
costs which it awarded to CECON. exercise of his extraordinary power of legislation as
This Court limits itself to the legal question of the CIAC contemplated in Section 6 of the 1976 amendments to the
Arbitral Tribunal’s competence. Unless any of the Constitution, whenever in his judgment, there exists a
exceptional circumstances that warrant revisiting the grave emergency or a threat or imminence thereof, or
factual matter of the accuracy of the particulars of every whenever the interim Batasan[g] Pambansa or the regular
item awarded to the parties is availing, this Court shall not National Assembly fails or is unable to act adequately on
embark on its own audit of the amounts owing to each.
I
209
This Court begins by demarcating the jurisdictional and
VOL. 836, AUGUST 9, 2017 209
technical competence of the CIAC and of its arbitral
tribunals. CE Construction Corporation vs. Araneta Center,
Inc.
I.A _______________
The Construction Industry Arbitration Commission was any matter for any reason that in his judgment requires
a creation of Executive Order No. 1008, otherwise known as immediate action.
In Irene B. Cortes, Executive Legislation: The Philippine general statutory framework of alternative dispute
Experience; 55 PHIL. L.J. 1, 27-29 (1979) Associate Justice resolution.
Irene Cortes noted that certain executive orders and letters Jurisprudence, too, has repeatedly and consistently referred
of instruction have indeed been on par with President to it as such a “law.” See, for example, National Irrigation
Marcos’ more commonly used mode of legislation (i.e., Administration v. Court of Appeals, 376 Phil. 362; 318
presidential decrees): SCRA 255 (1999) [Per CJ.Davide, Jr., First
Another problem arises from lack of precision in the Division]; Metropolitan Cebu Water District v. Mactan Rock
appropriate use of one form of issuance as against another. Industries, Inc., 690 Phil. 163; 675 SCRA 577 (2012)
A presidential decree is equivalent to a statute enacted by [Per J. Mendoza, Third Division]; and The Manila
the legislature, and is thus superior to implementing rules Insurance Co.,
issued as executive orders or letter of instructions. But, it is
not unheard of for an executive order to amend or repeal a
presidential decree or a letter of instructions to amend an
executive order, or lay down a rule of law. 210
Associate Justice Cortes specifically cited as an example 210 SUPREME COURT REPORTS
Exec. Order No. 543 (1979), which abolished the Philippine ANNOTATED
Center for Advanced Studies, a creation of Pres. Decree No. CE Construction Corporation vs. Araneta Center,
342 (1973). In disproving that Exec. Order No. 543 was Inc.
issued merely as an implementing rule, she explained that under the administrative supervision of the Philippine
its object — a state university — could not have fallen Domestic Construction Board106 which, in turn, was an
under the scope of the President’s reorganization powers, implementing agency of the Construction Industry
for which an executive order issued merely as an Authority of the Philippines (CIAP).107 The CIAP is
implementing rule was sufficient. presently attached to the Department of Trade and
The Construction Industry Arbitration Law’s own Industry.108
nomenclature reveals the intent that it be a statute. Its The CIAC was created with the specific purpose of an
whereas clauses and declaration of policy reveal the “early and expeditious settlement of disputes”109cognizant
urgency that impelled immediate action for the President to of the exceptional role of construction to “the furtherance of
exercise his concurrent legislative powers. national development goals.”110
Any doubt on the statutory efficacy of the Construction Section 4 of the Construction Industry Arbitration Law
Industry Arbitration Law is addressed by Congress’ own, spells out the jurisdiction of the CIAC:
voluntary and repeated reference to and affirmation of it as 4. SectionJurisdiction.—The CIAC shall have original
such a law. (SeeRep. Act No. 9184 and Rep. Act No. 9285). and exclusive jurisdiction over disputes arising from, or
Rep. Act No. 9285 did not only validate the Construction connected with, contracts entered into by parties involved
Industry Arbitration Law, it also incorporated it into the in construction in the Philippines, whether the dispute
arises before or after the completion of the contract, or after
the abandonment or breach thereof. These disputes may Though created by the act of a Chief Executive who then
involve government or private contracts. For the Board to exercised legislative powers concurrently with the Batasang
acquire jurisdiction, the parties to a dispute must agree to Pambansa, the creation, continuing existence, and
submit the same to voluntary arbitration. competence of the CIAC have since been validated by acts
The jurisdiction of the CIAC may include but is not of Congress.
limited to violation of specifications for materials and Republic Act No. 9184 or the Government Procurement
workmanship; violation of the terms of agreement; Reform Act, enacted on January 10, 2003, explicitly
interpretation and/or application of contractual time and recognized and confirmed the competence of the CIAC:
delays; maintenance and defects; payment, default of 59. SectionArbitration.—Any and all disputes arising
employer or contractor and changes in contract cost. from the implementation of a contract covered by this Act
shall be submitted to arbitration in the Philippines
_______________ according to the provisions of Republic Act No. 876,
otherwise known as the “Arbitration Law”: Provided,
Inc. v. Amurao, 701 Phil. 557; 688 SCRA 609 (2013) however, That, disputes that are within the competence of
[Per J. Del Castillo, Second Division]. the Construction Industry Arbitration Commission to
106 Exec. Order No. 1008, Sec. 3. resolve shall be referred thereto. The process of arbitration
107 Id., 4th Whereas Clause. shall be incorporated as a provision in the contract that will
108 See Department of Trade and Industry, Attached be executed pursuant to the provisions of this
Agencies, <http://www.dti.gov.ph/about/the- Act: Provided, That by mutual agreement, the parties may
organization/attached-agencies> (last visited on August 8, agree in writing to resort to alternative modes of dispute
2017). resolution. (Emphasis supplied)
109 Exec. Order No. 1008, Sec. 2.
110 Id., 3rd Whereas Clause.
Arbitration of construction disputes through the CIAC
was formally incorporated into the general statutory
framework on alternative dispute resolution through
211 Republic Act No. 9285, the Alternative Dispute Resolution
VOL. 836, AUGUST 9, 2017 211 Act of 2004 (ADR Law). Chapter 6, Section 34 of ADR Law
CE Construction Corporation vs. Araneta Center, made specific reference to the Construction Industry
Inc. Arbitration Law, while Section 35 confirmed the CIAC’s
Excluded from the coverage of this law are disputes jurisdiction:
arising from employer-employee relationships which shall
continue to be covered by the Labor Code of the Philippines.
