ALPHATEC CHEMICAL CORP.

www.alphatecphilippines.com

PROJECT : PROPOSED STRUCTURAL RETROFITTING OF MABULOD BRIDGE Date : NOV. 18,2019


LOCATION : SAN JOSE, TARLAC
CLIENT : Appro: 45,000,000.00

COST ESTIMATE

UNIT COST
ITEM NO. WORK DESCRIPTION QTY UNIT AMOUNT
(Labor+Matls.)
A. MAJOR WORKS
1.00 Epoxy Injection on Girder & Deckslab 620.00 m. 3,655.00 2,266,100.00
2.00 Patching on Abutment Cap, Piers, Deckslab & Girders 1.75 m³ 493,924.76 864,368.33
3.00 Carbon Fiber Plate bonding on Girder 47.70 m² 201,085.40 9,591,773.58
4.00 Carbon Fiber Sheet bonding into Girders,Deckslab & Piers (2 Layers) 1,202.00 m² 18,522.00 22,263,444.00
5.00 Protective Coating for Concrete ( Girders, Deckslab & Piers) 1,147.00 m² 3,677.90 4,218,551.30
6.00 Installation of Asphaltic Plug Joint 24.00 m 46,500.00 1,116,000.00
7.00 Finger Type Expansion Joint (both approach) 16.00 m 212,489.54 3,399,832.64
8.00 Provision/Installation of Corbel (ABUT-A/ 6 GIRDERS) 6.00 pcs 85,437.19 512,623.14

B. OTHERS
9.00 Traffic Management 5.00 mos. 7,000.00 35,000.00
10.00 Project Billboards 5.00 sets 5,000.00 25,000.00
11.00 Health and Safety 1.00 l.s 25,000.00 25,000.00
12.00 Progress Photographs 1.00 l.s 15,000.00 15,000.00
13.00 Scaffolding & Platforms (Rental) 1.00 l.s 300,000.00 300,000.00
14.00 Rental & Maintenance of Field Office 5.00 mos. 25,000.00 125,000.00
15.00 Provide Equipment & Facilities for the Engineers 1.00 l.s 25,000.00 25,000.00
16.00 Mobilization / Demobilization Cost 1.00 l.s 100,000.00 100,000.00

TOTAL ESTIMATED PROJECT COST 44,882,692.99

Prepared by: Noted by:

R.H.VICENCIO ROLANDO M. ROMERO


Project Engineer Executive Vice President