Professional Documents
Culture Documents
BOQ WTP (Basic Design)
BOQ WTP (Basic Design)
ENGINEERING ESTIMATE
I WTP 273,171,094,181.35
IX LANDSCAPE 41,416,218,603.85
ELECTRICAL 46,688,957,304.01
TOTAL 433,041,700,061.03
PPN 10% 43,304,170,006.10
CONTINGENCY 5% 21,652,085,003.05
GRAND TOTAL 497,997,955,070.18
108,260,425.02
12% 59,759,754,608.42
5% 24,899,897,753.51
899931273101.121
46,688,957,304.01
BILL OF QUANTITY
WTP 4.600 LPS
No. ITEM DESCRIPTION VOL.
I PREPATORY WORKS
Mobilization and demobilization (people & equipment) 1.00
Fields cleaning 12,800.00
Name plate project 1.00
Temporary fence 500.00
Temporary office and warehouse (lighting, clean water, sanitation) 1.00
Occupational health & safety 1.00
Documentation, permit, reporting, shop drawing, as built drawing 1.00
Security of project 1.00
II LAND WORKS
Work Foundation Pile 1.00
IV
a Pump Works
Backwash pump
Pompa Centrifugal Kapasitas 220 l/det, Head = 10 m, lengkap dengan motor 30 kW 2.00
Wafer Check Valve ND. 400 mm 2.00
Butterfly Valve dia. 400 mm, gear operated 2.00
Pipa GIP ND. 400 mm 160.00
Pressure Gauge Dia. 4", 0- 10 bar 3.00
Loose Flange Dia. 400 mm 4.00
Panel Kontrol pompa backwash 1.00
Kabel NYY 4 X 16 mm + kabel trey 10.00
Blower Pump
Root Blower Cap. 400 m3/jam, pressure 4500 mbar lengkap dengan motor 22 kW 2.00
Pressure Gauge Dia. 4", 0 - 1 bar 1.00
Pipa PVC ND. 150 mm 560.00
Bend 90° All Socket ND. 150 mm 114.00
Tee All Socket ND. 150x150x150 mm 87.00
Reducer all Flange ND. 100x150 mm 1.00
Flange socket PVC ND. 150 1.00
Mekanikal Joint Steel galvanis ND. 100 mm 1.00
Butterfly Valve ND. 100 mm, hand lever operated 1.00
Check Valve ND. 100 mm 1.00
Ball Valve 1/2 " bronze 1.00
Savety Valve 1" 1.00
Loose Flange ND. 100 mm 8.00
Panel Kontrol Root Blower ( 1 blower ) 1.00
Kabel NYY 4 X 10 mm 15.00
Dosing Pump
Unit Koagulant (PAC, Alum Sulfat)
- Pompa Dosing digital input analog, kap. 5750 l/h, 4bar 9.00
- CollectionTank FRP kapasitas 15.000 liter 8.00
- Solution Tank FRP, kapasitas 4.000 liter 4.00
- Pemipaan pada tanki kimia sesuai gambar rencana PVC S. 10 dan Ball valve PVC, 2.00
Union socket welded with actuator
b Piping Works
Steel Pipe dia. 1.800 mm 30.00
Steel Pipe dia. 1.000 mm 60.00
Steel Pipe dia. 700 mm 100.00
Steel Pipe dia. 400 mm 300.00
Steel Pipe dia. 300 mm 350.00
Steel Pipe dia. 200 mm 300.00
Steel Pipe dia. 150 mm 300.00
Settler
Media Filter
Acc. Perpipaan
Elektrikal 1.00
ITY
S
UNIT UNIT TOTAL
PRICE (Rp.) PRICE (Rp.)