212
212 SUPREME COURT REPORTS
ANNOTATED concerned with other specialized fields. The CIAC has the
CE Construction Corporation vs. Araneta Center, state’s confidence concerning the entire technical expanse of
Inc. construction, defined in jurisprudence as “referring to all
CHAPTER 6 on-site works on buildings or altering structures, from land
ARBITRATION OF CONSTRUCTION DISPUTES clearance through completion including ex-
34. SectionArbitration of Construction Disputes:
Governing Law.—The arbitration of construction disputes
213
shall be governed by Executive Order No. 1008, otherwise
known as the Construction Industry Arbitration Law. VOL. 836, AUGUST 9, 2017 213
35. SectionCoverage of the Law.—Construction CE Construction Corporation vs. Araneta Center,
disputes which fall within the original and exclusive Inc.
jurisdiction of the Construction Industry Arbitration cavation, erection and assembly and installation of
Commission (the “Commission”) shall include those components and equipment.”111
between or among parties to, or who are otherwise bound Jurisprudence has characterized the CIAC as a quasi-
by, an arbitration agreement, directly or by reference judicial, administrative agency equipped with technical
whether such parties are project owner, contractor, proficiency that enables it to efficiently and promptly
subcontractor, fabricator, project manager, design resolve conflicts:
professional, consultant, quantity surveyor, bondsman or [The CIAC] is a quasi-judicial agency. A quasi-judicial
issuer of an insurance policy in a construction project. agency or body has been defined as an organ of government
The Commission shall continue to exercise original and other than a court and other than a legislature, which
exclusive jurisdiction over construction disputes although affects the rights of private parties through either
the arbitration is “commercial” pursuant to Section 21 of adjudication or rule-making. The very definition of an
this Act. administrative agency includes its being vested with quasi-
judicial powers. The ever increasing variety of powers and
functions given to administrative agencies recognizes the
I.B need for the active intervention of administrative agencies
in matters calling for technical knowledge and speed in
The CIAC does not only serve the interest of speedy countless controversies which cannot possibly be handled
dispute resolution, it also facilitates authoritativedispute by regular courts. The CIAC’s primary function is that of a
resolution. Its authority proceeds not only from juridical quasi-judicial agency, which is to adjudicate claims and/or
legitimacy but equally from technical expertise. The determine rights in accordance with procedures set forth in
creation of a special adjudicatory body for construction E.O. No. 1008.112
disputes presupposes distinctive and nuanced competence
on matters that are conceded to be outside the innate
expertise of regular courts and adjudicatory bodies
The most recent jurisprudence maintains that the CIAC they intend to serve private, proprietary interests.115 In
is a quasi-judicial body. This Court’s November 23, 2016 contrast, voluntary arbitra-
Decision in Fruehauf Electronics v. Technology Electronics _______________
Assem-
_______________ 113 Fruehauf Electronics Philippines Corporation v.
Technology Electronics Assembly and Management Pacific
111 Fort Bonifacio Development Corporation v. Corporation, G.R. No. 204197, November 23, 2016, 810
Sorongon, 605 Phil. 689, 696; 587 SCRA 613, 621 (2009) SCRA 280 [Per J. Brion, Second Division].
[Per J. Tinga, Second Division]. 114 LABOR CODE, Art. 219 provides:
112 Metro Construction, Inc. v. Chatham Properties, 219. ArticleDefinitions.— . . . .
Inc., 418 Phil. 176, 202-203; 365 SCRA 697, 722 (2001) “Voluntary Arbitrator” means any person accredited by
[Per CJ. Davide, Jr., First Division], citing Presidential the Board as such, or any person named or designated in
Anti-Dollar Salting Task Force v. CA, 253 Phil. 344; 171 the Collective Bargaining Agreement by the parties to act
SCRA 348 (1989) [Per J. Sarmiento, En Banc]; Tropical as their Voluntary Arbitrator, or one chosen with or without
Homes, Inc. v. National Housing Authority, 236 Phil. 580; the assistance of the National Conciliation and Mediation
152 SCRA 540 (1987) [Per J.Gutierrez, Jr., En Board, pursuant to a selection procedure agreed upon in the
Banc]; Antipolo Realty Corp. v. National Housing Authority, Collective Bargaining Agreement, or any official that may
237 Phil. 389; 153 SCRA 399 (1987) [Per J. Feliciano, En be authorized by the Secretary of Labor and Employment to
Banc]; and Solid Homes, Inc. v. Payawal, 257 Phil. 914; 177 act as Voluntary Arbitrator upon the written request and
SCRA 72 (1989) [Per J. Cruz, First Division]. agreement of the parties to a labor dispute. 14.
115 Fruehauf Electronics Philippines Corporation v.
Technology Electronics Assembly and Management
Pacific Corporation, supra. It stated:
214 Quasi-judicial or administrative adjudicatory power is
214 SUPREME COURT REPORTS the power: (1) to hear and determine questions of fact to
ANNOTATED which legislative policy is to apply, and (2) to decide in
CE Construction Corporation vs. Araneta Center, accordance with the standards laid down by the law itself in
Inc. enforcing and administering the same law. Quasi-judicial
bly and Management Pacific113 distinguished construction power is only exercised by administrative agencies — legal
arbitration, as well as voluntary arbitration pursuant to organs of the government.
Article 219(14) of the Labor Code,114 from commercial Quasi-judicial bodies can only exercise such powers and
arbitration. It ruled that commercial arbitral tribunals jurisdiction as are expressly or by necessary implication
are notquasi-judicial agencies, as they are purely ad conferred upon them by their enabling statutes. Like
hocbodies operating through contractual consent and as courts, a quasi-judicial body’s jurisdiction over a subject
matter is conferred by law and exists independently from
the will of the parties. As government organs necessary for _______________
an effective legal system, a quasi-judicial tribunal’s legal
existence continues beyond the resolution of a specific As a contractual and consensual body, the arbitral
dispute. In other words, quasi-judicial bodies are creatures tribunal does not have any inherent powers over the
of law. parties. It has no power to issue coercive writs or
compulsory processes. Thus, there is a need to resort to the
regular courts for interim measures of protection and for
the recognition or enforcement of the arbitral award.
215 The arbitral tribunal acquires jurisdiction over the
VOL. 836, AUGUST 9, 2017 215 parties and the subject matter through stipulation. Upon
CE Construction Corporation vs. Araneta Center, the rendition of the final award, the tribunal
Inc. becomes functus officio and — save for a few exceptions —
tion under the Labor Code and construction arbitration ceases to have any further jurisdiction over the dispute. The
operate through the statutorily vested jurisdiction of tribunal’s powers (or in the case of ad hoc tribunals, their
government instrumentalities that exist independently of very existence) stem from the obligatory force of the
the will of contracting parties and to which these parties arbitration agreement and its ancillary stipulations. Simply
submit. They proceed from the public interest imbuing their put, an arbitral tribunal is a creature of contract. (Citations
respective spheres: omitted)
Voluntary Arbitrators resolve labor disputes and
grievances arising from the interpretation of Collective
Bargaining Agreements. These disputes were specifically
216
excluded from the coverage of both the Arbitration Law and
216 SUPREME COURT REPORTS
the ADR Law.
Unlike purely commercial relationships, the relationship ANNOTATED
between capital and labor are heavily impressed with CE Construction Corporation vs. Araneta Center,
public interest. Because of this, Voluntary Arbitrators Inc.
authorized to resolve labor disputes have been clothed with vate citizens instead of government instrumentalities
quasi-judicial authority. wielding quasi-judicial powers.
