Project Charter - Construccion de Carro
Project Charter - Construccion de Carro
Rental
All in Labor Equipment
Cost Estimate Labor Hours Rate ($/hr) Labor Costs Expenses Material Costs Costs Total Costs Notes
1.0 Develop Electric Car 878 $ 17,560.00 $ 3,450.00 $ 1,700.00 $ 1,400.00 $ 24,110.00 (1)
1.1 Initiating
1.1.1 Develop Scope and Plan 30 $ 20.00 $ 600.00 $ 600.00
1.1.2 Engage Stakeholders 60 $ 20.00 $ 1,200.00 $ 1,200.00
1.1.3 Raise Funds 40 $ 20.00 $ 800.00 $ 400.00 $ 1,200.00 (3)
1.2 Planning
1.2.1 Systems Design 120 $ 20.00 $ 2,400.00 $ 2,400.00
1.2.2 Cost Estimate 100 $ 20.00 $ 2,000.00 $ 2,000.00
1.2.3 Approvals 20 $ 20.00 $ 400.00 $ 400.00 (4)
1.3 Construction
1.3.1 Purchase Materials 40 $ 20.00 $ 800.00 $ 2,000.00 $ 2,800.00 (5)
1.3.2 Rent Equipment 40 $ 20.00 $ 800.00 $ 1,000.00 $ 1,800.00 (5)
1.3.3 Engage Specialist 20 $ 20.00 $ 400.00 $ 200.00 $ 600.00 (2)
1.3.4 Complete Assembly 240 $ 20.00 $ 4,800.00 $ 4,800.00
1.4 Testing
1.4.1 Component Testing 40 $ 20.00 $ 800.00 $ 200.00 $ 1,000.00 (7)
1.4.2 Track Testing 20 $ 20.00 $ 400.00 $ 400.00 $ 800.00 (6)
1.5 Competition
1.5.1 Travel 48 $ 20.00 $ 960.00 $ 1,850.00 $ 2,810.00 (8)
1.5.2 Event 30 $ 20.00 $ 600.00 $ 800.00 $ 1,400.00 (9)