-
ls 50,000,000.00 50,000,000.00 1
m² 20,870.00 267,136,000.00 35000
ls 750,000.00 750,000.00 1
m' 308,116.00 154,058,000.00 750
ls 193,673,664.00 193,673,664.00 1
ls 350,000,000.00 350,000,000.00 1
ls 25,000,000.00 25,000,000.00 1
ls 42,000,000.00 42,000,000.00 1
-
-
ls Persentase 5% 13,008,147,341.97
-
- besi
m3 1,225,630.74 2,314,199,201.76
-
m3 1,600,000.00 222,096,000.00
kg 30,232.70 3,234,475,107.27
m3 1,600,000.00 348,496,000.00
m2 410,277.45 2,194,697,163.29
-
m3 1,600,000.00 1,201,392,000.00
kg 30,232.70 29,165,873,891.54
m3 1,600,000.00 3,943,744,000.00
m2 410,277.45 19,789,999,481.09
-
m3 1,600,000.00 1,902,784,000.00
kg 30,232.70 30,402,360,884.34
m3 1,600,000.00 3,460,480,000.00
m2 410,277.45 20,628,996,352.47
-
m3 1,600,000.00 1,507,136,000.00
kg 30,232.70 17,630,982,139.32
m3 1,600,000.00 1,603,136,000.00
m2 410,277.45 11,963,198,109.06
-
m3 1,600,000.00 377,056,000.00
kg 30,232.70 3,155,477,075.24
m3 1,600,000.00 179,600,000.00
m2 410,277.45 2,141,094,414.44
-
m3 1,600,000.00 398,992,000.00
kg 30,232.70 3,455,597,038.50
m3 1,600,000.00 210,608,000.00
m2 410,277.45 2,344,735,626.75
-
-
-
-
unit 276,150,000.00 552,300,000.00
buah 21,000,000.00 42,000,000.00
buah 31,000,000.00 62,000,000.00
m 5,500,000.00 880,000,000.00
buah 735,000.00 2,205,000.00
buah 2,300,000.00 9,200,000.00
unit 35,000,000.00 35,000,000.00
m' 375,000.00 3,750,000.00
-
-
unit 160,000,000.00 320,000,000.00
buah 735,000.00 735,000.00
m 222,170.00 124,415,200.00
unit 190,416.60 21,707,492.40
unit 230,828.40 20,082,070.80
unit 633,981.65 633,981.65
unit 579,981.65 579,981.65
unit 4,986,761.50 4,986,761.50
unit 1,002,005.60 1,002,005.60
unit 3,446,805.60 3,446,805.60
unit 922,500.00 922,500.00
unit 7,794,600.00 7,794,600.00
unit 180,000.00 1,440,000.00
unit 27,916,000.00 27,916,000.00
m' 90,450.00 1,356,750.00
-
-
-
unit 152,115,600.00 1,369,040,400.00
unit 90,000,000.00 720,000,000.00
unit 26,400,000.00 105,600,000.00
set 43,750,000.00 87,500,000.00
-
-
-
unit 31,473,000.00 62,946,000.00
unit 18,375,000.00 36,750,000.00
unit 71,500,000.00 143,000,000.00
unit 109,650,000.00 219,300,000.00
set 44,000,000.00 88,000,000.00
set 150,000,000.00 150,000,000.00
-
-
-
m 10,893,701.00 326,811,030.00
m 6,033,196.00 361,991,760.00
m 4,779,424.00 477,942,400.00
m 2,389,712.00 716,913,600.00
m 1,911,769.60 669,119,360.00
m 1,194,856.00 358,456,800.00
m 955,884.80 286,765,440.00
34,967,649,417.65 20%
8,392,235,860.24 4%
21,819,813,236.62 10%
3,450,000,000.00 21,819,813,236.62
21,853,687,534.51 22,946,371,911.23
