M & E DIVISION

P.O. BOX:23980 P.O. BOX:23773


DOHA - QATAR DOHA - QATAR

METHOD STATEMENT

PROJECT : AL WAAB CITY


PACKAGE : 007.2 & 007.3-VILLA B & C
CLIENT : M/s. AL WAAB CITY
PROJECT MANAGER : M/s. CANSULT Ltd.
SUPERVISOR COSNULTANT : M/s. ECG (ENGINEERING CONSULTANTS GROUP)
MAIN CONTRACTOR : M/s. ARABTEC CONSTRUCTION COMPANY
MEP SUB. CONTRACTOR : M/s. ETA ENGINEERING & CONTRACTING

.TITLE: TESTING & COMMISSIONING OF MEP WORKS

DOCUMENT : ETA/MS/MEP/B1-REV 0

DISCIPLINE: MEP

Total no. of pages:- 16

Testing Commissining Page 1 09/12/2009


Testing Commissining Page 1 09/12/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction C
MEP Contractor :ETA Engg. & Contractin
METHOD STATEMENT
Rev.: 00 Date 09.12.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

INDEX

S. No. Contents Pag


1 Purpose

2 Scope

3 Reference documents

4 Responsibilities

5 Method of T & C 4

6 Villa type B1 Testing & Commissioning plan (For 1Villa)

7 Manpower Requirements

8 Equipment & Tools

9 Health & Safety Precaution

10 Reference

Testing Commissining Page 2 09/12/2009


Testing Commissining Page 2 09/12/2009
Client : M/s AL WAAB CITY
Project Manager : M/s Cansult Ltd.

Main Contractor : Arabtec Construction Co. M & E DIVISION


MEP Contractor :ETA Engg. & Contracting.
HOD STATEMENT
09.12.2009
Discipline: MEP
METHOD STATEMENT

Page No.
3

4 to 14

15

15

16

16

Testing Commissining Page 2 09/12/2009


Testing Commissining Page 2 09/12/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor : ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 09.12.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

1. Purpose:
The Purpose of this Method statement is to describe the Testing & Commissioning methodology for villas regards
works at Al Waab city Project.

2. Scope:
This method statement is applicable for Testing & Commissining of Mechanical, Electrical and Plumbing systems
in villa type B1 of Alwaab city project.

3. Referance Document:
Testing & Commissioning Manual
*Part 1 - Testing & Commissioning specifiction submitted.
*Part 2 - Testing & Commissioning Proceduce Manual submitted.

4. Resposibilities:
4.1 The Project Managar is over all responsible for implementation of this Method statement and to ensure that
his T & C team of Engineers and Supervisors are aware of this Method statement and all resources such as
manpower, material and equipment are available to carry out the Testing & Commissioning with quality and
without any delay.

4.2 The Project Manager will co-ordinate with the T & C Engineer/T & C Supervisor/Safety Officer for safe and pro
execution to accomplish the works on time as planned and respect the quality of finished works.

4.3 T & C Engineer along with T & C Supervisor will ensure that the T & C is carried out according to the
Specifications/Drawings and this Method Statement.

4.4 QA/QC Engineer, in close interaction with T & C personnel, will ensure that the works are carried out as per
the project requirements. He is also responsible for the implementation of QA /QC related to works as detail
in the procedure and for completing Quality Document for all related works.

4.5 Safety Coordinator / Officer will ensure implemention of all safety procedures, safety measures related to th
nature of works being carried out in accordance with Project HSE Plan and finishing the works with out any dameged
and fatality.
Testing Commissining Page 3 09/12/2009
5. MEP Testing & Commissioning procedure:
Testing & commissioning shall be carried out as per the described procedures in submitted method statements.