On the other hand, commercial relationships covered by Moreover, judicial or quasi-judicial jurisdiction cannot be
our commercial arbitration laws are purely private and conferred upon a tribunal by the parties alone. The Labor
contractual in nature. Unlike labor relationships, they do Code itself confers subject-matter jurisdiction to Voluntary
not possess the same compelling state interest that would Arbitrators.
justify state interference into the autonomy of contracts. Notably, the other arbitration body listed in Rule 43 —
Hence, commercial arbitration is a purely private system of the Construction Industry Arbitration Commission (CIAC)
adjudication facilitated by pri- — is also a government agency attached to the Department
of Trade and Industry. Its jurisdiction is likewise conferred CE Construction Corporation vs. Araneta Center,
by statute. By contrast, the subject matter jurisdiction of Inc.
commercial arbitrators is stipulated by the 8.1. SectionGeneral Qualification of Arbitrators.—The
parties.116(Emphasis supplied, citations omitted) Arbitrators shall be men of distinction in whom the
business sector and the government can have
confidence. They shall be technically qualified to resolve any
Consistent with the primacy of technical mastery,
construction dispute expeditiously and equitably. The
Section 14 of the Construction Industry Arbitration Law on
Arbitrators shall come from different professions. They may
the qualification of arbitrators provides:
include engineers, architects, construction managers,
14. SectionArbitrators.—A sole arbitrator or three
engineering consultants, and businessmen familiar with the
arbitrators may settle a dispute.
construction industry and lawyers who are experienced in
....
construction disputes. (Emphasis supplied)
Arbitrators shall be men of distinction in whom the
business sector and the government can have confidence.
They shall not be permanently employed with the CIAC. Of the 87 CIAC-accredited arbitrators as of January
Instead, they shall render services only when called to 2017, only 33 are lawyers. The majority are experts from
arbitrate. For each dispute they settle, they shall be given construction-related professions or engaged in related
fees. fields.117
Apart from arbitrators, technical experts aid the CIAC
in dispute resolution. Section 15 of the Construction
Section 8.1 of the Revised Rules of Procedure Governing
Industry Arbitration Law provides:
Construction Arbitration establishes that the foremost
15. SectionAppointment of Experts.—The services of
qualification of arbitrators shall be technical proficiency. It
technical or legal experts may be utilized in the settlement
explicitly enables not only lawyers but also “engineers,
of disputes if requested by any of the parties or by the
architects, construction managers, engineering consultants,
Arbitral Tribunal. If the request for an expert is done by
and businessmen familiar with the construction industry”
either or by both of the parties, it is necessary that the
to serve as arbitrators:
appointment of the expert be confirmed by the Arbitral
_______________
Tribunal.
116 Id., at pp. 307-308. Whenever the parties request for the services of an
expert, they shall equally shoulder the expert’s fees and
expenses, half of which shall be deposited with the
Secretariat before the expert renders service. When only
217 one party makes the request, it shall deposit the whole
VOL. 836, AUGUST 9, 2017 217 amount required.
_______________ _______________
117 Construction Arbitration and Mediation, 118 See Metro Construction, Inc. v. Chatham Properties,
Construction Industry Authority of the Philippines, Inc., supra note 112.
available at 119 RULES OF COURT, Rule 43, Sec. 1 provides:
<http://www.ciap.dti.gov.ph/content/construction- 1. SectionScope.—This Rule shall apply to appeals
arbitrationmediation> (last visited on August 8, 2017). from judgments or final orders of the Court of Tax Appeals
and from awards, judgments, final orders or resolutions of
or authorized by any quasi-judicial agency in the exercise of
its quasi-judicial functions. Among these agencies are the
218 Civil Service Commission, Central Board of Assessment
218 SUPREME COURT REPORTS Appeals, Securities and Exchange Commission, Office of the
ANNOTATED President, Land Registration Authority, Social Security
CE Construction Corporation vs. Araneta Center, Commission, Civil Aeronautics Board, Bureau of Patents,
Inc. Trademarks and Technology Transfer, National
II Electrification Administration, Energy Regulatory Board,
National Telecommunications Commission, Department of
Consistent with CIAC’s technical expertise is the Agrarian Reform under Republic Act No. 6657, Government
primacy and deference accorded to its decisions. There is Service Insurance System, Employees Compensation
only a very narrow room for assailing its rulings. Commission, Agricultural Inventions Board, Insurance
Section 19 of the Construction Industry Arbitration Law Commission, Philippine Atomic Energy Commission, Board
establishes that CIAC arbitral awards may not be assailed, of Investments, Construction Industry Arbitration
except on pure questions of law: Commission, and voluntary arbitrators authorized by law.
19. SectionFinality of Awards.—The arbitral award shall
be binding upon the parties. It shall be final and
inappealable except on questions of law which shall be
219
appealable to the Supreme Court.
VOL. 836, AUGUST 9, 2017 219
CE Construction Corporation vs. Araneta Center,
Rule 43 of the 1997 Rules of Civil Procedure Inc.
standardizes appeals from quasi-judicial agencies.118Rule peals . . . whether the appeal involves questions of fact, of
43, Section 1 explicitly lists CIAC as among the quasi- law, or mixed questions of fact and law.”120
judicial agencies covered by Rule 43.119Section 3 indicates This is not to say that factual findings of CIAC arbitral
that appeals through Petitions for Review under Rule 43 tribunals may now be assailed before the Court of Appeals.
are to “be taken to the Court of Ap- Section 3’s statement “whether the appeal involves
questions of fact, of law, or mixed questions of fact and law” 121 298-A Phil. 361; 228 SCRA 397 (1993)
merely recognizes variances in the disparate modes of [Per J. Feliciano, Third Division].
appeal that Rule 43 standardizes: there were those that
enabled questions of fact; there were those that enabled
questions of law, and there were those that enabled mixed
questions fact and law. Rule 43 emphasizes that though 220
there may have been variances, all appeals under its scope 220 SUPREME COURT REPORTS
are to be brought before the Court of Appeals. However, in ANNOTATED
keeping with the Construction Industry Arbitration Law, CE Construction Corporation vs. Araneta Center,
any appeal from CIAC arbitral tribunals must remain Inc.
limited to questions of law. chosen by the parties themselves, which parties freely
Hi-Precision Steel Center, Inc. v. Lim Kim Steel Builders, consent in advance to abide by the arbitral award issued
Inc.121 explained the wisdom underlying the limitation of after proceedings where both parties had the opportunity to
appeals to pure questions of law: be heard. The basic objective is to provide a speedy and
Section 19 makes it crystal clear that questions of fact inexpensive method of settling disputes by allowing the
cannot be raised in proceedings before the Supreme Court parties to avoid the formalities, delay, expense and
— which is not a trier of facts — in respect of an arbitral aggravation which commonly accompany ordinary
award rendered under the aegis of the CIAC. Consideration litigation, especially litigation which goes through the
of the animating purpose of voluntary arbitration in general entire hierarchy of courts. [The Construction Industry
and arbitration under the aegis of the CIAC in particular, Arbitration Law] created an arbitration facility to which the
requires us to apply rigorously the above principle construction industry in the Philippines can have recourse.
