Title : Basic wiring practice using Single, 3-way and 4-way switches
Performance Objective: Given all the materials and tools, you should be able to Terminate and
connect electrical circuit given in an illustration 4.1.1.
Supplies/Materials:
 Wire 2.0 mm2/ #14
 Wire Nut
Equipment:
 EIM Table Mock-Up
 Set of pliers (Long Nose, Combination plier and diagonal side cutter)
 Analog/Digital Multimeter

Steps / Procedure:

1. Perform the four circuit (Illustration 4.1.1) from basic to


complex.
2. Using the EIM Table Mock-up, connect the
corresponding wire for a given circuit in a junction box.
Make sure all the wires are all inside the conduit.
3.
4. Before turn-on the circuit breaker, check your wiring
with multimeter.

Illustration 4.1.1

Assessment Method:
Practical Demonstration, Observation, Performance Criteria checklist, Rubric

Performance Criteria Checklist 4.1-1

CRITERIA Yes No
Did you….
Prepare all the tools and materials needed?
Connect the wiring in a lamp controlled by own switch?
Connect the wiring in two lamps controlled by its own switch?
Connect the wiring in a lamp controlled in two locations and three locations?
Perform your task in a given period of time?
Apply OHS procedures?