273,171,094,181.35
59,385,020.47
30000000
20870
750000
308116
193673664
350000000
25000000
42000000
300
5750
54,634,218,836.27 13%
10,926,843,767.25 3%
27,317,109,418.14 8%
GENERATOR SET BUILDING
PEKERJAAN TANAH
Pengukuran dan pemasangan bouwplank 38.50 m 61,075.00
Galian Tanah 119.30 m³ 90,936.00
Urug pasir Bawah Pondasi & Lantai 22.41 m³ 294,710.00
Pasangan batu kosong 22.72 m³ 895,084.56
Urugan sirtu peninggian lantai 33.15 m³ 294,710.00
Lantai kerja u/ lantai K125
- Beton K 125 5.53 m³ 1,265,489.47
Timbunan tanah kembali dipadatkan 58.16 m³ 66,870.00
Pembuangan tanah sisa galian 10.48 m³ 39,824.00
PEKERJAAN PONDASI
Pondasi batu kali spesi 1:4 62.58 m³ 1,349,295.00
Pondasi Beton Genset
- Bekisting 12 mm 10.55 m² 191,530.78
- Pembesian polos 858.86 kg 30,232.70
- Beton K 225 6.32 m³ 1,393,910.00
Pondasi Beton Trafo
- Bekisting 12 mm 1.30 m² 191,530.78
- Pembesian polos 108.74 kg 30,232.70
- Beton K 225 0.50 m³ 1,393,910.00
Pondasi beton dudukan tangki bulanan
- Bekisting 12 mm 8.80 m' 191,530.78
- Pembesian ulir 698.40 kg 30,232.70
- Beton K225 7.20 m³ 1,393,910.00
PEKERJAAN BETON
Sloof 25/30
- Bekisting 12 mm 107.64 m² 200,730.78
- Pembesian polos 1,076.40 kg 30,232.70
- Beton K 225 8.97 m³ 1,393,910.00
Sloof 15/25
- Bekisting 12 mm 161.46 m² 200,730.78
- Pembesian polos 1,100.00 kg 30,232.70
- Beton K 225 8.80 m³ 1,393,910.00
Kolom 25/25
- Bekisting 12 mm 36.00 m² 333,227.45
- Pembesian polos 270.08 kg 30,232.70
- Beton K 225 1.50 m³ 1,393,910.00
Kolom Praktis 28.00 m' 108,589.56
Rabatan Lantai 10 cm dgn tulangan dia 8-150 (1 lapis)
- Pembesian polos 927.60 kg 30,232.70
- Beton K 125 11.05 m³ 1,265,489.47
Balok 25/30
- Bekisting 12 mm 48.46 m² 338,747.45
- Pembesian polos 719.11 kg 30,232.70
- Beton K 225 4.28 m³ 1,393,910.00
Balok Latai 15/20
- Bekisting papan 4.04 m² 338,747.45
- Pembesian polos 64.29 kg 30,232.70
- Beton K 225 0.30 m³ 1,393,910.00
Pelat Atap t= 15 cm
- Bekisting 12 mm 208.00 m² 402,227.45
- Pembesian polos 5,859.38 kg 30,232.70
- Beton K 225 46.88 m³ 1,393,910.00
Beton K225 untuk Kabel try 2.84 m³ 1,393,910.00
Galian tanah 7.63 m³ 90,936.00
- Urug pasir Bawah Pondasi & Lantai 0.75 m³ 294,710.00
- Pembesian 426.36 kg 30,232.70
- Bekisting 22.44 m² 410,277.45
- Besi beton dia. 10mm, besi siku 60x60x6 2,900.14 kg 13,800.00
- Pengelasan 736.78 cm 2,985.73
PEKERJAAN DINDING
Pasangan Bata 1:4 53.09 m² 335,621.75
Plesteran dinding bata t= 1,5 cm spesi 1:4 106.18 m² 78,190.00
Acian 106.18 m² 45,982.75
Floorhardeneer 110.50 m² 105,000.00
Waterproofing 114.75 m² 60,000.00