embodied in Section 19 that the Arbitral Tribunal’s findings The [Construction Industry Arbitration Law] was enacted
of fact shall be final and unappealable. to encourage the early and expeditious settlement of
Voluntary arbitration involves the reference of a dispute disputes in the construction industry, a public policy the
to an impartial body, the members of which are implementation of which is necessary and important for the
realization of national development goals.122
_______________
120 RULES OF COURT, Rule 43, Sec. 3 provides: Consistent with this restrictive approach, this Court is
3. SectionWhere to appeal.—An appeal under this duty-bound to be extremely watchful and to ensure that an
Rule may be taken to the Court of Appeals within the appeal does not become an ingenious means for
period and in the manner herein provided, whether the undermining the integrity of arbitration or for conveniently
appeal involves questions of fact, of law, or mixed questions setting aside the conclusions arbitral processes make. An
of fact and law. appeal is not an artifice for the parties to undermine the
process they voluntarily elected to engage in. To prevent
this Court from being a party to such perversion, this one or the other party of a fair opportunity to present its
Court’s primordial inclination must be to uphold the factual position before the Arbitral Tribunal, and an award
findings of arbitral tribunals: obtained through fraud or the corruption of arbitrators. Any
Aware of the objective of voluntary arbitration in the other, more relaxed, rule would result in setting at naught
labor field, in the construction industry, and in any other the basic objective of a voluntary arbitration and would
area for that matter, the Court will not assist one or the reduce arbitration to a largely inutile
other or even both parties in any effort to subvert or defeat institution.123 (Emphasis supplied, citations omitted)
that objective for their private purposes. The Court will not
review the factual findings of an arbitral tribunal upon the
artful allegation that such body had “misapprehended the Thus, even as exceptions to the highly restrictive nature
facts” and will not pass upon issues which are, at bottom, of appeals may be contemplated, these exceptions are only
issues of fact, no matter how clev- on the narrowest of grounds. Factual findings of CIAC
arbitral tribunals may be revisited not merely because
_______________ arbitral tribunals may have erred, not even on the already
exceptional grounds traditionally available in Rule 45
122 Id., at p. 372; pp. 404-405. Petitions.124 Rather,
_______________
_______________
Article 1379 of the Civil Code invokes principles from
147 Pacific Merchandising Corporation v. Consolacion the Revised Rules on Evidence. By invoking these
Insurance & Surety Co., Inc., 165 Phil. 543, 553-554; 73 principles, Article 1379 makes them properly applicable in
SCRA 564, 572-573 (1976) [Per J. Antonio, Second every instance of contractual interpretation, even those
Division], citing Perez v. Pomar, 2 Phil. 682 (1903) where the need for interpretation arises outside of court
[Per J.Torres, En Banc]; and Bonzon v. Standard Oil Co. proceedings:
and Osorio, 27 Phil. 141 (1914) [Per J. Carson, First The principles of interpretation stated in Rule 123 of the
Division]. (Fn 16) Rules of Court shall likewise be observed in the
construction of contracts. 1379. Article
_______________
148 Exec. Order No. 1008, Sec. 2.
149 CIAC RULES OF PROCEDURE, Rule 1, Sec. 1.3 Within its competence and in keeping with basic
provides: principles on contractual interpretation, the CIAC Arbitral
1.3. SectionJudicial rules not controlling.—In any Tribunal ascertained the true and just terms governing ACI
arbitration proceedings under these Rules, the judicial and CECON. Thus, the CIAC Arbitral Tribunal did not
rules of evidence need not be controlling, and it is the spirit conjure its own contractual creature out of nothing. In
and intention of these Rules to ascertain the facts in each keeping with this, the CIAC Arbitral Tribunal found it
case by every and all reasonable means without regard to proper to sustain CECON’s position. There having been no
technicalities of law or procedure. meeting of minds on the contract sum, the amount due to
150 Id. CECON became susceptible to reasonable adjustment,
subject to proof of legitimate costs that CECON can adduce.
V
237
VOL. 836, AUGUST 9, 2017 237 Unravelling the CIAC Arbitral Tribunal’s competence
CE Construction Corporation vs. Araneta Center, and establishing how it acted consistent with law resolves
Inc. the principal legal issue before us. From this threshold, the
As with Article 1371, therefore, the following principles inquiry transitions to the matter of whether or not the
from the Revised Rules on Evidence equally governed the conclusions made by the CIAC Arbitral Tribunal were
CIAC Arbitral Tribunal’s affairs: warranted.
Interpretation of Documents 4.
158
158 SUPREME COURT REPORTS
ANNOTATED 159
B.F. Corporation vs. Form-Eze Systems, Inc. VOL. 813, DECEMBER 7, 2016 159
C.A.-G.R. S.P. No. 102007 which affirmed the Final Award B.F. Corporation vs. Form-Eze Systems, Inc.
rendered by the Construction Industry Arbitration
Commission (CIAC) Arbitral Tribunal on 7 December 2007.
Factual Antecedents
160
Petitioner B.F. Corporation (BFC) is a corporation 160 SUPREME COURT REPORTS
engaged in general engineering and civil works ANNOTATED
construction. Petitioner Honorio H. Pineda (Pineda) is the B.F. Corporation vs. Form-Eze Systems, Inc.
President of BFC. Respondent Form-Eze Systems, Inc.
(Form-Eze) is a corporation engaged in highway and street
construction. _______________
On 29 August 2006, SM Prime Holdings, Inc. awarded
the contract for general construction of the SM City- 5 Id., at p. 162.
Marikina mall (the Project) to BFC whereby the latter
undertook to supply materials, labor, tools, equipment and
supervision for the complete construction of the Project.3 In
turn, BFC engaged Form-Eze for the lease of formwork 161
system and related equipment for and needed by the VOL. 813, DECEMBER 7, 2016 161
Project. Accordingly, five (5) contracts and two (2) letter-
B.F. Corporation vs. Form-Eze Systems, Inc. _______________
8 Id., at p. 165
_______________ 9 Id., at p. 166.
10 Id., at p. 167.
6 Id., at p. 163.
165
162 VOL. 813, DECEMBER 7, 2016 165
162 SUPREME COURT REPORTS B.F. Corporation vs. Form-Eze Systems, Inc.
ANNOTATED On 30 March 2007, Form-Eze filed a Request for
B.F. Corporation vs. Form-Eze Systems, Inc. Arbitration11 before the CIAC. In its Complaint, Form-Eze
alleged that BFC has an unpaid obligation amounting to
P9,189,024.58; that BFC wanted to renegotiate the
equipment leases; and that it was not complying with the
contractual and supplemental agreements in effect. Form-
163 Eze prayed for the following relief:
VOL. 813, DECEMBER 7, 2016 163 1. [For BFC] to pay the current monthly equipment rentals;
2. Provisions made to guarantee the earned monthly
B.F. Corporation vs. Form-Eze Systems, Inc.
equipment leased amounts are paid timely;
3. To legislate provisions to ensure the lease contracts are
not breached during the construction of the SM
_______________ Marikina Mall;
4. Provisions made to guarantee the performance of [BFC]
7 Id., at p. 164.
for the manufacturing of the shoring equipment
purchased by Form-Eze from BFC;
5. Provisions made to guarantee the return of all Form-Eze
164 equipment when the concrete structure is completed and
164 SUPREME COURT REPORTS all lost and damaged equipment has been paid for by
[BFC]; and
ANNOTATED
6. All cost related to Arbitration.12
B.F. Corporation vs. Form-Eze Systems, Inc.