Testing Commissining Page 3 09/12/2009


M & E DIVISION
MEP Contractor : ETA Engg. & Contracting.
OD STATEMENT
09.12.2009
Discipline: MEP
METHOD STATEMENT

e Testing & Commissioning methodology for villas regards MEP

missining of Mechanical, Electrical and Plumbing systems

ementation of this Method statement and to ensure that


are of this Method statement and all resources such as
carry out the Testing & Commissioning with quality and

Engineer/T & C Supervisor/Safety Officer for safe and proper

sonnel, will ensure that the works are carried out as per
the implementation of QA /QC related to works as detailed

on of all safety procedures, safety measures related to the


oject HSE Plan and finishing the works with out any dameged

Testing Commissining Page 3 09/12/2009


Testing Commissining Page 3 09/12/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

ELECTRICAL:

Sr.No. Activity Description Method statement ref. Format Re


i Continuity Test ETA-MS-EL-REV 0 CP -E2
ii Insulation / Resistance test (Megger Test) ETA-MS-EL-REV 0 CP -E5
iii Earth Continuity Resistance test (Cables & Wires) ETA-MS-EL-REV 0 CP -E2
iv RCBO Test ETA-MS-EL-REV 0 ETA Standard Fo
v Voltage Calibration Test ETA-MS-EL-REV 0 ETA Standard Fo
vi Illuminance Test ETA-MS-EL-REV 0 CP E7

1) CONITINUITY TEST:

PRE COMISSIONING CHECKS:


A)

B)

C)

D)

Conitinuity test Procedure / method statement:

Step 1:
After the completion of pre-commissioning checks, continuity test between DB and switch / socket points is to
the multimeter reading during this test should always be ZERO between phase and phase (CLOSE);between pha
nautral (OPEN), between phase and earth (OPEN) & between neutral and earth with the tolerance of 1Ω.

Step 2:
After the completion of continuity checks continuity test between DB and switch / socket, we shell proceed wit
continuity test between switch and light points, again the multimeter reading should be zero as described in ste
with the tolerance of 1Ω.
Testing Commissining page 4 09/12/2009
Step 3:
Now the continuity test between the ring circuit and power sockets is to be carried out, The multimeter reading
zero as described in step 1 with the tolerance of 1Ω.

Step 4:
All the reading are to be recorded in a standard format and submitted for final witness / approval.

Testing Commissining page 4 09/12/2009


M & E DIVISION

OD STATEMENT
09.12.2009
scipline: MEP
ETHOD STATEMENT

Format Reference

ETA Standard Format


ETA Standard Format

ontinuity test between DB and switch / socket points is to be started,


s be ZERO between phase and phase (CLOSE);between phase and
between neutral and earth with the tolerance of 1Ω.

test between DB and switch / socket, we shell proceed with the


n the multimeter reading should be zero as described in step 1

Testing Commissining page 4 09/12/2009


power sockets is to be carried out, The multimeter reading should be

Testing Commissining page 4 09/12/2009


Client : M/s AL WAAB CITY
Project : Project Manager : M/s Consult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co. M & E DIVI
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 8.12.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

2) INSULATION RESISTANCE TEST:

PER COMMISSING CHECKS FOR INSULATION RESISTANCE TEST:


A) Check the tightness of connections.

B) Check the arrangement of circuit breakers as per approved scheme.

C) Check all the supporting insulators of MDB/DB.

D) Isolate the cables on incoming & outgoing side of MDB/DB.

Insulation Resistance Test Procedure / Method.

Step 1:
Once the pre-commissioning checks are over, installation resistance test between phase and neutral wires / cable is
to started. The megger value should always be greater then 10MΩ for wires and 50MΩ for cables.

Step 2:
In the next step insulation resistance test between phase and earth wire / cables is to be done. The megger reading
in this care also should be greater then 10MΩ for wire and 50MΩ for cables.

Step 3:
The test between phase and wire / cables is to be carried out in the next stage, the megger reading acceptable are
similar reading should flow the same valve as described in step 1 to step 3.

