Daily Report CSK - 09'jan'2020

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Project : PEKERJAAN PEMBUATAN TANGGUL PERLUASAN KOLAM TAILING WP 6-9

Contractor : PT. Cemerlang Samudra Kontrindo

Daily Report

Date : 9-Jan-20 Thu Weather Conditions □ Clear ☑ Cloud ☑ Rain


Location of Work :
☑ Temporary Access Road □ 0,7 Ha Area ☑ 1,7 Ha Area
□ 7,4 Ha Area □ 1,0 Ha Area
No. of personal : List of Equipment : Safety Reporting :
1) Management Staff Wheel Loader
Manager 1 Excavator 3 1. Gunakan seragam kerja, safety
Supervisor 1 Dump Truck 20 Ton 8 shoes, radio/HT dan helm
Engineer 1 Bulldozer/Grader 3 2. Antisipasi jalan licin saat hujan
Safety Officer 1 Vibrator Roller 3
Mechanician/Electrician 4 Mobile Crane
Subtotal(1) 8 Trailer
2) Labours Water Tank / Sprayer 1
Surveyor 2 Generator 1
Oilman 1 Air Compressor 1
Foreman 2 Welding Machine 1
Worker 8 Sheet Piling Machine
Operator/Driver 20 Others (light truck) 4
Carpenter Total Station 1
Subtotal(2) 33
TOTAL(A) 41 TOTAL(B) 26
Work Description : 9-Jan-20 Planned Work schedule: 10-Jan-20

1. Pemadatan & finishing tanggul H-G-L 1. Timbunan / peninggian tanggul G-F


2. Grading & compacting tanggul E-F-G 2. Topo tanggul H-G-L elv. +40.342
3. Perbaikan jalan akses (grading & compacting) 3. Perbaikan jalan akses (grading & compacting)

Last Progress Last Update

Current Progress Next Plan

Detail of Delays : Delivery Schedule


1. Permasalahan lahan yg belum bebas Description Date Prepared By
2. Pengendalian genangan air di lahan tambahan 2 unit Excavator PC310 Januari 2020
sekitar tanggul A-B -
3. Hujan jam 15:16 s/d malam -
operasional dihentikan selama hujan -
karena kondisi jalan becek/licin -
- Jasriadi

PT. Cemerlang Samudra Kontrindo Page 1


Project : PEKERJAAN PEMBUATAN TANGGUL PERLUASAN KOLAM TAILING WP 6-9
Contractor : PT. Cemerlang Samudra Kontrindo

Daily Report

Note / Attachments :

Foto unit standby saat hujan Foto kondisi akses quary (Minsiluy) becek/licin

Foto progress penimbunan

Foto situasi pengambilan material di quary (Minsiluy)

Foto grading tanggul F-G dan finishing H-G-L

PT. Cemerlang Samudra Kontrindo Page 2