Cat dinding 274.86 m² 22,869.94
7,235,288,879.48
14,470,577,758.96
SECURITY BUILDING
Earth Works
Pengukuran dan pemasangan bouwplank 22.60 m
Galian tanah untuk pondasi 3.31 m3
Timbunan tanah kembali dipadatkan 0.99 m3
Pembuangan tanah sisa galian 2.32 m3
Pasir dipadatkan dibawah pondasi 1.48 m3
Concrete Works
Pasangan batu kosong 3.31 m³
Pondasi batu kali spesi 1:4 3.31 m³
Beton K 175 dengan besi tulangan untuk sloof 20/25
- Bekisting 6.62 m²
- Pembesian polos 106.20 kg
- Beton K 175 0.90 m³
Beton K 175 dengan besi tulangan untuk kolom 15/15
- Bekisting 21.00 m²
- Pembesian polos 57.71 kg
- Beton K 175 0.61 m³
Beton K 175 dengan besi tulangan untuk plat lantai atap t=12
- Bekisting 31.67 m²
- Pembesian polos 456.08 kg
- Beton K 175 3.80 m³
Door Works
Kusen dan jendela doubel 2.00 unit
Kusen dan daun pintu panel 2.00 unit
Kusen dan daun pintu PVC 1.00 unit
Kusen dan dan kaca polos t-5 cm 2.00 unit
Sanitary Works
Closed jongkok 1.00 unit
Bak Mandi Fiber glass ukuran 0.3m3 1.00 unit
Floor drain 1.00 set
Pemipaan air bersih 1.00 set
- Kran air Ø 1/2" 3.00 unit
- Pipa PVC AW Ø 3/4" 75.00 m
- Pipa PVC AW Ø 1/2" 20.00 m
- Fiting - fiting 1.00 set
Pemipaan air kotor
- Pipa PVC AW Ø 2,5" 15.00 m
- Pipa PVC AW Ø 3" 10.00 m
- Pipa PVC AW Ø 4" 15.00 m
- Fiting - fiting 1.00 unit
Septik Tank dan resapan bentuk dan ukuran sesuai gambar 1.00 unit
Finishing Works
Cat tembok untuk dinding dan plafon 42.26 m²
Rabat beton K 125 sekeliling bangunan
- Bekisting 2.46 m²
- Beton K 125 1.32 m³
61,075.00 1,380,295.00
90,936.00 301,180.03
66,870.00 66,442.03
39,824.00 92,327.96
294,710.00 436,170.80
-
-
895,084.56 2,964,520.06
1,349,295.00 4,468,865.04
-
200,730.78 1,329,640.65
3,023.27 321,071.22
1,332,595.28 1,199,335.75
-
333,227.45 6,997,776.45
3,023.27 174,480.44
1,332,595.28 809,551.63
-
-
338,747.45 3,658,472.46
3,023.27 232,640.59
1,332,595.28 1,079,402.18
-
-
402,227.45 12,739,548.91
3,023.27 1,378,864.85
1,332,595.28 5,064,794.89
-
335,621.75 22,956,527.70
78,190.00 10,696,392.00
45,982.75 6,290,440.20
250,970.00 5,019,400.00
274,650.00 823,950.00
264,070.00 2,746,328.00
-
-
1,229,200.00 2,458,400.00
2,250,000.00 4,500,000.00
3,000,000.00 3,000,000.00
439,200.00 878,400.00
-
-
509,944.50 509,944.50
619,190.00 619,190.00
162,080.00 162,080.00
-
217,800.00 653,400.00
4,033.33 302,500.00
3,116.67 62,333.33
203,646.67 203,646.67
-
77,390.00 1,160,850.00
94,870.00 948,700.00
135,600.00 2,034,000.00
414,355.00 414,355.00
5,511,017.35 5,511,017.35
-
-
22,869.94 966,540.63
-
402,227.45 989,479.53