Step 4:
All the reading should be recorded on a standard for format and submitted for final approval.

page 6 28/10/2009
page 6 28/10/2009
M & E DIVISION

D STATEMENT
8.12.2009
scipline: MEP
METHOD STATEMENT

lation resistance test between phase and neutral wires / cable is

phase and earth wire / cables is to be done. The megger reading

arried out in the next stage, the megger reading acceptable are

page 6 28/10/2009
page 6 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Consult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

3) LUX TEST:

PER COMMISSING CHECKS FOR LUX TEST:


A) Check the electrical components such as light fixtures are connected to the final of circuit of the distri

B) Check the final connection of light fitting with ceiling roses through heat resistance flexible cable whe
applicable such as false ceiling areas.

C) Check the tightness of connections.

D) Check the switching operator

E) Check the installation of light fixtures,make sure supports are supply installed.

Lux Test Procedure / Method.

STEP 1:
To perform the lux level test, select the area where level is to be checked.

STEP 2:
Switch on the lux meter, Measure the reading at four corners and the centre of illuminated area.

STEP 3:
Take the average of all recorded reading for comparison with the design lux level.

STEP 4:
Submit the reading on a standard format for final approval.

4) EARTHING TEST:

PER COMMISSING CHECKS FOR EARTHING TEST:


A) Earthing conductor and its size is as per approved drawing.

B) Check all links and junctions

C) Clamps are as per manufacture's recommendation.


M & E DIVISION

OD STATEMENT
28.10.2009
Discipline: MEP
METHOD STATEMENT

s light fixtures are connected to the final of circuit of the distribution board.

g with ceiling roses through heat resistance flexible cable whenever


Client : M/s AL WAAB CITY
Project : Project Manager : M/s Consult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 8.12.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

5)R.C.B.O. TEST METHOD STATEMENT:

STEP 1:
After a through visual check is conducted, set the leakage current on the instrument before the commencement o
the test.

STEP 2:
Connect the R.C.B.O. tester lead at the socket outlet of the circuit under test, press the test button of R.C.B.O. test
R.C.B.O. should trip.

STEP 3:
Similary at the terminal of any of the light fitting in the lighting circuit, connect the R.C.B.O. tester lead and perform
as mentioned in test I & II.

STEP 4:
All the measurements should be recorded on a standard format and sumitted for final approval.

6)SINGLE PHASE VOLTAGE CALIBRATION:

STEP 1:
240VAC Single Phase Voltage calibration to check the three Phase with reference to neutral.
i.e. R Phase to neutral, Y Phase to neutral and B Phase to neutral.The values should be in the range 220-240VAC.

STEP 2:
For three Phase voltage calibration check the voltage between the three Phase. i.e.Between R-Y,Y-B and B-R.The r
shown by the multimeter to 415-440VAC.

STEP 3:
Record all the reading on a standard format and submit for find approval.
M & E DIVISION

OD STATEMENT
8.12.2009
Discipline: MEP
METHOD STATEMENT

akage current on the instrument before the commencement of peforming

of the circuit under test, press the test button of R.C.B.O. tester, the

he lighting circuit, connect the R.C.B.O. tester lead and perform the test

se to neutral.The values should be in the range 220-240VAC.

e between the three Phase. i.e.Between R-Y,Y-B and B-R.The reading


Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

i) TESTING & COMMISSIONING OF HVAC SYSTEMS:

Sr.No. Activity Description Method statement ref. Format Referen


i Fan Perfomance Test ETA-MS-HVAC-REV0 CP M1.2
ii Air Balancing of HVAC System ETA-MS-HVAC-REV0 ETA Standard Form
iii Refrigerent Line Pressure Test ETA-MS-HVAC-REV0 ETA Standard Form
iv Temperature Mesurement ETA-MS-HVAC-REV0 ETA Standard Form

METHOD STATEMENT FOR I.D.U PERFORMANCE TEST


STEP 1:
After pre- commissioning checks are completed, start the unit by switching on power supply.

STEP 2:
Measure the ampacity of indoor unit with the help of an ameter and voltage with voltmeter. Check whether the
recorded values are in line with that shown in manufacture’s catalogue.

