SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.

00 30-Jun-16
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Asphalt Core Density Testing Inspection SAIC-Q-1043 15-Nov-17 MAH-SA-C-3189
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

HAWIYAH AND HARADH DEVELOPMENT SATELLITE GAS COMPRESSIO10 - 01996 / 0007 MOFARREH AL-HARBI & PARTNERS
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.

LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.

SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
SATIP-Q-006-02 3.7
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
W H
ITEM RE-INSP
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A
No. DATE

A Field Sampling

Note: To verify that the area/material being inspected was tested by a SA


approved third party testing agency, the test results attached with this
RFI shall be verified by the relevant PID inspection Unit if copy of the test
results had been received directly from the 3rd party lab. If not available
in the PID inspection Unit, the inspector shall contact the third party lab
rep and request for an explanation. If explanation is not reasonable, NCR
shall be issued to the 3rd party lab through the Batch Plants & Civil
Testing Group.

Cores for density and thickness test shall be taken daily from previous days
production at the following rates:
SAES Q-006
A1 For 0 to 4000m2 1 core per 600 m2 Sec.
For 4000 m2 to 20,000 m2 1 core per 900 m2 5.4.4.3

For more than 20,000m2 1 core per 1,200 m2


SAES Q-006
Each core shall be legibly and permanently marked as to the location from
A2 Sec.
which core was taken.
5.4.4.3
SAES Q-006
Measurement of any core shall not be deficient by more than 10mm or 15% of
A3 Sec.
the design thickness, whichever is less.
5.4.4.7.B
B Laboratory Testing

Tests are performed by a Saudi Aramco approved independent laboratory in


SAES Q-006
B1 accordance to applicable Standards in the presence of Contractor and Saudi
Sec. 5.4.5
Aramco Representatives.

Third Party Agency's Quality Personnel assigned to the Work must be


Schedule "Q"
B2 technically competent to perform their duties and shall have a recommendation
Section 5.5
for approval from Saudi Aramco to perform applicable Tests.

SAES Q-006
Core compaction requirements shall be equal to or greater than 95% of
B3 Sec.
Marshall density per ASTM D6926, using material sampled at the road site.
5.4.3.B

Areas of asphalt which fail to meet the required tolerances/compaction shall be SAES Q-006
B4 removed by saw cutting to the full depth of the wearing course and base Sec.
course. 5.4.3.D

REMARKS:

REFERENCE DOCUMENTS:
1- SAES-Q-006 -- Asphalt and Sulfur Extended Asphalt Concrete Paving, 22 May 2016
2- Schedule "Q" -- Project Quality Requirements

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: Work
T&I Witnessed QC Record Reviewed
Verified
Name, Initials and Date: Name, Initials and Date:
Mr. Tahir Muhammad
QC Inspector PID Representative
Work
Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed
Verified
Name, Initials and Date: Name, Initials and Date:
Mr. Hedayat Ullah Khan Mr. Reynold Casidsid
QC Supervisor Proponent and Others
Work
Quality Record Approved: T&I Witnessed QC Record Reviewed
Name, Organization, Verified
Name, Sign and Date:
Mr. Rehman Ali Initials and Date:

*Person Responsible for Completion of Quality Work/Test Y = YES N = NO F = FAILED


SAUDI ARAMCO ID/PIEU - 15-Nov-2017 - REV. 2016.06.00 (Standards Cutoff -June 30, 2016) Rev. 2016.06.00 30-Jun-16
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Asphalt Core Density Testing Inspection SAIC-Q-1043 15-Nov-17 CIVIL -
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR

ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.

Core compaction requirements shall be equal to or greater than 95% SAES Q-006
B3 of Marshall density per ASTM D6926, using material sampled at the Sec.
road site. 5.4.3.B

Areas of asphalt which fail to meet the required SAES Q-006


B4 tolerances/compaction shall be removed by saw cutting to the full Sec.
depth of the wearing course and base course. 5.4.3.D

REMARKS:

REFERENCE DOCUMENTS:
1- SAES-Q-006 -- Asphalt and Sulfur Extended Asphalt Concrete Paving, 22 May 2016
2- Schedule "Q" -- Project Quality Requirements

Contractor / Third-Party Saudi Aramco


Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Inspector PID Representative


Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:

QC Supervisor Proponent and Others


Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:

*Person Responsible for Completion of Quality Work/Test Y = YES N = NO F = FAILED

Saudi Aramco: Company General Use