Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 91

March 8, 2017. G.R. No. 211504.* agreeing to submit their dispute to voluntary arbitration.

The CIAC Revised Rules clarifies, however, that the


FEDERAL BUILDERS, INC., petitioner, vs. POWER agreement of the parties to submit their dispute to
FACTORS, INC., respondent. arbitration need not be signed or be formally agreed upon in
the contract because it can also be in the form of other
Construction Industry Arbitration Commission; modes of communication in writing.
Jurisdiction; Under the Construction Industry Arbitration
Commission Revised Rules of Procedure Governing _______________
Construction Arbitration (CIAC Revised Rules), all that is
required for the CIAC to acquire jurisdiction is for the * THIRD DIVISION.
parties of any construction contract to agree to submit their
dispute to arbitration.—The need to establish a proper
arbitral machinery to settle disputes expeditiously was
recognized by the Government in order to promote and 79
maintain the development of the country’s construction VOL. 820, MARCH 8, 2017 79
industry. With such recognition came the creation of the Federal Builders, Inc. vs. Power Factors, Inc.
CIAC through Executive Order No. 1008 (E.O. No. 1008), Same; Same; Executive Order (EO) No. 1008
also known as The Construction Industry Arbitration emphasizes that the modes of voluntary dispute resolution
Law. Section 4 of E.O. No. 1008 provides: Sec. like arbitration are always preferred because they settle
4. Jurisdiction.—The CIAC shall have original and disputes in a speedy and amicable manner.—The liberal
exclusive jurisdiction over disputes arising from, or application of procedural rules as to the form by which the
connected with, contracts entered into by parties involved agreement is embodied is the objective of the CIAC Revised
in construction in the Philippines, whether the dispute Rules. Such liberality conforms to the letter and spirit of
arises before or after the completion of the contract, or after E.O. No. 1008 itself which emphasizes that the modes of
the abandonment or breach thereof. These disputes may voluntary dispute resolution like arbitration are always
involve government or private contracts. For the Board to preferred because they settle disputes in a speedy and
acquire jurisdiction, the parties to a dispute must agree to amicable manner. They likewise help in alleviating or
submit the same to voluntary arbitration. x x x Under the unclogging the judicial dockets. Verily, E.O. No. 1008
CIAC Revised Rules of Procedure Governing Construction recognizes that the expeditious resolution of construction
Arbitration (CIACRevised Rules), all that is required for the disputes will promote a healthy partnership between the
CIAC to acquire jurisdiction is for the parties of any Government and the private sector as well as aid in the
construction contract to agree to submit their dispute to continuous growth of the country considering that the
arbitration. Also, Section 2.3 of the CIAC Revised construction industry provides employment to a large
Rules states that the agreement may be reflected in an segment of the national labor force aside from its being a
arbitration clause in their contract or by subsequently leading contributor to the gross national product.
Same; Same; Construction Disputes; Section 2.1, Rule 2 the contract; and (c) cause or consideration. Moreover,
of the Construction Industry Arbitration Commission a contract does not need to be in writing in order to be
(CIAC) Revised Rules particularly specifies that the CIAC obligatory and effective unless the law specifically requires
has original and exclusive jurisdiction over construction so. Pursuant to Article 1356 and Article 1357 of the Civil
disputes, whether such disputes arise from or are Code,contracts shall be obligatory in whatever form they
merely connected with the construction contracts entered may have been entered into, provided that all the essential
into by parties, and whether such disputes requisites for their validity are present. Indeed, there was a
arise before or after the completion of the contracts.—Worthy contract between Federal and Power even if the Contract of
to note is that the jurisdiction of the CIAC is over the Service was unsigned. Such contract was obligatory and
dispute, not over the contract between the parties. Section binding between them by virtue of all the essential
2.1, Rule 2 of the CIAC Revised Rulesparticularly specifies elements for a valid contract being present.
that the CIAC has original and exclusive jurisdiction Construction Industry Arbitration Commission;
over construction disputes, whether such disputes Jurisdiction; Although the agreement to submit to
arise from or are merelyconnected with the construction arbitration has been expressly required to be in writing and
contracts entered into by parties, and whether such signed by the parties therein by Section 4 of Republic Act
disputes arise before or after the completion of the (RA) No. 876 (Arbitration Law), the requirement is
contracts. Accordingly, the execution of the contracts and conspicuously absent from the Construction Industry
the effect of the agreement to submit to arbitration are Arbitration Commission (CIAC) Revised Rules, which even
different matters, and the signing or non-signing of one expressly allows such agreement not to be signed by the
does not necessarily affect the other. In other words, the parties therein.—The agreement contemplated in the
formalities of the contract have nothing to do with the CIAC Revised Rules to vest jurisdiction of the CIAC over
jurisdiction of the CIAC. the parties’ dispute is not necessarily an arbitration clause
Civil Law; Contracts; A contract does not need to be in to be contained only in a signed and finalized construction
writing in order to be obligatory and effective unless the law contract. The agreement could also be in a separate
specifically requires so.—Under Article 1318 of the Civil agreement, or any other form of written communication, as
Code, a valid contract should have the following essential long as their intent to submit their dispute to arbitration is
elements, namely: (a) consent of the contracting parties; clear. The fact that a contract was signed by both parties
(b) object certain that is the subject matter of has nothing to do with the jurisdiction of the CIAC, and this
is the explanation why the CIACRevised Rules itself
expressly provides that the written communication or
agreement need not be signed by the parties. Although the
80 agreement to submit to arbitration has been expressly
80 SUPREME COURT REPORTS required to be in writing and signed by the parties therein
ANNOTATED by Section 4 of Republic Act No. 876 (Arbitration Law), the
Federal Builders, Inc. vs. Power Factors, Inc. requirement is conspicuously absent from the CIAC Revised
Rules, which even expressly allows such agreement not to Federal Builders, Inc. (Federal) appeals to reverse the
be signed by the parties therein.Brushing aside the obvious decision promulgated on August 12, 2013,1 whereby the
contractual agreement in this case warranting the Court of Appeals (CA) affirmed the adverse decision
submission to arbitration is surely a step rendered on May 12, 2010 by the Construction Industry
backward. Consistent with the policy of encouraging Arbitration Commission (CIAC) with modification of the
alternative dispute resolution methods, therefore, any total amount awarded.2
doubt should be resolved in favor of arbitration. In this
connection, the CA correctly observed that the act of Atty. Antecedents
Albano in manifesting that Federal had agreed to the form
of arbitration was unnecessary and inconsequential Federal was the general contractor of the Bullion Mall
considering the recognition of the value of the Contract of under a construction agreement with Bullion Investment
Service despite its being an unsigned draft. and Development Corporation (BIDC). In 2004, Federal
engaged respondent Power Factors, Inc. (Power) as its
subcontractor for the electric works at the Bullion Mall and
the Precinct Building for P18,000,000.00.3
81 _______________
VOL. 820, MARCH 8, 2017 81
Federal Builders, Inc. vs. Power Factors, Inc. 1 Rollo, pp. 32-45; penned by Associate Justice Leoncia
PETITION for review on certiorari of a decision of the R. Dimagiba and concurred in by Associate Justices
Court of Appeals. Rosmari D. Carandang and Ricardo R. Rosario.
The facts are stated in the opinion of the Court. 2 Id., at pp. 98-128.
Atienza, Formento, Aquino & Alzate for petitioner. 3 Id., at p. 33.
Erlich V. Barraquias for respondent.

BERSAMIN, J.:
82
An agreement to submit to voluntary arbitration for 82 SUPREME COURT REPORTS
purposes of vesting jurisdiction over a construction dispute ANNOTATED
in the Construction Industry Arbitration Commission Federal Builders, Inc. vs. Power Factors, Inc.
(CIAC) need not be contained in the construction contract, On February 19, 2008, Power sent a demand letter to
or be signed by the parties. It is enough that the agreement Federal claiming the unpaid amount of P11,444,658.97 for
be in writing. work done by Power for the Bullion Mall and the Precinct
Building. Federal replied that its outstanding balance
The Case under the original contract only amounted to
P1,641,513.94, and that the demand for payment for work
done by Power after June 21, 2005 should be addressed
directly to BIDC.4Nonetheless, Power made several
demands on Federal to no avail. 83
On October 29, 2009, Power filed a request for VOL. 820, MARCH 8, 2017 83
arbitration in the CIAC invoking the arbitration clause of Federal Builders, Inc. vs. Power Factors, Inc.
the Contract of Service reading as follows: agreement for arbitration, the CIAC had no jurisdiction to
ARBITRATION COMMITTEE — All disputes, hear and decide the case.7
controversies or differences, which may arise between the On February 8, 2010, the CIAC issued an order setting
parties herein, out of or in relation to or in connection with the case for hearing, and directing that Federal’s motion to
this Agreement, or for breach thereof shall be settled by the dismiss be resolved after the reception of evidence of the
Construction Industry Arbitration Commission (CIAC) parties.8
which shall have original and exclusive jurisdiction over the Federal did not thereafter participate in the proceedings
aforementioned disputes. 15.5 until the CIAC rendered the Final Award dated May 12,
2010,9disposing:
In summary: Respondent Federal Builders, Inc. is
On November 20, 2009, Atty. Vivencio Albano, the
hereby ordered to pay claimant Power Factors, Inc. the
counsel of Federal, submitted a letter to the CIAC
manifesting that Federal agreed to arbitration and sought following sums:
an extension of 15 days to file its answer, which request the The foregoing amount shall earn legal interest at the
rate of 6% per annum from the date of this Final Award
CIAC granted.
On December 16, 2009, Atty. Albano filed his until this award becomes final and executory, Claimant
withdrawal of appearance stating that Federal had shall then be entitled to 12% per annum until the entire
meanwhile engaged another counsel.6 amount is fully satisfied by Respondent.
Federal, represented by new counsel (Domingo, Dizon,
Leonardo and Rodillas Law Office), moved to dismiss the Federal appealed the award to the CA insisting that the
case on the ground that CIAC had no jurisdiction over the CIAC had no jurisdiction to hear and decide the case; and
case inasmuch as the Contract of Service between Federal that the amounts thereby awarded to Power lacked legal
and Power had been a mere draft that was never finalized and factual bases.
or signed by the parties. Federal contended that in the _______________
absence of the
_______________ 7 Id., at p. 35.
8 Id.
4 Id. 9 Id., at pp. 98-128.
5 Id., at p. 44.
6 Id., at pp. 34-35.
to arbitrate need not be signed by the parties; that the
84 consent to submit to voluntary arbitration was not
84 SUPREME COURT REPORTS necessary in view of the arbitration clause contained in the
ANNOTATED Contract of Service; and that Federal’s contention that its
Federal Builders, Inc. vs. Power Factors, Inc. former counsel’s act of manifesting its consent to the
arbitration stipulated in the draft Contract of Service did
On August 12, 2013, the CA affirmed the CIAC’s
not bind it was inconsequential on the issue of
decision with modification as to the amounts due to
jurisdiction.12
Power,10 viz.:
_______________
WHEREFORE, the CIAC Final Award dated 12 May
2010 in CIAC Case No. 31-2009 is
10 Id., at pp. 32-42.
hereby AFFIRMED withMODIFICATION. As modified,
11 Id., at pp. 44-45.
FEDERAL BUILDERS, INC. is ordered to pay POWER
12 Id., at p. 38.
FACTORS, INC. the following:

1. Unpaid balance on the


P4,276,614.75;
original Contract
2. Unpaid balance on change 85
2,864,113.32; VOL. 820, MARCH 8, 2017 85
orders
3. Attorney’s Fees 250,000.00; Federal Builders, Inc. vs. Power Factors, Inc.
4. Cost of Arbitration 149,503.86; Concerning the amounts awarded, the CA opined that
The interest to be imposed on the net award (unpaid the CIAC should not have allowed the increase based on
balance on the original contract and change order) labor-cost escalation because of the absence of the
amounting to P7,140,728.07 awarded to POWER agreement between the parties on such escalation and
FACTORS, INC. shall be six (6%) per annum, reckoned because there was no authorization in writing allowing the
from 4 July 2006 until this Decision becomes final and adjustment or increase in the cost of materials and labor.13
executory. Further, the total award due to POWER After the CA denied Federal’s motion for reconsideration
FACTORS, INC. shall be subjected to an interest of twelve on February 19, 2004,14 Federal has come to the Court on
percent (12%) per annum computed from the time this appeal.
judgment becomes final and executory, until full
satisfaction. Issue
SO ORDERED.11 The issues to be resolved are: (a) whether the CA erred
in upholding CIAC’s jurisdiction over the present case; and
(b) whether the CA erred in holding that Federal was liable
Anent jurisdiction, the CA explained that the to pay Power the amount of P7,140,728.07.
CIACRevised Rules of Procedurestated that the agreement
Ruling of the Court acquire jurisdiction, the parties to a dispute must agree to
submit the same to voluntary arbitration. x x x
The appeal is bereft of merit.

1. Under the CIAC Revised Rules of Procedure Governing


The parties had an effective agreement Construction Arbitration (CIAC Revised Rules), all that is
to submit to voluntary arbitration; required for the CIAC to acquire jurisdiction is for the
hence, the CIAC had jurisdiction parties of any construction contract to agree to submit their
dispute to arbitration.15Also, Section 2.3 of the
The need to establish a proper arbitral machinery to CIACRevised Rules states that the agreement may be
settle disputes expeditiously was recognized by the reflected in an arbitration clause in their contract or by
Government in order to promote and maintain the subsequently agreeing to submit their dispute to voluntary
development of the country’s construction industry. With arbitration. The CIAC Revised Rules clarifies, however, that
such recognition came the creation of the CIAC through the agreement of the parties to submit their dispute to
Executive Order No. 1008 (E.O. No. 1008), also known arbitration need not be signed or be formally agreed upon in
as The Construction Industry Arbitration Law. Section 4 of the contract because it can also be in the form of other
E.O. No. 1008 provides: modes of communication in writing,viz.:
_______________ RULE 4 – EFFECT OF AGREEMENT TO ARBITRATE
4.1. SECTIONSubmission to CIAC jurisdiction.—An
13 Id., at pp. 42-43. arbitration clause in a construction contract or a
14 Id., at p. 47. submission to arbitration of a construction dispute shall be
deemed an agreement to submit an existing or future
controversy to CIAC jurisdiction, notwithstanding the
reference to a different arbitration institution or arbitral
86 body in such contract or submission.
86 SUPREME COURT REPORTS
ANNOTATED _______________
Federal Builders, Inc. vs. Power Factors, Inc.
15 Rule 4, CIAC Revised Rules;LICOMCEN,
4. Sec.Jurisdiction.—The CIAC shall have original Incorporated v. Foundation Specialists, Inc., G.R. Nos.
and exclusive jurisdiction over disputes arising from, or 167022 & 169678, April 4, 2011, 647 SCRA 83, 97.
connected with, contracts entered into by parties involved
in construction in the Philippines, whether the dispute
arises before or after the completion of the contract, or after
the abandonment or breach thereof. These disputes may 87
involve government or private contracts. For the Board to VOL. 820, MARCH 8, 2017 87
Federal Builders, Inc. vs. Power Factors, Inc. exclusive jurisdiction overconstruction disputes,whether
When a contract contains a clause for the submission of a such disputes arisefrom or are
future controversy to arbitration, it is not necessary for the _______________
parties to enter into a submission agreement before the
Claimant may invoke the jurisdiction of CIAC. 4.1.1 16 See Preambulatory clauses of E.O No. 1008.
An 4.1.2 arbitration agreement or a submission to 17 National Irrigation Administration v. Court of
arbitration shall be in writing, but it need not be Appeals,G.R. No. 129169, November 17, 1999, 318 SCRA
signed by the parties, as long as the intent is clear 255, 267.
that the parties agree to submit a present or future
controversy arising from a construction contract to
arbitration. It may be in the form of exchange of
88
letters sent by post or by telefax, telexes, telegrams,
88 SUPREME COURT REPORTS
electronic mail or any other mode of communication.
ANNOTATED
Federal Builders, Inc. vs. Power Factors, Inc.
The liberal application of procedural rules as to the form merely connected with the construction contracts entered
by which the agreement is embodied is the objective of the into by parties, and whether such disputes
CIACRevised Rules. Such liberality conforms to the letter arisebefore or after the completion of the contracts.
and spirit of E.O. No. 1008 itself which emphasizes that the Accordingly, the execution of the contracts and the effect of
modes of voluntary dispute resolution like arbitration are the agreement to submit to arbitration are different
always preferred because they settle disputes in a speedy matters, and the signing or non-signing of one does not
and amicable manner. They likewise help in alleviating or necessarily affect the other. In other words, the formalities
unclogging the judicial dockets. Verily, E.O. No. 1008 of the contract have nothing to do with the jurisdiction of
recognizes that the expeditious resolution of construction the CIAC.
disputes will promote a healthy partnership between the Federal contends that there was no mutual consent and
Government and the private sector as well as aid in the no meeting of the minds between it and Power as to the
continuous growth of the country considering that the operation and binding effect of the arbitration clause
construction industry provides employment to a large because they had rejected the draft service contract.
segment of the national labor force aside from its being a The contention of Federal deserves no consideration.
leading contributor to the gross national product.16 Under Article 1318 of theCivil Code, a valid contract
Worthy to note is that the jurisdiction of the CIAC is should have the following essential elements,
over the dispute, not over the contract between the namely:(a) consent of the contracting parties; (b) object
parties.17 Section 2.1, Rule 2 of the CIAC Revised certain that is the subject matter of the contract; and (c)
Rulesparticularly specifies that the CIAC has original and cause or consideration. Moreover, a contract does not need
to be in writing in order to be obligatory and effective
unless the law specifically requires so. Pursuant to Article the payment; and that the subject of their dispute
135618 and Article 135719 of the Civil Code,contracts shall concerned only the amounts still due to Power. The records
be obligatory in whatever form they may have been entered further show that Federal admitted having drafted the
into, provided that all the essential requisites for their Contract of Services containing the following clause on
validity are present. Indeed, there was a contract between submission to arbitration, to wit:
Federal and Power even if the Contract of Ser- ARBITRATION COMMITTEE — All disputes,
_______________ controversies or differences, which may arise between the
Parties herein, out of or in relation to or in connection with
18 Contracts shall be obligatory, in whatever form they this Agreement, or for breach thereof shall be settled by the
may have been entered into, provided all the essential Construction Industry Arbitration Commission (CIAC)
requisites for their validity are present. However, when the which shall have original and exclusive jurisdiction over the
law requires that a contract be in some form in order that it aforementioned disputes. 15.20
may be valid or enforceable, or that a contract be proved in
a certain way, that requirement is absolute and
indispensable. In such cases, the right of the parties stated With the parties having no issues on the provisions or
in the following article cannot be exercised. 1356. Article parts of the Contract of Service other than that pertaining
19 If the law requires a document or other special form, to the down payment that Federal was supposed to pay,
as in the acts and contracts enumerated in the following Federal could not validly insist on the lack of a contract in
article, the contracting parties may compel each other to order to defeat the jurisdiction of the CIAC. As earlier
observe that form, once the contract has been perfected. pointed out, the CIACRevised Rules specifically allows any
This right may be exercised simultaneously with the action written mode of communication to show the parties’ intent
upon the contract. 1357. Article or agreement to submit to arbitration their present or
future disputes arising from or connected with their
contract.
The CIAC and the CA both found that the parties had
89 disagreed on the amount of the down payment. On its part,
VOL. 820, MARCH 8, 2017 89 Power indicated after receiving and reviewing the draft of
Federal Builders, Inc. vs. Power Factors, Inc. the Contract of Service that it wanted 30% as the down
vice was unsigned. Such contract was obligatory and payment. Even so, Power did not modify anything else in
binding between them by virtue of all the essential the draft, and
elements for a valid contract being present. _______________
It clearly appears that the works promised to be done by
Power were already executed albeit still incomplete; that 20 Rollo, p. 34.
Federal paid Power P1,000,000.00 representing the
originally proposed down payment, and the latter accepted
21 Id.
90 22 4. SectionForm of arbitration agreement.—A
90 SUPREME COURT REPORTS contract to arbitrate a controversy thereafter arising
ANNOTATED between the parties, as well as a submission to arbitrate an
Federal Builders, Inc. vs. Power Factors, Inc. existing controversy, shall be in writing and subscribed by
the party sought to be charged, or by his lawful agent.
returned the draft to Federal after signing it. It was
The making of a contract or submission for arbitration
Federal that did not sign the draft because it was not
described in Section two hereof, providing for arbitration of
amenable to the amount as modified by Power. It is notable
any controversy, shall be deemed a consent of the parties of
that the arbitration clause written in the draft of Federal
the province or city where any of the parties resides, to
was unchallenged by the parties until their dispute arose.
enforce such contract of submission.
Moreover, Federal asserted the original contract to
support its claim against Power. If Federal would insist
that the remaining amount due to Power was only
P1,641,513.94 based on the original contract,21 it was really 91
inconsistent for Federal to rely on the draft when it is VOL. 820, MARCH 8, 2017 91
beneficial to its side, and to reject its efficacy and existence
Federal Builders, Inc. vs. Power Factors, Inc.
just to relieve itself from the CIAC’s unfavorable decision.
The agreement contemplated in the CIACRevised Law),23 the requirement is conspicuously absent from the
Rules to vest jurisdiction of the CIAC over the parties’ CIAC Revised Rules,which even expressly allows such
dispute is not necessarily an arbitration clause to be agreement not to be signed by the parties
contained only in a signed and finalized construction therein. Brushing
24 aside the obvious contractual
contract. The agreement could also be in a separate agreement in this case warranting the submission to
agreement, or any other form of written communication, as arbitration is surely a step backward.25 Consistent with the
long as their intent to submit their dispute to arbitration is policy of encouraging alternative dispute resolution
clear. The fact that a contract was signed by both parties methods, therefore, any doubt should be resolved in favor of
has nothing to do with the jurisdiction of the CIAC, and this arbitration.26 In this connection, the CA correctly observed
is the explanation why the CIACRevised Rules itself that the act of Atty. Albano in manifesting that Federal had
expressly provides that the written communication or agreed to the form of arbitration was unnecessary and
agreement need not be signed by the parties. inconsequential considering the recognition of the value of
Although the agreement to submit to arbitration has the Contract of Service despite its being an unsigned draft.
been expressly required to be in writing and signed by the
parties therein by Section 422 of Republic Act No. 2.
876(Arbitration Amounts as modified by the CA are correct
_______________
We find no reversible error regarding the amounts as Notes.—It is widely known that in the construction
modified by the CA. Power did not sufficiently establish industry, a project employee’s work depends on the
that the change or increase of the cost of materials and availability of projects, necessarily the duration of his
labor was to be separately determined and approved by employment. (Malicdem vs. Marulas Industrial
both parties as provided under Article 1724 of the Civil Corporation, 717 SCRA 563 [2014])
Code. As such, Federal should not be held liable for the The jurisdiction of the Construction Industry Arbitration
labor cost escalation. Commission (CIAC) is derived from law. It is broad enough
WHEREFORE, the Court AFFIRMS the decision to cover any dispute arising from, or connected with
promulgated on August 12, 2013; andORDERS the construction contracts, whether these involve mere
petitioner to pay the costs of suit. contractual money claims or execution of the works.
SO ORDERED. (Philippine Race Horse Trainer’s Association, Inc. vs.
_______________ Piedras Negras Construction & Development Corporation,
775 SCRA 631 [2015])
23 AN ACT TO AUTHORIZE THE MAKING OF ARBITRATION
AND SUBMISSION AGREEMENTS, TO PROVIDE FOR THE ——o0o——
APPOINTMENT OF ARBITRATORS AND THE PROCEDURE FOR
ARBITRATION IN CIVIL CONTROVERSIES, AND FOR OTHER © Copyright 2019 Central Book Supply, Inc. All rights
PURPOSES, June 19, 1953.
24 Subsection 4.1.2, Rule 4 of the CIAC Revised Rules.
25 LM Power Engineering Corporation v. Capitol
Industrial Construction Groups, Inc., G.R. No. 141833,
March 26, 2003, 399 SCRA 562, 569.
26 Id., at pp. 569-570.

92
92 SUPREME COURT REPORTS
ANNOTATED
Federal Builders, Inc. vs. Power Factors, Inc.
Velasco, Jr. (Chairperson), Reyes,
Jardeleza and Caguioa,**JJ., concur.

Judgment affirmed.
G.R. No. 184295.July 30, 2014.* Same; Same; It is well-settled that findings of fact of
NATIONAL TRANSMISSION quasi-judicial bodies, which have acquired expertise because
CORPORATION, petitioner, vs. ALPHAOMEGA their jurisdiction is confined to specific matters, are
INTEGRATED CORPORATION, respondent. generally accorded not only respect, but also finality,
especially when affirmed by the Court of Appeals (CA).—The
Remedial Law; Civil Procedure; Section 1, Rule 45 of Court finds no reason to disturb the factual findings of the
the Rules of Court provides that a petition for review on CIAC Arbitral Tribunal on the matter of AIC’s entitlement
certiorari under the said rule, as in this case, “shall raise to damages which the CA affirmed as being well supported
only questions of law which must be distinctly set forth.”— by evidence and properly referred to in the record. It is well-
TRANSCO seeks through this petition a recalibration of settled that findings of fact of quasi-judicial bodies, which
the evidence presented before the CIAC Arbitral Tribunal, have acquired expertise because their jurisdiction is
insisting that AIC is not entitled to any damages not only confined to specific matters, are generally accorded not only
because it had previously waived all claims for standby fees respect, but also finality, especially when affirmed by the
in case of project delays but had eventually failed to CA. The CIAC possesses that required expertise in the field
perform the workable portions of the projects. This is of construction arbitration and the factual findings of its
evidently a factual question which cannot be the proper construction arbitrators are final and conclusive, not
subject of the present petition. Section 1, Rule 45 of the reviewable by this Court on appeal.
Rules of Court provides that a petition for review Same; Same; It is well-settled that no relief can be
on certiorari under the said rule, as in this case, “shall raise granted a party who does not appeal and that a party who
only questions of law which must be distinctly set forth.” did not appeal the decision may not obtain any affirmative
Thus, absent any of the existing exceptions impelling the relief from the appellate court other than what he had
contrary, the Court is, as a obtained from the lower court, if any, whose decision is
_______________ brought up on appeal.—It must be emphasized that the
* SECOND DIVISION. petition for review before the CA was filed by TRANSCO.
AIC never elevated before the courts the matter concerning
300
the discrepancy between the amount of the award stated in
3 SUPREME COURT REPORTS the body of the Final Award and the total award shown in
its dispositive portion. The issue was touched upon by the
00 ANNOTATED
CA only after AIC raised the same through its Comment
National Transmission Corporation vs. (With Motion to Acknowledge Actual Amount of Award) to
Alphaomega Integrated Corporation TRANSCO’s petition for review. The CA should not have
general rule, precluded from delving on factual modified the amount of the award to favor AIC because it is
determinations, as what TRANSCO essentially seeks in well-settled that no relief can be granted a party who does
this case. not appeal and that a party who did not appeal the decision
may not obtain any affirmative relief from the appellate
court other than what he had obtained from the lower Reinforcement Project Schedule I (BTRP Schedule I
court, if any, whose decision is brought up on appeal. The Project); (c) Contract for the Construction, Erection &
disposition, as stated in the fallo of the CIAC Arbitral Installation of 230 KV and 69 KV S/S Equipment and
Tribunal’s Final Award, should therefore stand. Various Facilities for Makban Substation under the
_______________
PETITION for review on certiorari of the decision and [1] Rollo, pp. 10-82.
resolution of the Court of Appeals. [2] Id., at pp. 84-121. Penned by Associate Justice
301 Arcangelita M. Romilla-Lontok, with Associate Justices
Mariano C. Del Castillo (now member of the Court) and
VOL. 731, JULY 30, 2014 301 Ricardo R. Rosario, concurring.
National Transmission Corporation vs. [3] Id., at pp. 123-124.
Alphaomega Integrated Corporation [4] Id., at pp. 164-248.
The facts are stated in the opinion of the Court.
Office of the Government Corporate Counsel andNational 302
Transmission Corporation for petitioner. 302 SUPREME COURT REPORTS
Rivera, Santos and Maranan for respondent. ANNOTATED
National Transmission Corporation vs.
PERLAS-BERNABE, J.:
Alphaomega Integrated Corporation
Assailed in this petition for review on certiorari[1] are the
Batangas Transmission Reinforcement Project (Schedule II)
Decision[2] dated April 8, 2008 and the
(Makban Substation Project); (d) Contract for the
Resolution[3]dated August 27, 2008 of the Court of Appeals
Construction, Erection & Installation of 138 & 69 KV S/S
(CA) in C.A.-G.R. S.P. No. 99454 affirming with modification
Equipment for Bacolod Substation under the Negros III-
the Final Award[4] of the Construction Industry Arbitration
Commission (CIAC) Arbitral Tribunal in favor of respondent Panay III Substation Projects (Schedule II) (Bacolod
Substation Project); (e) Contract for the Construction,
Alphaomega Integrated Corporation (AIC) by increasing
Erection & Installation of 138 & 69 KV Substation
petitioner National Transmission Corporation’s (TRANSCO)
Equipment for the New Bunawan Switching Station Project
liability from P17,495,117.44 to P18,896,673.31.
The Facts (Bunawan Substation Project); and (f) Contract for the
AIC, a duly licensed transmission line contractor, Construction, Erection & Installation of 138 and 69 KV
Substation Equipment for Quiot Substation Project (Quiot
participated in the public biddings conducted by TRANSCO
Substation Project).[5]
and was awarded six (6) government construction projects,
namely: (a) Contract for the Construction & Erection of In the course of the performance of the contracts, AIC
Batangas Transmission Reinforcement Project Schedule encountered difficulties and incurred losses allegedly due to
III (BTRP Schedule III Project); (b) Contract for the TRANSCO’s breach of their contracts, prompting it to
Construction & Erection of Batangas Transmission surrender the projects to TRANSCO under protest. In
accordance with an express stipulation in the contracts that AIC prayed for judgment declaring all six (6) contracts
disagreements shall be settled by the parties through rescinded and ordering TRANSCO to pay, in addition to
arbitration before the CIAC, AIC submitted a request for what had already been paid under the contracts, moral
arbitration before the CIAC on August 28, 2006, and, damages, exemplary damages, and attorney’s fees at
thereafter, filed an Amended Complaint against TRANSCO P100,000.00 each, and a total of P40,201,467.19 as actual
alleging that the latter breached the contracts by its failure and compensatory damages.[8]
to: (a) furnish the required Detailed Engineering; (b) TRANSCO, for its part, contended that: (a) it had
arrange a well-established right-of-way to the project areas; conducted Detailed Engineering prior to the conduct of the
(c) secure the necessary permits and clearances from the bidding; and (b) it had obtained the necessary government
concerned local government units (LGUs); (d) ensure a permits and endorsements from the affected LGUs. It
continuous supply of construction materials; and (e) carry asserted that AIC was guilty of frontloading — that is,
out AIC’s requests for power shut down. The collecting the bulk of the contract price for work
aforementioned transgressions resulted in protracted accomplished at the early stages of the project and then
delays and contract suspensions for each project,[6] as abandoning the later stages of the project which has a lower
follows: contract price[9]— and that it disregarded the workable
_______________ portions of the projects not affected by the lack of supplies
[5] Id., at pp. 85-86. and drawings. TRANSCO further argued that AIC was
[6] Id., at pp. 87-89. estopped from asking for standby fees to cover its overhead
expenses during project suspensions considering that the
303 delays, such as the unresolved right-of-way
VOL. 731, JULY 30, 2014 303 _______________
National Transmission Corporation vs. [7] Id., at p. 87.
Alphaomega Integrated Corporation [8] Id., at pp. 95-96.
[9] Id., at p. 98.