STEP 3:
Measure the air flow rate from the main duct within the range of 2 meters from the indoor unit. Again check
whether the recorded values are in line with that show in manufacture’s catalogue.

STEP 4:
Record all the measurements on a standard format and submit for final approval.

CHARGING:
STEP 1:
After completion of the evacuation, close the end caps and service valve.

STEP 2:
Release the already charged refrigerant to the system by opening both the services valves.

STEP 3:
Switch on the system and check the ampacity and pressure reading.
Page 5 28/10/2009
STEP 4:
Adjust the pressure by charging the refrigerant gas.

STEP 5:
Record the final reading on the standard format & submit for final approval.

Page 5 28/10/2009
M & E DIVISION

OD STATEMENT
28.10.2009
ipline: MEP
METHOD STATEMENT

Format Reference
CP M1.2
ETA Standard Format
ETA Standard Format
ETA Standard Format

it by switching on power supply.

eter and voltage with voltmeter. Check whether the

ge of 2 meters from the indoor unit. Again check

mit for final approval.

ervice valve.

ning both the services valves.

eading.
Page 5 28/10/2009
final approval.

Page 5 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Consult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 8.12.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

A.REFRIGRANET LEAK TEST METHOD STATEMENT


STEP 1:
Connect the regulator inlet to nitrogen cylinder on one end and to Manifold Gauge on the other end.Connect the discha
outlet of manifold to outdoor unit suction service valve. Keep the manifold outlet closed.

STEP 2:
Open the shut off valve of the nitrogen cylinder with cylinder key and regulate the outlet pressure to 200 Psi.

STEP 3:
Open the manifold outlet slowly to allow entry of refrigerant gas into the system.

STEP 4:
Monitor the pressure reading in the discharge gauge, charge the system up to 150 Psi (as per manufacture’s recommend

STEP 5:
Check for any leak in all joints using liquid detergent.

STEP 6:
If any leak is found release the pressure, repair and again repeat the process.

STEP 7:
Hold the pressure for 30 min and recheck the pressure, the reading should be submitted in the standard format for final

B. EVACUATION
STEP 1:
After the pressure test is approved, release the nitrogen by opening suction & discharge service valves to release all the
from the system.

STEP 2:
Close the service valves and connect the suitable vacuum pump manifold gauge to the suction service valve.

STEP 3:
Switch on the vacuum pump, open the manifold gauge valve and suction service valve, ensure that the manifold discharg
and discharge service valve of outdoor unit is fully closed before the vacuum pump is switched on.

STEP 4:
Run the vacuum pump for 1hr continuously and keep monitoring the compound gauge of the vacuum pump.
M & E DIVISION

OD STATEMENT
8.12.2009
Discipline: MEP
METHOD STATEMENT

d and to Manifold Gauge on the other end.Connect the discharge


eep the manifold outlet closed.

der key and regulate the outlet pressure to 200 Psi.

nt gas into the system.

ge the system up to 150 Psi (as per manufacture’s recommendation).

epeat the process.

e reading should be submitted in the standard format for final approval.

y opening suction & discharge service valves to release all the nitrogen

pump manifold gauge to the suction service valve.

ve and suction service valve, ensure that the manifold discharge outlet
before the vacuum pump is switched on.

itoring the compound gauge of the vacuum pump.


Client : M/s AL WAAB CITY
Project : Project Manager : M/s Consult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 8.12.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

AIR BALANCING METHOD STATEMENT


A. INDOOR UNIT AIR BALANCING:

1. Prior to Testing & Commissioning all pre commissioning checks should be carried out.

2. Select the specified speed of the Indoor Unit.

3. Set all the dampers in the Grille outlet at full open position.

4. Take initial flow of the unit by adding up all the measured from of the design flow.

5. Compare the reading against the designed flow. Find out the percentage of the design flow.

6. Find out the index outlet (i.e. which has the very low percentage of reading) from the initial scan.

7. Keep the index outlet damper fully open.

8. Then throttle the air volume at each outlet to get the design percentage of flow proportionally by using the flow hood
hood (Balometer) / anemometer.

