A Multiple Counter Plan Is Used in Counter Based
A Multiple Counter Plan Is Used in Counter Based
A Multiple Counter Plan Is Used in Counter Based
Below are the list of basic Master data required to process Multiple Counter Plan.
Equipment
Characteristics for measuring point / counter
Measuring Point/Counter assigned to Equipment
Cycle sets as per requirement
We are going to record the running hours of the Pump. To record the running hours we need
to create measuring point / counter.
Create the Measuring point for Equipment, enter the object type IEQ
To make the measurement point as a Counter, you need to check “MeasPoint is counter”
Ensure characteristics you want to assign to measuring point / counter were created
In the measuring counter, you need to maintain below fields
Header 1
Meas Position
Description
Characteristics
Counter Overflow reading
Annual Estimate
MeasPosition – This describes the position of the measuring point / counter with respect to the Technical Object.
Counter Overflow reading – The first counter reading that the counter cannot display. Enter a logical value for the first counter
reading.
Annual Estimate – Estimated hours the equipment can run in a year. This needs to be filled, maintenance intervals
are calculated based on this data.
On save, first measurement document created for measuring point / counter. Two documents are
posted for this measuring point / counter.
Cycle sets are used as a copy model for the creation of multiple counter plan. It defines the
period of time between two maintenance tasks. Also cycle sets can be complied directly in
multiple counter plan itself.
Select the Maintenance plan category and Cycle set (Cycle set not mandatory)
Press Enter
Cycle set sequence needs to be filled and same has to be linked to maintenance item. Here
the scenario has only one cycle set sequence.
Cycle set sequence, Scheduling period, Start date will be populated in the multiple counter
maintenance plan (IP43) after activating the “Configure Special Functions for Maintenance
Planning” in SPRO.
Kindly update the maintenance plan with relevant details like Maintenance Plan Description,
Maintenance Item Description, Order Type, Planner Group, Work Center, Task list and Priority.
Kindly refer the scheduling column for the Operation type and difference on scheduling the maintenance plan.
On scheduling the plan, we need to consider the Operation Type and the behavior of scheduling
will be different based on the type.
OR Operation Type:
For an OR Operation, a maintenance order is generated for the earliest possible planned date.
In our case, if the maintenance is due every 250 hrs or 3 months, the decisive factor is which
occurs first.
On scheduling the Maintenance plan
Since the measuring counter reading is already reached 250, a maintenance is already due, on
save, work order will be generated.
For an AND Operation, a maintenance order is generated for the last planned date.
In our case, if the maintenance is due every 250 hrs or 3 months, the decisive factor is which
occurs last.
Measuring counter is reached, but the 3 months is not reached so the maintenance is planned
for the future date based on the start date.
Here I have covered the basic scenario of Multiple Counter Plan, there are lot of options
available to explore in this area.