304
304 SUPREME COURT REPORTS
ANNOTATED
National Transmission Corporation vs.
Alphaomega Integrated Corporation
issues and nonavailability of materials, were factors
already covered by the time extensions and suspensions of
work allowed under the contracts.[10]
On April 18, 2007, the CIAC Arbitral Tribunal rendered
its Final Award[11]in CIAC Case No. 21-2006 ordering the
payment of actual and compensatory damages which AIC VOL. 731, JULY 30, 2014 305
would not have suffered had it not been for the project National Transmission Corporation vs.
delays attributable to TRANSCO. It found ample evidence Alphaomega Integrated Corporation
to support the claim for the increase in subcontract cost in WHEREFORE, Respondent, National Transmission
BTRP Schedule I, as well as such items of cost as house and Corporation [TRANSCO] is hereby ordered to pay
yard rentals, electric bills, water bills, and maintained Claimant, Alphaomega Integrated Corporation, the
personnel, but disallowed the claims for communications following sums:
bills, maintenance costs for idle equipment, finance
charges, and materials cost increases.[12] According to the
Arbitral Tribunal, even if AIC itself made the requests for
contract time extensions, this did not bar its claim for
damages as a result of project delays since a contrary ruling
would allow TRANSCO to profit from its own negligence
and leave AIC to suffer serious material prejudice as a
direct consequence of that negligence leaving it without any
remedy at law.[13] The Arbitral Tribunal upheld AIC’s Each Party shall shoulder its own cost of arbitration.
right to rescind the contracts in accordance with Resolution The foregoing amount of P17,495,117.44 shall earn interest
No. 018-2004 of the Government Procurement Policy Board at the rate of six percent (6%) per annum from the date of
(GPPB), which explicitly gives the contractor the right to promulgation of this Final Award until it becomes final and
terminate the contract if the works are completely stopped executory. Thereafter, the Final Award, including accrued
for a continuous period of at least 60 calendar days, through interest, shall earn interest at the rate of 12% per
no fault of its own, due to the failure of the procuring entity annum until the entire amount due is fully
to deliver within a reasonable time, supplied materials, paid.[15] (Emphasis supplied)
right-of-way, or other items that it is obligated to furnish
Unconvinced, TRANSCO instituted a petition for
under the terms of the contract, among others.[14] The
review[16] with the CA.
dispositive portion of the Arbitral Tribunal’s Final Award
Before filing its comment[17] to the
reads:
petition, AIC moved for the issuance of a writ of
_______________
execution,[18] not for the amount of P17,495,117.44
[10] Id.
awarded in the Final Award, but for the increased
[11] Id., at pp. 164-248.
amount of P18,967,318.49.[19] It sought correction of the
[12] Id., at pp. 244-246.
discrepancies between the amount of the award appearing
[13] Id., at p. 229.
in the dispositive portion[20] and the body of the
[14] Id., at p. 227.
_______________
305 [15] Id., at p. 248.
[16] Id., at pp. 252-312. Dated June 12, 2007. signifying its satisfaction with AIC’s performance negate
[17] Id., at pp. 313-343. Comment (With Motion to such claim and, secondly, because all the orders issued by
Acknowledge Actual Amount of Award) Dated August 24, TRANSCO suspended the contracts not only in part but in
2007. their entirety, thus, permitting no work activity at all
[18] Id., at pp. 344-349. Motion for Issuance of Writ of during such periods.[25]
Execution for the Total Amount of P18,967,318.49 as The CA upheld the Arbitral Tribunal’s Final Award as
Embodied in the Final Award dated June 13, 2007. having been sufficiently established by evidence but
[19] Id., at p. 349. modified the total amount of the award after noting a
[20] Id., at p. 248. supposed mathematical error in the computation.
Setting aside
306 _______________
306 SUPREME COURT REPORTS [21] Id., at pp. 245-246.
ANNOTATED [22] Id., at pp. 350-352. Order dated June 18, 2007
National Transmission Corporation vs. issued by Chairman Custodio O. Parlade.
Alphaomega Integrated Corporation [23] Id., at pp. 84-121.
Final Award.[21] The Arbitral Tribunal, however, denied [24] Id., at pp. 112-113.
AIC’s motion, holding that while the CIAC Revised Rules of [25] Id., at pp. 117-118.
Procedure Governing Construction Arbitration (CIAC
307
Rules) would have allowed the correction of the Final
VOL. 731, JULY 30, 2014 307
Award for evident miscalculation of figures, typographical
or arithmetical errors, AIC failed to file its motion for National Transmission Corporation vs.
the purpose within the time limitation of 15 days Alphaomega Integrated Corporation
from its receipt of the Final Award.[22] TRANSCO’s objections, it ruled that when a case is brought
The CA’s Ruling to a superior court on appeal every aspect of the case is
In the Decision[23] dated April 8, 2008, the CA affirmed thrown open for review,[26] hence, the subject error could
the Arbitral Tribunal’s factual findings that TRANSCO be rectified. The CA held that the correct amount of the
failed to exercise due diligence in resolving the problems award should be P18,896,673.31, and not P17,495,117.44 as
regarding the right-of-way and the lack of materials before stated in the Arbitral Tribunal’s Final Award.[27]
undertaking the bidding process and entering into the Dissatisfied, TRANSCO moved for
contracts with AIC.[24] It found no merit in TRANSCO’s reconsideration[28]but was, however, denied by the CA in a
allegation that AIC refused to perform the remaining Resolution[29]dated August 27, 2008, hence, the instant
workable portions of the projects not affected by problems of petition.
right-of-way, shutdowns, supplies and drawings, firstly,
because the certificates of accomplishments issued by The Issues Before the Court
TRANSCO in the course of project implementation
The essential issues for the Court’s consideration are a petition for review on certiorari under the said rule, as in
whether or not the CA erred (a) in affirming the CIAC this case, “shall raise only questions of law which must be
Arbitral Tribunal’s findings that AIC was entitled to its distinctly set forth.” Thus, absent any of the existing
claims for damages as a result of project delays, and (b) in exceptions impelling the contrary, the Court is, as a general
increasing the total amount of compensation awarded in rule, precluded from delving on factual determinations, as
favor of AIC despite the latter’s failure to raise the allegedly what TRANSCO essentially seeks in this case. Similar to
erroneous computation of the award before the CIAC in a the foregoing is the Court’s ruling in Hanjin Heavy
timely manner, that is, within fifteen (15) days from receipt Industries and Construction Co., Ltd. v. Dynamic Planners
of the Final Award as provided under Section 17.1 of the and Construction Corp.,[30] the pertinent portions of which
CIAC Rules. are hereunder quoted:
Dynamic maintains that the issues Hanjin raised in its
The Court’s Ruling petitions are factual in nature and are, therefore, not
proper subject of review under Section 1 of Rule 45,
TRANSCO seeks through this petition a recalibration
prescribing that a petition under the said rule, like the one
of the evidence presented before the CIAC Arbitral
at bench, “shall raise only questions of law which must be
Tribunal, insisting that AIC is not entitled to any damages
distinctly set forth.”
not only because it had previously waived all claims for
Dynamic’s contention is valid to point as, indeed,
standby fees in case of project delays but had eventually
the matters raised by Hanjin are factual, revolving as
failed to perform the workable portions of the projects. This
they do on the entitlement of Dynamic to the awards
is evidently a factual question which cannot be the proper
granted and computed by the CIAC and the CA.
subject of the present petition. Section 1, Rule 45 of the
Generally, this would be a question of fact that this
Rules of Court provides that
Court would not delve upon. Imperial v.
_______________
Jaucian suggests as much. There, the Court ruled that the
[26] Id., at p. 119.
computation of outstanding obligation is a question of fact:
[27] Id., at pp. 119-120.
Arguing that she had already fully paid the loan x x x,
[28] See Motion for Reconsideration dated April 29,
petitioner alleges that the two lower courts misappreciated
2008; id., at pp. 125-155
the facts when they ruled that she still had an outstanding
[29] Id., at pp. 123-124.
balance of P208,430.
308 This issue involves a question of fact. Such question
308 SUPREME COURT REPORTS exists when a doubt or difference arises as to the truth or
the falsehood of alleged facts; and when there is need for
ANNOTATED
a calibration of the evidence, considering mainly the
National Transmission Corporation vs. credibility of witnesses and the existence
Alphaomega Integrated Corporation _______________
[30] 576 Phil. 502; 553 SCRA 541 (2008).
309 (6) when the judgment of the [CA] is
premised on a misapprehension of
VOL. 731, JULY 30, 2014 309 facts;
National Transmission Corporation vs. (7) when the [CA] fails to notice
Alphaomega Integrated Corporation certain relevant facts which, if
and the relevancy of specific surrounding circumstances, properly considered, will justify a
their relation to each other and to the whole, and the different conclusion;
probabilities of the situation. (G.R. No. 149004, April 14, (8) when the findings of fact are
2004, 427 SCRA 517, 523-524.) themselves conflicting;
The rule, however, precluding the Court from delving on (9) when the findings of fact are
the factual determinations of the CA, admits of several conclusions without citation of the
exceptions. In Fuentes v. Court of Appeals, we held that the specific evidence on which they are
findings of facts of the CA, which are generally deemed based; and
conclusive, may admit review by the Court in any of the (10) when the findings of fact of the
following instances, among others: [CA] are premised on the absence of
(1) when the factual findings of the evidence but such findings are
[CA] and the trial court are contradicted by the
contradictory; 310
(2) when the findings are grounded
310 SUPREME COURT REPORTS
entirely on speculation, surmises, or
ANNOTATED
conjectures;
National Transmission Corporation vs.
(3) when the inference made by the
Alphaomega Integrated Corporation
[CA] from its findings of fact is
manifestly mistaken, absurd, or evidence on record. (G.R. No. 109849,
impossible; February 26, 1997, 268 SCRA 703,
(4) when there is grave abuse of 709.)
discretion in the appreciation of Significantly, jurisprudence teaches that
facts; mathematical computations as well as the propriety
of the arbitral awards are factual determinations.
(5) when the [CA], in making its And just as significant is that the factual findings of the
findings, goes beyond the issues of CIAC and CA — in each separate appealed decisions —
the case, and such findings are practically dovetail with each other. The perceptible
contrary to the admissions of both essential difference, at least insofar as the CIAC’s Final
appellant and appellee;
Award and the CA Decision in C.A.-G.R. S.P. No. 86641 are VOL. 731, JULY 30, 2014 311
concerned, rests merely on mathematical computations or National Transmission Corporation vs.
adjustments of baseline amounts which the CIAC may have Alphaomega Integrated Corporation
inadvertently utilized.[31] (Emphases and underscoring cation did not observe the proper procedure for the
supplied) correction of an evident miscalculation of figures,
In any case, the Court finds no reason to disturb the including typographical or arithmetical errors, in
factual findings of the CIAC Arbitral Tribunal on the the arbitral award. Section 17.1 of the CIAC Rules
matter of AIC’s entitlement to damages which the CA mandates the filing of a motion for the foregoing purpose
affirmed as being well supported by evidence and properly within fifteen (15) days from receipt thereof, viz.:
referred to in the record. It is well-settled that findings of 17.1 Section Motion for correction of final award.—Any of
fact of quasi-judicial bodies, which have acquired expertise the parties may file a motion for correction of the Final
because their jurisdiction is confined to specific matters, are Award within fifteen (15) days from receipt thereof upon
generally accorded not only respect, but also finality, any of the following grounds:
especially when affirmed by the CA.[32] The CIAC a.An evident miscalculation of figures, a
possesses that required expertise in the field of construction typographical or arithmetical error; (Emphasis
arbitration and the factual findings of its construction supplied)
arbitrators are final and conclusive, not reviewable by this xxxx
Court on appeal.[33]
Failure to file said motion would consequently render
While the CA correctly affirmed in full the CIAC the award final and executory under Section 18. 1 of the
Arbitral Tribunal’s factual determinations, it improperly same rules, viz.:
modified the amount of the award in favor of AIC,
18.1 Section Execution of Award.—A final arbitral
which modifi- award shall become executory upon the lapse of fifteen (15)
_______________ days from receipt thereof by the parties.
[31] Id., at pp. 519-520.
[32] Public Estates Authority v. Uy, 423 Phil. 407, 416; AIC admitted that it had ample time to file a motion
372 SCRA 180, 189 (2001). for correction of the Final Award but claimed to have
[33] Shinryo (Philippines) Company, Inc. v. RRN purposely sat on its right to seek correction supposedly as a
Incorporated, G.R. No. 172525, October 20, 2010, 634 SCRA strategic move against TRANSCO[34]and, instead, filed
123, 130, citing IBEX International, Inc. v. Government with the CIAC Arbitral Tribunal on June 13, 2007 a
Service Insurance System, 618 Phil. 306, 312; 603 SCRA “Motion for Issuance of Writ of Execution for the Total
306, 314 (2009). Amount of P18,967,318.49 as Embodied in the Final
Award.”[35] The Arbitral Tribunal eventually denied AIC’s
aforesaid motion for execution because, despite its merit,
311 the Arbitral Tribunal could not disregard the time-
limitation under the CIAC Rules.[36] Clearly, having failed modified the amount of the award to favor AIC because it is
to move for the correction of the Final Award and, well-settled that no relief can be granted a party who does
_______________ not appeal[41] and that a party who did not appeal the
[34] See Rollo, p. 348. decision may not obtain any affirmative relief from the
[35] Id., at pp. 344-349. appellate court other than what he had obtained from the
[36] Id., at p. 250. lower court, if any, whose decision is
_______________
312 [37] Soler v. Bastida, No. L-22822, March 19, 1925, 47
312 SUPREME COURT REPORTS Phil. 676. See also National Bank v. De la Viña, 46 Phil. 63
ANNOTATED (1924).
National Transmission Corporation vs. [38] Office of the Ombudsman v. Chavez, G.R. No.
Alphaomega Integrated Corporation 172206, July 3, 2013, 700 SCRA 409.
thereafter, having opted to file instead a motion for [39] Rollo, pp. 252-312.
execution of the arbitral tribunal’s unopposed and [40] Id., at pp. 318-343.
uncorrected Final Award, AIC cannot now question against [41] Pascual v. Ramos, G.R. No. 144712, July 4, 2002,
the correctness of the CIAC’s disposition. Notably, while 384 SCRA 105, 116.
there is jurisprudential authority stating that “[a] clerical
313
error in the judgment appealed from may be corrected by
VOL. 731, JULY 30, 2014 313
the appellate court,”[37] the application of that rule cannot
be made in this case considering that the CIAC Rules National Transmission Corporation vs.
provides for a specific procedure to deal with particular Alphaomega Integrated Corporation
errors involving “[a]n evident miscalculation of figures, a brought up on appeal.[42]The disposition, as stated in
typographical or arithmetical error.” Indeed, the rule is well the fallo of the CIAC Arbitral Tribunal’s Final Award,
entrenched: Specialis derogat generali. When two rules should therefore stand.[43]
apply to a particular case, that which was specially WHEREFORE, the petition is PARTLY
designed for the said case must prevail over the other.[38] GRANTED. The Decision dated April 8, 2008 of the Court
Furthermore, it must be emphasized that the petition for of Appeals in C.A.-G.R. S.P. No. 99454 is
review before the CA was filed by TRANSCO.[39] AIC hereby AFFIRMED with MODIFICATION. The
never elevated before the courts the matter concerning the compensation awarded in favor of Alphaomega Integrated
discrepancy between the amount of the award stated in the Corporation in the amount of P17,495,117.44, as shown in
body of the Final Award and the total award shown in its the fallo of the construction Industry Arbitration
dispositive portion. The issue was touched upon by the CA Commission’s Final Award dated April 18, 2007, stands.
only after AIC raised the same through its Comment (With SO ORDERED.
Motion to Acknowledge Actual Amount of Award)[40]to Carpio (Chairperson), Brion,
TRANSCO’s petition for review. The CA should not have Perez and Reyes,** JJ.,concur.
Petition partly granted, judgment and resolution Gaming Corporation [PAGCOR] vs. Marquez, 698 SCRA
affirmed with modification. 709 [2013])
——o0o——
Notes.—It is axiomatic that a party who does not
appeal, or file a petition for certiorari, is not entitled to any
affirmative relief. (Unilever Philippines, Inc. vs. Rivera, 697
SCRA 136 [2013]) © Copyright 2019 Central Book Supply, Inc. All rights
_______________ reserved.
[42] Daabay v. Coca-Cola Bottlers Phils., Inc., G.R. No.
199890, August 19, 2013, 384 SCRA 105, 116.
[43] “The resolution of the court in a given issue
embodied in the fallo or dispositive part of a decision or
order is the controlling factor as to settlement of rights of
the parties. Thus, where there is a conflict between
the fallo and the ratio decidendi or body of the decision,
the fallo controls. This rule rests on the theory that
the fallo is the final order while the opinion in the body is
merely a statement ordering nothing. The rule applies
when the dispositive part of a final decision or order is
definite, clear, and unequivocal, and can wholly be given
effect without need of interpretation or construction.” (Obra
v. Spouses Badua, 556 Phil. 456, 461; 529 SCRA 621, 629
[2007]; citations omitted)
** Designated additional member in lieu of Justice
Mariano C. Del Castillo per Raffle dated July 23, 2014.

314

314 SUPREME COURT REPORTS


ANNOTATED
National Transmission Corporation vs.
Alphaomega Integrated Corporation
In petitions for review on certiorari under Rule 45 of the
1997 Revised Rules of Civil Procedure, as amended, only
questions of law may be raised. (Philippine Amusement and
August 9, 2017. G.R. No. 192725.* incorporated as a provision in the contract that will be
executed pursuant to the provisions of this Act: Provided,
CE CONSTRUCTION CORPORATION, That by mutual agreement, the parties may agree in
petitioner, vs. ARANETA CENTER, INC., respondent. writing to resort to alternative modes of dispute resolution.
Arbitration of construction disputes through the CIAC was
Construction Industry Arbitration Commission; The formally incorporated into the general statu-
Construction Industry Arbitration Commission (CIAC) was
a creation of Executive Order (EO) No. 1008, otherwise _______________
known as the Construction Industry Arbitration Law.—The
Construction Industry Arbitration Commission was a * SECOND DIVISION.
creation of Executive Order No. 1008, otherwise known as
the Construction Industry Arbitration Law. At inception, it
was under the administrative supervision of the Philippine
Domestic Construction Board which, in turn, was an 182
implementing agency of the Construction Industry 182 SUPREME COURT REPORTS
Authority of the Philippines (CIAP). The CIAP is presently ANNOTATED
attached to the Department of Trade and Industry. CE Construction Corporation vs. Araneta Center,
Same; Construction Disputes; Alternative Dispute Inc.
Resolution; Alternative Dispute Resolution Act of 2004; tory framework on alternative dispute resolution
Arbitration of construction disputes through the through Republic Act No. 9285, the Alternative Dispute
Construction Industry Arbitration Commission (CIAC) was Resolution Act of 2004 (ADR Law). Chapter 6, Section 34 of
formally incorporated into the general statutory framework ADR Law made specific reference to the Construction
on alternative dispute resolution through Republic Act No. Industry Arbitration Law, while Section 35 confirmed the
9285, the Alternative Dispute Resolution Act of 2004 (ADR CIAC’s jurisdiction.
Law).—Republic Act No. 9184 or the Government Same; Construction; Words and Phrases; The
Procurement Reform Act, enacted on January 10, 2003, Construction Industry Arbitration Commission (CIAC) has
explicitly recognized and confirmed the competence of the the state’s confidence concerning the entire technical expanse
CIAC: Section 59. Arbitration.—Any and all disputes of construction, defined in jurisprudence as “referring to all
arising from the implementation of a contract covered by on-site works on buildings or altering structures, from land
this Act shall be submitted to arbitration in the Philippines clearance through completion including excavation, erection
according to the provisions of Republic Act No. 876, and assembly and installation of components and
otherwise known as the “Arbitration Law”: Provided, equipment.”—The CIAC does not only serve the interest of
however, That,disputes that are within the competence of the speedy dispute resolution, it also
Construction Industry Arbitration Commission to resolve facilitates authoritativedispute resolution. Its authority
shall be referred thereto. The process of arbitration shall be proceeds not only from juridical legitimacy but equally from
technical expertise. The creation of a special adjudicatory Inc.
body for construction disputes presupposes distinctive and Same; Appeals; Petitions for Review; Rule 43, Section 1
nuanced competence on matters that are conceded to be explicitly lists Construction Industry Arbitration
outside the innate expertise of regular courts and Commission (CIAC) as among the quasi-judicial agencies
adjudicatory bodies concerned with other specialized fields. covered by Rule 43. Section 3 indicates that appeals through
The CIAC has the state’s confidence concerning the entire Petitions for Review under Rule 43 are to “be taken to the
technical expanse of construction, defined in jurisprudence Court of Appeals (CA) . . . whether the appeal involves
as “referring to all on-site works on buildings or altering questions of fact, of law, or mixed questions of fact and
structures, from land clearance through completion law.”—Rule 43 of the 1997 Rules of Civil Procedure
including excavation, erection and assembly and standardizes appeals from quasi-judicial agencies. Rule 43,
installation of components and equipment.” Section 1 explicitly lists CIAC as among the quasi-judicial
Same; The most recent jurisprudence maintains that agencies covered by Rule 43. Section 3 indicates that
the Construction Industry Arbitration Commission (CIAC) appeals through Petitions for Review under Rule 43 are to
is a quasi-judicial body.—The most recent jurisprudence “be taken to the Court of Appeals . . . whether the appeal
maintains that the CIAC is a quasi-judicial body. This involves questions of fact, of law, or mixed questions of fact
Court’s November 23, 2016 Decision in Fruehauf and law.”
Electronics v. Technology Electronics Assembly and Same; Same; Arbitral Tribunals; The Supreme Court’s
Management Pacific, 810 SCRA 280, distinguished (SC’s) primordial inclination must be to uphold the factual
construction arbitration, as well as voluntary arbitration findings of arbitral tribunals.—Consistent with this
pursuant to Article 219(14) of the Labor Code, from restrictive approach, this Court is duty-bound to be
commercial arbitration. It ruled that commercial arbitral extremely watchful and to ensure that an appeal does not
tribunals are not quasi-judicial agencies, as they are become an ingenious means for undermining the integrity
purely ad hoc bodies operating through contractual consent of arbitration or for conveniently setting aside the
and as they intend to serve private, proprietary interests. conclusions arbitral processes make. An appeal is not an
In contrast, voluntary arbitration under the Labor Code artifice for the parties to undermine the process they
and construction arbitration operate through the statutorily voluntarily elected to engage in. To prevent this Court from
vested jurisdiction of government instrumentalities that being a party to such perversion, this Court’s primordial
exist independently of the will of contracting parties and to inclination must be to uphold the factual findings of
which these parties submit. arbitral tribunals.
Arbitral Tribunals; Common sense dictates that by the
parties’ voluntary submission, they acknowledge that an
arbitral tribunal constituted under the Construction
183 Industry Arbitration Commission (CIAC) has full
VOL. 836, AUGUST 9, 2017 183 competence to rule on the dispute presented to it.—ACI and
CE Construction Corporation vs. Araneta Center, CECON voluntarilysubmitted themselves to the CIAC
Arbitral Tribunal’s jurisdiction. The contending parties’ dispense justice “by every and all reasonable means without
own volition is at the inception of every construction regard to technicalities of law or procedure.”
arbitration proceeding. Common sense dictates that by the Construction Contracts; Jurisprudence has settled that
parties’ voluntary submission, they acknowledge that an even in cases where parties enter into contracts which do not
arbitral tribunal constituted under the CIAC has full strictly conform to standard formalities or to the typifying
competence to rule on the dispute presented to it. They provisions of nominate contracts, when one renders services
concede this not only with respect to the literal issues to another, the latter must compensate the former for the
recited in their terms of reference, as ACI suggests, but also reasonable value of the services rendered.—Jurisprudence
with respect to their necessary incidents. Accordingly, in has settled that even in cases where parties enter into
delineating the authority of arbitrators, the CIAC Rules of contracts which do not strictly conform to standard
Procedure speak not only of the literally recited issues but formalities or to the typifying provisions of nominate
also of “related matters”: SECTION 21.3. contracts, when one renders services to another, the latter
must compensate the former for the reasonable value of the
services rendered. This amount shall be fixed by a court.
This is a matter so basic, this Court has once characterized
184 it as one that “springs from the fountain of good
184 SUPREME COURT REPORTS conscience”: As early as 1903, in Perez v. Pomar, this Court
ANNOTATED ruled that where one has rendered services to another, and
CE Construction Corporation vs. Araneta Center, these services are accepted by the latter, in the absence of
Inc. proof that the service was rendered gratuitously, it is but
Extent of power of arbitrator.—The Arbitral Tribunal just that he should pay a reasonable remuneration
shall decide only such issues and related matters as are therefore because “it is a well known principle of law, that
submitted to them for adjudication. They have no power to no one should be permitted to enrich himself to the damage
add, to subtract from, modify, or amend any of the terms of of another.” Similary in 1914, this Court declared that in
the contract or any supplementary agreement thereto, or this jurisdiction, even in the absence of statute, “. . . under
any rule, regulation or policy promulgated by the CIAC. To the general principle that one person may not enrich
otherwise be puritanical about cognizable issues would be himself at the expense of another, a judgment creditor
to cripple CIAC arbitral tribunals. It would potentially be to would not be permitted to retain the purchase price of land
condone the parties’ efforts at tying the hands of tribunals sold as the property of the judgment debtor after it has been
through circuitous, trivial recitals that fail to address the made to appear that the judgment debtor had no title to the
complete extent of their claims and which are ultimately land and that the purchaser had failed to secure title
ineffectual in dispensing an exhaustive and dependable thereto . . .” The foregoing
resolution. Construction arbitration is not a game of guile
which may be left to ingenious textual or technical
acrobatics, but an endeavor to ascertain the truth and to
184 Angara, Abello, Concepcion, Regala & Cruzfor Araneta
184 SUPREME COURT REPORTS Center, Inc.
ANNOTATED
LEONEN,J.:
CE Construction Corporation vs. Araneta Center,
Inc. A tribunal confronted not only with ambiguous
equitable principle which springs from the fountain of contractual terms but also with the total absence of an
good conscience are applicable to the case at bar. Consistent instrument which definitively articulates the contracting
with the Construction Industry Arbitration Law’s declared parties’ agreement does not act in excess of jurisdiction
policy, the CIAC Arbitral Tribunal was specifically charged when it employs aids in interpretation, such as those
with “ascertain[ing] the facts in each case by every and all articulated in Articles 1370 to
reasonable means.” In discharging its task, it was
permitted to even transcend technical rules on admissibility
of evidence. 186
Same; Article 1724 demands two (2) requisites in order 186 SUPREME COURT REPORTS
that a price may become immutable: first, there must be an ANNOTATED
actual, stipulated price; and second, plans and
CE Construction Corporation vs. Araneta Center,
specifications must have definitely been agreed upon.—
Article 1724 demands two (2) requisites in order that a Inc.
price may become immutable: first, there must be an actual, 1379 of the Civil Code. In so doing, a tribunal does not
stipulated price; and second, plans and specifications must conjure its own contractual terms and force them upon the
have definitely been agreed upon. Neither requisite avails parties.
in this case. Yet again, ACI is begging the question. It is In addressing an iniquitous predicament of a contractor
precisely the crux of the controversy that no price has been that actually renders services but remains inadequately
set. Article 1724 does not work to entrench a disputed price compensated, arbitral tribunals of the Construction
and make it sacrosanct. Moreover, it was ACI which thrust Industry Arbitration Commission (CIAC) enjoy a wide
itself upon a situation where no plans and specifications latitude consistent with their technical expertise and the
were immediately agreed upon and from which no deviation arbitral process’ inherent inclination to afford the most
could be made. It was ACI, not CECON, which made, exhaustive means for dispute resolution. When their
revised, and deviated from designs and specifications. awards become the subject of judicial review, courts must
defer to the factual findings borne by arbitral tribunals’
PETITION for review on certiorari of the decision and technical expertise and irreplaceable experience of
amended decision of the Court of Appeals. presiding over the arbitral process. Exceptions may be
The facts are stated in the opinion of the Court. availing but only in instances when the integrity of the
Tan, Acut, Lopez & Pison for petitioner. arbitral tribunal itself has been put in jeopardy. These
grounds are more exceptional than those which are petitioner CE Construction Corporation (CECON). This
regularly sanctioned in Rule 45 petitions. sum represented adjustments in unit costs plus interest,
This resolves a Petition for Review on Certiorari1under variance in takeout costs, change orders, time extensions,
Rule 45 of the 1997 Rules of Civil Procedure, praying that attendance fees, contractor-supplied equipment, and costs
the assailed April 28, 2008 Decision2 and July 1, 2010 of arbitration. This amount was net of the countervailing
Amended Decision3 of the Court of Appeals in C.A.-G.R. awards in favor of respondent Araneta Center, Inc. (ACI),
S.P. No. 96834 be reversed and set aside. It likewise prays for defective and incomplete works, permits, licenses and
that the October 25, 2006 Decision4 of the CIAC Arbitral other advances.5
Tribunal be reinstated. The assailed Court of Appeals’ April 28, 2008 Decision
_______________ modified the CIAC Arbitral Tribunal’s October 25, 2006
Decision by awarding a net amount of P82,758,358.80 in
1 Rollo, pp. 153-268. favor of CECON.6 The Court of Appeals’ July 1, 2010
2 Id., at pp. 11-85. The Decision was penned by Amended Decision adjusted this amount to
Associate Justice Agustin S. Dizon, and concurred in by P93,896,335.71.7
Associate Justices Regalado E. Maambong and Celia C. Petitioner CECON was a construction contractor, which,
Librea-Leagogo of the Sixteenth Division, Court of Appeals, for more than 25 years, had been doing business with
Manila. respondent ACI, the developer of Araneta Center, Cubao,
3 Id., at pp. 87-137. The Amended Decision was penned Quezon City.8
by Presiding Justice Andres B. Reyes, Jr., and concurred in In June 2002, ACI sent invitations to different
by Associate Justices Hakim S. Abdulwahid, Francisco P. construction companies, including CECON, for them to bid
Acosta, and Michael P. Elbinias, and dissented in by on a project identified as “Package #4
Associate Justice Sesinando E. Villon of the Former Special Structure/Mechanical, Electrical, and Plumbing/Finishes
Sixteenth Division of Five, Court of Appeals, Manila. (excluding Part A Substructure),” a part of its
4 Id., at pp. 3762-4029. The Arbitral Tribunal is redevelopment plan for Araneta Center Complex.9The
composed of Ernesto S. De Castro as Chairman and James project would eventually be the Gateway Mall. As described
S. Villafranca and Reynaldo T. Viray as members. by ACI, “[t]he Project involved the design, coordination,
construction and completion of all architectural and
structural portions of Part B of the Works[;] and the
construction of the architectural and structural portions of
187 Part A of
VOL. 836, AUGUST 9, 2017 187 _______________
CE Construction Corporation vs. Araneta Center,
Inc. 5 Id., at pp. 4028-4029.
The CIAC Arbitral Tribunal’s October 25, 2006 Decision 6 Id., at pp. 84-85.
awarded a total sum of P217,428,155.75 in favor of 7 Id., at pp. 136-137.
8 Id., at p. 6221, CECON’s Memorandum; and id., at p. Rates, and with regard to the Value Engineering
6372, ACI’s Memorandum. Proposals under Clause 27. The Contract Sum shall not
9 Id., at p. 12. be adjusted for changes in the cost of labour, materials
or other matters.12