1,265,489.47 1,670,446.10
120,273,701.97
OFFICIAL RESIDENCE
PEKERJAAN TANAH
Pembersihan lokasi 69.00 m2
Pengukuran 69.00 m2
Galian tanah untuk pondasi 6.30 m3
Timbunan tanah kembali dipadatkan 20.70
Pembuangan tanah sisa galian 48.30
Pasir dipadatkan dibawah pondasi 0.63
PEKERJAAN FINISHING
Cat tembok untuk dinding dan plafon 407.04 m2
Rabat beton K 125 sekeliling bangunan
- Bekisting 12 mm 8.00 m2
- Beton K 125 7.76 m3
6 UNIT
15,120.00 1,043,280.00
145,800.00 10,060,200.00
3,685.00 23,215.50
12,000.00 248,400.00
120,000.00 5,796,000.00
10,000.00 6,300.00
-
-
174,000.00 1,221,480.00
39,900.00 280,098.00
-
8,800.00 206,624.00
55,000.00 20,487,500.00
404,240.00 1,204,635.20
-
8,800.00 221,760.00
55,000.00 4,963,750.00
404,240.00 384,028.00
-
-
8,800.00 158,796.00
55,000.00 12,375,000.00
404,240.00 727,632.00
-
105,000.00 10,684,800.00
7,737.60 1,574,756.35
12,152.00 4,946,350.08
-
250,970.00 11,519,523.00
160,000.00 2,520,000.00
220,000.00 3,872,000.00
96,000.00 1,214,400.00
64,000.00 1,152,000.00
-
-
1,682,720.00 10,096,320.00
7,683,000.00 30,732,000.00
3,000,000.00 3,000,000.00
2,000,000.00 2,000,000.00
-
-
594,680.00 594,680.00
919,970.00 919,970.00
80,170.00 80,170.00
236,775.00 236,775.00
-
-
-
-
-
176,500.00 2,647,500.00
250,000.00 2,500,000.00
331,500.00 4,972,500.00
7,500,000.00 7,500,000.00
5,341,180.00 5,341,180.00
-
-
13,600.00 5,535,744.00
-
207,940.00 1,663,520.00
404,240.00 3,136,902.40
-
-
3,685.00 20,812.88
120,000.00 677,760.00
105,000.00 1,111,950.00
7,737.60 81,941.18
12,152.00 128,689.68
404,240.00 165,536.28
-
32,660.00 2,586,672.00
182,623,151.56
1,095,738,909.34
CHEMICAL & OPERATIONAL BUILDING
PEKERJAAN TANAH
Pengukuran dan pemasangan bouwplank 36.60 m
Galian tanah untuk pondasi 59.29 m³
Timbunan tanah kembali dipadatkan 26.35 m³
Pembuangan tanah sisa galian 32.94 m³
Pasir dipadatkan dibawah pondasi 2.61 m³
Beton K 175 dengan besi tulangan untuk plat lantai atap t=12
- Bekisting 100.88 m²
- Pembesian polos 1,530.31 kg
- Beton K 175 12.75 m³
PEKERJAAN SANITER
Closed jongkok 1.00 unit
Bak Mandi Fiber glass ukuran 0.3m3 1.00 unit
Floor drain 1.00 set
Pemipaan air bersih 1.00 set
- Kran air Ø 1/2" 3.00 unit
- Pipa PVC AW Ø 3/4" 75.00 m
- Pipa PVC AW Ø 1/2" 20.00 m
- Fiting - fiting 1.00 set
Pemipaan air kotor
- Pipa PVC AW Ø 2,5" 15.00 m
- Pipa PVC AW Ø 3" 10.00 m
- Pipa PVC AW Ø 4" 15.00 m
- Fiting - fiting 1.00 unit
Septik Tank dan resapan bentuk dan ukuran sesuai gambar 1.00 unit
PEKERJAAN FINISHING
Cat tembok untuk dinding dan plafon 270.20 m²
Rabat beton K 125 sekeliling bangunan
