Professional Documents
Culture Documents
Method of Statement For Road Works
Method of Statement For Road Works
Introduction:
This package involves improvement of 10.9 Km of road from Kebithigollewa towards Horowupathana.
According to the Tender documents main work involved are
Mobilization
Survey, setting out and cross-sections
Clearing
Embankment Fill – 6 fill sections of total length 1490 m with height of fill varying from 0.45 m to
1.8 m.
Excavation – about 1600 m towards the end of the road in the section from Km 31+000 to End
station.
Trench excavation and fill for road widening
Culverts – 16 Nos extensions, 10 Nos reconstruction and 2 nos minor works
Reconstruction of Bridges – 4 Nos
13 bus bays, 580 m lined drains and small quantity of Retaining walls
Construction of Subbase and DGAB
Priming and Asphalt surfacing
Protection, drains, Guard rails, road signs, Road marking ect..
Performance based Maintenance
METHOD
Mobilization;
On receipt of Letter of Acceptance, we will attend to preliminary arrangement required for mobilization
at site on instruction from Engineer to commence work. We will attend to Preliminary and General items
of works as required under the contract. Engineer’s housing will be arranged to the satisfaction of the
Engineer. If Engineer’s facility provided under Bill 11 is instructed, these works will be attended during
this period.
Initially we propose to rent houses for Contractor’s facility. However a suitable land will be located close
to the project area for establishment of Contractor’s facility during construction and also to continue for
performance based Maintenance period. We intend to use prefabricated units to construct Contractor’s
facility such as office, accommodation, stores, workshops etc..
section will be prepared based on Drawing TS-003 by our Highway Engineer to be submitted to Engineer
for approval. This work will be carried out in comply with Specification Clause 117.
Clearing
Clearing and grubbing will be carried out before commencement of construction. Since this work will not
obstruct traffic a reasonable section will be cleared at a time.
At this stage trench excavation and backfilling will be completed only upto existing road level. It is our
intension to execute work at Kebithigollewa town during dry season. According to contract
Kebithigollewa town will have Type 2 section requiring only overlay of DGAB on the existing road.
Culverts, Lined Drains, Retaining Walls, Bus bays, Ancillary works etc..
These works are not critical. We will engage sufficient number of teams to complete this work within
contract period. The concrete requirement will be supplied from our own batch plant.
Bridges
Initially we will construct diversion roads at all bridge locations. If permitted the bailey bridges removed
from the existing bridges will be used at some locations.
All four bridges are founded on spread footing with mass concrete abutments. Two bridges are with
central concrete piers. We will complete foundation work in the dry season to take advantage of the
lower ground water level. Coffer dam will be constructed to cast the foundation and abutments and
piers above water level. Pre-cast pre-stressed bridge beams will be purchased from reputed precast yard
with the approval of Engineer. A concrete batching plant will be set up by us at the project. We wish to
mention here that two number concrete batching plants are available with us at STDP project.
METHOD STATEMENT