_______________
188
188 SUPREME COURT REPORTS 10 Id., at p. 6373, ACI’s Memorandum.
ANNOTATED 11 Id.
12 Id., at p. 6374, Conditions of Contract, Clause 6.0.
CE Construction Corporation vs. Araneta Center,
Reproduced in ACI’s Memorandum.
Inc.
the Works known as Package 4 of the Araneta Center
Redevelopment Project.”10
As part of its invitation to prospective contractors, ACI 189
furnished bidders with Tender Documents, consisting of: VOL. 836, AUGUST 9, 2017 189
Tender Invitation, Project Description, Instructions to CE Construction Corporation vs. Araneta Center,
Tenderers, Form of Tender, Dayworks, Preliminaries and
Inc.
General Requirements, and Conditions of Contract; I:
TENDER AND CONTRACT
Volume
Fixed Price Contract
Technical Specifications for the Architectural,
1. The Contract Sum payable to the Contactor is a Lump
Structural, Mechanical, Plumbing, Fire Protection and
Electrical Works; and II: Volume Sum Fixed Price and will not be subject to adjustment,
save only where expressly provided for within the
Addenda Nos. 1, 2, 3, and 4 relating to modifications to
Contract Documents and the Form of Agreement.
portions of the Tender Documents.11
2. The Contract Sum shall not be subject to any adjustment
The Tender Documents described the project’s contract
“in respect of rise and fall in the cost of materials[,]
sum to be a “lump sum” or “lump sum fixed price” and
restricted cost adjustments, as follows: labor, plant, equipment, exchange rates or any other
matters affecting the cost of execution of Contract, save
TYPE OF CONTRACT 6
only where expressly provided for within the Contract
6.1. This is a Lump Sum Contract and the price is a fixed
Documents or the Form of Agreement.
price not subject to measurement or recalculation should
3. The Contract Sum shall further not be subject to any
the actual quantities of work and materials differ from
change in subsequent legislation, which causes
any estimate available at the time of contracting, except
additional or reduced costs to the Contractor.13
in regard to Cost-Bearing Changes which may be
ordered by the Owner which shall be valued under the
terms of the Contract in accordance with the Schedule of
The bidders’ proposals for the project were submitted on ACI, however, was unable to deliver to CECON the entire
August 30, 2002. These were based on “design and project site. Only half, identified as the Malvar-to-Roxas
construct” bidding.14 portion, was immediately available. The other half,
CECON submitted its bid, indicating a tender amount of identified as the Roxas to-Coliseum portion, was delivered
P1,449,089,174.00. This amount was inclusive of “both the only about five (5) months later.17
act of designing the building and executing its As the details of the project had yet to be finalized, ACI
construction.” Its bid and tender were based on schematic and CECON pursued further negotiations. ACI and
drawings, i.e., conceptual designs and suppositions culled CECON subsequently agreed to include in the project the
from ACI’s Tender Documents. CECON’s proposal construction of an office tower atop the portion identified as
“specifically stated that its bid was valid for only ninety (90) Part A of the project. This escalated CECON’s project cost
days, or only until 29 November 2002.” This tender to P1,582,810,525.00.18
proposed a total of 400 days, or until January 10, 2004, for After further negotiations, the project cost was again
the implementation and completion of the project.15 adjusted to P1,613,615,244.00. Still later, CECON extended
_______________ to ACI a P73,615,244.00 discount, thereby reducing its
offered project cost to P1,540,000,000.00.19
13 Id. Preliminaries and General Requirements, Section Despite these developments, ACI still failed to formally
4.0. Reproduced in ACI’s Memorandum. award the project to CECON. The parties had yet to execute
14 Id., at p. 3773. a formal contract. This prompted CECON to write a letter
15 Id., at p. 6222, CECON’s Memorandum. to ACI, dated December 27, 2002,20emphasizing that the
project cost quoted to ACI was “based upon the prices
prevailing at December 26, 2002” price levels.21
_______________
190
190 SUPREME COURT REPORTS 16 Id., at p. 6223, CECON’s Memorandum.
ANNOTATED 17 Id.
CE Construction Corporation vs. Araneta Center, 18 Id.
Inc. 19 Id., at p. 6224, CECON’s Memorandum.
CECON offered the lowest tender amount. However, 20 Id., at pp. 549-553, Annex D to CECON’s Petition.
ACI did not award the project to any bidder, even as the 21 Id., at p. 549.
validity of CECON’s proposal lapsed on November 29, 2002.
ACI only subsequently informed CECON that the contract
was being awarded to it. ACI elected to inform CECON
191
verbally and not in writing.16
VOL. 836, AUGUST 9, 2017 191
In a phone call on December 7, 2002, ACI instructed
CECON to proceed with excavation works on the project. CE Construction Corporation vs. Araneta Center,
Inc. 22 Id., at pp. 554-555, Annex E to CECON’s Petition.
By January 2003 and with the project yet to be formally 23 Id., at pp. 556-557, Annex F to CECON’s Petition.
awarded, the prices of steel products had increased by 5% 24 Id., at p. 556.
and of cement by P5.00 per bag. On January 8, 2003, 25 Id., at pp. 3786 and 6225.
CECON again wrote ACI notifying it of these increasing 26 Id., at p. 6225.
costs and specifically stating that further delays may affect
the contract sum.22
Still without a formal award, CECON again wrote to
ACI on January 21, 200323 indicating cost and time 192
adjustments to its original proposal. Specifically, it referred 192 SUPREME COURT REPORTS
to an 11.52% increase for the cost of steel products, totalling ANNOTATED
P24,921,418.00 for the project; a P5.00 increase per bag of CE Construction Corporation vs. Araneta Center,
cement, totalling P3,698,540.00 for the project; and costs Inc.
incurred because of changes to the project’s structural On June 2, 2003, ACI finally wrote a letter27 to CECON
framing, totalling P26,011,460.00. The contract sum, indicating its acceptance of CECON’s August 30, 2002
therefore, needed to be increased to P1,594,631,418.00. tender for an adjusted contract sum of P1,540,000.00 only:
CECON also specifically stated that its tender relating to Araneta Center, Inc. (ACI) hereby accepts the C-E
these adjusted prices were valid only until January 31, Construction Corporation (CEC) tender dated August 30,
2003, as further price changes may be forthcoming. CECON 2002, submitted to ACI in the adjusted sum of One Billion
emphasized that its steel supplier had actually already Five Hundred Forty Million Pesos Only
advised it of a forthcoming 10% increase in steel prices by (P1,540,000,000.00), which sum includes all additionally
the first week of February 2003. CECON further impressed quoted and accepted items within this acceptance letter and
upon ACI the need to adjust the 400 days allotted for the attachments, Appendix A, consisting of one (1) page, and
completion of the project.24 Appendix B, consisting of seven (7) pages plus attachments,
On February 4, 2003, ACI delivered to CECON the which sum of One Billion Five Hundred Forty Million Pesos
initial tranche of its down payment for the project. By then, Only (P1,540,000,000.00) is inclusive of any Government
prices of steel had been noted to have increased by 24% Customs Duty and Taxes including Value Added Tax (VAT)
from December 2002 prices. This increase was validated by and Expanded Value-Added Tax (EVAD), and which sum is
ACI.25 hereinafter referred to as the Contract Sum.28
Subsequently, ACI informed CECON that it was taking
upon itself the design component of the project, removing
from CECON’s scope of work the task of coming up with Item 4, Appendix B of this acceptance letter explicitly
designs.26 recognized that “all design except support to excavation
_______________ sites, is now by ACI.”29 It thereby confirmed that the parties
were not bound by a design-and-construct agreement, as
initially contemplated in ACI’s June 2002 invitation, but by frequently pertained to revisions of prior items of work.35 Of
a construct-only agreement. The letter stated that these drawings, more than 600 were issued by ACI well
“[CECON] acknowledge[s] that a binding contract is now after the intended completion date of January 10, 2004:
existing.”30 However, consistent with ACI’s admitted Drawing No. 1040 was issued on January 12, 2004, and the
changes, it also expressed ACI’s corresponding undertaking: latest, Drawing No. 1675, was issued on November 26,
“This notwithstanding, formal contract documents 2004.36
embodying these positions will shortly be prepared and Apart from shifting its arrangement with CECON from
forwarded to you for execution.”31 design-and-construct to construct-only, ACI introduced
_______________ other changes to its arrangements with CECON. CECON
underscored two (2) of the most notable of these changes
27 Id., at pp. 558-560, Annex G of CECON’s Petition. which impelled it to seek legal relief.
28 Id., at p. 558. First, on January 30, 2003, ACI issued Change Order
29 Id., at p. 641. No. 11,37 which shifted the portion identified as Part B of
30 Id., at p. 560, Annex G to CECON’s Petition. the project from reinforced concrete framing to structural
31 Id. steel framing. Deleting the cost for reinforced concrete
framing meant removing P380,560,300.00 from the contract
sum. Nevertheless, replacing reinforced concrete framing
with structural
193 _______________
VOL. 836, AUGUST 9, 2017 193
CE Construction Corporation vs. Araneta Center, 32 Id., at p. 6227, CECON’s Memorandum.
Inc. 33 Id.
Despite ACI’s undertaking, no formal contract 34 Id.
documents were delivered to CECON or otherwise executed 35 Id.
between ACI and CECON.32 36 Id., at p. 6228, CECON’s Memorandum.
As it assumed the design aspect of the project, ACI 37 Id., at pp. 663-669, Annex H to CECON’s Petition;
issued to CECON the construction drawings for the project. and, p. 6228, CECON’s Memorandum.
Unlike schematics, these drawings specified “the kind of
work to be done and the kind of material to be
used.”33CECON laments, however, that “ACI issued the
construction drawings in piece-meal fashion at times of its 194
own choosing.”34 From the commencement of CECON’s 194 SUPREME COURT REPORTS
engagement until its turnover of the project to ACI, ACI ANNOTATED
issued some 1,675 construction drawings. CECON CE Construction Corporation vs. Araneta Center,
emphasized that many of these drawings were partial and Inc.
steel framing “entailed substitute cost of P217,585,000, an 38 Id., at p. 6229, CECON’s Memorandum.
additional P44,281,100 for the additional steel frames due 39 Id.
to revisions, and another P1,950,000 for the additional 40 Id.
pylon.”38
Second, instead of leaving it to CECON, ACI opted to
purchase on its own certain pieces of equipment —
elevators, escalators, chillers, generator sets, indoor 195
substations, cooling towers, pumps, and tanks — which VOL. 836, AUGUST 9, 2017 195
were to be installed in the project. This entailed “takeout CE Construction Corporation vs. Araneta Center,
costs”; that is, the value of these pieces of equipment Inc.
needed to be removed from the total amount due to claimed P26,892,019.00 by way of compensation for the
CECON. ACI considered a sum totalling P251,443,749.00 to work that it rendered.41
have been removed from the contract sum due to CECON. With many changes to the project and ACI’s delays in
This amount of P251,443,749.00 was broken down, as delivering drawings and specifications, CECON
follows: increasingly found itself unable to complete the project on
For Elevators/escalators, P106,000,000; (a) January 10, 2004. It noted that it had to file a total of 15
For Chillers, P41,152,900; (b) Requests for Time Extension from June 10, 2003 to
For Generator Sets, P53,040,000; (c) December 15, 2003, all of which ACI failed to timely act
For Indoor Substation, P23,024,150; (d) on.42
For Cooling Towers, P5,472,809; and (e) Exasperated, CECON served notice upon ACI that it
For Pumps and Tanks, P22,753,890. (f) 39 would avail of arbitration. On January 29, 2004, it filed
with the CIAC its Request for Adjudication.43 It prayed that
a total sum of P183,910,176.92 representing adjusted
CECON avers that in removing the sum of
project costs be awarded in its favor.44
P251,443,749.00, ACI “simply deleted the amount in the
On March 31, 2004, CECON and ACI filed before the
cost breakdown corresponding to each of the items taken
CIAC a Joint Manifestation45 indicating that some issues
out in the contract documents.”40 ACI thereby disregarded
between them had already been settled. Proceedings before
that the corresponding stipulated costs pertained not only
the CIAC were then suspended to enable CECON and ACI
to the acquisition cost of these pieces of equipment but also
to arrive at an amicable settlement.46 On October 14, 2004,
to so-called “builder’s works” and other costs relating to
ACI filed a motion before the CIAC noting that it has
their preparation for and installation in the project. Finding
validated P85,000,000.00 of the total amount claimed by
it unjust to be performing auxiliary services practically for
CECON. It prayed for more time to arrive at a settlement.47
free, CECON proposed a reduction in the takeout costs
In the meantime, CECON completed the project and
claimed by ACI. It instead
turned over Gateway Mall to ACI.48 It had its blessing on
_______________
November 26, 2004.49
_______________ was to be composed of Dr. Ernesto S. De Castro, who acted
as Chairperson with Engr. Reynaldo T. Viray and Atty.
41 Id., at p. 6230, CECON’s Memorandum. James S. Villafranca as members.54
42 Id. ACI filed a Motion for Reconsideration of the CIAC’s
43 Id., at pp. 670-673, Annex I to CECON’s Petition. March 16, 2005 Order. This was denied in the Order dated
44 Id., at p. 673. March 30, 2005.55
45 Id., at p. 3763. In the Order dated April 1, 2005, the CIAC Arbitral
46 Id., at p. 6231, CECON’s Memorandum. Tribunal set the preliminary conference on April 13, 2005.56
47 Id., at p. 3764. At the preliminary conference, CECON indicated that,
48 Id., at p. 6231. the total sum it was entitled to recover from ACI needed to
49 Id., at p. 3764. be adjusted to P324,113,410.08. The CIAC Arbitral
Tribunal,
_______________

196 50 Id., at p. 3765.


196 SUPREME COURT REPORTS 51 Id.
ANNOTATED 52 Id.
CE Construction Corporation vs. Araneta Center, 53 Id., at p. 3765, CECON’s Memorandum
Inc. 54 Id., at pp. 3765 and 4029.
As negotiations seemed futile, on December 29, 2004, 55 Id., at p. 3766, CECON’s Memorandum.
CECON filed with the CIAC a Motion to Proceed with 56 Id.
arbitration proceedings. ACI filed an Opposition.50
After its Opposition was denied, ACI filed its Answer
dated January 26, 2005.51 It attributed liability for delays to
197
CECON and sought to recover counterclaims totalling
VOL. 836, AUGUST 9, 2017 197
P180,752, 297.84. This amount covered liquidated damages
for CECON’s supposed delays, the cost of defective works CE Construction Corporation vs. Araneta Center,
which had to be rectified, the cost of procuring permits and Inc.
licenses, and ACI’s other advances.52 thus, directed CECON to file an Amended Request for
On February 8, 2005, ACI filed a Manifestation and Adjudication/Amended Complaint.57
Motion seeking the CIAC’s clearance for the parties to enter Following the filing of CECON’s Amended Request for
into mediation. Mediation was then instituted with Atty. Adjudication/Amended Complaint and the ensuing
Sedfrey Ordoñez acting as mediator.53 responsive pleadings, another preliminary conference was
After mediation failed, an arbitral tribunal was set on May 13, 2005. The initial hearing of the case was
constituted through a March 16, 2005 Order of the CIAC. It then set on June 10, 2005.58
At the initial hearing, the CIAC Arbitral Tribunal 198
resolved to exclude the amount of P20,483,505.12 from 198 SUPREME COURT REPORTS
CECON’s claims as these pertained to unpaid ANNOTATED
accomplishments that did not relate to the issue of cost CE Construction Corporation vs. Araneta Center,
adjustments attributed to ACI, as originally pleaded by Inc.
CECON.59
as values accruing to the various change orders issued by
Following the conduct of hearings, the submission of the
ACI, totalling P159,827,046.94.61
parties’ memoranda and offers of exhibits, the CIAC
The CIAC Arbitral Tribunal found ACI liable for the
Arbitral Tribunal rendered its Decision on October 25,
delays. This entitled CECON to extended overhead costs
2006. It awarded a total of P229,223,318.69 to CECON,
and the ensuing extension cost of its Contractor’s All Risk
inclusive of the costs of arbitration. It completely denied
Insurance. For these costs, the CIAC Arbitral Tribunal
ACI’s claims for liquidated damages, but awarded to ACI a
awarded CECON the total amount of P16,289,623.08. As it
total of P11,795,162.93 on account of defective and
was ACI that was liable for the delays, the CIAC Arbitral
rectification works, as well as permits, licenses, and other
Tribunal ruled that ACI was not entitled to liquidated
advances.60 Thus, the net amount due to CECON was
damages.62
determined to be P217,428,155.75.
The CIAC Arbitral Tribunal ruled that CECON was
The CIAC Arbitral Tribunal noted that while ACI’s
entitled to a differential in take out costs representing
initial invitation to bidders was for a lump sum design-and-
builder’s works and related costs with respect to the
construct arrangement, the way that events actually
equipment purchased by ACI. This differential cost was in
unfolded clearly indicated a shift to an arrangement where
the amount of P15,332,091.47.63The CIAC Arbitral Tribunal
the designs were contingent upon ACI itself. Considering
further noted that while ACI initially opted to purchase by
that the premise for CECON’s August 30, 2002 lump sum
itself pumps, tanks, and cooling towers and removed these
offer of P1,540,000.00 was no longer availing, CECON was
from CECON’s scope of work, it subsequently elected to still
no longer bound by its representations in respect of that
obtain these through CECON. Considering that the
lump sum amount. It may then claim cost adjustments
corresponding amount deducted as takeout costs did not
totalling P16,429,630.74, as well
encompass the overhead costs and profits under day work,
_______________
which should have accrued to CECON because of these
57 Id. equipment, the CIAC Arbitral Tribunal ruled that CECON
58 Id., at pp. 3767-3769. was entitled to 18% day work rate or a total of
59 Id., at pp. 3768-3769. P21,267,908.00.64
60 Id., at pp. 4028-4029. The CIAC Arbitral Tribunal also found that, apart from
adjusted costs incurred on account of ACI’s own activities, it
also became necessary for CECON, as main contractor, to
continue extending auxiliary services to the project’s
subcontractors because of the delays. Thus, the CIAC The dispositive portion of the CIAC Arbitral Tribunal’s
Arbitral Tribunal awarded CECON attendance fees — the Decision read:
main contractor’s markup for auxiliary services extended to WHEREFORE, Respondent is hereby ordered to pay the
subcontractors — totalling P14,335,674.88. This amount Claimant the amount of PESOS TWO HUNDRED
was lower than the SEVENTEEN MILLION, FOUR HUNDRED TWENTY-
_______________ EIGHT THOUSAND, ONE HUNDRED FIFTY[-]FIVE
PESOS AND SEVENTY[-]FIVE CENTAVOS
61 Id., at pp. 3811-3813 and 3882-3888. (Php217,428,155.75) within thirty (30) days upon
62 Id., at pp. 3940-3943. promulgation of the award. Interest 6% per annum shall be
63 Id., at pp. 3832-3833. imposed on the award for any balance remaining from the
64 Id., at pp. 3954-3955. promulgation of the award up to the time the award
becomes final and executory. Thereafter, interest of 12% per
annum shall be imposed on any balance of the award until
fully paid.
199
VOL. 836, AUGUST 9, 2017 199 _______________
CE Construction Corporation vs. Araneta Center,
Inc. 65 Id., at p. 3768.
66 Id., at pp. 3980-3990.
original amount prayed for by CECON (i.e.,
67 Id., at pp. 4027-4028.
P19,544,667.81)65 as the CIAC Arbitral Tribunal ruled that
68 Id., at pp. 3997-3998.
CECON may not claim attendance fees pertaining to
69 Id., at pp. 4012-4014.
subcontractors which directly dealt with ACI.66
Considering that CECON’s predicament was borne by
ACI’s fault, the CIAC Arbitral Tribunal saw it fit to award
to CECON the costs of arbitration totalling P1,083,802.58.67 200
While mainly ruling in CECON’s favor, the CIAC 200 SUPREME COURT REPORTS
Arbitral Tribunal found CECON liable for discolored and
ANNOTATED
mismatched tiles. It noted that CECON had engaged the
services of a subcontractor for the installation of tiles, for CE Construction Corporation vs. Araneta Center,
which it claimed attendance fees. Thus, it awarded Inc.
P7,980,000.00 to ACI.68 In addition, it found CECON liable SO ORDERED.70
to ACI for amounts paid in advance for permits and licenses
for the additional office tower, electrical consumption, and
garbage collection. Thus, it awarded another P3,815,162.93
to ACI.69
On December 4, 2006, ACI filed before the Court of 75 Id., at p. 85.
Appeals a Petition for Review71 under Rule 43 of the 1997 76 Id., at pp. 32-34.
Rules of Civil Procedure. 77 Id., at pp. 84-85.
In the meantime, on December 28, 2006, the CIAC
Arbitral Tribunal issued an Order72acknowledging
arithmetical errors in its October 25, 2006 Decision. Thus,
it modified its October 25, 2006 Decision, indicating that 201
the net amount due to CECON was P231,357,136.72, rather VOL. 836, AUGUST 9, 2017 201
than P217,428,155.75.73 CE Construction Corporation vs. Araneta Center,
In its assailed April 28, 2008 Decision,74 the Court of Inc.
Appeals reduced the award in favor of CECON to On the cost increases borne by Change Order No. 11 —
P114,324,605.00 and increased the award to ACI to the shift from reinforced concrete to structural steel
P31,566,246.20.75 framing — and by transitions from schematic diagrams to
The Court of Appeals held as inviolable the lump sum construction drawings, the Court of Appeals dismissed the
fixed price arrangement between ACI and CECON. It CIAC Arbitral Tribunals award to CECON as arising from
faulted the CIAC Arbitral Tribunal for acting in excess of “pity” and unwarranted by the lump sum, fixed price
jurisdiction as it supposedly took it upon itself to arrangement.78
unilaterally modify the arrangement between ACI and The Court of Appeals held ACI liable to CECON for the
CECON.76 sum of P12,672,488.36 for miscellaneous change orders,
Thus, the Court of Appeals deleted the CIAC Arbitral which it construed to be “separate contracts that have been
Tribunal’s award representing cost adjustments. However, entered into at the time [ACI] required them.”79 It likewise
the Court of Appeals also noted that in ACI’s and CECON’s held ACI liable for P1,132,946.17 representing the balance
March 30, 2004 Joint Manifestation before CIAC, ACI of 12 other partially paid change orders.80
conceded that P10,266,628.00 worth of cost adjustments The Court of Appeals noted that CECON was not
was due to CECON and undertook to pay CECON that entitled to time extensions because the arrangement
amount. The Court of Appeals, hence, maintained a between ACI and CECON had never been altered.
P10,266,628.00 award of cost adjustment in favor of Consequently, it was not entitled to acceleration costs,
CECON.77 additional overhead, and reimbursement for extending the
_______________ Contractor’s All Risk Insurance.81Conversely, the Court of
Appeals held CECON liable for delays thereby entitling
70 Id., at p. 4029. ACI to liquidated damages corresponding to 10% of the
71 Id., at pp. 4030-4881. supposed contract sum of P1,540,000,000.00, or
72 Id., at pp. 4882-4887. P15,400,000.00.82
73 Id., at p. 4886. Also on account of the supposed lump sum arrangement,
74 Id., at pp. 11-85. the Court of Appeals held that CECON was not entitled to
attendance fees on contract amounts increased by change to P3,811,289.70, the Court of Appeals concluded that an
order works.83 It also stated that the rate for attendance award for takeout costs in that amount was proper.86
fees, overhead, and profit for subcontractors’ works On the CIAC Arbitral Tribunal’s award for overhead
remained subject to the original contract documents based costs and profits under day work, the Court of Appeals held
on ACI’s original invitation to bidders and had never been that it was improper to grant this award based on
altered.84 stipulations on day works pertaining “only to ‘materials’
_______________ and not to equipment.”87
Finally, the Court of Appeals held that CECON was not
78 Id., at p. 50. entitled to costs of litigation considering that “no premium
79 Id. is to be placed on the right to litigate”88 and since ACI could
80 Id., at p. 52. not be faulted for delays.
81 Id., at pp. 54-56. The dispositive portion of the assailed Court of Appeals’
82 Id., at pp. 56-59. April 28, 2008 Decision read:
83 Id., at pp. 72-73. WHEREFORE, based on all the foregoing, the Decision
84 Id., at pp. 70-72. of the Arbitral Tribunal is modified as follows:
AWARD TO CECON a.

