LABOUR :
Mason 2nd Class Each 7.00000 158.67 1110.69
Beldar each 10.80000 116.67 1260.04
Beldar Each
(Skilled)for rubbing and polishing Each 10.80000 116.67 1260.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3780.75
Labour for cement mortar 1:4 28.74
TOTAL : 3809.49
WATER CHARGES @ 1.5% : 147.56
TOTAL : 3957.05
ADD FOR CONTRACTORS PROFIT @10% : 395.70
ADD FOR OVER HEAD CHARGES@5% : 197.85
LABOUR FOR 10.000sqm. 4550.60
LABOUR PER sqm. 455.05
13550000 Kota stone slab 25 mm thick in
risers of steps,skirting dado
and pillars laid on 12 mm
(average) thick cement mortor
MATERIAL :
CARRIAGE :
Cement
1 KM BY MECH. TRANSPORT 1 Tonne 0.06400 73.95 4.73
LABOUR :
Mason 2nd Class Each 6.50000 158.67 1031.36
Beldar Each 10.80000 116.67 1260.04
Beldar Each
(Skilled)for rubbing and polishing Each 10.80000 116.67 1260.04
LABOUR RATE :
ACTUAL LABOUR+SUNDRIES 3704.38
Labour for cement mortar 1:3 18.48
TOTAL : 3722.86
WATER CHARGES @ 1.5% : 126.78
TOTAL : 3849.64
ADD FOR CONTRACTORS PROFIT @10% : 384.96
ADD FOR OVER HEAD CHARGES@5% : 192.48
LABOUR FOR 10.000sqm. 4427.08
LABOUR PER sqm. 442.70
13560000 20 cm flagged stone flooring
laid in cement mortor 1:5 (1
cement :5 sand)
Detail of cost for 10 sq.m.
MATERIAL :
Stone
10 square metre x20 cum. =2.00 cum
Add for wastage @ 10% =0.2 cum
-------------
Total=2.20 cum
1 cum 2.20000 350.00 770.00
CARRIAGE :
LABOUR :