Date: October 10, 2019

HILMARC'S CONSTRUCTION CORP. Validity Date: 60 Days


1835 E. Rodriguez Sr., Ave., Cubao Quezon City Terms of Payment: Progress Billing
Warranty: 1 year warranty against delamination
Attention: Ms. Goldamier De Villa

:NATIONAL GOVERNMENT ADMINISTRATIVE CENTER


PROJECT (NGAC) Athletics Stadium

LOCATION : NEW CLARK CITY, CAPAS, TARLAC


SUBJECT : PAINTING OF CATWALK, COLUMNS & BEAMS (ENTRANCE AREA)
SUBCON : PIONEER SPECIALTY BUILDING SYSTEMS INC.

Unit Rate
Item Description Quantity Unit Total Cost Remarks
Material Labor Total

CATWALK BEAM 235 m² 161.00 69.00 230.00 54,096.00


JOTUN- CHARCOAL GRAY (1 Coat Only)

BEAMS- ENTRANCE AREA (GROUND FLOOR) 89 m² 161.00 69.00 230.00 20,396.40


JOTUN-GRAY (1 Coat Only)

PWD 53 m² 161.00 69.00 230.00 12,144.00


JOTUN-LAHAR GRAY (1 Coat Only)

BEAMS- ENTRANCE AREA 2ND FLOOR) 369 m² 161.00 69.00 230.00 84,897.60
JOTUN-GRAY (1 Coat Only)

MANHOLE IN PUBLIC TOILET 9 m² 140.00 60.00 200.00 1,770.00


LATEX PAINT-LAHAR GRAY (1 Coat with Primer)

Delivery & Mobilization Cost (For Misc.) 30,000.00


Installation of Scaffoldings 62,400.00

TOTAL AMOUNT inclusive of VAT Php 265,704.00