202 _______________
202 SUPREME COURT REPORTS
ANNOTATED 85 Id., at p. 69.
CE Construction Corporation vs. Araneta Center, 86 Id., at pp. 42-45.
87 Id., at pp. 62-63.
Inc.
88 Id., at p. 83.
Regarding attendance fees, the Court of Appeals
proffered that the work attributed to subcontractors was
merely work done by CECON itself, thereby negating the
need for attendance fees.85 203
Concerning takeout costs, the Court of Appeals stated VOL. 836, AUGUST 9, 2017 203
that CECON was in no position to propose its own takeout
CE Construction Corporation vs. Araneta Center,
costs as the tender documents issued along with ACI’s
Inc.
invitation to bidders stated that takeout costs must be
based exclusively on the rates provided in the Contract Cost AWARD TO ARANETA b.
Breakdown. Nevertheless, as ACI had previously
NO. ISSUE Pesos (PHP)
undertaken to pay the variance in takeout costs amounting
[5] Liquidated Damages 15,400,000.00
NO. ISSUE Pesos (PHP) The dispositive portion of the assailed Court of Appeals’
Defective and Incomplete July 1, 2010 Amended Decision read:
[6] 3,000,000.00
Works WHEREFORE, Our Decisiondated 28 April 2008 is
Bookmarking Granite Tiles 6,980,000.00 hereby modified as follows:
Permits, Licenses and Other I – AWARD:
[7] 6,186,246.23
Advances AWARD TO CE CONSTRUCTION, INC. a.
31,566,246.20
Total NO. ISSUE PESOS (PhP)
(sic)
In addition, CECON is directed to submit all required 1
Additional costs spent on
10,266,628.00
closeout documents within thirty (30) days from receipt of rebars.
this Decision. Increase in the costs of cement
The parties shall bear their own costs of arbitration and 2 and formworks falling under 5,205,004.02
litigation. cost-bearing change.
SO ORDERED.89 Representing undervaluation of
respondent’s works in the
3 1,209,782.50
_______________ supply and installation of G.I.
sheets.
89 Id., at pp. 84-85. 4
Representing Miscellaneous
27,601,469.32
Change Orders
5 Drilling of Holes 4,543,450.00
[Schematic Drawings] to
6 80,108,761.60
204 [Construction Drawings]
204 SUPREME COURT REPORTS Installation of equipment
[7] 1,127,486.50
ANNOTATED supplied by owner
CE Construction Corporation vs. Araneta Center, TOTAL 130,062,581.94
Inc.
_______________
Acting on CECON’s Motion for Reconsideration, the
Court of Appeals issued its Amended Decision on July 1,
90 Id., at pp. 87-137.
2010.90 This Amended Decision increased the award for
91 Id., at pp. 105-106.
miscellaneous change orders to P27,601,469.32; reinstated
92 Id., at p. 107.
awards for undervalued works in supplying and installing
93 Id., at p. 104.
G.I. sheets worth P1,209,782.5091 and for the drilling of
holes and application of epoxy worth P4,543,456.00;92 and
deleted the award for takeout costs.93
205
VOL. 836, AUGUST 9, 2017 205 offer to bid. It cites specific provisions of these documents
CE Construction Corporation vs. Araneta Center, such as valuation rules
Inc. _______________
AWARD TO ARANETA CENTER, INC. b.
94 Id., at pp. 136-137.
1 Liquidated Damage (sic) 20,000,000.00 95 Id., at pp. 153-268.
2 Defective and Incomplete Works 3,000,000.00 96 Id., at pp. 263-264.
3 Bookmarking Granite Tiles 6,980,000.00 97 Id., at p. 6098.
Permits, Licenses and other
4 6,186,246.23
Advances
TOTAL 36,166,246.23
206
II – COMPUTATION:
206 SUPREME COURT REPORTS
AWARD TO CE ANNOTATED
130,062,581.94
CONSTRUCTION, INC. CE Construction Corporation vs. Araneta Center,
LESS Inc.
AWARD TO ARANETA CENTER,
36,166,246.23 and required notices for extensions and changes, reckoning
INC. of losses and expenses, the ensuing liquidated damages for
BALANCE PAYABLE BY
93,896,335.71 defects, cost-bearing changes and provisional sums,98which
ARANETA TO CECON define parameters for permissible changes and for
SO ORDERED.94 reckoning corresponding costs and liabilities. However, it
did not attach any of these documents to its Comment or
Memorandum. It also cites statutory provisions — Articles
Aggrieved at the Court of Appeals’ ruling, CECON filed
171599and 1724100 of the Civil Code — on CECON’s
the present Petition insisting on the propriety of the CIAC
liabilities and the primacy of stipulated contract prices.101
Arbitral Tribunal’s conclusions and findings.95 It prays that
By the inviolability of their agreement, ACI insists on
the assailed Court of Appeals’ decisions be reversed and
the supposed immutability of the stipulated contract sum
that the CIAC Arbitral Tribunal’s October 25, 2006
and on the impropriety of the CIAC Arbitral Tribunal in
Decision, as modified by its December 28, 2006 Order, be
writing its own terms for ACI and CECON to follow.102 It
reinstated.96
faults the CIAC
ACI counters that the Court of Appeals’ July 1, 2010
_______________
Amended Decision must be upheld.97
ACI insists on the inviolability of its supposed 98 Id., at pp. 5914-5929 and 5934-5936.
agreement with CECON, as embodied in the contract 99 CIVIL CODE, Art. 1715 provides:
documents delivered to contractors alongside the original
The contractor shall execute the work in such a manner that run afoul of contractual stipulations and on bases such
that it has the qualities agreed upon and has no defects as industry practices and standards, which supposedly
which destroy or lessen its value or fitness for its ordinary should not have even been considered as the parties have
or stipulated use. Should the work be not of such quality, already adduced their respective evidence.103 It insists upon
the employer may require that the contractor remove the CECON’s fault for delays and defects, making it liable for
defect or execute another work. If the contractor fails or liquidated damages.104
refuses to comply with this obligation, the employer may Though nominally modifying the CIAC Arbitral
have the defect removed or another work executed, at the Tribunal’s October 25, 2006 Decision, the Court of Appeals
contractor’s cost. 1715. Article actually reversed it on the pivotal matter of the
100 CIVIL CODE, Art. 1724 provides: characterization of the contract between CECON and ACI.
The contractor who undertakes to build a structure or Upon its characterization of the contract as one for a lump
any other work for a stipulated price, in conformity with sum fixed price, the Court of Appeals deleted much of the
plans and specifications agreed upon with the landowner, CIAC Arbitral Tribunal’s monetary awards to CECON and
can neither withdraw from the contract nor demand an awarded liquidated damages to ACI.
increase in the price on account of the higher cost of labor On initial impression, what demands resolution is the
or materials, save when there has been a change in the issue of whether or not the Court of Appeals erred in
plans and specifications, provided: 1724. Article characterizing the contractual arrangement between
Such change has been authorized by the proprietor in petitioner CE Construction Corporation and respondent
writing; and (1) Araneta Center, Inc. as immutably one for a lump sum
The additional price to be paid to the contractor has fixed price.
been determined in writing by both parties. (2) However, this is not merely a matter of applying and
101 Rollo, pp. 5930-5933. deriving conclusions from cut and dried contractual
102 Id., at p. 5893. ACI’s Comment states, “the Arbitral provisions. More accurately, what is on issue is whether or
Tribunal significantly modified and amended the clear not the Court of Appeals correctly held that the CIAC
terms of the parties’ contract documents by rewriting their Arbitral Tribunal acted beyond its jurisdiction in holding
construction agreement and that the price of P1,540,000,000.00 did not bind the parties
as an immutable lump sum. Subsumed in this issue is the
matter of whether or not the Court of Appeals correctly
ruled that CECON was rightfully entitled to time
207 extensions and that intervening circumstances had made
VOL. 836, AUGUST 9, 2017 207 ACI liable for cost adjustments, increases borne by change
CE Construction Corporation vs. Araneta Center, orders, additional overhead costs,
Inc. _______________
Arbitral Tribunal for erroneously reckoning the sums due to
CECON, particularly in relying on factual considerations
unilaterally imposing upon ACI newly-created obligations, the Construction Industry Arbitration Law.105 At inception,
notwithstanding that there was no issue on the exact terms it was
of the contract documents and the intent of the parties in _______________
executing the same.”
103 Id., at pp. 5894-5895. 105 Though nominally an “executive order” the
104 Id., at pp. 5897-5898. Construction Industry Arbitration Law is a statute.
Jurisprudence has clarified that, in exercising legislative
powers, then President Marcos did not only use the
modality of presidential decrees, but also of executive
208 orders and letters of instruction. Though, this is not to say
208 SUPREME COURT REPORTS that all executive orders and letters of intruction issued by
ANNOTATED him are statutes.
CE Construction Corporation vs. Araneta Center, In Garcia-Padilla v. Enrile, 206 Phil. 392, 428; 121 SCRA
Inc. 472, 499 (1983) [Per J. De Castro, En Banc]:
extended contractor’s all risk insurance coverage, increased To form part of the law of the land, the decree, order or
attendance fees vis-à-vis subcontractors, and arbitration [letter of instruction] must be issued by the President in the
costs which it awarded to CECON. exercise of his extraordinary power of legislation as
This Court limits itself to the legal question of the CIAC contemplated in Section 6 of the 1976 amendments to the
Arbitral Tribunal’s competence. Unless any of the Constitution, whenever in his judgment, there exists a
exceptional circumstances that warrant revisiting the grave emergency or a threat or imminence thereof, or
factual matter of the accuracy of the particulars of every whenever the interim Batasan[g] Pambansa or the regular
item awarded to the parties is availing, this Court shall not National Assembly fails or is unable to act adequately on
embark on its own audit of the amounts owing to each.

I
209
This Court begins by demarcating the jurisdictional and
VOL. 836, AUGUST 9, 2017 209
technical competence of the CIAC and of its arbitral
tribunals. CE Construction Corporation vs. Araneta Center,
Inc.
I.A _______________

The Construction Industry Arbitration Commission was any matter for any reason that in his judgment requires
a creation of Executive Order No. 1008, otherwise known as immediate action.
In Irene B. Cortes, Executive Legislation: The Philippine general statutory framework of alternative dispute
Experience; 55 PHIL. L.J. 1, 27-29 (1979) Associate Justice resolution.
Irene Cortes noted that certain executive orders and letters Jurisprudence, too, has repeatedly and consistently referred
of instruction have indeed been on par with President to it as such a “law.” See, for example, National Irrigation
Marcos’ more commonly used mode of legislation (i.e., Administration v. Court of Appeals, 376 Phil. 362; 318
presidential decrees): SCRA 255 (1999) [Per CJ.Davide, Jr., First
Another problem arises from lack of precision in the Division]; Metropolitan Cebu Water District v. Mactan Rock
appropriate use of one form of issuance as against another. Industries, Inc., 690 Phil. 163; 675 SCRA 577 (2012)
A presidential decree is equivalent to a statute enacted by [Per J. Mendoza, Third Division]; and The Manila
the legislature, and is thus superior to implementing rules Insurance Co.,
issued as executive orders or letter of instructions. But, it is
not unheard of for an executive order to amend or repeal a
presidential decree or a letter of instructions to amend an
executive order, or lay down a rule of law. 210
Associate Justice Cortes specifically cited as an example 210 SUPREME COURT REPORTS
Exec. Order No. 543 (1979), which abolished the Philippine ANNOTATED
Center for Advanced Studies, a creation of Pres. Decree No. CE Construction Corporation vs. Araneta Center,
342 (1973). In disproving that Exec. Order No. 543 was Inc.
issued merely as an implementing rule, she explained that under the administrative supervision of the Philippine
its object — a state university — could not have fallen Domestic Construction Board106 which, in turn, was an
under the scope of the President’s reorganization powers, implementing agency of the Construction Industry
for which an executive order issued merely as an Authority of the Philippines (CIAP).107 The CIAP is
implementing rule was sufficient. presently attached to the Department of Trade and
The Construction Industry Arbitration Law’s own Industry.108
nomenclature reveals the intent that it be a statute. Its The CIAC was created with the specific purpose of an
whereas clauses and declaration of policy reveal the “early and expeditious settlement of disputes”109cognizant
urgency that impelled immediate action for the President to of the exceptional role of construction to “the furtherance of
exercise his concurrent legislative powers. national development goals.”110
Any doubt on the statutory efficacy of the Construction Section 4 of the Construction Industry Arbitration Law
Industry Arbitration Law is addressed by Congress’ own, spells out the jurisdiction of the CIAC:
voluntary and repeated reference to and affirmation of it as 4. SectionJurisdiction.—The CIAC shall have original
such a law. (SeeRep. Act No. 9184 and Rep. Act No. 9285). and exclusive jurisdiction over disputes arising from, or
Rep. Act No. 9285 did not only validate the Construction connected with, contracts entered into by parties involved
Industry Arbitration Law, it also incorporated it into the in construction in the Philippines, whether the dispute
arises before or after the completion of the contract, or after
the abandonment or breach thereof. These disputes may Though created by the act of a Chief Executive who then
involve government or private contracts. For the Board to exercised legislative powers concurrently with the Batasang
acquire jurisdiction, the parties to a dispute must agree to Pambansa, the creation, continuing existence, and
submit the same to voluntary arbitration. competence of the CIAC have since been validated by acts
The jurisdiction of the CIAC may include but is not of Congress.
limited to violation of specifications for materials and Republic Act No. 9184 or the Government Procurement
workmanship; violation of the terms of agreement; Reform Act, enacted on January 10, 2003, explicitly
interpretation and/or application of contractual time and recognized and confirmed the competence of the CIAC:
delays; maintenance and defects; payment, default of 59. SectionArbitration.—Any and all disputes arising
employer or contractor and changes in contract cost. from the implementation of a contract covered by this Act
shall be submitted to arbitration in the Philippines
_______________ according to the provisions of Republic Act No. 876,
otherwise known as the “Arbitration Law”: Provided,
Inc. v. Amurao, 701 Phil. 557; 688 SCRA 609 (2013) however, That, disputes that are within the competence of
[Per J. Del Castillo, Second Division]. the Construction Industry Arbitration Commission to
106 Exec. Order No. 1008, Sec. 3. resolve shall be referred thereto. The process of arbitration
107 Id., 4th Whereas Clause. shall be incorporated as a provision in the contract that will
108 See Department of Trade and Industry, Attached be executed pursuant to the provisions of this
Agencies, <http://www.dti.gov.ph/about/the- Act: Provided, That by mutual agreement, the parties may
organization/attached-agencies> (last visited on August 8, agree in writing to resort to alternative modes of dispute
2017). resolution. (Emphasis supplied)
109 Exec. Order No. 1008, Sec. 2.
110 Id., 3rd Whereas Clause.
Arbitration of construction disputes through the CIAC
was formally incorporated into the general statutory
framework on alternative dispute resolution through
211 Republic Act No. 9285, the Alternative Dispute Resolution
VOL. 836, AUGUST 9, 2017 211 Act of 2004 (ADR Law). Chapter 6, Section 34 of ADR Law
CE Construction Corporation vs. Araneta Center, made specific reference to the Construction Industry
Inc. Arbitration Law, while Section 35 confirmed the CIAC’s
Excluded from the coverage of this law are disputes jurisdiction:
arising from employer-employee relationships which shall
continue to be covered by the Labor Code of the Philippines.
212
212 SUPREME COURT REPORTS
ANNOTATED concerned with other specialized fields. The CIAC has the
CE Construction Corporation vs. Araneta Center, state’s confidence concerning the entire technical expanse of
Inc. construction, defined in jurisprudence as “referring to all
CHAPTER 6 on-site works on buildings or altering structures, from land
ARBITRATION OF CONSTRUCTION DISPUTES clearance through completion including ex-
34. SectionArbitration of Construction Disputes:
Governing Law.—The arbitration of construction disputes
213
shall be governed by Executive Order No. 1008, otherwise
known as the Construction Industry Arbitration Law. VOL. 836, AUGUST 9, 2017 213
35. SectionCoverage of the Law.—Construction CE Construction Corporation vs. Araneta Center,
disputes which fall within the original and exclusive Inc.
jurisdiction of the Construction Industry Arbitration cavation, erection and assembly and installation of
Commission (the “Commission”) shall include those components and equipment.”111
between or among parties to, or who are otherwise bound Jurisprudence has characterized the CIAC as a quasi-
by, an arbitration agreement, directly or by reference judicial, administrative agency equipped with technical
whether such parties are project owner, contractor, proficiency that enables it to efficiently and promptly
subcontractor, fabricator, project manager, design resolve conflicts:
professional, consultant, quantity surveyor, bondsman or [The CIAC] is a quasi-judicial agency. A quasi-judicial
issuer of an insurance policy in a construction project. agency or body has been defined as an organ of government
The Commission shall continue to exercise original and other than a court and other than a legislature, which
exclusive jurisdiction over construction disputes although affects the rights of private parties through either
the arbitration is “commercial” pursuant to Section 21 of adjudication or rule-making. The very definition of an
this Act. administrative agency includes its being vested with quasi-
judicial powers. The ever increasing variety of powers and
functions given to administrative agencies recognizes the
I.B need for the active intervention of administrative agencies
in matters calling for technical knowledge and speed in
The CIAC does not only serve the interest of speedy countless controversies which cannot possibly be handled
dispute resolution, it also facilitates authoritativedispute by regular courts. The CIAC’s primary function is that of a
resolution. Its authority proceeds not only from juridical quasi-judicial agency, which is to adjudicate claims and/or
legitimacy but equally from technical expertise. The determine rights in accordance with procedures set forth in
creation of a special adjudicatory body for construction E.O. No. 1008.112
disputes presupposes distinctive and nuanced competence
on matters that are conceded to be outside the innate
expertise of regular courts and adjudicatory bodies
The most recent jurisprudence maintains that the CIAC they intend to serve private, proprietary interests.115 In
is a quasi-judicial body. This Court’s November 23, 2016 contrast, voluntary arbitra-
Decision in Fruehauf Electronics v. Technology Electronics _______________
Assem-
_______________ 113 Fruehauf Electronics Philippines Corporation v.
Technology Electronics Assembly and Management Pacific
111 Fort Bonifacio Development Corporation v. Corporation, G.R. No. 204197, November 23, 2016, 810
Sorongon, 605 Phil. 689, 696; 587 SCRA 613, 621 (2009) SCRA 280 [Per J. Brion, Second Division].
[Per J. Tinga, Second Division]. 114 LABOR CODE, Art. 219 provides:
112 Metro Construction, Inc. v. Chatham Properties, 219. ArticleDefinitions.— . . . .
Inc., 418 Phil. 176, 202-203; 365 SCRA 697, 722 (2001) “Voluntary Arbitrator” means any person accredited by
[Per CJ. Davide, Jr., First Division], citing Presidential the Board as such, or any person named or designated in
Anti-Dollar Salting Task Force v. CA, 253 Phil. 344; 171 the Collective Bargaining Agreement by the parties to act
SCRA 348 (1989) [Per J. Sarmiento, En Banc]; Tropical as their Voluntary Arbitrator, or one chosen with or without
Homes, Inc. v. National Housing Authority, 236 Phil. 580; the assistance of the National Conciliation and Mediation
152 SCRA 540 (1987) [Per J.Gutierrez, Jr., En Board, pursuant to a selection procedure agreed upon in the
Banc]; Antipolo Realty Corp. v. National Housing Authority, Collective Bargaining Agreement, or any official that may
237 Phil. 389; 153 SCRA 399 (1987) [Per J. Feliciano, En be authorized by the Secretary of Labor and Employment to
Banc]; and Solid Homes, Inc. v. Payawal, 257 Phil. 914; 177 act as Voluntary Arbitrator upon the written request and
SCRA 72 (1989) [Per J. Cruz, First Division]. agreement of the parties to a labor dispute. 14.
115 Fruehauf Electronics Philippines Corporation v.
Technology Electronics Assembly and Management
Pacific Corporation, supra. It stated:
214 Quasi-judicial or administrative adjudicatory power is
214 SUPREME COURT REPORTS the power: (1) to hear and determine questions of fact to
ANNOTATED which legislative policy is to apply, and (2) to decide in
CE Construction Corporation vs. Araneta Center, accordance with the standards laid down by the law itself in
Inc. enforcing and administering the same law. Quasi-judicial
bly and Management Pacific113 distinguished construction power is only exercised by administrative agencies — legal
arbitration, as well as voluntary arbitration pursuant to organs of the government.
Article 219(14) of the Labor Code,114 from commercial Quasi-judicial bodies can only exercise such powers and
arbitration. It ruled that commercial arbitral tribunals jurisdiction as are expressly or by necessary implication
are notquasi-judicial agencies, as they are purely ad conferred upon them by their enabling statutes. Like
hocbodies operating through contractual consent and as courts, a quasi-judicial body’s jurisdiction over a subject
matter is conferred by law and exists independently from
the will of the parties. As government organs necessary for _______________
an effective legal system, a quasi-judicial tribunal’s legal
existence continues beyond the resolution of a specific As a contractual and consensual body, the arbitral
dispute. In other words, quasi-judicial bodies are creatures tribunal does not have any inherent powers over the
of law. parties. It has no power to issue coercive writs or
compulsory processes. Thus, there is a need to resort to the
regular courts for interim measures of protection and for
the recognition or enforcement of the arbitral award.
215 The arbitral tribunal acquires jurisdiction over the
VOL. 836, AUGUST 9, 2017 215 parties and the subject matter through stipulation. Upon
CE Construction Corporation vs. Araneta Center, the rendition of the final award, the tribunal
Inc. becomes functus officio and — save for a few exceptions —
tion under the Labor Code and construction arbitration ceases to have any further jurisdiction over the dispute. The
operate through the statutorily vested jurisdiction of tribunal’s powers (or in the case of ad hoc tribunals, their
government instrumentalities that exist independently of very existence) stem from the obligatory force of the
the will of contracting parties and to which these parties arbitration agreement and its ancillary stipulations. Simply
submit. They proceed from the public interest imbuing their put, an arbitral tribunal is a creature of contract. (Citations
respective spheres: omitted)
Voluntary Arbitrators resolve labor disputes and
grievances arising from the interpretation of Collective
Bargaining Agreements. These disputes were specifically
216
excluded from the coverage of both the Arbitration Law and
216 SUPREME COURT REPORTS
the ADR Law.
Unlike purely commercial relationships, the relationship ANNOTATED
between capital and labor are heavily impressed with CE Construction Corporation vs. Araneta Center,
public interest. Because of this, Voluntary Arbitrators Inc.
authorized to resolve labor disputes have been clothed with vate citizens instead of government instrumentalities
quasi-judicial authority. wielding quasi-judicial powers.
On the other hand, commercial relationships covered by Moreover, judicial or quasi-judicial jurisdiction cannot be
our commercial arbitration laws are purely private and conferred upon a tribunal by the parties alone. The Labor
contractual in nature. Unlike labor relationships, they do Code itself confers subject-matter jurisdiction to Voluntary
not possess the same compelling state interest that would Arbitrators.
justify state interference into the autonomy of contracts. Notably, the other arbitration body listed in Rule 43 —
Hence, commercial arbitration is a purely private system of the Construction Industry Arbitration Commission (CIAC)
adjudication facilitated by pri- — is also a government agency attached to the Department
of Trade and Industry. Its jurisdiction is likewise conferred CE Construction Corporation vs. Araneta Center,
by statute. By contrast, the subject matter jurisdiction of Inc.
commercial arbitrators is stipulated by the 8.1. SectionGeneral Qualification of Arbitrators.—The
parties.116(Emphasis supplied, citations omitted) Arbitrators shall be men of distinction in whom the
business sector and the government can have
confidence. They shall be technically qualified to resolve any
Consistent with the primacy of technical mastery,
construction dispute expeditiously and equitably. The
Section 14 of the Construction Industry Arbitration Law on
Arbitrators shall come from different professions. They may
the qualification of arbitrators provides:
include engineers, architects, construction managers,
14. SectionArbitrators.—A sole arbitrator or three
engineering consultants, and businessmen familiar with the
arbitrators may settle a dispute.
construction industry and lawyers who are experienced in
....
construction disputes. (Emphasis supplied)
Arbitrators shall be men of distinction in whom the
business sector and the government can have confidence.
They shall not be permanently employed with the CIAC. Of the 87 CIAC-accredited arbitrators as of January
Instead, they shall render services only when called to 2017, only 33 are lawyers. The majority are experts from
arbitrate. For each dispute they settle, they shall be given construction-related professions or engaged in related
fees. fields.117
Apart from arbitrators, technical experts aid the CIAC
in dispute resolution. Section 15 of the Construction
Section 8.1 of the Revised Rules of Procedure Governing
Industry Arbitration Law provides:
Construction Arbitration establishes that the foremost
15. SectionAppointment of Experts.—The services of
qualification of arbitrators shall be technical proficiency. It
technical or legal experts may be utilized in the settlement
explicitly enables not only lawyers but also “engineers,
of disputes if requested by any of the parties or by the
architects, construction managers, engineering consultants,
Arbitral Tribunal. If the request for an expert is done by
and businessmen familiar with the construction industry”
either or by both of the parties, it is necessary that the
to serve as arbitrators:
appointment of the expert be confirmed by the Arbitral
_______________
Tribunal.
116 Id., at pp. 307-308. Whenever the parties request for the services of an
expert, they shall equally shoulder the expert’s fees and
expenses, half of which shall be deposited with the
Secretariat before the expert renders service. When only
217 one party makes the request, it shall deposit the whole
VOL. 836, AUGUST 9, 2017 217 amount required.
_______________ _______________