In its Amended Answer with Counterclaim, BFC sought 3. Under Contract #1, BFC is willing and ready to pay
for reformation of Contract #1 to incorporate a provision Form-Eze the amount of P3,515,003.59, which amount
that BFC shall deduct from said billing the cost of labor shall be deducted from the amount of the latter’s claim.
supplied by it for the fabrication and assembly of the 4. Under Contract #2 BFC is willing and ready to pay
forming system and for the stripping, cleaning, resetting Form-Eze the amount of P675,788.97, which amount
thereof at the rate of P60.00 per man-hour. BFC also shall be deducted from the amount of the latter’s claim.
demanded the refund of P5,773,440.00 as expenses for the 5. BFC admits that it has the obligation to return to Form-
manufacture of additional hardware to complete the 7,000 Eze equipment furnished them under Contracts #1, 2,
square meters of formwork and 3, and all heavy-duty galvanized scaffold frames and
_______________ related accessories, heavy-duty galvanized x-bracing and
adjustable U-heads and base plates fabricated and
11 Id., at p. 158. manufactured by BFC under Contracts #4, 5 and letters
12 Id., at p. 160. dated 5 January 2007.14
The CIAC Arbitral Tribunal denied the motion Whether or not the Court of Appeals committed a
prompting BFC to file a petition for review before the Court reversible error in affirming the CIAC’s conclusion that
of Appeals. [Form-Eze] was able to supply BFC with such quantity of
While the case was pending before the Court of Appeals, deckforms sufficient to provide the stipulated 7,000 contact
Form-Eze filed a Motion with Leave to Direct BFC to return square meter of formworks as to entitle said [Form-Eze] to
pieces of equipment on 14 July 2009. the stipulated minimum contract rental price of
On 15 January 2010, the Court of Appeals dismissed the Php28,350,000.00 under Contract No. 1 and consequently to
petition for lack of merit. The Court of Appeals heavily Php6,300,000.00 under Contract No. 2, when, based on the
relied on factual findings of the CIAC Arbitral Tribunal. quantity of the delivered accessories, which are component
parts of deckform system, but which the CIAC totally
The Petition ignored, [Form-Eze] can only provide 4,441.73 contact
BFC filed a motion for reconsideration but it was denied square meters of formworks that will entitle it to only
by the Court of Appeals in a Resolution dated 13 July 2010. Php17,989,006.05 and Php3,997,557.00, respectively
Hence, the present petition. BFC, in its Memorandum, thereunder.
raised the following issues for our resolution:
_______________ III.
19 Id. (Vol. II), pp. 2179-2181. Whether or not the Court of Appeals committed
reversible error in affirming the CIAC’s ruling that [Form-
Eze] is entitled to two-thirds of the stipulated minimum
contract amount of Php3,230,500.00 or Php2,153,666.67
174
under Contract No. 3, considering that CIAC did not state
174 SUPREME COURT REPORTS
the factual and legal basis of said ruling and despite its
ANNOTATED contrary factual finding that [Form-Eze] failed to supply
B.F. Corporation vs. Form-Eze Systems, Inc. the minimum required columnforms.
I.
IV.
Whether or not the Court of Appeals committed a
reversible error in affirming the CIAC’s ruling that BFC is
Whether or not the Court of Appeals committed a Whether or not the Court of Appeals committed a
reversible error in affirming the CIAC’s ruling against the reversible error in affirming the CIAC in ordering BFC to
reformation of Contract No. 1 to include a provision that pay rental fees under letter dated 5 January 2007, covering
BFC shall furnish the labor needed by [Form-Eze] in the period from 25 June 2007 to 17 December 2007 in the
assembling the deckforms and that it shall deduct sum total of Php560,000.00 at Php96,000.00 a month, when
therefrom the agreed cost of labor at Php60.00 per man- the acquisition cost of the pieces of u-heads and plates
hour, referred to therein is allegedly only Php96,000.00, and
there is evidence presented to show that these items were
purchased at Php96,000.00 and there is on evidence to
show the prevailing rate of rent for the same items.
175 VII.
VOL. 813, DECEMBER 7, 2016 175 Whether or not the Court of Appeals committed a
B.F. Corporation vs. Form-Eze Systems, Inc. reversible error in affirming the CIAC in ruling that Re-
since it has been the true intention and real agreement of
the parties thereto.
V.
Whether or not the Court of Appeals committed a 176
reversible error in affirming the CIAC when it did not 176 SUPREME COURT REPORTS
deduct the following costs incurred by BFC from the ANNOTATED
minimum contract amounts due: B.F. Corporation vs. Form-Eze Systems, Inc.
(1) under Contract No. 1 for the cost of labor in spondent Pineda can be held as corespondent (in the
assembling the deckforms, the cost of helmets of arbitration case) when he is not a party to the contracts and
said laborers, and the expenses for x-bracing agreements involved in this case, as well as the arbitration
supplied by BFC for the assembly of said forms in agreement, and he did not voluntarily submit himself to
the total amount of Php812,791.09; arbitration in this case.
(2) under Contract No. 2 for the cost of labor in the VIII.
stripping of said deckforms, the cost of petroleum, Whether or not the Court of Appeals committed a
oil and lubricant and helmet up to the end of the reversible error when it ruled that the attorney’s fees and
contract in the sum total of Php1,391,086.02; and cost of arbitration shall be for the account of Petitioners,
(3) under Contract No. 3 for the cost of labor in considering that [Form-Eze] failed to supply the minimum
installing and forming the built up columnforms required equipment under the contracts and when the root
from 25 June 2007 up to the end of the contract in cause of the dispute is the imprecision of the language and
the sum total of Php273,240.00, when BFC is the incompleteness of the contracts and agreements, which
legally entitled thereto. were prepared by the Respondents.20
VI.
BFC prays for a modification of the Final Award to read: the principle that the final award of CIAC may be still be
subject to judicial review, thus:
_______________ To begin, Executive Order No. (EO) 1008, which vests
upon the CIAC original and exclusive jurisdiction over
20 Id., at pp. 3368-3370. disputes arising from, or connected with, contracts entered
into by parties involved in construction in the Philippines,
plainly states that the arbitral award “shall be final and
inappealable except on questions of law which shall be
177 appealable to the Court.” Later, however, the Court, in
VOL. 813, DECEMBER 7, 2016 177 Revised Administrative Circular (RAC) No. 1-95, modified
B.F. Corporation vs. Form-Eze Systems, Inc. this rule, directing that the appeals from the arbitral award
of the CIAC be first brought to the CA on “questions of fact,
law or mixed questions of fact and law.” This amendment
The Court’s Ruling was eventually transposed into the present CIAC Revised
Rules which direct that “a petition for review from a final
The Final Award of CIAC award may be taken by any of the parties within fifteen (15)
is subject to review by the days from receipt thereof in accordance with the provisions
Court of Appeals. of Rule 43 of the Rules of Court.” Notably, the current
_______________ provision is in harmony with the Court’s pronouncement
that ‘‘despite statutory provisions making the decisions of
21 Id. (Vol. I), pp. 123-124. certain administrative agencies ‘final,’ the Court still takes
cognizance of petitions showing want of jurisdiction, grave
abuse of discretion, violation of due process, denial of
substantial justice or erroneous interpretation of the law”
178 and that, in particular, “voluntary arbitrators, by the
178 SUPREME COURT REPORTS nature of their functions, act in a quasi-judicial capacity,
ANNOTATED such that their decisions are within the scope of judicial
B.F. Corporation vs. Form-Eze Systems, Inc. review.”23
BFC first asserts that the Court of Appeals has the
power and the duty to review the factual findings made by _______________
CIAC and that the Court of Appeals should not be bound by
22 716 Phil. 788; 704 SCRA 332 (2013).
the factual findings of the construction arbitrators.