9. Each time when you throttle the outlet by closing the diffuser/ grill damper, the index outlet air flow raises gradually.
Measure the index point each time.
proportionally

11. Note all reading at all out lets and keep records.

12. Allowable Tolerance:- +10% of design cfm.

13. Reference codes: - Commissioning – CIBSE TM 43:200F


Indoor units
M & E DIVISION

OD STATEMENT
8.12.2009
Discipline: MEP
METHOD STATEMENT

checks should be carried out.

on.

d from of the design flow.

the percentage of the design flow.

rcentage of reading) from the initial scan.

sign percentage of flow proportionally by using the flow hood

ffuser/ grill damper, the index outlet air flow raises gradually.
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Consult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 8.12.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

B. BALANCING AIR TERMINALS PROCEDURE

Depending upon the location and access to air terminals, various types of air flow measuring instruments will be utilized t
the actual air flow at terminals.Assuming adequate access provided, a direct reading balometer would be used which give
reading in volume rather than velocity, which cancels out need for effective grill areas, terminal configuration considerati
velocity corrections.

If access is restricted then a rotating vane anemometer shall be used and the velocity reading obtained would be convert
volume (velocity X free area = volume).

1. Air quantities shall be measured according to CIBSE application Guide 3/89 standard.

2. Any main branch may be chosen to start with but as normal practice and having carried out a rough balance of main an
branches, start with the most remote branch and then sub-branch.

3. Locate the terminal, which is discharging the lowest percentage of its design flow rate.This is generally the last terminal
If not, adjust the damper in the last terminal until it is working with the same percentage as the lowest one previously

4. Measure the flow from the terminal next to the index and work percentage flow as close as possible to that of the inde
Fix the damper in position.

5. Repeat the procedure for the next terminal, again comparing it with the index.

6. As the dampers a close are along the run, more air will be driven towards the downstream terminals and volume of air
discharged at the terminal index will rise. This does not affect the balancing procedure since each terminal being adjus
is related in turn with the index.

7. When all the terminals have been balanced on a sub- branch, each terminal will be running with an equal percentage
design flow rate, within the allowable tolerances.

8. The flow rates at each terminal must be measured and recorded. Once again a summation should be made to check th
check that the total is in reasonable agreement with the measured sub – branch flow.

9. Test result shall be recorded in the approved test sheets and documents.

10. Allowable Tolerance: - +10% of design cfm.

11. Reference codes: - Commissioning of air system – BSRIA AG3 – 89.2


Air Distribution System – CIBSE CODE A
M & E DIVISION

OD STATEMENT
8.12.2009
Discipline: MEP
METHOD STATEMENT

arious types of air flow measuring instruments will be utilized to record


provided, a direct reading balometer would be used which gives a direct
eed for effective grill areas, terminal configuration consideration and

l be used and the velocity reading obtained would be converted to

ication Guide 3/89 standard.

mal practice and having carried out a rough balance of main and
ub-branch.

entage of its design flow rate.This is generally the last terminal in the run.
orking with the same percentage as the lowest one previously measured.

d work percentage flow as close as possible to that of the index.

aring it with the index.

e driven towards the downstream terminals and volume of air


affect the balancing procedure since each terminal being adjusted

anch, each terminal will be running with an equal percentage of the

ecorded. Once again a summation should be made to check that the


measured sub – branch flow.

and documents.