117 Construction Arbitration and Mediation, 118 See Metro Construction, Inc. v. Chatham Properties,
Construction Industry Authority of the Philippines, Inc., supra note 112.
available at 119 RULES OF COURT, Rule 43, Sec. 1 provides:
<http://www.ciap.dti.gov.ph/content/construction- 1. SectionScope.—This Rule shall apply to appeals
arbitrationmediation> (last visited on August 8, 2017). from judgments or final orders of the Court of Tax Appeals
and from awards, judgments, final orders or resolutions of
or authorized by any quasi-judicial agency in the exercise of
its quasi-judicial functions. Among these agencies are the
218 Civil Service Commission, Central Board of Assessment
218 SUPREME COURT REPORTS Appeals, Securities and Exchange Commission, Office of the
ANNOTATED President, Land Registration Authority, Social Security
CE Construction Corporation vs. Araneta Center, Commission, Civil Aeronautics Board, Bureau of Patents,
Inc. Trademarks and Technology Transfer, National
II Electrification Administration, Energy Regulatory Board,
National Telecommunications Commission, Department of
Consistent with CIAC’s technical expertise is the Agrarian Reform under Republic Act No. 6657, Government
primacy and deference accorded to its decisions. There is Service Insurance System, Employees Compensation
only a very narrow room for assailing its rulings. Commission, Agricultural Inventions Board, Insurance
Section 19 of the Construction Industry Arbitration Law Commission, Philippine Atomic Energy Commission, Board
establishes that CIAC arbitral awards may not be assailed, of Investments, Construction Industry Arbitration
except on pure questions of law: Commission, and voluntary arbitrators authorized by law.
19. SectionFinality of Awards.—The arbitral award shall
be binding upon the parties. It shall be final and
inappealable except on questions of law which shall be
219
appealable to the Supreme Court.
VOL. 836, AUGUST 9, 2017 219
CE Construction Corporation vs. Araneta Center,
Rule 43 of the 1997 Rules of Civil Procedure Inc.
standardizes appeals from quasi-judicial agencies.118Rule peals . . . whether the appeal involves questions of fact, of
43, Section 1 explicitly lists CIAC as among the quasi- law, or mixed questions of fact and law.”120
judicial agencies covered by Rule 43.119Section 3 indicates This is not to say that factual findings of CIAC arbitral
that appeals through Petitions for Review under Rule 43 tribunals may now be assailed before the Court of Appeals.
are to “be taken to the Court of Ap- Section 3’s statement “whether the appeal involves
questions of fact, of law, or mixed questions of fact and law” 121 298-A Phil. 361; 228 SCRA 397 (1993)
merely recognizes variances in the disparate modes of [Per J. Feliciano, Third Division].
appeal that Rule 43 standardizes: there were those that
enabled questions of fact; there were those that enabled
questions of law, and there were those that enabled mixed
questions fact and law. Rule 43 emphasizes that though 220
there may have been variances, all appeals under its scope 220 SUPREME COURT REPORTS
are to be brought before the Court of Appeals. However, in ANNOTATED
keeping with the Construction Industry Arbitration Law, CE Construction Corporation vs. Araneta Center,
any appeal from CIAC arbitral tribunals must remain Inc.
limited to questions of law. chosen by the parties themselves, which parties freely
Hi-Precision Steel Center, Inc. v. Lim Kim Steel Builders, consent in advance to abide by the arbitral award issued
Inc.121 explained the wisdom underlying the limitation of after proceedings where both parties had the opportunity to
appeals to pure questions of law: be heard. The basic objective is to provide a speedy and
Section 19 makes it crystal clear that questions of fact inexpensive method of settling disputes by allowing the
cannot be raised in proceedings before the Supreme Court parties to avoid the formalities, delay, expense and
— which is not a trier of facts — in respect of an arbitral aggravation which commonly accompany ordinary
award rendered under the aegis of the CIAC. Consideration litigation, especially litigation which goes through the
of the animating purpose of voluntary arbitration in general entire hierarchy of courts. [The Construction Industry
and arbitration under the aegis of the CIAC in particular, Arbitration Law] created an arbitration facility to which the
requires us to apply rigorously the above principle construction industry in the Philippines can have recourse.
embodied in Section 19 that the Arbitral Tribunal’s findings The [Construction Industry Arbitration Law] was enacted
of fact shall be final and unappealable. to encourage the early and expeditious settlement of
Voluntary arbitration involves the reference of a dispute disputes in the construction industry, a public policy the
to an impartial body, the members of which are implementation of which is necessary and important for the
realization of national development goals.122
_______________

120 RULES OF COURT, Rule 43, Sec. 3 provides: Consistent with this restrictive approach, this Court is
3. SectionWhere to appeal.—An appeal under this duty-bound to be extremely watchful and to ensure that an
Rule may be taken to the Court of Appeals within the appeal does not become an ingenious means for
period and in the manner herein provided, whether the undermining the integrity of arbitration or for conveniently
appeal involves questions of fact, of law, or mixed questions setting aside the conclusions arbitral processes make. An
of fact and law. appeal is not an artifice for the parties to undermine the
process they voluntarily elected to engage in. To prevent
this Court from being a party to such perversion, this one or the other party of a fair opportunity to present its
Court’s primordial inclination must be to uphold the factual position before the Arbitral Tribunal, and an award
findings of arbitral tribunals: obtained through fraud or the corruption of arbitrators. Any
Aware of the objective of voluntary arbitration in the other, more relaxed, rule would result in setting at naught
labor field, in the construction industry, and in any other the basic objective of a voluntary arbitration and would
area for that matter, the Court will not assist one or the reduce arbitration to a largely inutile
other or even both parties in any effort to subvert or defeat institution.123 (Emphasis supplied, citations omitted)
that objective for their private purposes. The Court will not
review the factual findings of an arbitral tribunal upon the
artful allegation that such body had “misapprehended the Thus, even as exceptions to the highly restrictive nature
facts” and will not pass upon issues which are, at bottom, of appeals may be contemplated, these exceptions are only
issues of fact, no matter how clev- on the narrowest of grounds. Factual findings of CIAC
arbitral tribunals may be revisited not merely because
_______________ arbitral tribunals may have erred, not even on the already
exceptional grounds traditionally available in Rule 45
122 Id., at p. 372; pp. 404-405. Petitions.124 Rather,
_______________

123 Id., at pp. 373-374; pp. 405-407.


221 124 In Marasigan v. Fuentes, G.R. No. 201310, January
VOL. 836, AUGUST 9, 2017 221 11, 2016, 778 SCRA 645 [Per J. Leonen, Second Division];
CE Construction Corporation vs. Araneta Center, It is basic that petitions for review on certiorari under
Inc. Rule 45 may only raise pure questions of law and that
erly disguised they might be as “legal questions.” The findings of fact are generally binding and conclusive on this
parties here had recourse to arbitration and chose the court. Nevertheless, there are recognized exceptions that
arbitrators themselves; they must have had confidence in will allow this court to overturn the factual findings
such arbitrators. The Court will not, therefore, permit the confronting it. These exceptions are the following:
parties to relitigate before it the issues of facts previously When the conclusion is a finding grounded entirely on
presented and argued before the Arbitral Tribunal, save speculation, surmises and conjectures; (1)
only where a very clear showing is made that, in reaching When the inference made is manifestly mistaken,
its factual conclusions, the Arbitral Tribunal committed an absurd or impossible; (2)
error so egregious and hurtful to one party as to constitute Where there is a grave abuse of discretion; (3)
a grave abuse of discretion resulting in lack or loss of
jurisdiction. Prototypical examples would be factual
conclusions of the Tribunal which resulted in deprivation of
222 When the Court of Appeals, in making its findings, went
222 SUPREME COURT REPORTS beyond the issues of the case and the same is contrary to
ANNOTATED the admissions of both appellant and appellee; (6)
CE Construction Corporation vs. Araneta Center, When the findings are contrary to those of the trial
Inc. court; (7)
When the findings of fact are conclusions without
factual findings may be reviewed only in cases where the
citation of specific evidence on which they are based; (8)
CIAC arbitral tribunals conducted their affairs in a
When the facts set forth in the petition as well as in the
haphazard, immodest manner that the most basic integrity
petitioners’ main and reply briefs are not disputed by the
of the arbitral process was imperiled. In Spouses David v.
respondents; and (9)
Construction Industry and Arbitration Commission:125
When the findings of fact of the Court of Appeals are
We reiterate the rule that factual findings of construction
premised on the supposed absence of evidence and
arbitrators are final and conclusive and not reviewable by
contradicted by the evidence on record. (Citations omitted)
this Court on appeal, except when the petitioner proves
(10)
affirmatively that: (1) the award was procured by
125 479 Phil. 578; 435 SCRA 654 (2004) [Per J. Puno,
corruption, fraud or other undue means; (2) there was
Second Division].
evident partiality or corruption of the arbitrators or of any
of them; (3) the arbitrators were guilty of misconduct in
refusing to postpone the hearing upon sufficient cause
shown, or in refusing to hear evidence pertinent and 223
material to the controversy; (4) one or more of the VOL. 836, AUGUST 9, 2017 223
arbitrators were disqualified to act as such under section
CE Construction Corporation vs. Araneta Center,
nine of Republic Act No. 876 and willfully refrained from
Inc.
disclosing such disqualifications or of any other
misbehavior by which the rights of any party have been definite award upon the subject matter submitted to them
materially prejudiced; or (5) the arbitrators exceeded their was not made.126 (Citation omitted)
powers, or so imperfectly executed them, that a mutual,
final and
Guided by the primacy of CIAC’s technical competence,
_______________ in exercising this Court’s limited power of judicial review,
this Court proceeds to rule on whether or not the Court of
When the judgment is based on a misapprehension of Appeals erred in its assailed decisions.
facts; (4)
When the findings of fact are conflicting; (5) III
Properly discerning the issues in this case reveals that CE Construction Corporation vs. Araneta Center,
what is involved is not a mere matter of contractual Inc.
interpretation but a question of the CIAC Arbitral It further explained that an inquiry into the true
Tribunal’s exercise of its powers. intention of the contracting parties is a legal, rather than a
factual issue:
III.A On the surface, the instant petition appears to merely
raise factual questions as it mainly puts in issue the
F.F. Cruz v. HR Construction127distinguished questions appropriate amount that is due to HRCC. However, a more
of law, properly cognizable in appeals from CIAC arbitral thorough analysis of the issues raised by FFCCI would
awards, from questions of fact: show that it actually asserts questions of law.
FFCCI primarily seeks from this Court a determination
A question of law arises when there is doubt as to what of whether [the] amount claimed by HRCC in its progress
the law is on a certain state of facts, while there is a billing may be enforced against it in the absence of a joint
question of fact when the doubt arises as to the truth or measurement of the former’s completed works. Otherwise
falsity of the alleged facts. For a question to be one of law, stated, the main question advanced by FFCCI is this: in the
the same must not involve an examination of the probative absence of the joint measurement agreed upon in the
value of the evidence presented by the litigants or any of Subcontract Agreement, how will the completed works of
them. The resolution of the issue must rest solely on what HRCC be verified and the amount due thereon be
the law provides on the given set of circumstances. Once it computed?
is clear that the issue invites a review of the evidence The determination of the foregoing question entails an
presented, the question posed is one of fact.128 interpretation of the terms of the Subcontract Agreement vis-
_______________ à-visthe respective rights of the parties herein. On this
point, it should be stressed that where an interpretation of
126 Id., at p. 590; p. 666. the true agreement between the parties is involved in an
127 684 Phil. 330; 668 SCRA 302 (2012) [Per J. Reyes, appeal, the appeal is in effect an inquiry of the law between
Second Division]. the parties, its interpretation necessarily involves a question
128 Id., at p. 346; p. 317, citingVda. de Formoso v. of law.
Philippine National Bank, 665 Phil. 174; 650 SCRA 35 Moreover, we are not called upon to examine the
(2011) [Per J. Mendoza, Second Division]. probative value of the evidence presented before the CIAC.
Rather, what is actually sought from this Court is an
interpretation of the terms of the Subcontract Agreement as
it relates to the dispute between the parties.129(Emphasis
224
supplied)
224 SUPREME COURT REPORTS
ANNOTATED _______________
129 Id., at pp. 346-347; pp. 317-318, citing Philippine III.B
National Construction Corporation v. Court of Appeals, 541 In this case, there is no established contract that simply
Phil. 658; 512 SCRA 684 (2007) [Per J. Chico-Nazario, required interpretation and application.
Third Division]. The assailed Court of Appeals’ April 28, 2008 Decision
implies that all that had to be done to resolve the present
controversy was to apply the supposedly clear and
unmistakable terms of the contract between ACI and
225 CECON. It even echoes the words of F.F. Cruz:
VOL. 836, AUGUST 9, 2017 225
CE Construction Corporation vs. Araneta Center, _______________
Inc.
130 Id.
Though similarly concerned with “an interpretation of
131 Id., at pp. 347-348; pp. 318-319, citing Civil Code,
the true agreement between the parties,”130 this case is not
Art. 1370.
entirely congruent with F.F. Cruz.
132 Id., at p. 349; p. 320.
In F.F. Cruz, the parties’ agreement had been clearly set
out in writing. There was a definitive instrument which
needed only to be consulted to ascertain the parties’ intent:
In resolving the dispute as to the proper valuation of the 226
works accomplished by HRCC, the primordial consideration 226 SUPREME COURT REPORTS
should be the terms of the Subcontract Agreement. It is ANNOTATED
basic that if the terms of a contract are clear and leave no
CE Construction Corporation vs. Araneta Center,
doubt upon the intention of the contracting parties, the
literal meaning of its stipulations shall control.131 Inc.
It is a legal principle of long standing that when the
language of the contract is explicit, leaving no doubt as to
Thus, this Court concluded: the intention of the parties, the courts may not read into it
Pursuant to the terms of payment agreed upon by the any other intention that would contradict its plain import.
parties, FFCCI obliged itself to pay the monthly progress The clear terms of the contract should never be the subject
billings of HRCC within 30 days from receipt of the same. matter of interpretation. Neither abstract justice nor the
Additionally, the monthly progress billings of HRCC should rule of liberal interpretation justifies the creation of a
indicate the extent of the works completed by it, the same contract for the parties which they did not make themselves
being essential to the valuation of the amount that FFCCI or the imposition upon one party to a contract or obligation
would pay to HRCC.132 not assumed simply or merely to avoid seeming hardships.
Their true meaning must be enforced, as it is to be
presumed that the contracting parties know their scope and CE Construction Corporation vs. Araneta Center,
effects. Inc.
.... this conclusion in support of points that should have made
The Contract Documents expressly characterize the up its anterior framework, points that would have been the
construction contract between [ACI] and CECON as “lump ones to lead to a conclusion. It then used this abortive
sum” and “fixed price” in nature. As a consequence, the conclusion to injudiciously dispose of the case.
Contract Documents expressly prohibit any adjustment of The Court of Appeals took the parties’ contractual
the contract sum due to any changes or fluctuations in the relation as a revealed and preordained starting point. Then,
cost of labor, materials or other matters.133 (Citations it dismissed every prior or subsequent detail that
omitted) contradicted this assumption. It thereby conveniently
terminated the discussion before it even began.
Upon its characterization of the contract as one for the
III.C
lump sum, fixed price of P1,540,000,000.00, the Court of
Appeals faulted the CIAC Arbitral Tribunal for acting in
There was never a meeting of minds on the price of
excess of jurisdiction as it supposedly countermanded the
P1,540,000,000.00. Thus, that stipulation could not have
parties’ agreement, or worse, conjured its own terms for the
been the basis of any obligation.
parties’ compliance.134
The only thing that ACI has in its favor is its initial
It was the Court of Appeals, not the CIAC Arbitral
delivery of tender documents to prospective bidders.
Tribunal, that committed serious error.
Everything that transpired after this delivery militates
To rule that the CIAC Arbitral Tribunal modified the
against ACI’s position.
parties’ agreement because it was indisputably one for a
Before proceeding to a consideration of the
lump sum, fixed price of P1,540,000,000.00 is begging the
circumstances that negate a meeting of minds, this Court
question. The Court of Appeals used a conclusion as a
emphasizes that ACI would have this Court sustain claims
premise to support itself. It erroneously jumped to a
premised on supposed inviolable documents. Yet, it did not
conclusion only to plead
annex copies of these documents either to its Comment or to
_______________
its Memorandum.
133 Rollo, pp. 32-37. ACI leaves this Court compelled to rely purely on their
134 Id., at pp. 32-33. packaged presentation and in a bind, unable to verify even
the accuracy of the syntax of its citations. This Court
cannot approve of this predicament. To cursorily acquiesce
to ACI’s overtures without due diligence and substantiation
227 is being overly solicitous, even manifestly partisan.
VOL. 836, AUGUST 9, 2017 227 ACI and its counsel must have fully known the
importance of equipping this Court with a reliable means of
confirmation, especially in a case so steeped in the sway of Consent is manifested by the meeting of the offer and the
circumstances. ACI’s omission can only work against its acceptance upon the thing and the cause which are to
cause. constitute the contract. 1319. Article The offer must be
certain and the acceptance absolute. A qualified acceptance
constitutes a counteroffer.
228 Acceptance made by letter or telegram does not bind the
228 SUPREME COURT REPORTS offerer except from the time it came to his knowledge. The
ANNOTATED contract, in such a case, is presumed to have been entered
CE Construction Corporation vs. Araneta Center, into in the place where the offer was made. (Emphasis
supplied)
Inc.
By delivering tender documents to bidders, ACI made an
offer. By these documents, it specified its terms and defined Subsequent events do not only show that there was no
the parameters within which bidders could operate. These meeting of minds on CECON’s initial offered contract sum
tender documents, therefore, guided the bidders in of P1,449,089,174.00 as stated in its August 30, 2002 bid.
formulating their own offers to ACI, or, even more They
fundamentally, helped them make up their minds if they
were even willing to consider undertaking the proposed
project. In responding and submitting their bids, 229
contractors, including CECON, did not peremptorily VOL. 836, AUGUST 9, 2017 229
become subservient to ACI’s terms. Rather, they made their
CE Construction Corporation vs. Araneta Center,
own representations as to their own willingness and ability.
Inc.
They adduced their own counteroffers, although these were
already tailored to work within ACI’s parameters. also show that there was never any meeting of minds on the
These exchanges were in keeping with Article 1326 of contract sum at all.
the Civil Code: In accordance with Article 1321 of the Civil Code,135 an
Advertisements for bidders are simply invitations to make offeror may fix the time of acceptance. Thus, CECON’s
proposals, and the advertiser is not bound to accept the August 30, 2002 offer of P1,449,089,174.00 “specifically
highest or lowest bidder, unless the contrary appears. stated that its bid was valid for only ninety (90) days, or
1326. Article only until 29 November 2002.”136November 29, 2002 lapsed
and ACI failed to manifest its acceptance of CECON’s
offered contract sum.
The mere occurrence of these exchanges of offers fails to It was only sometime after November 29, 2002 that ACI
satisfy the Civil Code’s requirement of absolute and verbally informed CECON that the contract was being
unqualified acceptance: awarded to it. Through a telephone call on December 7,
2002, ACI informed CECON that it may commence
excavation works. However, there is no indication that an Inc.
agreement was reached on the contract sum in any of these CECON agreed to extend a discount and reduced its offered
conversations. ACI, CECON, the CIAC Arbitral Tribunal, project cost to P1,540,000,000.00.138
and the Court of Appeals all concede that negotiations After all these, ACI demurred on the terms of its own
persisted. tender documents and changed the project from one
Still without settling on a contract sum, even the object encompassing both design and construction to one that was
of the contract was subjected to multiple modifications. limited to construction.
Absent a concurrence of consent and object, no contract was Though not pertaining to the object of the contract itself
perfected.137 but only to one (1) of its many facets, ACI also removed
An office tower atop Part A was included in CECON’s from CECON’s scope of works the acquisition of elevators,
scope of works and the contract sum increased to escalators, chillers, generator sets, indoor substations,
P1,582,810,525.00. Price fluctuations were conceded after cooling towers, pumps, and tanks. However, much later,
this and the project cost was again adjusted to ACI reneged on its own and opted to still obtain pumps,
P1,613,615,244.00. Thereafter, tanks, and cooling towers through CECON.
_______________ It is ACI’s contention that the offered project cost of
P1,540,000,000.00 is what binds the parties because its
135 CIVIL CODE, Art. 1321 provides: June 2, 2003 letter indicated acceptance of this offered
The person making the offer may fix the time, place, and amount.
manner of acceptance, all of which must be complied with. This is plain error.
1321. Article CECON was never remiss in impressing upon ACI that
136 Rollo, p. 6222, CECON’s Memorandum. the P1,540,000,000.00 offer was not perpetually availing.
137 CIVIL CODE, Art. 1318 provides: Without ACI’s timely acceptance, on December 27, 2002,
There is no contract unless the following requisites CECON wrote to ACI emphasizing that the quoted sum of
concur: 1318. Article P1,540,000,000.00 was “based [only] upon the prices
Consent of the contracting parties; (1) prevailing at December 26, 2002” levels.139 On January 8,
Object certain which is the subject matter of the 2003, CECON notified ACI of further increases in costs and
contract; (2) specifically stated that “[f]urther delay in the acceptance of
Cause of the obligation which is established. (3) the revised offer and release of the down payment may
affect the revised lump sum amount.”140 Finally, on
January 21, 2003, CECON wrote again to ACI,141stating
that the contract sum had to be increased to
230
P1,594,631,418.00. CECON also specifically stated,
230 SUPREME COURT REPORTS
consistent with Article 1321 of the Civil Code, that its
ANNOTATED _______________
CE Construction Corporation vs. Araneta Center,
138 Rollo, pp. 6224-6225 and 6383. ACI’s delivery CECON’s review, and both parties’ final
139 Id., at pp. 549 and 6224. act of formalizing their respective consent and affixing their
140 Id., at pp. 3773 and 6225. respective signatures would have established a clear point
141 Id., at pp. 556-557. in which the contract between ACI and CECON has been
perfected. These points, i.e., ACI’s delivery, CECON’s
review, and parties’ formalization, too, would have
validated the Court of Appeals’ assertion that all that
231 remained to be done was to apply unequivocal contractual
VOL. 836, AUGUST 9, 2017 231 provisions.
CE Construction Corporation vs. Araneta Center, ACI would fail on its own undertaking.
Inc. _______________
tender of this adjusted price was valid only until January
31, 2003, as further price changes may be forthcoming. 142 Id., at pp. 556 and 6224-6225.
CECON also impressed upon ACI that the 400 days allotted 143 Id., at p. 560.
for the completion of the project had to be adjusted.142
When ACI indicated acceptance, CECON’s
P1,540,000,000.00 offer had been superseded. Even
232
CECON’s subsequent offer of P1,594,631,418.00 had, by
232 SUPREME COURT REPORTS
then, lapsed by more than four (4) months. Apparently
totally misinformed, ACI’s acceptance letter did not even ANNOTATED
realize or remotely reference CECON’s most recent CE Construction Corporation vs. Araneta Center,
P1,594,631,418.00 stipulation but insisted on the passi offer Inc.
of P1,540,000,000.00 from the past year. III.D
ACI’s supposed acceptance was not an effective,
unqualified acceptance, as contemplated by Article 1319 of Without properly executed contract documents, what
the Civil Code. At most, it was a counteroffer to revert to would have been a straightforward exercise, akin to the
P1,540,000,000.00. experience in F.F. Cruz, became a drawn out fact-finding
ACI’s June 2, 2003 letter stated an undertaking: “This affair. The situation that ACI engendered made it
notwithstanding, formal contract documents embodying necessary for the CIAC Arbitral Tribunal to unravel the
these positions will shortly be prepared and forwarded to terms binding ACI to CECON from sources other than
you for execution.”143 Through this letter, ACI not only definitive documents.
undertook to deliver documents, it also admitted that the It is these actions of the CIAC Arbitral Tribunal that
final, definitive terms between the parties had yet to be raise an issue, purely as a matter of law, now the subject of
articulated in writing. this Court’s review; that is, faced with
the lacunae confronting it, whether or not the CIAC workmanship; violation of the terms of agreement;
Arbitral Tribunal acted within its jurisdiction. interpretation and/or application of contractual time and
delays; maintenance and defects; payment, default of
IV employer or contractor and changes in contract cost.