23 Id., at pp. 802-803; pp. 345-346.
The case of Asian Construction and Dev’t. Corp. v.
Sumitomo Corporation22 summarized the development of
While factual findings are not within the purview of a
179 petition for review before this Court, we take exception in
VOL. 813, DECEMBER 7, 2016 179 this
B.F. Corporation vs. Form-Eze Systems, Inc. _______________
Factual findings of construction arbitrators may be
24 IBEX International, Inc. v. Government Service
reviewed by the Court in cases where: 1) the award was
Insurance System, 618 Phil. 304, 312-313; 603 SCRA 306,
procured by corruption, fraud or other undue means; (2)
315 (2009), citing Uniwide Sales Realty and Resources
there was evident partiality or corruption of the arbitrators
Corporation v. Titan-Ikeda Construction and Development
or any of them; (3) the arbitrators were guilty of misconduct
Corporation, 540 Phil. 350, 360-361; 511 SCRA 335, 345-
in refusing to hear evidence pertinent and material to the
346 (2006).
controversy; (4) one or more of the arbitrators were
disqualified to act as such under Section nine of Republic
Act (R.A.) No. 876 and willfully refrained from disclosing
such disqualifications or of any other misbehavior by which 180
the rights of any party have been materially prejudiced; (5) 180 SUPREME COURT REPORTS
the arbitrators exceeded their powers, or so imperfectly
ANNOTATED
executed them, that a mutual, final and definite award
upon the subject matter submitted to them was not made; B.F. Corporation vs. Form-Eze Systems, Inc.
(6) when there is a very clear showing of grave abuse of case on the ground of the appellate court’s refusal to delve
discretion resulting in lack or loss of jurisdiction as when a into the findings of facts of the CIAC Arbitral Tribunal.
party was deprived of a fair opportunity to present its Under Contract No. 1, Form-
position before the Arbitral Tribunal or when an award is Eze was not able to supply
obtained through fraud or the corruption of arbitrators; (7) BFC with deckforms suffi-
when the findings of the Court of Appeals are contrary to cient to provide 7,000 contact
those of the CIAC, and (8) when a party is deprived of square meter of formworks.
administrative due process.24 The CIAC Arbitral Tribunal conducted its own study
While this rule, which limits the scope of the review of and came up with the following findings:
CIAC findings, applies only to the Supreme Court, the The receipted hardware deliveries made by [Form-Eze]
Court of Appeals nonetheless is not precluded from show that the total length of loose truss chords delivered
reviewing findings of facts, it being a reviewer of facts. By was 11,912 lineal feet and the length of the truss chords
conveniently adopting the CIAC’s decision as its own and from the assembled trusses delivered was 2,052 lineal feet
refusing to delve into its factual findings, the Court of or a total available length of trusses of 13,964 lineal feet. By
Appeals had effectively turned a blind eye to the an iterative process of selection and elimination, 175 units
evidentiary facts which should have been the basis for an of 44’ long trusses could be assembled, equivalent to 87
equitable and just award. deckforms of 44 feet in length. The assembled 87-44’
deckforms can provide 7,268.58 square meters of contact BFC considerable labor and eliminate the use of BFC’s light
area, broken down as follows: duty scaffolding underneath and beam. By doing that it will
also speed up the forming operation and save BFC labor.
Contact Area The only light duty scaffolding that BFC will be installing
(%) is that under the girder which supports tremendous loading
during the stressing of the beams prior to it being stressed.
Interior & Near 4,156.89 sq.
= By forming the girder in this manner, [Form-Eze] is not
Column Slabs m. (57.19%)
involved in the tripping or resetting of the girder formwork.
Grid Beams (B- 740.37 sq. m.
= However, [Form-Eze] is has purchased and furnished
1) (10.19%)
Interior Beams 1,663.20 sq. considerable forming hardware and consumables (tie rods,
(B-2)
=
m. (22.88%) pvc sleeves, pvc cones, whaler clips and brackets and wing-
Grid Girders (G- 708.12 sq. m. nuts) which are being used on girders and the beams.
2)
=
(9.74%) [Form-Eze] will give the ownership of this equipment to
7,268.58 sq. BFC and BFC will buy all additional consumables and
Total = hardware (as needed) directly from Comer. In return,
m. (100%)
The resulting contact area of 7,628.58 sq. m. is 3.84% [Form-Eze] will include the contact square meters of
over the 7,000 sq. m. requirement of the contract. But the formwork in the girders in its billing for both the equipment
former figure includes the contact area of girders which lease and for the moving contract.” This letter-contract,
according to [petitioners] should not be included. As shown Exhibit C-12, binds [BFC] to pay Claimant for the girder
in ANNEX “A,” sheets 5 & 6 of 6, the contact area formworks contact area for both Contract No. 1 and
contributed by the girders is only 708.12 sq. m., and if this Contract No. 2.
is deducted from the computed total contact area, Petitioners argued that the formwork of the girder (or
large beam) is independent of the deckform system and so
should not be counted in favor of [Form-Eze]. The Tribunal
does not agree. How could the girder formwork be
181 considered independent from the deckform system when
VOL. 813, DECEMBER 7, 2016 181 both sides of the girder formworks are held stiff together by
B.F. Corporation vs. Form-Eze Systems, Inc. “tie rods, pvc sleeves (to make the tie rods reusable), pvc
the remaining available contact area would be 6,560.46 sq. cones, whaler clips and brackets and wing-nuts” supplied by
m. or 93.72%. The fact, however, is that the noninclusion of the [Form-Eze] and pressed between deckforms preparatory
the contact area provided by the girders would be a to concrete pouring? The girder cannot be considered
violation of the letter-contract dated 8 February 2007, structurally independent of the deck slabs because it is the
paragraph 9 of which provides that: “[Form-Eze] offered to requirement of design and the National Building Code and
install beam hangers and ledger angles in order to support its reference code the
the moment beam from column to column and thereby save
are being used. BFC reiterates that based on the provisions
of Contract No. 1 on the contemporaneous and subsequent
182 acts of the parties, as well as application of principles of
182 SUPREME COURT REPORTS contract interpretation, the inclusion of loose truss chords
ANNOTATED in the computation of the quantity of hardware supplied by
B.F. Corporation vs. Form-Eze Systems, Inc. Form-Eze is an erroneous interpretation by CIAC. BFC also
claims that the CIAC wrongfully included the contact area
American Concrete Institute Code (ACI Code) that the
of girders in the computation of the sufficiency of
girders are to be poured monolithically with the slabs and
_______________
beams up to L/3 or 1/3 of the floor span (the point of
infection and location of the construction joint where the
25 Rollo (Vol. I), pp. 2137-2139.
bending moment is the least or zero), as is clearly shown on
the floor concrete pouring schedule plans.