AG3 – 89.2
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

PLUMBING:

i) PRE COMMISSIONING OF PLUMBING SYSTEM:

Sr.No. Activity Description Method statement ref. Format Referen


i Checking of Water Supply system ETA-MS-PLUM-REV0 CP M2.1
ii Pressur test of Water supply ETA-MS-PLUM-REV0 CP M2.2
iii Pump check list ETA-MS-PLUM-REV0 CP M2.6

ii) TESTING & COMMISSIONING OF PLUMBING SYSTEMS:

Sr.No. Activity Description Method statement ref. Format Referen


i Pump preformance Test ETA-MS-PLUM-REV0 CP M2.7
ii Water supply pressure Test ETA-MS-PLUM-REV0 CP M2.2
iii Temperature Measurment ETA-MS-PLUM-REV0 CP M2.4, CP M2.
iv Gravity Flow Test ETA-MS-PLUM-REV0 ETA Standard Form

Page 5 28/10/2009
Page 5 28/10/2009
M & E DIVISION

OD STATEMENT
28.10.2009
ipline: MEP
METHOD STATEMENT

Format Reference
CP M2.1
CP M2.2
CP M2.6

Format Reference
CP M2.7
CP M2.2
CP M2.4, CP M2.5
ETA Standard Format

Page 5 28/10/2009
Page 5 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT
THE TEST REQUIREMENT:
“The water system shall be capable of withstanding an internal water pressure not less than 11/2 times the maximum pressure
installation or relevant part is designed to be subjected in operation.“ So, for water piping system that will operate at 3-bar the
will be 3 x 1.5 = 4.5bar. Pressurize the system to 11/2 times the normal maximum pressure, stop pumping and wait for 1 hour t
pressure loss is indicated whilst checking the system for visible signs of leakage.

The whole system is subjected to the test pressure by pumping after which the test continues 90 minutes without further pum
end of the pumping period the pressure is reduced to one third of the test pressure. Test is passed if the pressure does not dro
third of the test pressure over the following 90 minutes and there is no visible leakage throughout the test.

A. HYDRAULIC PRESSURE TEST METHOD STATEMENT:


1. Start to fill the piping and then ‘walk’ the route of the piping under test, continuously visually checking for leaks and b
for the sound of escaping air.

2. Release air from all the high points systematically through the system to completely fill it with water.

3. Once the system is full, raise the pressure to the test pressure and, if a plastics piping system, continue pumping for th
period.

4. If the pressure falls, check that stop valves are not letting by, then walk the system again for leaks.

5. Once the system is proven sound, have the test witnessed if necessary and obtain a signature on the test certificate.

6. After testing release the pressure. If necessary, ensure that any vents on cylinders, tanks, and pressure-vessels are ope
atmosphere before draining down and refitting vulnerableitems. If the system has to carry fluids other than water, it ma
necessary to dry out thepiping internally by passing hot air through it, (this can take some time to achieve).

7. All the readings are to the recorded on standard format and submitted for final approval.

8. Allowable Tolerance:- ± 10% of design valve.

9. Reference code:

B. TESTING UNDERGROUND WATER MAINS


Underground water mains are jointed using a variety of methods including socket and spigot, push-fit and mechanical fittin
that have to be contained within the piping can be considerable so, in addition to the above procedures, the following items ar
recommended when pressure testing underground water mains:
1. Install and test long mains in sections determined by agreement with the contractor.
2. Pressure testing must not commence until anchor blocks are in position and the tre
backfilled and rammed (leaving the joints exposed). This is to prevent any movement causing damage due to the pressure insid
Testing against valves is best avoided, but in any case check that the valves can withstand the test pressure, if necessary blankin
valves that cannot. Fill the main slowly and allow any air to escape before beginning to test, and pressurize slowly. Once the ma
sound, complete backfilling, then perform a final test and obtain a witness signature as necessary.
3. All the reading are to recorded on a sta
and submitted for final approval. 4. Allowable Tolerance: - ± 10%
valve. 5. Reference code
Commissioning of water system – BSRIA AGZ – 89.3
Commissioning of water system – CIBSE CODE W.
Page 8 28/10/2009
5. Once the system is proven sound, have the test witnessed if necessary and obtain a signature on the test certificate.

6. After testing release the pressure. If necessary, ensure that any vents on cylinders, tanks, and pressure-vessels are ope
atmosphere before draining down and refitting vulnerableitems. If the system has to carry fluids other than water, it ma
necessary to dry out thepiping internally by passing hot air through it, (this can take some time to achieve).