- Bekisting 4.06 m²
- Beton K 125 1.94 m³
PEKERJAAN TANAH
Pengukuran dan pemasangan bouwplank 36.60 m
Galian tanah untuk pondasi 59.29 m³
Timbunan tanah kembali dipadatkan 26.35 m³
Pembuangan tanah sisa galian 32.94 m³
Pasir dipadatkan dibawah pondasi 2.61 m³
Beton K 175 dengan besi tulangan untuk plat lantai atap t=12
- Bekisting 100.88 m²
- Pembesian polos 1,530.31 kg
- Beton K 175 12.75 m³
PEKERJAAN SANITER
Closed jongkok 1.00 unit
Bak Mandi Fiber glass ukuran 0.3m3 1.00 unit
Floor drain 1.00 set
Pemipaan air bersih 1.00 set
- Kran air Ø 1/2" 3.00 unit
- Pipa PVC AW Ø 3/4" 75.00 m
- Pipa PVC AW Ø 1/2" 20.00 m
- Fiting - fiting 1.00 set
Pemipaan air kotor
- Pipa PVC AW Ø 2,5" 15.00 m
- Pipa PVC AW Ø 3" 10.00 m
- Pipa PVC AW Ø 4" 15.00 m
- Fiting - fiting 1.00 unit
Septik Tank dan resapan bentuk dan ukuran sesuai gambar 1.00 unit
PEKERJAAN FINISHING
Cat tembok untuk dinding dan plafon 270.20 m²
Rabat beton K 125 sekeliling bangunan
- Bekisting 4.06 m²
- Beton K 125 1.94 m³
61,075.00 2,235,345.00
90,936.00 5,391,777.31
66,870.00 1,762,158.24
39,824.00 1,311,802.56
294,710.00 768,530.00
-
-
895,084.56 9,336,627.05
1,349,295.00 30,371,281.16
-
200,730.78 4,440,084.45
3,023.27 789,121.71
1,332,595.28 2,947,700.77
-
333,227.45 10,556,645.62
3,023.27 341,206.20
1,332,595.28 1,583,123.20
-
-
338,747.45 6,045,761.24
3,023.27 384,431.39
1,332,595.28 1,783,678.79
-
-
402,227.45 40,576,825.82
3,023.27 4,626,545.60
1,332,595.28 16,994,054.61
-
335,621.75 45,342,498.43
78,190.00 21,126,938.00
45,982.75 12,424,539.05
250,970.00 18,069,840.00
-
-
4,687,560.00 9,375,120.00
439,200.00 1,756,800.00
-
-
509,944.50 509,944.50
619,190.00 619,190.00
162,080.00 162,080.00
-
217,800.00 653,400.00
4,033.33 302,500.00
3,116.67 62,333.33
203,646.67 203,646.67
-
77,390.00 1,160,850.00
94,870.00 948,700.00
135,600.00 2,034,000.00
414,355.00 414,355.00
5,511,017.35 5,511,017.35
-
-
22,869.94 6,179,456.44
-
402,227.45 1,634,250.13
1,265,489.47 2,449,861.07
273,188,020.66
RESERVOIR 16.000 M3
Earth Works
Staking-out and Bouwplank Installation 280.00 m'
Galian tanah sampai kedalaman sesuai rencana 18,816.00 m³
Pondasi sirtu dipadatkan tebal 50 cm 2,352.00 m³
Pasir urug dipadatkan, tebal 10 cm 470.40 m³
Timbunan tanah kembali dipadatkan 1,120.00 m³
Pembuangan tanah sisa galian disekitar lokasi 17,696.00 m³
Concrete Works
Lantai kerja beton K-125, t= 5 cm 235.20 m³
Plat Lantai
- Beton K-300 Ready Mix 1,034.60 m³
- Besi diameter 12 mm dan 16 mm, mutu U-32 206,920.00 kg
- Bekisting multiplek tebal 18mm 10,346.00 m²