The CIAC Arbitral Tribunal did not act in excess of its


jurisdiction. Contrary to the Court of Appeals’ and ACI’s CECON raised the principal issue of the payment due to
assertions, it did not draw up its own terms and force these it on account, not only of fluctuating project costs but more
terms upon ACI and CECON. so because of ACI’s inability to timely act on many
contingencies, despite proper notice and communication
IV.A from and by CECON. Therefore, at the heart of the
controversy was the “interpretation and/or application of
The CIAC Arbitral Tribunal was not confronted with a contractual time and delays.” ACI’s counter-arguments, too,
barefaced controversy for which a formulaic resolution directly appealed to CIAC’s subject matter jurisdiction. ACI
sufficed. More pressingly, it was confronted with a state of countered by asserting that sanctioning CECON’s claims
affairs where CECON rendered services to ACI, with was tantamount to violating the terms of their agreement.
neither definitive governing instruments nor a confirmed, It further claimed liability on CECON’s part for
fixed remuneration for its services. Thus, did the CIAC “maintenance and defects,” and for “violation of
Arbitral Tribunal go about the task of ascertaining the sum specifications for materials and workmanship.”
properly due to CECON. ACI and CECON voluntarily submitted themselves to
This task was well within its jurisdiction. This the CIAC Arbitral Tribunal’s jurisdiction. The contending
determination entailed the full range of subjects expressly parties’ own volition is at the inception of every
stipulated by Section 4 of the Construction Industry construction arbitration proceeding.144 Common sense
Arbitration Law to be within the CIAC’s subject matter dictates that by the parties’ voluntary submission, they
jurisdiction. acknowledge that an arbitral tribunal constituted under the
CIAC has full competence to rule on the dispute presented
to it. They concede this not only with respect to the literal
233 issues recited in their terms of reference, as ACI
VOL. 836, AUGUST 9, 2017 233 suggests,145 but also with respect to their necessary
incidents. Accordingly, in delineating the authority of
CE Construction Corporation vs. Araneta Center,
arbitrators, the CIAC Rules of Procedure speak not only of
Inc.
the literally recited issues but also of “related matters”:
4. SectionJurisdiction.—. . . . _______________
The jurisdiction of the CIAC may include but is not
limited to violation of specifications for materials and
144 Exec. Order No. 1008, Section 4 states, among
others, that, “the parties to a dispute must agree to submit Two (2) guiding principles steered the CIAC Arbitral
the same to voluntary arbitration.” Tribunal in going about its task. First was the basic matter
145 Rollo, pp. 6454-6461. of fairness. Second was effective dispute resolution or the
overarching principle of arbitration as a mechanism
relieved of the encumbrances of litigation. In Section 1.1 of
the CIAC Rules of Procedure:
234 1.1. SECTIONStatement of policy and objectives.—It is
234 SUPREME COURT REPORTS the policy and objective of these Rules to provide a fair and
ANNOTATED expeditious resolution of construction disputes as an
CE Construction Corporation vs. Araneta Center, alternative to judicial proceedings, which may restore the
Inc. disrupted harmonious and friendly relationships between or
21.3. SECTIONExtent of power of arbitrator.—The among the parties. (Emphasis supplied)
Arbitral Tribunal shall decide only such issues and related
_______________
matters as are submitted to them for adjudication. They
have no power to add, to subtract from, modify, or amend 146 CIAC RULES OF PROCEDURE, Sec. 1.3.
any of the terms of the contract or any supplementary
agreement thereto, or any rule, regulation or policy
promulgated by the CIAC.
235
VOL. 836, AUGUST 9, 2017 235
To otherwise be puritanical about cognizable issues
would be to cripple CIAC arbitral tribunals. It would CE Construction Corporation vs. Araneta Center,
potentially be to condone the parties’ efforts at tying the Inc.
hands of tribunals through circuitous, trivial recitals that CECON’s predicament demanded compensation. The
fail to address the complete extent of their claims and precise extent may yet to have been settled; yet, as the
which are ultimately ineffectual in dispensing an exigencies that prompted CECON to request for arbitration
exhaustive and dependable resolution. Construction unraveled, it became clear that it was not for the CIAC
arbitration is not a game of guile which may be left to Arbitral Tribunal to turn a blind eye to CECON’s just
ingenious textual or technical acrobatics, but an endeavor entitlement to compensation.
to ascertain the truth and to dispense justice “by every and Jurisprudence has settled that even in cases where
all reasonable means without regard to technicalities of law parties enter into contracts which do not strictly conform to
or procedure.”146 standard formalities or to the typifying provisions of
nominate contracts, when one renders services to another,
IV.B the latter must compensate the former for the reasonable
value of the services rendered. This amount shall be fixed 236
by a court. This is a matter so basic, this Court has once 236 SUPREME COURT REPORTS
characterized it as one that “springs from the fountain of ANNOTATED
good conscience”: CE Construction Corporation vs. Araneta Center,
As early as 1903, in Perez v. Pomar, this Court ruled Inc.
that where one has rendered services to another, and these
Consistent with the Construction Industry Arbitration
services are accepted by the latter, in the absence of proof
Law’s declared policy,148 the CIAC Arbitral Tribunal was
that the service was rendered gratuitously, it is but just
specifically charged with “ascertain[ing] the facts in each
that he should pay a reasonable remuneration therefore
case by every and all reasonable means.”149 In discharging
because “it is a well-known principle of law, that no one
its task, it was permitted to even transcend technical rules
should be permitted to enrich himself to the damage of
on admissibility of evidence.150
another.” Similary in 1914, this Court declared that in this
jurisdiction, even in the absence of statute, “. . . under the
IV.C
general principle that one person may not enrich himself at
The reality of a vacuum where there were no definite
the expense of another, a judgment creditor would not be
contractual terms, coupled with the demands of a “fair and
permitted to retain the purchase price of land sold as the
expeditious resolution” of a dispute centered on contractual
property of the judgment debtor after it has been made to
interpretation, called into operation Article 1371 of the
appear that the judgment debtor had no title to the land
Civil Code:
and that the purchaser had failed to secure title thereto . . .”
In order to judge the intention of the contracting parties,
The foregoing equitable principle which springs from the
1371. Article their contemporaneous and subsequent acts
fountain of good conscience are applicable to the case at
shall be principally considered. (Emphasis supplied)
bar.147

_______________
Article 1379 of the Civil Code invokes principles from
147 Pacific Merchandising Corporation v. Consolacion the Revised Rules on Evidence. By invoking these
Insurance & Surety Co., Inc., 165 Phil. 543, 553-554; 73 principles, Article 1379 makes them properly applicable in
SCRA 564, 572-573 (1976) [Per J. Antonio, Second every instance of contractual interpretation, even those
Division], citing Perez v. Pomar, 2 Phil. 682 (1903) where the need for interpretation arises outside of court
[Per J.Torres, En Banc]; and Bonzon v. Standard Oil Co. proceedings:
and Osorio, 27 Phil. 141 (1914) [Per J. Carson, First The principles of interpretation stated in Rule 123 of the
Division]. (Fn 16) Rules of Court shall likewise be observed in the
construction of contracts. 1379. Article

_______________
148 Exec. Order No. 1008, Sec. 2.
149 CIAC RULES OF PROCEDURE, Rule 1, Sec. 1.3 Within its competence and in keeping with basic
provides: principles on contractual interpretation, the CIAC Arbitral
1.3. SectionJudicial rules not controlling.—In any Tribunal ascertained the true and just terms governing ACI
arbitration proceedings under these Rules, the judicial and CECON. Thus, the CIAC Arbitral Tribunal did not
rules of evidence need not be controlling, and it is the spirit conjure its own contractual creature out of nothing. In
and intention of these Rules to ascertain the facts in each keeping with this, the CIAC Arbitral Tribunal found it
case by every and all reasonable means without regard to proper to sustain CECON’s position. There having been no
technicalities of law or procedure. meeting of minds on the contract sum, the amount due to
150 Id. CECON became susceptible to reasonable adjustment,
subject to proof of legitimate costs that CECON can adduce.

V
237
VOL. 836, AUGUST 9, 2017 237 Unravelling the CIAC Arbitral Tribunal’s competence
CE Construction Corporation vs. Araneta Center, and establishing how it acted consistent with law resolves
Inc. the principal legal issue before us. From this threshold, the
As with Article 1371, therefore, the following principles inquiry transitions to the matter of whether or not the
from the Revised Rules on Evidence equally governed the conclusions made by the CIAC Arbitral Tribunal were
CIAC Arbitral Tribunal’s affairs: warranted.
Interpretation of Documents 4.

12. SectionInterpretation according to intention; general 238


and particular provisions.—In the construction of an 238 SUPREME COURT REPORTS
instrument, the intention of the parties is to be pursued; and ANNOTATED
when a general and a particular provision are inconsistent, CE Construction Corporation vs. Araneta Center,
the latter is paramount to the former. So a particular intent Inc.
will control a general one that is inconsistent with it. They were. Far from being capricious, the CIAC Arbitral
13. SectionInterpretation according to circumstances.— Tribunal’s conclusions find solid basis in law and evidence.
For the proper construction of an instrument, the
circumstances under which it was made, including the V.A
situation of the subject thereof and of the parties to it, may
be shown, so that the judge may be placed in the position of The tender documents may have characterized the
those whose language he is to interpret. contract sum as fixed and lump sum, but the premises for
this arrangement have undoubtedly been repudiated by Inc.
intervening circumstances. mediately deliver the project site to CECON so that
When CECON made its offer of P1,540,000,000.00, it CECON may commence excavation, the most basic task in
proceeded from several premises. First, ACI would timely setting up a structure’s foundation. ACI also failed to
respond to the representations made in its bid. Second, produce definite instruments articulating its agreement
CECON could act on the basis of prices prevailing with CECON, the final contract documents.
then. Third, the subject matter of the contract was the With the withering of the premises upon which a lump
entire expanse of design and construction covering all sum, fixed price arrangement would have been founded,
elements disclosed in the tender documents, nothing more such an arrangement must have certainly been negated:
and nothing less. Fourth, the basic specifications for [T]he contract is fixed and lump sum when it was tendered
designing and building the Gateway Mall, as stated in the and contracted as a design and construct package. The
tender documents, would remain consistent. Lastly, ACI contract scope and character significantly changed when
would timely deliver on its concomitant obligations. the design was taken over by the Respondent. At the time
Contrary to CECON’s reasonable expectations, ACI of the negotiation and agreement of the amount of Php1.54
failed to timely act either on CECON’s bid or on those of its billion, there were no final plans for the change to
competitors. Negotiations persisted for the better part of structural steel, and all the [mechanical, electrical and
two (2) calendar years, during which the quoted contract plumbing] drawings were all schematics.
sum had to be revised at least five (5) times. The object of [I]t is apparent to the Tribunal that the quantity and
the contract and CECON’s scope of work widely varied. materials at the time of the P1.54B agreement are
There were radical changes like the addition of an entire significantly different from the original plans to the finally
office tower to the project and the change in the project’s implemented plans. The price increases in the steel
structural framing. There was also the undoing of CECON’s products and cement were established to have already
freedom to design, thereby rendering it entirely dependent increased by 11.52% and by P5.00 per bag respectively by
on configurations that ACI was to unilaterally resolve. It January 21, 2003. The Tribunal finds agreement with the
turned out that ACI took its time in delivering construction Claimant that it is fairer to award the price increase.
drawings to CECON, with almost 38% of construction ....
drawings being delivered after the intended completion It should also be mentioned that Respondent had
date. There were many other less expansive changes to the changed the scope and character of the agreement. First,
project, such as ACI’s fickleness on which equipment it there were major changes in the plans and specifications.
would acquire by itself. ACI even failed to im- Originally, the contract was for design and construct. The
design was deleted from the scope of the Claimant. It was
changed to a straight construction contract. As a straight
239 construction contract, there were no final plans to speak of
VOL. 836, AUGUST 9, 2017 239 at the time of the instructions to change. Then there was a
CE Construction Corporation vs. Araneta Center, verbal change to structural steel frame. No plans were
available upon this instruction to change. Next, the Contrary to ACI’s oft-repeated argument,152 the CIAC
[mechanical, electrical and plumbing] plans were all Arbitral Tribunal correctly found that ACI had gained no
schematics. It is therefore expected that changes solace in statutory provisions on the immutability of
prices stipulated between a contractor and a landowner.
Article 1724 of the Civil Code reads:
The contractor who undertakes to build a structure or
240 any other work for a stipulated price, in conformity with
240 SUPREME COURT REPORTS plans and specifications agreed upon with the landowner,
ANNOTATED can neither withdraw from the contract nor demand an
CE Construction Corporation vs. Araneta Center, increase in the price on account of the higher cost of labor
Inc. or materials, save when there has been a change in the
of plans are forthcoming, and that changes in costs would plans and specifications, provided: 1724. Article
follow . . .
_______________
....
It has been established that the original tender, request 151 Rollo, pp. 3812-3813 and 3884.
for proposal and award is for a design and construct 152 Id., at pp. 6483-6487.
contract. The contract documents are therefore associated
for said system of construction. When Respondent decided
to change and take over the design, such as the change from
concrete to structural steel framing, “takeout” equipment 241
from the contract and modify the [mechanical, electrical VOL. 836, AUGUST 9, 2017 241
and plumbing w]orks, the original scope of work had been CE Construction Corporation vs. Araneta Center,
drastically changed. To tie down the Claimant to the unit
Inc.
prices for the proposal for a different scope of work would be
Such change has been authorized by the proprietor in
grossly unfair. This Tribunal will hold that unit price
writing; and (1)
adjustment could be allowed but only for change orders that
were not in the original scope of work, such as the change The additional price to be paid to the contractor has
been determined in writing by both parties. (2)
order from concrete to structural framing, the [mechanical,
electrical and plumbing w]orks, [schematic drawings to
construction drawings] and the Miscellaneous Change Article 1724 demands two (2) requisites in order that a
Order Works.151 price may become immutable: first, there must be an actual,
stipulated price; and second, plans and specifications must
have definitely been agreed upon.
V.B
Neither requisite avails in this case. Yet again, ACI is Respondent has agreed to the price increase in structural
begging the question. It is precisely the crux of the steel and after some negotiation paid the agreed amount.
controversy that no price has been set. Article 1724 does not Respondent also agreed to the price increase in the
work to entrench a disputed price and make it sacrosanct. reinforcing bars and instructed the Claimant to bill it
Moreover, it was ACI which thrust itself upon a situation accordingly. To the Tribunal, such action is an
where no plans and specifications were immediately agreed acknowledgment of the price increase. Respondent can
upon and from which no deviation could be made. It was make the case that said agreement is conditional, i.e., the
ACI, not CECON, which made, revised, and deviated from Complaint must be withdrawn. To the Tribunal, the
designs and specifications. conditionality falls both ways. The Claimant has as much
interest to agree to a negotiated price increase so that it can
V.C collect payments for the claims. The conditionalities do not
change the basis for the quantity and the amount. The
The CIAC Arbitral Tribunal also merely held ACI to process of the negotiation has arrived at the price difference
account for its voluntarily admitted adjustments. The CIAC and quantities. The Tribunal finds the process in arriving
Rules of Procedure permit deviations from technical rules at the Joint Manifestation, a fair determination of the unit
on evidence, including those on admissions. Still, common price increase. This holding will render the discussions on
sense dictates that the principle that “[t]he act, declaration Exhibit JJJJ, and the demand of the burden of proof of the
or omission of a party as to a relevant fact may be given in Respondent superfluous.154
evidence against him”153 must equally hold true in
administrative or quasi-judicial proceedings as they do in
court actions. Certainly, each must be held to account for This absurdity is so patent that the Court of Appeals
his or her own voluntary declarations. It would have been was still compelled to uphold awards premised on ACI’s
plainly absurd to disregard ACI’s reneging on its own admissions, even as it reversed the CIAC Arbitral
admissions: Tribunal’s decision on the primordial issue of the
_______________ characterization of the contractual arrangement between
CECON and ACI:
153 RULES OF COURT, Rule 130, Sec. 26. As stated, the contract between [ACI] and CECON has
not been amended or revised. The Arbitral Tribunal had no
power to amend the contract to provide that there be
allowed price and/or cost adjustment removing the express
242 stipulation that the Project is for a lump sum or fixed price
242 SUPREME COURT REPORTS consideration. Accordingly, this Court removes the award
ANNOTATED for additional costs spent by CECON on cement and
CE Construction Corporation vs. Araneta Center, formworks due to price increases or removing the award for
Inc. these items in the total amount of P5,598,338.20. Since
CECON is not entitled to its claim for price increase, it is enrichment enabled by the gradual wilting of what should
likewise not entitled to the award of the interest rate of have been a reliable contractual relation. Basic decency
6% per annum. impels this Court to not give in to ACI’s advances and
instead sustain the CIAC Arbitral Tribunal’s conclusion
_______________ that the amount due to CECON has become susceptible to
reasonable adjustment.
154 Rollo, p. 3812.
VI

The Arbitral Tribunal’s award must be reinstated.


243
VOL. 836, AUGUST 9, 2017 243
VI.A
CE Construction Corporation vs. Araneta Center,
Inc. With the undoing of the foundation for the Court of
With regard however to the additional costs for the Appeal’s fallacious, circular reasoning, its monetary awards
rebars due to price increases, this Court finds that CECON must also necessarily give way to the reinstatement of the
is entitled to the amount of P10,266,628.00 representing CIAC Arbitral Tribunal’s awards.
the additional costs spent by CECON for rebars due to price _______________
increases, notwithstanding the Arbitral Tribunal’s excess of
jurisdiction in amending the contract between the parties 155 Id., at pp. 38-39.
because [ACI] and CECON had in fact agreed that CECON
was entitled to such an amount and that [ACI] would pay
the same. This agreement was made in the parties’ Joint
Manifestation of Compliance dated March 30, 2004 which 244
they filed with the Arbitral Tribunal (“Joint 244 SUPREME COURT REPORTS
Manifestation”).155 ANNOTATED
CE Construction Corporation vs. Araneta Center,
Inc.
No extraordinary technical or legal proficiency is
required to see that it would be the height of absurdity and The inevitable changes borne by ACI’s own trifling
actions justify, as a consequence, compensation for cost
injustice to insist on the payment of an amount the
adjustments and the ensuing change orders, additional
consideration of which has been reduced to a distant
overhead costs for the period of extension, extended
memory. ACI’s invocation of Article 1724 is useless as the
coverage for contractor’s all risk insurance, and attendance
premises for its application are absent. ACI’s position is an
invitation for this Court to lend its imprimatur to unjust fees for auxiliary services to subcontractors whose functions
were also necessarily prolonged. ACI’s frivolity on the
acquisition of elevators, escalators, chillers, generator sets, VOL. 836, AUGUST 9, 2017 245
indoor substations, cooling towers, pumps, and tanks also CE Construction Corporation vs. Araneta Center,
vindicates compensation for the works that remained under Inc.
CECON’s account. ACI’s authorship of the causes of delay sanctioned by the statutory framework of contractual
supports time extensions favoring CECON and, conversely, interpretation within which the CIAC Arbitral Tribunal
discredits liquidated damages benefitting ACI. operated. Thus, the following principles governed the
This Court upholds the Arbitral Tribunal’s awards on interpretation of the change orders, requests, and other
each of the items due to CECON, as well as on its findings communications, which had effectively been surrogates of a
relating to CECON’s countervailing liabilities.
single definite instrument executed by the parties.
In fulfilling its task, the CIAC Arbitral Tribunal was
From the Civil Code:
equipped with its technical competence, adhered to the Words which may have different significations shall be
rigors demanded by the CIAC Rules of Procedure, and was understood in that which is most in keeping with the
endowed with the experience of exclusively presiding over
nature and object of the contract. 1375. Article
19 months of arbitral proceedings, examining object and The usage or custom of the place shall be borne in mind in
documentary evidence, and probing witnesses. the interpretation of the ambiguities of a contract, and shall
fill the omission of stipulations which are ordinarily
VI.B established. 1376. Article
Within the CIAC Arbitral Tribunal’s technical
competence was its reference to prevailing industry From the Revised Rules on Evidence, the following have
practices, a much-bewailed point by ACI.156 This reference been made applicable even outside regular litigation by
was made not only desirable but even necessary by the Article 1379 of the Civil Code:
absence of definitive governing instruments. Moreover, this 14. SectionPeculiar signification of terms.—The terms of
reference was made feasible by the CIAC Arbitral a writing are presumed to have been used in their primary
Tribunal’s inherent expertise in the construction industry. and general acceptation, but evidence is admissible to show
This reference was not only borne by practical that they have a local, technical, or otherwise peculiar
contingencies and buttressed by recognized proficiency, it signification, and were so used and understood in the
was also particular instance, in which case the agreement must be
_______________ construed accordingly.
....
156 Id., at pp. 5894-5895. 19. SectionInterpretation according to usage.—An
instrument may be construed according to usage, in order
to determine its true character.157(Emphasis supplied)
245
Equally availing is the following principle. This is observed, tested, and propounded questions to each of the
especially true of the remuneration due to CECON, witnesses. Having been constituted solely and precisely for
considering the purpose of resolving the dispute between ACI and
_______________ CECON for 19 months, the CIAC Arbitral Tribunal devoted
itself to no other task than resolving that controversy. This
157 RULES OF COURT, Rule 130, Secs. 14 and 19. Court has the benefit neither of the CIAC Arbitral
Tribunal’s technical competence nor of its irreplaceable
experience of hearing the case, scrutinizing every piece of
evidence, and probing the witnesses.
246 True, the inhibition that impels this Court admits of
246 SUPREME COURT REPORTS exceptions enabling it to embark on its own factual inquiry.
ANNOTATED Yet, none of these exceptions, which are all anchored on
CE Construction Corporation vs. Araneta Center, considera-
Inc. _______________
that stipulations for remuneration are devised for the
benefit of the person rendering the service: 158 Id., Sec. 17.
17. SectionOf two constructions, which preferred.—When 159 Rollo, p. 3771. Exhibits were so voluminous,
the terms of an agreement have been intended in a different markings such as “BBBBB” and “MMMMM” were
sense by the different parties to it, that sense is to prevail necessary.
against either party in which he supposed the other
understood it, and when different constructions of a
provision are otherwise equally proper, that is to be taken
247
which is the most favorable to the party in whose favor the
VOL. 836, AUGUST 9, 2017 247
provision was made.158
CE Construction Corporation vs. Araneta Center,
Inc.
VI.C tions of the CIAC Arbitral Tribunal’s integrity and not
merely on mistake, doubt, or conflict, is availing.
In appraising the CIAC Arbitral Tribunal’s awards, it is This Court finds no basis for casting aspersions on the
not the province of the present Rule 45 Petition to supplant integrity of the CIAC Arbitral Tribunal. There does not
this Court’s wisdom for the inherent technical competence appear to have been an undisclosed disqualification for any
of and the insights drawn by the CIAC Arbitral Tribunal of its three (3) members or proof of any prejudicial
throughout the protracted proceedings before it. The CIAC misdemeanor. There is nothing to sustain an allegation
Arbitral Tribunal perused each of the parties’ voluminous that the parties’ voluntarily selected arbitrators were
pieces of evidence.159 Its members personally heard, corrupt, fraudulent, manifestly partial, or otherwise
abusive. From all indications, it appears that the CIAC Without a showing of any of the exceptional
Arbitral Tribunal extended every possible opportunity for circumstances justifying factual review, it is neither this
each of the parties to not only plead their case but also to Court’s business nor in this Court’s competence to
arrive at a mutually beneficial settlement. This Court has pontificate on technical matters. These include things such
ruled, precisely, that the arbitrators acted in keeping with as fluctuations in prices of materials from 2002 to 2004, the
their lawful competencies. This enabled them to come up architectural and engineering consequences — with their
with an otherwise definite and reliable award on the ensuing financial effects — of shifting from reinforced
controversy before it. concrete to structural steel, the feasibility of rectification
Inventive, hair-splitting recitals of the supposed works for defective installations and fixtures, the viability
imperfections in the CIAC Arbitral Tribunal’s execution of of a given schedule of rates as against another, the audit of
its tasks will not compel this Court to supplant itself as a changes for every schematic drawing as revised by
fact-finding, technical expert. construction drawings, the proper mechanism for
ACI’s refutations on each of the specific items claimed by examining discolored and mismatched tiles, the minutiae of
CECON and its counterclaims of sums call for the point by installing G.I. sheets and sealing cracks with epoxy
point appraisal of work, progress, defects and rectifications, sealants, or even unpaid sums for garbage collection.
and delays and their causes. They are, in truth, invitations The CIAC Arbitral Tribunal acted in keeping with the
for this Court to engage in its own audit of works and law, its competence, and the adduced evidence; thus, this
corresponding financial consequences. In the alternative, its Court upholds and reinstates the CIAC Arbitral Tribunal’s
refutations insist on the application of rates, schedules, and monetary awards.
other stipulations in the same tender documents, copies of
which ACI never adduced and the efficacy of which this VII
Court has previously discussed to be, at best, doubtful.
This Court now rectifies the error made by the Court of It does not escape this Court’s attention that this
Appeals. By this rectification, this Court does not open the controversy has dragged on for more than 13 years since
doors to an inordinate and overzealous display of this CECON initially sought to avail of arbitration.
Court’s authority as a final arbiter. The CIAC Arbitral Tribunal noted that ACI consumed a
total of 840 days filing several motions and manifestations,
including at least eight (8) posturings at pursuing
248 settlement.160 It added, however, that ACI repeatedly failed
248 SUPREME COURT REPORTS to respond to CECON’s claims during meetings thereby
ANNOTATED constraining CECON to file motions to proceed after
CE Construction Corporation vs. Araneta Center, repeatedly being dangled hope of an early resolution.161 It
Inc. appeared that ACI was more interested in buying time than
in effecting a consummate voluntary settlement.
_______________
160 Id., at p. 4027. These faults began as soon as bidders responded to ACI’s
161 Id., at pp. 4027-4028. invitation. In CECON’s case, its communicated time for the
validity of its offer lapsed without confirmation from ACI.
ACI only verbally responded and only after CECON’s
communicated timeframe. It told CECON to commence
249 excavation works but failed to completely deliver the project
VOL. 836, AUGUST 9, 2017 249 site until
CE Construction Corporation vs. Araneta Center, _______________
Inc.
The CIAC Arbitral Tribunal’s October 25, 2006 Decision 162 Id., at p. 6127.
should have long brought this matter to an end. This Court 163 Id., at p. 6656.
does not fault ACI for availing of remedies. Yet, this Court
also notes that even in proceedings outside of the CIAC
Arbitral Tribunal, ACI seems to not have been sufficiently
250
conscientious of time.
250 SUPREME COURT REPORTS
In this Court alone, ACI sought extensions to file its
Comment no less than five (5) times.162 It sought several ANNOTATED
other extensions in the filing of its Memorandum.163 CE Construction Corporation vs. Araneta Center,
It also does not escape this Court’s attention that while Inc.
ACI’s arguments have perennially pleaded the supposed five (5) months later. It engaged in protracted negotiations,
primacy and immutability of stipulations originally never confirming acceptance until the tenth month, after
articulated in the tender documents, it never bothered to bidders had submitted their offers. By then, ACI’s supposed
annex any of these documents either to its Comment or to acceptance could not even identify CECON’s most recent
its Memorandum. Without these and other supporting quoted price. It undertook to process and deliver formal
materials, this Court is left in the uneasy predicament of documents, yet this controversy already reached this Court
merely relying on ACI’s self-stated assertions and without and not a single page of those documents has seen the light
means of verifying even the syntax of its citations. of day. It has repeatedly added and taken from CECON’s
While presumptions of good faith may be indulged, the scope of works but vigorously opposed adjustments that
repercussions of ACI’s vacillation cannot be denied. should have at least been given reasonable consideration,
Even if this Court were to ignore the delays borne by only to admit and partially stipulate on them. In taking
ACI’s procedural posturing, this Court is compelled to upon itself the task of designing, it took its time in
hearken to ACI’s original faults. These are, after all, what delivering as many as 1,675 construction drawings to
begot these proceedings. These are the same original faults CECON, more than 600 of which were not delivered until
which so exasperated CECON; it was left with no recourse well after the project’s intended completion date.
but to seek the intervention of CIAC.
This Court commenced its discussion by underscoring Legal interest at the rate of six percent (6%) per
that arbitration primarily serves the need of expeditious annum is imposed on the award from the finality of this
dispute resolution. This interest takes on an even greater Decision until its full satisfaction.
urgency in the context of construction projects and the Costs against respondent.
national interest so intimately tied with them. ACI’s actions SO ORDERED.
have so bogged down its contractor. Nearing 13 years after Carpio (Chairperson), Peralta, Mendoza andMartires,
the Gateway Mall’s completion, its contractor has yet to be JJ., concur.
fully and properly compensated. Not only have ACI’s
actions begotten this dispute, they have hyperextended Petition granted, judgment and amended decision
arbitration proceedings and dragged courts into the reversed and set aside. That of CIAC Arbitral Tribunal
controversy. The delays have virtually bastardized the reinstated.
hopes at expeditious and effective dispute resolution which
Note.—The jurisdiction of the Construction Industry
are supposedly the hallmarks of arbitration proceedings.
Arbitration Commission (CIAC) is derived from law. It is
For these, in addition to sustaining each of the awards
broad enough to cover any dispute arising from, or
due to CECON arising from the facets of the project, this
connected with construction contracts, whether these
Court also sustains the CIAC Arbitral Tribunal’s award to
involve mere contractual money claims or execution of the
CECON of arbitration costs. Further, this Court imposes
works. (Philippine Race Horse Trainer’s Association, Inc. vs.
upon respondent Araneta Corporation, Inc. the burden of
Piedras Negras Construction and Development Corporation,
bearing the costs of what have mutated into a full-fledged
775 SCRA 631 [2015])
litigation before this Court and the Court of Appeals.
——o0o——
251 © Copyright 2019 Central Book Supply, Inc. All rights
VOL. 836, AUGUST 9, 2017 251 reserved.
CE Construction Corporation vs. Araneta Center,
Inc.
WHEREFORE, the Petition is GRANTED. The
assailed April 28, 2008 Decision and July 1, 2010 Amended
Decision of the Court of Appeals in C.A.-G.R. S.P. No. 96834
are REVERSED and SET ASIDE. The Construction
Industry Arbitration Commission Arbitral Tribunal’s
October 25, 2006 Decision in CIAC Case No. 01-2004
is REINSTATED.
December 7, 2016. G.R. No. 192948.* the Civil Code when (1) a person is unjustly benefited, and
(2) such benefit is derived at the expense of or with
B.F. CORPORATION and HONORIO PINEDA, damages to another. The principle of unjust enrichment
petitioners, vs. FORM-EZE SYSTEMS, INC., respondent. essentially contemplates payment when there is no duty to
pay, and the person who receives the payment has no right
Construction Contracts; Cases in which Factual to receive it. By requiring BFC to pay the full contract price
Finding of Construction Arbitrators May be Reviewed by the when it only supplied deckforms which covered
Court.—Factual findings of construction arbitrators may be
reviewed by the Court in cases where: 1) the award was _______________
procured by corruption, fraud or other undue means; (2)
there was evident partiality or corruption of the arbitrators * THIRD DIVISION.
or any of them; (3) the arbitrators were guilty of misconduct
in refusing to hear evidence pertinent and material to the
controversy; (4) one or more of the arbitrators were
disqualified to act as such under Section nine of Republic 156
Act (R.A.) No. 876 and willfully refrained from disclosing 156 SUPREME COURT REPORTS
such disqualifications or of any other misbehavior by which ANNOTATED
the rights of any party have been materially prejudiced; (5) B.F. Corporation vs. Form-Eze Systems, Inc.
the arbitrators exceeded their powers, or so imperfectly only 5,149.85 contact square meters of formworks, the
executed them, that a mutual, final and definite award CIAC Arbitral Tribunal is essentially unjustly giving
upon the subject matter submitted to them was not made; unwarranted benefit to Form-Eze by allowing it to earn
(6) when there is a very clear showing of grave abuse of more than it legally and contractually deserved. It is also
discretion resulting in lack or loss of jurisdiction as when a worth mentioning that Form-Eze had in fact only been
party was deprived of a fair opportunity to present its claiming for the contact area where its equipment was used.
position before the Arbitral Tribunal or when an award is Same; Contracts; Reformation of Contracts;
obtained through fraud or the corruption of arbitrators; (7) Reformation is a remedy in equity, whereby a written
when the findings of the Court of Appeals are contrary to instrument is made or construed so as to express or conform
those of the CIAC, and (8) when a party is deprived of to the real intention of the parties, where some error or
administrative due process. mistake has been committed.—An action for reform a
Civil Law; Unjust Enrichment; The principle of unjust contract is grounded on Article 1359 of the New Civil Code
enrichment essentially contemplates payment when there is which provides: ARTICLE 1359. When, there having been a
no duty to pay, and the person who receives the payment has meeting of the minds of the parties to a contract, their true
no right to receive it.—To award the full contract price to intention is not expressed in the instrument purporting to
Form-Eze in Contract No. 1 is tantamount to unjust embody the agreement, by reason of mistake, fraud,
enrichment. There is unjust enrichment under Article 22 of inequitable conduct or accident, one of the parties may ask
for the reformation of the instrument to the end that such dispute arises before or after the completion of the contract,
true intention may be expressed. x x x x Reformation is a or after the abandonment or breach thereof. Moreover, the
remedy in equity, whereby a written instrument is made or party involved must agree to submit to voluntary
construed so as to express or conform to the real intention arbitration. In other words, anyone who is not a party to
of the parties, where some error or mistake has been the contract in his personal capacity is not subject to the
committed. In granting reformation, the remedy in equity is jurisdiction of the CIAC. In this case, Pineda signed the
not making a new contract for the parties, but establishing challenged contracts in his capacity as President of BFC.
and perpetuating the real contract between the parties There is no indication that he voluntarily submitted himself
which, under the technical rules of law, could not be as a party to the arbitration case. In fact, he has been
enforced but for such reformation. In order that an action consistently contesting his inclusion as a respondent in the
for reformation of instrument may prosper, the following CIAC proceedings. CIAC however considered Pineda as a
requisites must concur: (1) there must have been a meeting joint tortfeasor, thus justifying his joinder as a codefendant.
of the minds of the parties to the contract; (2) the Attorney’s Fees; Under Article 2208 of the Civil Code,
instrument does not express the true intention of the attorney’s fees may, among others, be recovered where
parties; and (3) the failure of the instrument to express the defendant acted in gross and evident bad faith in refusing to
true intention of the parties is due to mistake, fraud, satisfy the plaintiff’s plainly valid, just and demandable
inequitable conduct or accident. claim.—Under Article 2208 of the Civil Code, attorney’s
Construction Industry Arbitration Commission; fees may, among others, be recovered where defendant
Jurisdiction; Section 4 of Executive Order (EO) No. 1008 acted in gross and evident bad faith in refusing to satisfy
vests jurisdiction on Construction Industry Arbitration the plaintiff’s plainly valid, just and demandable claim. We
Commission (CIAC) over disputes arising from, or connected observe that in filing the complaint against BFC, Form-Eze
with, contracts entered into by parties involved in was merely seeking payment for its service under the
construction in the Philippines, whether the dispute arises contract. BFC had admitted to its obligation. The problem
before or after the lies only on the amount to be paid. This is not tantamount
to bad faith.