Conclusion of Tribunal
In view of the above, it is the finding of the Arbitral 183
Tribunal that [Form-Eze] had been able to furnish the VOL. 813, DECEMBER 7, 2016 183
amount of hardware that was sufficient to provide 7,000
B.F. Corporation vs. Form-Eze Systems, Inc.
contact square meters of formwork, all in accordance to
equipment supplied by Form-Eze. BFC contends that the
Contract No. 1. Thus, the remaining question to resolve is
girders are not part of the deckforms contemplated in
the area of the project covered by the formwork equipment
Contract No. 1. BFC offers to compensate Form-Eze to the
in contact square meters.25
extent that its supplied deckforms were used under the
principle of quantum meruit. BFC submits that 4,441.73
BFC accuses the CIAC of coming up with its own biased contact square meters or 63.45% of the 7,000 minimum
computation of the contact area of the hardware supplied by contact area required under Contract No. 1 is a reasonable
Form-Eze under Contract No. 1. According to BFC, Form- computation.
Eze had furnished only 53 completely assembled deckforms We reverse the finding of the CIAC on this point as it is
of 44 ft. in length which correspond to only 4,441.73 contact contrary to the evidence on record.
square meters of formworks, while CIAC found that Form- We agree with BFC that the CIAC should not have
Eze had delivered truss chords equivalent to 87 deckforms included the unassembled truss chords in theoretically
which can provide 7,268.58 contact square meters. BFC forming deckforms. We subscribe to BFC’s submission that
maintains that Contract No. 1 is clear that the object is the the object of Contract No. 1 is the deckforms and not just
supply of the complete deckform system and not the hardware that make up the formwork. Contract No. 1,
unassembled hardware such as loose truss chords. BFC in itself, is clear that “F-E has agreed to furnish all
adds that Form-Eze judicially admitted that it is only hardware required in the formwork system for the poured
claiming equipment rentals for the areas that its equipment in place beam and slab concrete decks x x x.” In fact, the
equipment rental is only due and payable to Form-Eze theoretical findings, only 2,512 pieces of joists and only
when the concrete is placed on the slab forms, which 3,626 pieces of beam hangers were actually delivered by
provision is based on the premise that the hardware had [Form- Eze].26
already been assembled into deckforms ready for concrete
pouring. Moreover, the Proposed SM Marikina Mall Project
Elevated Beam and Slab Formwork dated 7 December BFC’s computation of the total contact area covered by
2006, which document has been admitted by the parties in the deckforms furnished by Form-Eze is backed by delivery
the Term of Reference, provides that Form-Eze will furnish receipts of the joists and beam hangers while CIAC’s
sufficient deckforms to produce 1/2 floor each month on the computation is more theoretical than it is actual.
project. The inclusion of the additional contact area of the grid
BFC had also explained to our satisfaction that loose girders in the calculation of the total contact area of the
truss chords alone could not be assembled into deckforms, equipment supplied by Form-Eze under Contract No. 1,
to wit: however, should be upheld. Paragraph 9 of the Letter dated
To try to assemble truss chords alone into a deckform is 8 February 2007, which was also admitted by the parties,
like taking three two-foot round pegs, trying to stand them clearly provides:
upright, then balancing twelve-inch round wooden slab on [Form-Eze] offered to install beam hangers and ledger
top, and expect it to be a stool capable of supporting a angles in order to support the moment beam fro column to
person. Joist, beam hangers and other component parts fix column and thereby save BFC considerable labor and
the truss chords into place for the structural integrity of a eliminate the use of BFC’s light duty scaffolding
deckform. In the case of a deckform 44 ft. in length, it will underneath that beam. By doing that it will also speed up
need, for it to be completely assem- the forming operation and save BFC labor. The only light
duty scaffolding that BFC will be installing is under the
girder which supports tremendous loading during the
stressing for the beams prior to it being stressed. By
184 forming the girder in this manner F-E is not involved in the
184 SUPREME COURT REPORTS stripping or resetting of the girder formwork. However,
ANNOTATED [Form-Eze] has purchased and furnished considerable
B.F. Corporation vs. Form-Eze Systems, Inc. forming hardware and consumables (tie rods, pvc sleeves,
pvc cones, whaler clips and brackets and wing-nuts) which
bled, 34 pieces of joists and 68 pieces of beam hangers as
are being used on the girders and the beams.
illustrated in the Petitioner’s Motion for Correction of Final
Award. _______________
Thus, assembling 87 deckforms of 44 ft. in length would
require 2,958 pieces of joist and 5,916 pieces of beam 26 See BFC’s Memorandum, id.(Vol. II), p. 3382.
hangers to assemble such 87-44-foot deckforms. However,
as show in the same documents that CIAC anchored its
185 5,149.85, which still falls short of the 7,000 contact area
VOL. 813, DECEMBER 7, 2016 185 requirement.
B.F. Corporation vs. Form-Eze Systems, Inc. To award the full contract price to Form-Eze in Contract
[Form-Eze] will give ownership to this equipment to BFC No. 1 is tantamount to unjust enrichment. There is unjust
and BFC will buy all additional consumables and hardware enrichment under Article 22 of the Civil Code when (1) a
(as needed) directly from Comer. In return [Form-Eze] will person is unjustly benefited, and (2) such benefit is derived
include the contact square meters of formwork in the at the expense of or with damages to another. The principle
girders in its billing for both the equipment lease and for of
the moving contract.27 _______________
BFC avers that CIAC erred when it stated the BFC was Obligation of BFC under
given the exclusive license to manufacture Form-Eze’s Contract No. 2.
equipment consisting of scaffoldings and accessories and
they became part of that provided by Form Eze to BFC. BFC maintains that since Form-Eze failed to meet the
At the outset, we agree that the subsequent minimum conditions under Contract No. 1 where the
Memorandum of Agreement executed by the parties on 5 minimum 126,000 contact square meters were not reached,
January 2007 is an exclusive licensing agreement. It was then the forklifts under Contract No. 2 were also not used
signed by both parties wherein BFC has agreed to sell the for a minimum of 126,000 contact square meters.
scaffolding frames and accessories it manufactured to We agree. BFC is liable only to pay the amount
Form-Eze at the end of the project. This Agreement was proportionate to 92,696.40 contact square meters at P50.00
incorporated in Contract No. 4 wherein BFC will be allowed per contact square meter, the rental rate for the forklifts.
to deduct P6,352,500.00 from the equipment lease contract, Thus:
which is presumably Contract No. 1. At this point, Contract
No. 4 is deemed to have novated the obligation of BFC with 92,696.40 contact square meters x P50.00 = P4,634,820.00
respect to furnishing all scaffoldings. Contract No. 1 states Less: Payments made 990,000.00
that BFC shall furnish the scaffoldings at no cost to Form- Cost of Labor 1,286,377.50
Eze. On the other hand, Contract No. 4 requires BFC to sell _____________
the scaffoldings to Form-Eze at the SUBTOTAL P2,358,442.50
Obligation of BFC
192 under Contract No. 3.
192 SUPREME COURT REPORTS
ANNOTATED The CIAC had correctly noted the ambiguity in Contract
B.F. Corporation vs. Form-Eze Systems, Inc. No. 3, particularly the “sufficient number of columnforms as
required to complete six (6) poured in place columns per
end of the project and deduct the cost of the same from the
day.” For BFC, the sufficient number of columnforms is 12
contract price of Contract No. 1. This setup cannot in any
sets a day while Form-Eze considered its supply of six (6)
full height built up columnforms as sufficient. The CIAC BFC is then liable to pay P441,502.87 broken down as
found that follows:
1,516.67 x P355.00 = P538,417.85
Less: Cost of Labor 96,915.00
193 _____________
VOL. 813, DECEMBER 7, 2016 193 SUBTOTAL: P441,502.87
B.F. Corporation vs. Form-Eze Systems, Inc.
