COST ESTIMATE
UNIT COST
ITEM NO. WORK DESCRIPTION QTY UNIT AMOUNT
(Labor+Matls.)
A. MAJOR WORKS
1.00 Epoxy Injection on Girder & Deckslab 620.00 m. 3,655.00 2,266,100.00
2.00 Patching on Abutment Cap, Piers, Deckslab & Girders 1.75 m³ 493,924.76 864,368.33
3.00 Carbon Fiber Plate bonding on Girder 47.70 m² 201,085.40 9,591,773.58
4.00 Carbon Fiber Sheet bonding into Girders,Deckslab & Piers (2 Layers) 1,202.00 m² 18,522.00 22,263,444.00
5.00 Protective Coating for Concrete ( Girders, Deckslab & Piers) 1,147.00 m² 3,677.90 4,218,551.30
6.00 Installation of Asphaltic Plug Joint 24.00 m 46,500.00 1,116,000.00
7.00 Finger Type Expansion Joint (both approach) 16.00 m 212,489.54 3,399,832.64
8.00 Provision/Installation of Corbel (ABUT-A/ 6 GIRDERS) 6.00 pcs 85,437.19 512,623.14
B. OTHERS
9.00 Traffic Management 5.00 mos. 7,000.00 35,000.00
10.00 Project Billboards 5.00 sets 5,000.00 25,000.00
11.00 Health and Safety 1.00 l.s 25,000.00 25,000.00
12.00 Progress Photographs 1.00 l.s 15,000.00 15,000.00
13.00 Scaffolding & Platforms (Rental) 1.00 l.s 300,000.00 300,000.00
14.00 Rental & Maintenance of Field Office 5.00 mos. 25,000.00 125,000.00
15.00 Provide Equipment & Facilities for the Engineers 1.00 l.s 25,000.00 25,000.00
16.00 Mobilization / Demobilization Cost 1.00 l.s 100,000.00 100,000.00