Dinding
- Beton K-300 Ready Mix 1,093.56 m³
- Besi diameter 12 mm dan 16 mm, mutu U-32 218,712.00 kg
- Bekisting multiplek tebal 18mm 10,935.60 m²
Atap
- Beton K-300 Ready Mix 661.32 m³
- Besi diameter 12 mm dan 16 mm, mutu U-32 132,264.00 kg
- Bekisting multiplek tebal 18mm 6,613.20 m²
Kolom
- Beton K-300 Ready Mix 226.34 m³
- Besi diameter 12 mm dan 16 mm, mutu U-32 45,268.00 kg
- Bekisting multiplek tebal 18mm 2,263.40 m²
Balok
- Beton K-300 Ready Mix 159.79 m³
- Besi diameter 12 mm dan 16 mm, mutu U-32 31,958.00 kg
- Bekisting multiplek tebal 18mm 1,597.90 m²
Plesteran dinding bata spesi 1:4 t= 1,5 cm 420.00 m²
Iron Works
Tutup manhole dari plat baja t= 3 mm dengan rangka besi
siku uk. 50x50x5 mm bentuk dan ukuran sesuai gambar 10.00 unit
Pintu Besi P2 uk 3 x 3 m2, di ruang Pompa 1.00 unit
Tangga alumunium 10.00 unit
Piping Works
Pipa Dinding (Wall pipe) steel galvanis, termasuk plat pudle t=3mm
- Pipa Inlet ND. 900 mm 2.00 buah
- Pipa Outlet ND. 900 mm 2.00 buah
- Pipa Overflow ND. 600 mm 4.00 buah
Pipa inlet dari IPA ke Reservoir
- Pipa Steel Ø 900 mm AWWA C200 ASTM A283, pipa inlet 10.00 m'
- Bend 45° Las Steel ND. 900 2.00 buah
- Butterfly With Worm Gear and Handwheel PN.16 DN. 900 mm 2.00 buah
Pipa Outlet
- Pipa Steel ND. 900 mm, AWWA C200 ASTM A283, Pipa Hisap 8.00 m'
- Dismantling Joint CI 900 mm 2.00 buah
- Butterfly Gear 900 mm 2.00 buah
- Pipa Steel ND. 1800 mm, AWWA C200 ASTM A283, Pipa Header 20.00 m'
- Flanges Las PN 16 ND Buta 1800 mm 1.00 buah
Pipa Overflow
- Pipa GIP Klass Medium ND. 600 mm 6.00 m'
- Bend 90 All flange CI ND. 600 mm 2.00 buah
- Loose flange Steel ND. 600 mm 6.00 buah
Pipa Drain
- Pipa GIP Medium A ND. 300 mm 12.00 m'
- Bend 90 All flange CI ND. 300 mm 1.00 buah
- Tee All flange CI ND. 300x300x300 mm 1.00 buah
- Loose flange steel ND. 300 mm 9.00 buah
Thrus Block K-175 Pembesian 125 Kg/m3
- Lokasi Semua meter induk, 0.6x1.4x1.2m, dan ruang pompa 10.00 buah
Other Works
Water proofing non toxin dinding dalam resevoar 8,372.00 m²
Water level control (clear PVC ND 1") 2.00 unit
Pengecatan dinding luar resevoar dan ruang valve 4,984.00 m²
Pengecatan pekerjaan besi dan perpipaan 162.00 m²
Lampu penerangan di ruang pompa lengkap dengan 10.00 titik
kabel dan saklar
Pemasangan Realing 40 mm Galvanis 75.00 m'
750,000.00 210,000,000.00
111,935.00 2,106,168,960.00
267,760.00 629,771,520.00
294,710.00 138,631,584.00
66,870.00 74,894,400.00
50,000.00 884,800,000.00
-
-
300,000.00 156,800,000.00
90,000.00 47,040,000.00
55,000.00 28,746,666.67