Form-Eze failed to comply with the requirements under
194
Contract No. 3, hence it merely awarded Form-Eze 2/3 of
194 SUPREME COURT REPORTS
the minimum contract amount at P2,153,666.67.
We find that the CIAC’s award lacked bases. It gave ANNOTATED
credence to the methodology used by Form-Eze and noted B.F. Corporation vs. Form-Eze Systems, Inc.
that the latter had supplied six (6) full height built-up BFC is obliged to pay rental for
columnforms, albeitinsufficient. We hold the contrary. The u-heads under Letter-Agreement
methodology used by BFC, which involves “columnforms dated 5 January 2007.
with window openings and that from its installation,
alignment, bracing, inspection, approval of alignment, Under the letter dated 8 February 2007, “BFC has
verticality and rigidity of the erected columnforms, pouring, completed fabrication on a sufficient quantity of u-heads
drying and removal of the forms, it will require twelve (12) with screw assemblies and heavy-duty bases so that BFC
columnforms a day, should have been considered. The CIAC can immediately start returning the 24-inch and 18-inch u-
itself had already ruled that the ambiguity in Contract No. head assemblies (561 pcs.) and heavy-duty bases (483 pcs.)
3 should not favor Form-Eze, the party who prepared the which were on temporary loan to BFC by [Form-Eze] until
contract. Thus, it is only logical that the methodology BFC could manufacture their own equipment. The
employed by BFC should be credited. temporary loan was expected to be approximately [two] (2)
Using 12 columnforms as the minimum requisite and weeks and the equipment was picked up January 9, 2007
Form-Eze having supplied only four (4) usable and still in used today.”36 It is understood that upon
columnforms, it can be established that the delivered expiration of the two-week temporary loan and upon failure
columnforms can only be used for 1/3 portion of the 9,100 by BFC to return the equipment, it is then liable to pay for
contact square meters or 3,033.33 contact square meters. It rent. We find that the monthly rental amount of P96,600.00
was further proven by BFC that about 50% of the was substantiated by Form-Eze. 483 pieces of 24 inch and
columnform requirements of the project were already 18 inch galvanized adjustable heads and 483 pieces of
completed with the use of their own equipment. Thus, it is galvanized heavy-duty plates were indeed delivered to BFC
but equitable that the 3,033.33 contact square meters be as evidenced by the delivery receipts.37 According to Mr.
further reduced by 50% or 1,516.67 contact square meters. Clemente, Form-Eze’s Sales Engineer, the rental amount
for adjustable u-heads are fixed at P160.00 per unit, while
the galvanized heavy-duty plates are at P40.00 per his inclusion as a respondent in the CIAC proceedings.
unit.38 By agreeing to the terms of the 8 February 2007 CIAC however considered Pineda as a joint tortfeasor, thus
Letter, BFC is deemed to have acquiesced to the rental fee justifying his joinder as a codefendant.
in case it failed to return the u-heads and plates on time. We do not consider the imputed acts of Pineda as
Therefore, we affirm the CIAC’s ruling that BFC is liable to an indicia of bad faith to classify him as a joint
pay rental of the equipment in the amount of P96,000.00 tortfeasor. First, it was proven that Form-Eze is not
per month until the equipment leased is fully returned to entitled to all its monetary claims under the
Form-Eze. contract. Second, we have also subscribed to BFC’s position
_______________ that Contract No. 1 should have included a labor guarantee
provision and that it was by mistake that said clause was
36 Id., at p. 204. excluded. Third, BFC’s alleged refusal to return the u-head
37 Id., at pp. 324-325, 330 and 334. assemblies and heavy-duty bases was meted with a heavy
38 Id., at p. 387. Judicial Affidavit of Mr. Clemente. penalty in the form of a huge rental fee. BFC had, as a
matter of fact, admitted to owing Form-Eze rental
payment. Fourth, the claim of threat against Form-Eze’s
President is unsubstantiated and uncorroborated.
195
VOL. 813, DECEMBER 7, 2016 195 Attorney’s Fees and Costs
B.F. Corporation vs. Form-Eze Systems, Inc. of Arbitration.
BFC President should not be
included as party to this case? The controversy essentially boils down to the
interpretation and factual application of the existing
Section 4 of Executive Order No. 1008 vests jurisdiction contracts. Neither
on CIAC over disputes disputes arising from, or connected
with, contracts entered into by parties involved in
construction in the Philippines, whether the dispute arises 196
before or after the completion of the contract, or after the 196 SUPREME COURT REPORTS
abandonment or breach thereof. Moreover, the party ANNOTATED
involved must agree to submit to voluntary arbitration. In B.F. Corporation vs. Form-Eze Systems, Inc.
other words, anyone who is not a party to the contract in
party was able to prove bad faith in their dealing with each
his personal capacity is not subject to the jurisdiction of the
other. Under Article 2208 of the Civil Code, attorney’s fees
CIAC. In this case, Pineda signed the challenged contracts
may, among others, be recovered where defendant acted in
in his capacity as President of BFC. There is no indication
gross and evident bad faith in refusing to satisfy the
that he voluntarily submitted himself as a party to the
plaintiff’s plainly valid, just and demandable claim. We
arbitration case. In fact, he has been consistently contesting
observe that in filing the complaint against BFC, Form-Eze
was merely seeking payment for its service under the 197
contract. BFC had admitted to its obligation. The problem VOL. 813, DECEMBER 7, 2016 197
lies only on the amount to be paid. This is not tantamount B.F. Corporation vs. Form-Eze Systems, Inc.
to bad faith.
Finally, both parties should equally share the costs of Petition partially granted, judgment and resolution
arbitration since their prayers were only partially modified.
granted.39
Notes.—The Supreme Court (SC) has ruled that when a
WHEREFORE, the petition is PARTIALLY dispute arises from a construction contract, the
GRANTED. The Decision dated 15 January 2010 and Construction Industry Arbitration Commission (CIAC) has
Resolution dated 13 July 2010 are MODIFIED. Petitioner exclusive and original jurisdiction. (Stronghold Insurance
B.F. Corporation is ordered to pay respondent Form-Eze Company, Inc. vs. Stroem, 746 SCRA 598 [2015])
Systems, Inc. the following amounts: Under Article 22 of the Civil Code, there is unjust
Under Contract No. 1: P11,857,317.45 enrichment when (1) a person is unjustly benefited and (2)
2,358,442.50 Under Contract No. 2: such benefit is derived at the expense of or with damages to
441,502.87 Under Contract No. 3: another. (Bliss Development Corp./Home Guaranty
Under Letter-Agreement Corporation vs. Diaz, 765 SCRA 453 [2015])
560,000.00 dated 7 January 2007:
GRAND TOTAL: P15,217,262.82 ——o0o——
and 50% of the Cost of Arbitration. © Copyright 2019 Central Book Supply, Inc. All rights
reserved.
SO ORDERED.
Velasco, Jr. (Chairperson), Del
Castillo,**Reyes and Jardeleza, JJ., concur.
_______________