MS - RCD Bored Pile
MS - RCD Bored Pile
MS - RCD Bored Pile
OF PALU IV BRIDGE
Contract No. :
METHOD STATEMENT
Table of Contents
1. Introduction ....................................................................................................................................................... 2
3. Materials ............................................................................................................................................................. 2
5. Manpower........................................................................................................................................................... 3
6. Method of Work................................................................................................................................................ 4
Page 1 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
1. Introduction
Reverse circulation drilling or RC drilling is a method of drilling which uses dual wall drill rods that
consist of an outer drill rod with an inner tube. These hollow inner tubes allow the drill cuttings to be
transported back to the surface in a continuous, steady flow. In non-cohesive ground condition, a
temporary steel casing is inserted to prevent soil collapse or ground water inflow. The casing is either
screwed using the rig or vibrated into place using ancillary service crane. Further explanation of RCD
bored pile method will be explained below.
All the information in this method statement are reference only. Actual method statement for
implementation will be submitted for approval before implementation
2. Scope of works
The scope of work is as follow:
3. Materials
Material that will be used are as follow:
- Reinforcement bar
- Concrete materials
- Rebar wire
- Tremie pipe
- Osterberg cell (O-Cell) (if necessary)
- Sonic logging tube
- Water
- Grouting
- Bentonite/polymer
Page 2 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
- Temporary casing
- Plugging ball
4. Construction Equipment
Equipment that will be used are as follow:
- Survey equipment
- Dump truck
- Crawler crane
- Hand tools
- Bar bender
- Bar cutter
- Truck mixer
- Concrete pump (if necessary)
- Welding machine
- Temporary steel casing
- RCD machine set
- Vibro-hammer
- Excavator
- Generator set
- Koden machine
5. Manpower
Allocated manpower shall be as follow:
- Supervisor (1)
- Safety officer (1)
- Driver (5)
- Operator (3)
- Surveyor (1)
- Ast. Survey (1)
- Skilled/unskilled Worker
Actual manpower shall be adjusted according to the current situation required at site.
Page 3 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
6. Method of Work
6.1. Working Sequence
Pile boring is planned to use 2 set of RCD machine, working parallelly. The 1st sequence is piling
on Pier 1 & Pier 2, then the 2nd sequence is on Abutment A & Abutment B.
6.2. Preparation
Surveyor to start marking the pile position/temporary steel casing location on the embankment
platform.
Piling marking
Pile marking in accordance with the latest and approved shop drawings. After the marking has
been done, temporary steel casing can be installed using vibro-hammer or other method, as can
be seen on figure below.
Page 4 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
Necessity of temporary steel casing is determined in accordance with the soil condition, and if
temporary steel casing is needed, the length will be determined later in accordance with the soil
condition.
Page 5 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
Surveyor to continue to supervise the temporary steel casing installation, this intended to make
sure that the location point of the pile is correct and the verticality is maintained.
Page 6 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
When boring, water, bentonite or polymer slurry is used, the function of the bentonite slurry
and/or polymer are to stabilize the wellbore, and controlling the formation pressure so that the
side of the wellbore is stable and not collapsed or eroded. Also, the slurry can help cooling and
lubricating the drill string and drill bit.
Slurry top elevation shall always be kept more than 2 meters above the underground water, or
river water (whichever is higher).
Verticality and the diameter of the borehole shall be checked by using Koden machine during
and/or after completion of the drilling.
Removal of the sediment will be done in accordance with the specification in 2 steps, the 1st
removal of sediment is before rebar cage installation, and the 2nd removal of sediment is done
before concrete casting.
Page 7 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
With pile diameter is 1.8 m, and pile depth is 60 m, assuming the reinforcement steel bar weight
per cubic concrete is 150 kg/m3, the total weight of concrete pile rebar that will be lifted is around
23 tons. Rebar will be lifted using crawler crane 50T, with 24.4 m boom length, working angle of
76°, and working radius 6 m as can be seen on lifting table below.
Page 8 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
Reinforcement steel bar installation (for test pile with O-Cell – if necessary).
Page 9 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
2nd set of reinforcement steel bar installation (for test pile with O-Cell – if necessary).
Install O-Cell (if necessary) for Bidirectional Load Test in rebar cage for the test pile, and install
sonic logging pipe in rebar cage for later used for grouting the O-Cell installed pile after testing.
Page 10 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
Concrete casting until nearly top of the pile cap, so that after pile head cutting, there still have
rebars as a starter bar and connecting from concrete piles to pile cap.
Page 11 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
Concrete soundness shall be checked by Sonic Logging after 3-7 days (or accordance with the
specification).
Page 12 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
1) Ensure that all safety precautions and recommendations outlined in the Risk Assessments have
been applied.
All personnel including Third Parties are safety inducted prior to site entry.
Operators are qualified, hold license for machine operation and trained in the maintenance of
machinery.
3) Provide First Aid Facility on working Site in case of minor injury treatment.
4) Arrange for all personnel the pertinent Personal Protective Equipment (PPE) including safety
helmet, safety boots (Boots up to the knees are required when clearing shrubs and trees, to avoid
snake bites), ear / eye protectors, dust mask, gloves and reflective vest (When working in vicinity
of the road or nearby the excavator or other heavy machines).
5) Place warning signs, barricades, lightings or fences at relevant locations such as:
Critical excavations.
Access roads where traffic flow is disturbed by the work – use signalmen wearing high visibility
clothes to arrange traffic.
6) Investigate fall prevention method to identify the presence of any abandoned wells or drainage
systems to prevent personals from falling in it.
7) Ensure safe access to the Site Area and maintain the permanent and temporary access roads in a
good condition during construction activities.
8) Ensure on-site earth moving operation such as site levelling, excavation, cut and fill, pile boring,
etc. to have proper maintenance and proper disposal location to avoid damage to surrounding
environment.
9) Ensure vehicle movement route, in and out, and along the project area.
10) Ensure dump truck carrying excavated soil (in and out project site and along route to disposal area)
is properly checked to avoid accidental load spillage.
Page 13 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile
PALU IV BRIDGE, CENTRAL SULAWESI, INDONESIA
11) Ensure proper management to vegetative wastes from the clearing of vegetation within ROW,
Scheduled wastes, particularly oil and grease form leakage, spills, cleaning and — sloughing
associated with vehicle and equipment engines and suspensions, leaking and breaks in hydraulic
systems, and waste oil disposal.
Page 14 of 14
Method Statement
Reversed Circulation Drill (RCD) Bored Pile