14,500,000.00 29,000,000.00
-
-
1,265,489.47 297,643,124.02 BESI 200 KG/M3
-
1,600,000.00 1,655,360,000.00
30,232.70 6,255,749,249.40
500,000.00 5,173,000,000.00
-
1,600,000.00 1,749,696,000.00
30,232.70 6,612,253,188.84
500,000.00 5,467,800,000.00
-
1,600,000.00 1,058,112,000.00
30,232.70 3,998,697,171.48
500,000.00 3,306,600,000.00
-
1,600,000.00 362,144,000.00
30,232.70 1,368,573,637.26
500,000.00 1,131,700,000.00
-
1,600,000.00 255,664,000.00
30,232.70 966,176,466.81
500,000.00 798,950,000.00
80,180.00 33,675,600.00
-
-
-
1,100,000.00 11,000,000.00
13,500,000.00 13,500,000.00
3,100,500.00 31,005,000.00
-
-
-
5,617,352.00 11,234,704.00
6,740,822.40 13,481,644.80
3,216,876.00 12,867,504.00
-
6,355,837.65 63,558,376.55
18,362,500.00 36,725,000.00
369,224,212.50 738,448,425.00
-
6,250,000.00 50,000,000.00
55,146,562.50 110,293,125.00
311,746,250.00 623,492,500.00
13,500,000.00 270,000,000.00
19,218,871.88 19,218,871.88
-
349,800.00 2,098,800.00
2,736,000.00 5,472,000.00
1,203,600.00 7,221,600.00
583,000.00 6,996,000.00
540,000.00 540,000.00
1,840,000.00 1,840,000.00
242,660.00 2,183,940.00
-
3,037,120.00 30,371,200.00
-
-
92,370.00 773,321,640.00
10,000,000.00 20,000,000.00
22,869.94 113,983,756.04
195,620.00 31,690,440.00
330,000.00 3,300,000.00
-
650,000.00 48,750,000.00
47,850,242,095.74
2,990,640.13
LAGOON
PEKERJAAN TANAH
Pengukuran dan pemasangan bouwplank 256.60 m²
Galian tanah sedalam sampai kedalaman di tentukan dalam gambar 12,440.00 m³
Buangan tanah sisa galian keluar lokasi 12,440.00 m³
Urugan Sirtu (jalan masuk truk) 642.06 m3
Pengadaan Pompa Penguras submersible Pump (Lagoon) kap. 5.5 2.00 unit
l/det H = 14mka, casing CI dan impele DCI semi open, Lengkap dengan
motor 1,5 kW, 3x380V, 50Hz
Pemasangan Pompa Penguras submersible Pump (Lagoon) kap. 5.5 2.00 unit
l/det H = 14mka, casing CI dan impele DCI semi open, Lengkap dengan
motor 1,5 kW, 3x380V, 50Hz
61,075.00 15,671,845.00
160,130.00 1,992,017,200.00
39,824.00 495,410,560.00
267,760.00 171,917,021.66
-
-
1,397,135.00 2,171,410,591.09
-
1,393,910.00 196,398,713.01
30,232.70 511,166,062.84
410,277.45 75,620,616.42
-
294,710.00 3,642,615.60
1,225,630.74 7,574,398.00
1,393,910.00 117,208,316.26
30,232.70 305,057,567.01
410,277.45 34,914,611.00
74,752.30 13,078,363.40
74,752.30 126,829,760.58
34,071,000.00 272,568,000.00
20,250.00 728,595,000.00
-
-
-
364,375.00 4,372,500.00
456,500.00 1,826,000.00
1,065,000.00 2,130,000.00
1,125,000.00 2,250,000.00
-
17,000,000.00 34,000,000.00
-
-
-
2,550,000.00 5,100,000.00
-
7,288,759,741.87