PETITION for review on certiorari of the decision and


157 resolution of the Court of Appeals.
VOL. 813, DECEMBER 7, 2016 157 The facts are stated in the opinion of the Court.
B.F. Corporation vs. Form-Eze Systems, Inc. Castelo & Associates Law Office for petitioners.
completion of the contract, or after the abandonment or Mendoza, Arzaga-Mendoza for respondent.
breach thereof.—Section 4 of Executive Order No. 1008
vests jurisdiction on CIAC over disputes disputes arising PEREZ,J.:
from, or connected with, contracts entered into by parties
involved in construction in the Philippines, whether the
This petition for review assails the 15 January 2010 agreements were executed by the BFC, represented by its
Decision1 and 13 July 2010 Resolution2 of the Court of President Pineda, and Form-Eze, represented by its
Appeals in President, James W. Franklin. These contracts and their
_______________ salient provisions are provided in the following table:

1 Rollo (Vol. I), pp. 131-151; penned by Associate Justice _______________


Marlene Gonzales-Sison, with Associate Justices Fernanda
Lampas-Peralta and Florito S. Macalino, concurring. 2 Id., at pp. 153-157.
3 Id., at pp. 1596-1600.
4 Id., at p. 161.

158
158 SUPREME COURT REPORTS
ANNOTATED 159
B.F. Corporation vs. Form-Eze Systems, Inc. VOL. 813, DECEMBER 7, 2016 159
C.A.-G.R. S.P. No. 102007 which affirmed the Final Award B.F. Corporation vs. Form-Eze Systems, Inc.
rendered by the Construction Industry Arbitration
Commission (CIAC) Arbitral Tribunal on 7 December 2007.

Factual Antecedents
160
Petitioner B.F. Corporation (BFC) is a corporation 160 SUPREME COURT REPORTS
engaged in general engineering and civil works ANNOTATED
construction. Petitioner Honorio H. Pineda (Pineda) is the B.F. Corporation vs. Form-Eze Systems, Inc.
President of BFC. Respondent Form-Eze Systems, Inc.
(Form-Eze) is a corporation engaged in highway and street
construction. _______________
On 29 August 2006, SM Prime Holdings, Inc. awarded
the contract for general construction of the SM City- 5 Id., at p. 162.
Marikina mall (the Project) to BFC whereby the latter
undertook to supply materials, labor, tools, equipment and
supervision for the complete construction of the Project.3 In
turn, BFC engaged Form-Eze for the lease of formwork 161
system and related equipment for and needed by the VOL. 813, DECEMBER 7, 2016 161
Project. Accordingly, five (5) contracts and two (2) letter-
B.F. Corporation vs. Form-Eze Systems, Inc. _______________

8 Id., at p. 165
_______________ 9 Id., at p. 166.
10 Id., at p. 167.
6 Id., at p. 163.

165
162 VOL. 813, DECEMBER 7, 2016 165
162 SUPREME COURT REPORTS B.F. Corporation vs. Form-Eze Systems, Inc.
ANNOTATED On 30 March 2007, Form-Eze filed a Request for
B.F. Corporation vs. Form-Eze Systems, Inc. Arbitration11 before the CIAC. In its Complaint, Form-Eze
alleged that BFC has an unpaid obligation amounting to
P9,189,024.58; that BFC wanted to renegotiate the
equipment leases; and that it was not complying with the
contractual and supplemental agreements in effect. Form-
163 Eze prayed for the following relief:
VOL. 813, DECEMBER 7, 2016 163 1. [For BFC] to pay the current monthly equipment rentals;
2. Provisions made to guarantee the earned monthly
B.F. Corporation vs. Form-Eze Systems, Inc.
equipment leased amounts are paid timely;
3. To legislate provisions to ensure the lease contracts are
not breached during the construction of the SM
_______________ Marikina Mall;
4. Provisions made to guarantee the performance of [BFC]
7 Id., at p. 164.
for the manufacturing of the shoring equipment
purchased by Form-Eze from BFC;
5. Provisions made to guarantee the return of all Form-Eze
164 equipment when the concrete structure is completed and
164 SUPREME COURT REPORTS all lost and damaged equipment has been paid for by
[BFC]; and
ANNOTATED
6. All cost related to Arbitration.12
B.F. Corporation vs. Form-Eze Systems, Inc.
In its Amended Answer with Counterclaim, BFC sought 3. Under Contract #1, BFC is willing and ready to pay
for reformation of Contract #1 to incorporate a provision Form-Eze the amount of P3,515,003.59, which amount
that BFC shall deduct from said billing the cost of labor shall be deducted from the amount of the latter’s claim.
supplied by it for the fabrication and assembly of the 4. Under Contract #2 BFC is willing and ready to pay
forming system and for the stripping, cleaning, resetting Form-Eze the amount of P675,788.97, which amount
thereof at the rate of P60.00 per man-hour. BFC also shall be deducted from the amount of the latter’s claim.
demanded the refund of P5,773,440.00 as expenses for the 5. BFC admits that it has the obligation to return to Form-
manufacture of additional hardware to complete the 7,000 Eze equipment furnished them under Contracts #1, 2,
square meters of formwork and 3, and all heavy-duty galvanized scaffold frames and
_______________ related accessories, heavy-duty galvanized x-bracing and
adjustable U-heads and base plates fabricated and
11 Id., at p. 158. manufactured by BFC under Contracts #4, 5 and letters
12 Id., at p. 160. dated 5 January 2007.14

The claims15 of the parties are summarized, as follows:


166 _______________
166 SUPREME COURT REPORTS
ANNOTATED 13 Id., at pp. 195-196.
B.F. Corporation vs. Form-Eze Systems, Inc. 14 Id., at pp. 250-251.
15 Id., at pp. 253-254.
required in Contract #1. BFC explained that Form-Eze had
only furnished 4,682.4 square meters of formwork.13

The CIAC appointed a 3-member Arbitral Tribunal 167


(CIAC Arbitral Tribunal), composed of Atty. Custodio O. VOL. 813, DECEMBER 7, 2016 167
Parlade, Atty. Alfredo F. Tadiar and Engineer Romeo C.
B.F. Corporation vs. Form-Eze Systems, Inc.
David, to adjudicate Form-Eze’s claims.
Under the Terms of Reference, the parties made the
following admissions:
1. The existence of five contracts, a memorandum of
agreement and a supplemental contract. The total arbitration fees amounted to P616,393.73.
2. BFC renegotiated Contract #1 but it did not result in a CIAC Arbitral Tribunal was tasked to resolve the
separate written contract. following issues, to wit:
1. Is Claimant entitled to its total claim of P34,284,996.41 6. Is [BFC] #1 entitled to the reformation of Contract #1 to
representing the alleged arrear on equipment rental include a provision that [BFC] #1 shall deduct from
under Contract #1? [Form-Eze’s] billing the cost of labor, helmet and
expenses for x-bracing supplied by it for the
assembly of the form system amounting to P812,791.09,
to deduct from the billing under Contract #2 the cost of
168 labor for the stripping thereof, the costs of petroleum, oil
168 SUPREME COURT REPORTS and lubricant and helmet of the said laborers up to the
ANNOTATED end of the contract in the sum of P1,391,086.02 and from
B.F. Corporation vs. Form-Eze Systems, Inc. the billing under Contract #3, the cost of labor for the
2. Is Claimant entitled to its claim of P5,624,211.03 installation and forming of the built up column forms
representing the alleged arrears under Contract #2? from
3. Is Claimant entitled to its claim of P3,230,500.00
representing the alleged arrears under Contract #3?
4. Is Claimant entitled to its claim of P1,374,408.00
representing the rental fees under Letter dated 5 169
January 2007? VOL. 813, DECEMBER 7, 2016 169
5. Is Claimant entitled to its claim for the reformation of B.F. Corporation vs. Form-Eze Systems, Inc.
the subject Contracts to include the following: June 19, 2007 up to the end of the project in the sum of
a. Contract #1 – Provisions to guarantee the earned P273,240.00?16
monthly equipment leased amounts are paid 7. Is it proper to include Mr. Honorio Pineda as Respondent
timely; No. 2?
b. Contract #1 – Provision to ensure that the lease 8. Does the Arbitral Tribunal have the jurisdiction to award
contracts are not breached during the construction claims that accrued after the filing of the Request for
of the SM Marikina Mall; Arbitration or does the Claimant have a cause of action
c. Contracts #4 and 5 – Provision to guarantee the for claims that accrued during the same period?
performance of [BFC] for the manufacturing of the 9. Who between the parties is entitled to attorney’s fees?
shoring equipment purchased by Form-Eze from 10. Who between the parties should bear the arbitration
BF Corp.; costs?17
d. Contracts #1, 2, 3, 4 and 5 – Provision for [BFC] to
pay for the lost and damaged equipment furnished Final Award by Ciac
them by the [Form-Eze]; and
e. Contract #1 – Provision in the Contract to include On 7 December 2007, the CIAC Arbitral Tribunal
the P75 per contact sq. m. for labor guarantee. rendered a Final Award in favor of Form-Eze. The
dispositive portion reads:
WHEREFORE, award is hereby made in favor of
Claimant and against [BFC], ordering the latter to pay the
former the following amounts: 171
VOL. 813, DECEMBER 7, 2016 171
16 The CIAC Arbitral Tribunal corrected Issue No. 6 in
B.F. Corporation vs. Form-Eze Systems, Inc.
the TOR upon BFC’s motion.
17 Rollo (Vol. I), pp. 252-253. states a cause of action as to claims that accrued
after the filing of the Complaint.
d) All other claims and counterclaims submitted
pursuant to the definition of issues in the Terms of
170 Reference, not otherwise disposed of or resolved
170 SUPREME COURT REPORTS above, are dismissed for lack of merit. All claims
ANNOTATED and counterclaims peripherally discussed in these
proceedings which are outside the scope of the
B.F. Corporation vs. Form-Eze Systems, Inc.
definition of issues in the Terms of Reference are
likewise outside the scope of this Final Award.
On Letter Agreement of January 5, 2008 to December 8, e) The net award in favor of [Form-Eze] amounting to
2007 P28,517,251.67 shall earn interest at the rate of
P560,000.00 6% per annum from the date of this Final Award,
and 12% from the date the Final Award becomes
IN SUM THE FOLLOWING AWARDS ARE MADE: final and executory until the same is fully paid.18
The Tribunal further awards in favor of [Form-Eze] and
against [BFC] and [Pineda] who are ordered, jointly and BFC filed a Motion for Correction of the Final Award.
severally to pay [Form Eze] P300,00.00 as attorney’s fees, Form-Eze asserted that the calculations made on the total
and to indemnify [Form-Eze’s] cost of arbitration paid to quantity of deckforms supplied to be used under Contract
CIAC. No. 1 is erroneous because the quantity of the accessories
The Tribunal likewise disposes of the remaining issues that were delivered together with the loose truss chords and
as follows: assembled trusses that were backloaded were ignored in
a) The claims under Issue Nos. 5 and 6 for reformation the computation. BFC explained that the hardware
of Contracts No. 1, 2, 3, 4 and 5 are denied for lack supplied must be assembled first into deckforms since what
of merit. is actually rented under Contract No. 1 are the deckforms,
b) The inclusion of Mr. Honorio Pineda in the and not the hardware, thus:
Complaint as additional respondent is proper. Evidently, in the computation thereof, the total quantity
c) The Tribunal has jurisdiction over the claims of [Form- of the accessories that were delivered together with the said
Eze] and finds that the Complaint loose truss chords and assembled trusses, both of which are
shown in the same delivery receipts, and the total length of Accordingly, 87 deckforms of 44 ft. in length can not be
the loose truss chords and assembled trusses that were completely assembled from the delivered chords and trusses
backloaded, were not considered and totally ignored. because the quantity of the delivered accessories is
insufficient for the purpose. To be precise, only 53
_______________ deckforms of 44 ft. in length can be completely assembled
out of the total length of the chords and trusses with the
18 Id., at pp. 2157-2159. use of 1,802 pieces of joists and 3,604 pieces of beam
hangers (with an excess of 22 pieces of beam hangers, 710
pieces of joist and 2,720 ft. of chords and trusses) which are
sufficient to provide only 4,441.73 contact sq. m. of
172
formworks.
172 SUPREME COURT REPORTS
To therefore conclude that 87 deckforms of 44 ft. in
ANNOTATED length can be completely assembled with the use of/out of
B.F. Corporation vs. Form-Eze Systems, Inc. 2,512 pieces of joists and 3,626 pieces of beam hangers, is
Needless to state, these accessories, such as joist and an evident miscalculation.
beam hanger, just like the chords and the trusses, are xxxx
component and indispensable parts of a deckform without
which it can not be completely assembled to be used for the
purpose intended. In the case of a deckform 44 ft. in length,
it will need, for it to be completely assembled, 34 pieces of 173
joists and 68 pieces of beam hangers, as shown in the VOL. 813, DECEMBER 7, 2016 173
herewith attached Annex “A” hereof. B.F. Corporation vs. Form-Eze Systems, Inc.
Therefore, to form 87 completely assembled deckforms of Inasmuch as only 3,626 pieces of beam hangers were
44 ft. in length out of/from the delivered chords and trusses, actually delivered, which, when used with the delivered
it will require 2,958 pieces of joist and 5,916 pieces of beam quantity of joists and length of the delivered chords and
hangers. trusses in completely assembling 53 deckforms of 44 ft. in
However, as show in Exhibits “C-9(5),” “C-9(11),” “C- length, is sufficient to provide only 4,441.73 contact sq. m.
9(15),” “C-9(18),” “C-9(21),” “C-9(25),” “C-9(27),” “C-9(30),” of formworks, the minimum rental amount stipulated under
and “C-9(31),” only 2,512 pieces of joists and in Exhibits “C- Contract No. 1 should correspondingly be reduced to only
9(8),” “C-9(15),” “C-9(16),” “C-9(18),” “C-9(21),” “C-9(27),” “C- Php17,989,006.50, less payment of Php7,700,000.00 =
9(32),” “C-9(34),” “C-9(35),” “C-9(37),” “C-9(38),” “C-9(41),” Php10,829,006.50 as the net amount of rent due the
“C-9(35),” “C-9(38),” “C-9(40),” and “C-9(41),” only 3,626 Claimant thereunder, as shown in the herewith attached
pieces of beam hangers, the very documents on which this Annex “B” hereof.
Commission/Tribunal anchored its finding now sought to be On the same ground, the minimum contact amount
corrected, were actually delivered by the Claimant. stipulated under Contract No. 2 should also be
proportionately reduced to Php3,997,557.00, less payment liable to pay rent to the [Form-Eze] under Contract Nos. 1,
of Php990,000.00 + cost of labor of Php60,000.00 = 2, and 3 even for portions where the latter’s supplied
Php2,947,557.00 as the net amount due the Claimant formwork system were not used.
thereunder.19
II.

The CIAC Arbitral Tribunal denied the motion Whether or not the Court of Appeals committed a
prompting BFC to file a petition for review before the Court reversible error in affirming the CIAC’s conclusion that
of Appeals. [Form-Eze] was able to supply BFC with such quantity of
While the case was pending before the Court of Appeals, deckforms sufficient to provide the stipulated 7,000 contact
Form-Eze filed a Motion with Leave to Direct BFC to return square meter of formworks as to entitle said [Form-Eze] to
pieces of equipment on 14 July 2009. the stipulated minimum contract rental price of
On 15 January 2010, the Court of Appeals dismissed the Php28,350,000.00 under Contract No. 1 and consequently to
petition for lack of merit. The Court of Appeals heavily Php6,300,000.00 under Contract No. 2, when, based on the
relied on factual findings of the CIAC Arbitral Tribunal. quantity of the delivered accessories, which are component
parts of deckform system, but which the CIAC totally
The Petition ignored, [Form-Eze] can only provide 4,441.73 contact
BFC filed a motion for reconsideration but it was denied square meters of formworks that will entitle it to only
by the Court of Appeals in a Resolution dated 13 July 2010. Php17,989,006.05 and Php3,997,557.00, respectively
Hence, the present petition. BFC, in its Memorandum, thereunder.
raised the following issues for our resolution:
_______________ III.
19 Id. (Vol. II), pp. 2179-2181. Whether or not the Court of Appeals committed
reversible error in affirming the CIAC’s ruling that [Form-
Eze] is entitled to two-thirds of the stipulated minimum
contract amount of Php3,230,500.00 or Php2,153,666.67
174
under Contract No. 3, considering that CIAC did not state
174 SUPREME COURT REPORTS
the factual and legal basis of said ruling and despite its
ANNOTATED contrary factual finding that [Form-Eze] failed to supply
B.F. Corporation vs. Form-Eze Systems, Inc. the minimum required columnforms.
I.
IV.
Whether or not the Court of Appeals committed a
reversible error in affirming the CIAC’s ruling that BFC is
Whether or not the Court of Appeals committed a Whether or not the Court of Appeals committed a
reversible error in affirming the CIAC’s ruling against the reversible error in affirming the CIAC in ordering BFC to
reformation of Contract No. 1 to include a provision that pay rental fees under letter dated 5 January 2007, covering
BFC shall furnish the labor needed by [Form-Eze] in the period from 25 June 2007 to 17 December 2007 in the
assembling the deckforms and that it shall deduct sum total of Php560,000.00 at Php96,000.00 a month, when
therefrom the agreed cost of labor at Php60.00 per man- the acquisition cost of the pieces of u-heads and plates
hour, referred to therein is allegedly only Php96,000.00, and
there is evidence presented to show that these items were
purchased at Php96,000.00 and there is on evidence to
show the prevailing rate of rent for the same items.
175 VII.
VOL. 813, DECEMBER 7, 2016 175 Whether or not the Court of Appeals committed a
B.F. Corporation vs. Form-Eze Systems, Inc. reversible error in affirming the CIAC in ruling that Re-
since it has been the true intention and real agreement of
the parties thereto.
V.
Whether or not the Court of Appeals committed a 176
reversible error in affirming the CIAC when it did not 176 SUPREME COURT REPORTS
deduct the following costs incurred by BFC from the ANNOTATED
minimum contract amounts due: B.F. Corporation vs. Form-Eze Systems, Inc.
(1) under Contract No. 1 for the cost of labor in spondent Pineda can be held as corespondent (in the
assembling the deckforms, the cost of helmets of arbitration case) when he is not a party to the contracts and
said laborers, and the expenses for x-bracing agreements involved in this case, as well as the arbitration
supplied by BFC for the assembly of said forms in agreement, and he did not voluntarily submit himself to
the total amount of Php812,791.09; arbitration in this case.
(2) under Contract No. 2 for the cost of labor in the VIII.
stripping of said deckforms, the cost of petroleum, Whether or not the Court of Appeals committed a
oil and lubricant and helmet up to the end of the reversible error when it ruled that the attorney’s fees and
contract in the sum total of Php1,391,086.02; and cost of arbitration shall be for the account of Petitioners,
(3) under Contract No. 3 for the cost of labor in considering that [Form-Eze] failed to supply the minimum
installing and forming the built up columnforms required equipment under the contracts and when the root
from 25 June 2007 up to the end of the contract in cause of the dispute is the imprecision of the language and
the sum total of Php273,240.00, when BFC is the incompleteness of the contracts and agreements, which
legally entitled thereto. were prepared by the Respondents.20
VI.
BFC prays for a modification of the Final Award to read: the principle that the final award of CIAC may be still be
subject to judicial review, thus:
_______________ To begin, Executive Order No. (EO) 1008, which vests
upon the CIAC original and exclusive jurisdiction over
20 Id., at pp. 3368-3370. disputes arising from, or connected with, contracts entered
into by parties involved in construction in the Philippines,
plainly states that the arbitral award “shall be final and
inappealable except on questions of law which shall be
177 appealable to the Court.” Later, however, the Court, in
VOL. 813, DECEMBER 7, 2016 177 Revised Administrative Circular (RAC) No. 1-95, modified
B.F. Corporation vs. Form-Eze Systems, Inc. this rule, directing that the appeals from the arbitral award
of the CIAC be first brought to the CA on “questions of fact,
law or mixed questions of fact and law.” This amendment
The Court’s Ruling was eventually transposed into the present CIAC Revised
Rules which direct that “a petition for review from a final
The Final Award of CIAC award may be taken by any of the parties within fifteen (15)
is subject to review by the days from receipt thereof in accordance with the provisions
Court of Appeals. of Rule 43 of the Rules of Court.” Notably, the current
_______________ provision is in harmony with the Court’s pronouncement
that ‘‘despite statutory provisions making the decisions of
21 Id. (Vol. I), pp. 123-124. certain administrative agencies ‘final,’ the Court still takes
cognizance of petitions showing want of jurisdiction, grave
abuse of discretion, violation of due process, denial of
substantial justice or erroneous interpretation of the law”
178 and that, in particular, “voluntary arbitrators, by the
178 SUPREME COURT REPORTS nature of their functions, act in a quasi-judicial capacity,
ANNOTATED such that their decisions are within the scope of judicial
B.F. Corporation vs. Form-Eze Systems, Inc. review.”23
BFC first asserts that the Court of Appeals has the
power and the duty to review the factual findings made by _______________
CIAC and that the Court of Appeals should not be bound by
22 716 Phil. 788; 704 SCRA 332 (2013).
the factual findings of the construction arbitrators.
23 Id., at pp. 802-803; pp. 345-346.
The case of Asian Construction and Dev’t. Corp. v.
Sumitomo Corporation22 summarized the development of
While factual findings are not within the purview of a
179 petition for review before this Court, we take exception in
VOL. 813, DECEMBER 7, 2016 179 this
B.F. Corporation vs. Form-Eze Systems, Inc. _______________
Factual findings of construction arbitrators may be
24 IBEX International, Inc. v. Government Service
reviewed by the Court in cases where: 1) the award was
Insurance System, 618 Phil. 304, 312-313; 603 SCRA 306,
procured by corruption, fraud or other undue means; (2)
315 (2009), citing Uniwide Sales Realty and Resources
there was evident partiality or corruption of the arbitrators
Corporation v. Titan-Ikeda Construction and Development
or any of them; (3) the arbitrators were guilty of misconduct
Corporation, 540 Phil. 350, 360-361; 511 SCRA 335, 345-
in refusing to hear evidence pertinent and material to the
346 (2006).
controversy; (4) one or more of the arbitrators were
disqualified to act as such under Section nine of Republic
Act (R.A.) No. 876 and willfully refrained from disclosing
such disqualifications or of any other misbehavior by which 180
the rights of any party have been materially prejudiced; (5) 180 SUPREME COURT REPORTS
the arbitrators exceeded their powers, or so imperfectly
ANNOTATED
executed them, that a mutual, final and definite award
upon the subject matter submitted to them was not made; B.F. Corporation vs. Form-Eze Systems, Inc.
(6) when there is a very clear showing of grave abuse of case on the ground of the appellate court’s refusal to delve
discretion resulting in lack or loss of jurisdiction as when a into the findings of facts of the CIAC Arbitral Tribunal.
party was deprived of a fair opportunity to present its Under Contract No. 1, Form-
position before the Arbitral Tribunal or when an award is Eze was not able to supply
obtained through fraud or the corruption of arbitrators; (7) BFC with deckforms suffi-
when the findings of the Court of Appeals are contrary to cient to provide 7,000 contact
those of the CIAC, and (8) when a party is deprived of square meter of formworks.
administrative due process.24 The CIAC Arbitral Tribunal conducted its own study
While this rule, which limits the scope of the review of and came up with the following findings:
CIAC findings, applies only to the Supreme Court, the The receipted hardware deliveries made by [Form-Eze]
Court of Appeals nonetheless is not precluded from show that the total length of loose truss chords delivered
reviewing findings of facts, it being a reviewer of facts. By was 11,912 lineal feet and the length of the truss chords
conveniently adopting the CIAC’s decision as its own and from the assembled trusses delivered was 2,052 lineal feet
refusing to delve into its factual findings, the Court of or a total available length of trusses of 13,964 lineal feet. By
Appeals had effectively turned a blind eye to the an iterative process of selection and elimination, 175 units
evidentiary facts which should have been the basis for an of 44’ long trusses could be assembled, equivalent to 87
equitable and just award. deckforms of 44 feet in length. The assembled 87-44’
deckforms can provide 7,268.58 square meters of contact BFC considerable labor and eliminate the use of BFC’s light
area, broken down as follows: duty scaffolding underneath and beam. By doing that it will
also speed up the forming operation and save BFC labor.
Contact Area The only light duty scaffolding that BFC will be installing
(%) is that under the girder which supports tremendous loading
during the stressing of the beams prior to it being stressed.
Interior & Near 4,156.89 sq.
= By forming the girder in this manner, [Form-Eze] is not
Column Slabs m. (57.19%)
involved in the tripping or resetting of the girder formwork.
Grid Beams (B- 740.37 sq. m.
= However, [Form-Eze] is has purchased and furnished
1) (10.19%)
Interior Beams 1,663.20 sq. considerable forming hardware and consumables (tie rods,
(B-2)
=
m. (22.88%) pvc sleeves, pvc cones, whaler clips and brackets and wing-
Grid Girders (G- 708.12 sq. m. nuts) which are being used on girders and the beams.
2)
=
(9.74%) [Form-Eze] will give the ownership of this equipment to
7,268.58 sq. BFC and BFC will buy all additional consumables and
Total = hardware (as needed) directly from Comer. In return,
m. (100%)
The resulting contact area of 7,628.58 sq. m. is 3.84% [Form-Eze] will include the contact square meters of
over the 7,000 sq. m. requirement of the contract. But the formwork in the girders in its billing for both the equipment
former figure includes the contact area of girders which lease and for the moving contract.” This letter-contract,
according to [petitioners] should not be included. As shown Exhibit C-12, binds [BFC] to pay Claimant for the girder
in ANNEX “A,” sheets 5 & 6 of 6, the contact area formworks contact area for both Contract No. 1 and
contributed by the girders is only 708.12 sq. m., and if this Contract No. 2.
is deducted from the computed total contact area, Petitioners argued that the formwork of the girder (or
large beam) is independent of the deckform system and so
should not be counted in favor of [Form-Eze]. The Tribunal
does not agree. How could the girder formwork be
181 considered independent from the deckform system when
VOL. 813, DECEMBER 7, 2016 181 both sides of the girder formworks are held stiff together by
B.F. Corporation vs. Form-Eze Systems, Inc. “tie rods, pvc sleeves (to make the tie rods reusable), pvc
the remaining available contact area would be 6,560.46 sq. cones, whaler clips and brackets and wing-nuts” supplied by
m. or 93.72%. The fact, however, is that the noninclusion of the [Form-Eze] and pressed between deckforms preparatory
the contact area provided by the girders would be a to concrete pouring? The girder cannot be considered
violation of the letter-contract dated 8 February 2007, structurally independent of the deck slabs because it is the
paragraph 9 of which provides that: “[Form-Eze] offered to requirement of design and the National Building Code and
install beam hangers and ledger angles in order to support its reference code the
the moment beam from column to column and thereby save
are being used. BFC reiterates that based on the provisions
of Contract No. 1 on the contemporaneous and subsequent
182 acts of the parties, as well as application of principles of
182 SUPREME COURT REPORTS contract interpretation, the inclusion of loose truss chords
ANNOTATED in the computation of the quantity of hardware supplied by
B.F. Corporation vs. Form-Eze Systems, Inc. Form-Eze is an erroneous interpretation by CIAC. BFC also
claims that the CIAC wrongfully included the contact area
American Concrete Institute Code (ACI Code) that the
of girders in the computation of the sufficiency of
girders are to be poured monolithically with the slabs and
_______________
beams up to L/3 or 1/3 of the floor span (the point of
infection and location of the construction joint where the
25 Rollo (Vol. I), pp. 2137-2139.
bending moment is the least or zero), as is clearly shown on
the floor concrete pouring schedule plans.
Conclusion of Tribunal
In view of the above, it is the finding of the Arbitral 183
Tribunal that [Form-Eze] had been able to furnish the VOL. 813, DECEMBER 7, 2016 183
amount of hardware that was sufficient to provide 7,000
B.F. Corporation vs. Form-Eze Systems, Inc.
contact square meters of formwork, all in accordance to
equipment supplied by Form-Eze. BFC contends that the
Contract No. 1. Thus, the remaining question to resolve is
girders are not part of the deckforms contemplated in
the area of the project covered by the formwork equipment
Contract No. 1. BFC offers to compensate Form-Eze to the
in contact square meters.25
extent that its supplied deckforms were used under the
principle of quantum meruit. BFC submits that 4,441.73
BFC accuses the CIAC of coming up with its own biased contact square meters or 63.45% of the 7,000 minimum
computation of the contact area of the hardware supplied by contact area required under Contract No. 1 is a reasonable
Form-Eze under Contract No. 1. According to BFC, Form- computation.
Eze had furnished only 53 completely assembled deckforms We reverse the finding of the CIAC on this point as it is
of 44 ft. in length which correspond to only 4,441.73 contact contrary to the evidence on record.
square meters of formworks, while CIAC found that Form- We agree with BFC that the CIAC should not have
Eze had delivered truss chords equivalent to 87 deckforms included the unassembled truss chords in theoretically
which can provide 7,268.58 contact square meters. BFC forming deckforms. We subscribe to BFC’s submission that
maintains that Contract No. 1 is clear that the object is the the object of Contract No. 1 is the deckforms and not just
supply of the complete deckform system and not the hardware that make up the formwork. Contract No. 1,
unassembled hardware such as loose truss chords. BFC in itself, is clear that “F-E has agreed to furnish all
adds that Form-Eze judicially admitted that it is only hardware required in the formwork system for the poured
claiming equipment rentals for the areas that its equipment in place beam and slab concrete decks x x x.” In fact, the
equipment rental is only due and payable to Form-Eze theoretical findings, only 2,512 pieces of joists and only
when the concrete is placed on the slab forms, which 3,626 pieces of beam hangers were actually delivered by
provision is based on the premise that the hardware had [Form- Eze].26
already been assembled into deckforms ready for concrete
pouring. Moreover, the Proposed SM Marikina Mall Project
Elevated Beam and Slab Formwork dated 7 December BFC’s computation of the total contact area covered by
2006, which document has been admitted by the parties in the deckforms furnished by Form-Eze is backed by delivery
the Term of Reference, provides that Form-Eze will furnish receipts of the joists and beam hangers while CIAC’s
sufficient deckforms to produce 1/2 floor each month on the computation is more theoretical than it is actual.
project. The inclusion of the additional contact area of the grid
BFC had also explained to our satisfaction that loose girders in the calculation of the total contact area of the
truss chords alone could not be assembled into deckforms, equipment supplied by Form-Eze under Contract No. 1,
to wit: however, should be upheld. Paragraph 9 of the Letter dated
To try to assemble truss chords alone into a deckform is 8 February 2007, which was also admitted by the parties,
like taking three two-foot round pegs, trying to stand them clearly provides:
upright, then balancing twelve-inch round wooden slab on [Form-Eze] offered to install beam hangers and ledger
top, and expect it to be a stool capable of supporting a angles in order to support the moment beam fro column to
person. Joist, beam hangers and other component parts fix column and thereby save BFC considerable labor and
the truss chords into place for the structural integrity of a eliminate the use of BFC’s light duty scaffolding
deckform. In the case of a deckform 44 ft. in length, it will underneath that beam. By doing that it will also speed up
need, for it to be completely assem- the forming operation and save BFC labor. The only light
duty scaffolding that BFC will be installing is under the
girder which supports tremendous loading during the
stressing for the beams prior to it being stressed. By
184 forming the girder in this manner F-E is not involved in the
184 SUPREME COURT REPORTS stripping or resetting of the girder formwork. However,
ANNOTATED [Form-Eze] has purchased and furnished considerable
B.F. Corporation vs. Form-Eze Systems, Inc. forming hardware and consumables (tie rods, pvc sleeves,
pvc cones, whaler clips and brackets and wing-nuts) which
bled, 34 pieces of joists and 68 pieces of beam hangers as
are being used on the girders and the beams.
illustrated in the Petitioner’s Motion for Correction of Final
Award. _______________
Thus, assembling 87 deckforms of 44 ft. in length would
require 2,958 pieces of joist and 5,916 pieces of beam 26 See BFC’s Memorandum, id.(Vol. II), p. 3382.
hangers to assemble such 87-44-foot deckforms. However,
as show in the same documents that CIAC anchored its
185 5,149.85, which still falls short of the 7,000 contact area
VOL. 813, DECEMBER 7, 2016 185 requirement.
B.F. Corporation vs. Form-Eze Systems, Inc. To award the full contract price to Form-Eze in Contract
[Form-Eze] will give ownership to this equipment to BFC No. 1 is tantamount to unjust enrichment. There is unjust
and BFC will buy all additional consumables and hardware enrichment under Article 22 of the Civil Code when (1) a
(as needed) directly from Comer. In return [Form-Eze] will person is unjustly benefited, and (2) such benefit is derived
include the contact square meters of formwork in the at the expense of or with damages to another. The principle
girders in its billing for both the equipment lease and for of
the moving contract.27 _______________

27 Id. (Vol. I), p. 204.


BFC cannot claim that this provision does not refer to
Contract No. 1. Said provision mentions beam hangers and
ledger angles which are used to support the beams forming
186
the deckform and to eliminate the use of light duty
scaffolding on the part of BFC which it had initially 186 SUPREME COURT REPORTS
obligated to provide under Contract No. 1. More ANNOTATED
pertinently, the inclusion of the contact square meters of B.F. Corporation vs. Form-Eze Systems, Inc.
formwork in the girders is a mere application of one of the unjust enrichment essentially contemplates payment when
provisions in Contract No. 1, i.e., “BFC agrees to purchase there is no duty to pay, and the person who receives the
materials for the formwork as requested by F-E and the payment has no right to receive it.28By requiring BFC to
direct cost of those materials will be deducted from this pay the full contract price when it only supplied deckforms
contract and the balance paid to [Form-Eze].” Form-Eze is which covered only 5,149.85 contact square meters of
giving ownership of the forming hardware and consumables formworks, the CIAC Arbitral Tribunal is essentially
which are used on the girders and beams to BFC. Instead of unjustly giving unwarranted benefit to Form-Eze by
deducting the cost of these materials from the contract, allowing it to earn more than it legally and contractually
Form-Eze will instead include the contact square meters of deserved. It is also worth mentioning that Form-Eze had in
formwork in the girder in its billing for the lease of the fact only been claiming for the contact area where its
deckforms. equipment was used.
As agreed upon by the parties, the 708.12 sq. m. contact
area covered by the grid girders should be included in the Therefore, using the computation of BFC, the amount of
billing. Taking into account this contact area corresponding contact square meters that the delivered hardware and
the grid girders and the 4,441.73 contact square meters deckforms can handle is:
assembled deckforms, the total contact area is only
Contract No. 1 be reformed must have been a meeting of the minds of the parties to the
to include a labor guarantee contract; (2) the instrument does not express the true
provision. intention of the parties; and (3) the failure of the
instrument to express the true intention of the parties is
An action for reform a contract is grounded on Article due to mistake, fraud, inequitable conduct or accident.30
1359 of the New Civil Code which provides: In the instant case, the question to be resolved is
When, there having been a meeting of the minds of the whether the contract expressed their true intention; and, if
parties to a contract, their true intention is not expressed in not, whether it was due to mistake, fraud, inequitable
the instrument purporting to embody the agreement, by conduct or accident. While intentions involve a state of
reason of mistake, fraud, inequitable conduct or accident, mind which may sometimes be difficult to decipher,
one of the parties may ask for the reformation of the subsequent and contemporaneous acts of the parties as well
instrument to the end that such true intention may be as the evidentiary facts as proved and admitted can be
expressed. 1359. ARTICLE reflective of one’s intention.31
xxxx BFC relies on the Form-Eze Proposed SM Marikina Mall
Project Elevated Beam and Slab Formwork dated 7
_______________ December 200632 to support its contention that Contract
No. 1 should have a provision on the cost of labor. Indeed,
28 Filinvest Land, Inc. v. Ngilay, 697 Phil. 403, 412-413; in the aforementioned proposal, BFC has agreed “to furnish
684 SCRA 119, 128-129 (2012). the labor required for fabrication and assembly of the
forming equipment” and that “BFC will deduct from the
total contract
_______________
187
VOL. 813, DECEMBER 7, 2016 187 29 Multi-Ventures Capital and Management
B.F. Corporation vs. Form-Eze Systems, Inc. Corporation v. Stalwart Management Services Corporation,
Reformation is a remedy in equity, whereby a written 553 Phil. 385, 391; 526 SCRA 420, 424-425 (2007).
instrument is made or construed so as to express or conform 30 Id.
to the real intention of the parties, where some error or 31 Id.
mistake has been committed. In granting reformation, the 32 Rollo (Vol. I), pp. 198-200.
remedy in equity is not making a new contract for the
parties, but establishing and perpetuating the real contract
between the parties which, under the technical rules of law,
could not be enforced but for such reformation.29 188
In order that an action for reformation of instrument 188 SUPREME COURT REPORTS
may prosper, the following requisites must concur: (1) there ANNOTATED
B.F. Corporation vs. Form-Eze Systems, Inc.
amount P50.00 per man-hour each carpenter or laborer
supplied to Form-Eze.” Notably, Contract Nos. 2 and 3 189
contain labor-guarantee provisions considering that BFC VOL. 813, DECEMBER 7, 2016 189
has committed to provide the necessary labor for both B.F. Corporation vs. Form-Eze Systems, Inc.
contracts. MR. R.V. CLEMENTE (CLAIMANT):
As initially agreed upon, BFC hired workers for the That is why we were there in your jobsite. If they
assembly of the deckforms since Form-Eze only undertook don’t have really the expertise we are the one who
to supervise the installation of the deckforms. This was supervise them to install the deckforms. Supervise
evident during the cross-examination of Mr. Romano them to install the deckforms.
Clemente (Mr. Clemente) who admitted that no workers of ATTY. D. MORGA, JR. (COUNSEL-RESPONDENT):
Form-Eze were employed for the installation of the You mean no former workers of the Claimant were
deckforms, thus: employed for the purpose.
ATTY. D. MORGA, JR. (COUNSEL-RESPONDENT): MR. R.V. CLEMENTE (CLAIMANT):
Since it is the obligation of the Claimant to assemble the No.33
hardware into deckform, how many workers were
employed for the purpose?
MR. R.V. CLEMENTE (CLAIMANT): Obviously, BFC would want to be compensated for the
We are only supplier sir. We supervise the guys in the labor it provided to Form-Eze as shown in Contract Nos. 2
jobsite for them to install all these deckforms. and 3.
ATTY. D. MORGA, JR. (COUNSEL-RESPONDENT): As a matter of fact, Mr. James Franklin, the President of
Ano? MR. R.V. CLEMENTE (CLAIMANT): Form-Eze conceded that Contract No. 1 should be modified
To install the guys in the jobsite like for example your to include a labor-guarantee provision, to wit:
laborers carpenters to install this deckforms. We just Q: Mr. Witness, respondent [BFC], in their
only supply one supervisor in the jobsite for him to counterclaims, would like this Commission to reform
supervise the installation of this form. Contract No. 1 to include a provision that it should deduct
ATTY. D. MORGA, JR. (COUNSEL-RESPONDENT): from your billing the cost of labor, helmet and expense for
You mean BF Corporation has the expertise to assemble x-bracing supplied by it for the assembly of the form
this. system, what can you say?
MR. R.V. CLEMENTE (CLAIMANT): A: [BFC] is allowed to deduct the cost of the x-bracing
No, we will supervise your guys for them to assemble purchase from Comer that was used in the FORM-EZE
this. deck assemblies. [BFC] is allowed to deduct the cost of the
ATTY. D. MORGA, JR. (COUNSEL-RESPONDENT): assembly labor for the deckforms which is included in the
Do you know if BF has the expertise to assemble this? Labor Guarantee. These deductions have been reflected in
all our billings where the P75.00 Labor Guarantee has been
applied. The cost of helmet is not included and should not
be included. Contract No. 1 is only a lease contract but it Expenses for x-bracing and the
was modified to include a Labor Guarantee. For the [BFC] cost of labor should be deducted
to deduct from our billing the cost of labor, etc. which under Contract Nos. 2 and 3.
allegedly they supplied for the use of our said equipment for Except for the expenses for x-bracing used in deck
the assembly thereof is included in the Labor Guarantee. assemblies which had been admitted by Form-Eze
They President James Franklin, BFC is not entitled to be
reimbursed for the cost of helmets, petroleum, and oil
_______________ lubricants in the absence of any stipulations in the
contracts. The cost of labor, on the other hand, should be
33 Rollo, pp. 861-862; TSN, 13 August 2007. deducted pursuant to the labor-guarantee provisions in
Contract Nos. 2 and 3.
The cost for x-bracing amounts to P358,250.00 as
190
evidenced by the receipt issued by Comer.35
190 SUPREME COURT REPORTS
_______________
ANNOTATED
B.F. Corporation vs. Form-Eze Systems, Inc. 34 See Judicial Affidavit of Mr. James W. Franklin; id.,
should be allowed to do so in conformance with the Labor at pp. 287-288.
Guarantee but definitely the cost of helmet and their other 35 Id. (Vol. I), p. 482.
claims of deductions would not have any basis at all since
these have not been agreed upon both in the original
contract and in the subsequent agreement as contain (sic)
in the February 8, 2007 signed letter.34 191
VOL. 813, DECEMBER 7, 2016 191
B.F. Corporation vs. Form-Eze Systems, Inc.
This admission by Form-Eze bolsters the conclusion that The costs of labor are as follows:
the parties intended to include a labor-guarantee provision Contract No. 1 = P453,294.50
in Contract No. 1. Both Contract Nos. 2 and 3 set the labor Contract No. 2 = P1,373,634.60
rate at P60.00 per carpenter man-hour. BFC fixed the cost Contract No. 3 = P273,240.00
of labor at P453,294.50. Obligation of BFC under Contract No. 1.
Considering that both parties admitted that there 92,696.40 contact square meters x P225.00 =
should be a labor guarantee clause in Contract No. 1, it can P20,856,690.00
be reasonably inferred that the failure to include said Less: Amount paid 7,700,000.00
provision was due to mistake. A reformation is in order to Payment for billing for Pour 1 487,828.05
include a cost of labor provision in Contract No. 1. Cost of labor 453,294.50
Cost of X-bracing 358,250.00 way be interpreted as part of the deckform supplied by
_____________ Form-Eze. As pointed out by BFC, the scaffoldings and
P11,857,317.45 accessories were the responsibility of BFC under Contract
No. 1. Thus, the manufactured hardware under Contract
The Memorandum of Agreement No. 4 could not have added to the deckform system because
dated 5 January 2007 is an ex- they are not the equipment of Form-Eze had obligated itself
clusive licensing agreement. to supply under Contract No. 1.

BFC avers that CIAC erred when it stated the BFC was Obligation of BFC under
given the exclusive license to manufacture Form-Eze’s Contract No. 2.
equipment consisting of scaffoldings and accessories and
they became part of that provided by Form Eze to BFC. BFC maintains that since Form-Eze failed to meet the
At the outset, we agree that the subsequent minimum conditions under Contract No. 1 where the
Memorandum of Agreement executed by the parties on 5 minimum 126,000 contact square meters were not reached,
January 2007 is an exclusive licensing agreement. It was then the forklifts under Contract No. 2 were also not used
signed by both parties wherein BFC has agreed to sell the for a minimum of 126,000 contact square meters.
scaffolding frames and accessories it manufactured to We agree. BFC is liable only to pay the amount
Form-Eze at the end of the project. This Agreement was proportionate to 92,696.40 contact square meters at P50.00
incorporated in Contract No. 4 wherein BFC will be allowed per contact square meter, the rental rate for the forklifts.
to deduct P6,352,500.00 from the equipment lease contract, Thus:
which is presumably Contract No. 1. At this point, Contract
No. 4 is deemed to have novated the obligation of BFC with 92,696.40 contact square meters x P50.00 = P4,634,820.00
respect to furnishing all scaffoldings. Contract No. 1 states Less: Payments made 990,000.00
that BFC shall furnish the scaffoldings at no cost to Form- Cost of Labor 1,286,377.50
Eze. On the other hand, Contract No. 4 requires BFC to sell _____________
the scaffoldings to Form-Eze at the SUBTOTAL P2,358,442.50

Obligation of BFC
192 under Contract No. 3.
192 SUPREME COURT REPORTS
ANNOTATED The CIAC had correctly noted the ambiguity in Contract
B.F. Corporation vs. Form-Eze Systems, Inc. No. 3, particularly the “sufficient number of columnforms as
required to complete six (6) poured in place columns per
end of the project and deduct the cost of the same from the
day.” For BFC, the sufficient number of columnforms is 12
contract price of Contract No. 1. This setup cannot in any
sets a day while Form-Eze considered its supply of six (6)
full height built up columnforms as sufficient. The CIAC BFC is then liable to pay P441,502.87 broken down as
found that follows:
1,516.67 x P355.00 = P538,417.85
Less: Cost of Labor 96,915.00
193 _____________
VOL. 813, DECEMBER 7, 2016 193 SUBTOTAL: P441,502.87
B.F. Corporation vs. Form-Eze Systems, Inc.
Form-Eze failed to comply with the requirements under
194
Contract No. 3, hence it merely awarded Form-Eze 2/3 of
194 SUPREME COURT REPORTS
the minimum contract amount at P2,153,666.67.
We find that the CIAC’s award lacked bases. It gave ANNOTATED
credence to the methodology used by Form-Eze and noted B.F. Corporation vs. Form-Eze Systems, Inc.
that the latter had supplied six (6) full height built-up BFC is obliged to pay rental for
columnforms, albeitinsufficient. We hold the contrary. The u-heads under Letter-Agreement
methodology used by BFC, which involves “columnforms dated 5 January 2007.
with window openings and that from its installation,
alignment, bracing, inspection, approval of alignment, Under the letter dated 8 February 2007, “BFC has
verticality and rigidity of the erected columnforms, pouring, completed fabrication on a sufficient quantity of u-heads
drying and removal of the forms, it will require twelve (12) with screw assemblies and heavy-duty bases so that BFC
columnforms a day, should have been considered. The CIAC can immediately start returning the 24-inch and 18-inch u-
itself had already ruled that the ambiguity in Contract No. head assemblies (561 pcs.) and heavy-duty bases (483 pcs.)
3 should not favor Form-Eze, the party who prepared the which were on temporary loan to BFC by [Form-Eze] until
contract. Thus, it is only logical that the methodology BFC could manufacture their own equipment. The
employed by BFC should be credited. temporary loan was expected to be approximately [two] (2)
Using 12 columnforms as the minimum requisite and weeks and the equipment was picked up January 9, 2007
Form-Eze having supplied only four (4) usable and still in used today.”36 It is understood that upon
columnforms, it can be established that the delivered expiration of the two-week temporary loan and upon failure
columnforms can only be used for 1/3 portion of the 9,100 by BFC to return the equipment, it is then liable to pay for
contact square meters or 3,033.33 contact square meters. It rent. We find that the monthly rental amount of P96,600.00
was further proven by BFC that about 50% of the was substantiated by Form-Eze. 483 pieces of 24 inch and
columnform requirements of the project were already 18 inch galvanized adjustable heads and 483 pieces of
completed with the use of their own equipment. Thus, it is galvanized heavy-duty plates were indeed delivered to BFC
but equitable that the 3,033.33 contact square meters be as evidenced by the delivery receipts.37 According to Mr.
further reduced by 50% or 1,516.67 contact square meters. Clemente, Form-Eze’s Sales Engineer, the rental amount
for adjustable u-heads are fixed at P160.00 per unit, while
the galvanized heavy-duty plates are at P40.00 per his inclusion as a respondent in the CIAC proceedings.
unit.38 By agreeing to the terms of the 8 February 2007 CIAC however considered Pineda as a joint tortfeasor, thus
Letter, BFC is deemed to have acquiesced to the rental fee justifying his joinder as a codefendant.
in case it failed to return the u-heads and plates on time. We do not consider the imputed acts of Pineda as
Therefore, we affirm the CIAC’s ruling that BFC is liable to an indicia of bad faith to classify him as a joint
pay rental of the equipment in the amount of P96,000.00 tortfeasor. First, it was proven that Form-Eze is not
per month until the equipment leased is fully returned to entitled to all its monetary claims under the
Form-Eze. contract. Second, we have also subscribed to BFC’s position
_______________ that Contract No. 1 should have included a labor guarantee
provision and that it was by mistake that said clause was
36 Id., at p. 204. excluded. Third, BFC’s alleged refusal to return the u-head
37 Id., at pp. 324-325, 330 and 334. assemblies and heavy-duty bases was meted with a heavy
38 Id., at p. 387. Judicial Affidavit of Mr. Clemente. penalty in the form of a huge rental fee. BFC had, as a
matter of fact, admitted to owing Form-Eze rental
payment. Fourth, the claim of threat against Form-Eze’s
President is unsubstantiated and uncorroborated.
195
VOL. 813, DECEMBER 7, 2016 195 Attorney’s Fees and Costs
B.F. Corporation vs. Form-Eze Systems, Inc. of Arbitration.
BFC President should not be
included as party to this case? The controversy essentially boils down to the
interpretation and factual application of the existing
Section 4 of Executive Order No. 1008 vests jurisdiction contracts. Neither
on CIAC over disputes disputes arising from, or connected
with, contracts entered into by parties involved in
construction in the Philippines, whether the dispute arises 196
before or after the completion of the contract, or after the 196 SUPREME COURT REPORTS
abandonment or breach thereof. Moreover, the party ANNOTATED
involved must agree to submit to voluntary arbitration. In B.F. Corporation vs. Form-Eze Systems, Inc.
other words, anyone who is not a party to the contract in
party was able to prove bad faith in their dealing with each
his personal capacity is not subject to the jurisdiction of the
other. Under Article 2208 of the Civil Code, attorney’s fees
CIAC. In this case, Pineda signed the challenged contracts
may, among others, be recovered where defendant acted in
in his capacity as President of BFC. There is no indication
gross and evident bad faith in refusing to satisfy the
that he voluntarily submitted himself as a party to the
plaintiff’s plainly valid, just and demandable claim. We
arbitration case. In fact, he has been consistently contesting
observe that in filing the complaint against BFC, Form-Eze
was merely seeking payment for its service under the 197
contract. BFC had admitted to its obligation. The problem VOL. 813, DECEMBER 7, 2016 197
lies only on the amount to be paid. This is not tantamount B.F. Corporation vs. Form-Eze Systems, Inc.
to bad faith.
Finally, both parties should equally share the costs of Petition partially granted, judgment and resolution
arbitration since their prayers were only partially modified.
granted.39
Notes.—The Supreme Court (SC) has ruled that when a
WHEREFORE, the petition is PARTIALLY dispute arises from a construction contract, the
GRANTED. The Decision dated 15 January 2010 and Construction Industry Arbitration Commission (CIAC) has
Resolution dated 13 July 2010 are MODIFIED. Petitioner exclusive and original jurisdiction. (Stronghold Insurance
B.F. Corporation is ordered to pay respondent Form-Eze Company, Inc. vs. Stroem, 746 SCRA 598 [2015])
Systems, Inc. the following amounts: Under Article 22 of the Civil Code, there is unjust
Under Contract No. 1: P11,857,317.45 enrichment when (1) a person is unjustly benefited and (2)
2,358,442.50 Under Contract No. 2: such benefit is derived at the expense of or with damages to
441,502.87 Under Contract No. 3: another. (Bliss Development Corp./Home Guaranty
Under Letter-Agreement Corporation vs. Diaz, 765 SCRA 453 [2015])
560,000.00 dated 7 January 2007:
GRAND TOTAL: P15,217,262.82 ——o0o——
and 50% of the Cost of Arbitration. © Copyright 2019 Central Book Supply, Inc. All rights
reserved.
SO ORDERED.
Velasco, Jr. (Chairperson), Del
Castillo,**Reyes and Jardeleza, JJ., concur.

_______________

39 Filipinas (Pre-Fab Bldg.) System, Inc. v. MRT


Development Corporation, 563 Phil. 184, 218; 537 SCRA
609, 642 (2007).
** Designated additional member per Raffle dated 5
December 2016.

You might also like