7. All the readings are to the recorded on standard format and submitted for final approval.

8. Allowable Tolerance:- ± 10% of design valve.

9. Reference code:

B. TESTING UNDERGROUND WATER MAINS


Underground water mains are jointed using a variety of methods including socket and spigot, push-fit and mechanical fittin
that have to be contained within the piping can be considerable so, in addition to the above procedures, the following items ar
recommended when pressure testing underground water mains:
1. Install and test long mains in sections determined by agreement with the contractor.
2. Pressure testing must not commence until anchor blocks are in position and the tre
backfilled and rammed (leaving the joints exposed). This is to prevent any movement causing damage due to the pressure insid
Testing against valves is best avoided, but in any case check that the valves can withstand the test pressure, if necessary blankin
valves that cannot. Fill the main slowly and allow any air to escape before beginning to test, and pressurize slowly. Once the ma
sound, complete backfilling, then perform a final test and obtain a witness signature as necessary.
3. All the reading are to recorded on a sta
and submitted for final approval. 4. Allowable Tolerance: - ± 10%
valve. 5. Reference code
Commissioning of water system – BSRIA AGZ – 89.3
Commissioning of water system – CIBSE CODE W.

Page 8 28/10/2009
M & E DIVISION

OD STATEMENT
28.10.2009
Discipline: MEP
METHOD STATEMENT

ater pressure not less than 11/2 times the maximum pressure to which the
on.“ So, for water piping system that will operate at 3-bar the test pressure
ormal maximum pressure, stop pumping and wait for 1 hour to see if any
ns of leakage.

fter which the test continues 90 minutes without further pumping; at the
f the test pressure. Test is passed if the pressure does not drop below one
is no visible leakage throughout the test.

ping under test, continuously visually checking for leaks and by listening

ssure and, if a plastics piping system, continue pumping for the specified

by, then walk the system again for leaks.

d if necessary and obtain a signature on the test certificate.

at any vents on cylinders, tanks, and pressure-vessels are opened to


eitems. If the system has to carry fluids other than water, it may be
r through it, (this can take some time to achieve).

nd submitted for final approval.

ods including socket and spigot, push-fit and mechanical fittings. The forces
o, in addition to the above procedures, the following items are also

ections determined by agreement with the contractor.


not commence until anchor blocks are in position and the trench partially
vent any movement causing damage due to the pressure inside the piping.
he valves can withstand the test pressure, if necessary blanking off any
e before beginning to test, and pressurize slowly. Once the main is proved
a witness signature as necessary.
3. All the reading are to recorded on a standard format
4. Allowable Tolerance: - ± 10% of design
5. Reference code: -

Page 8 28/10/2009
Page 8 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT
PRE COMMISSIONING CHECK FOR DOMESTIC WATER SYSTEM:

i) Check whether domestic water system i.e. Pipes,Valves,Pumps,Heaters and Terminal Fitting are installed as per approve
shop drawings.

ii) Check for the proper supporting of pipe work.

iii) Check whether all installtion works have been carried out.

iv) Check whether pumps are properly aligned.

v) Check for the proper rotation of pumps.

vi) Check whether all the isolator are on.

vii) Check whether all power and control wiring for pumps & heaters is completed as per manufactures circuit diagram.

viii) Check whether declared voltage is available on all phases.

ix) Check whether all domestic water system has been cleaned of dust and debris.

PRE COMMISSIONING FOR DRAINAGE SYSTEM:

i) Check whether the drainage system i.e. Pipes,Cleanouts etc,. Are installed as per the approved shop drawings.

ii) Check whether all cleanouts are fitted, undamaged and accessible.

iii) Check whether terminal units are fitted and cleaned.

iv) Check whether all sanitarywares are set and sealed properly.

v) Check whether drainage system flushing and cleaning has been done as per the specialist contractor's procedures and
recommendations prior to start up of commissions.

GRAVTITY TEST PROCEDURE / METHOD STATEMENT:


i) After the completion of pre-commissining of drainage choose any section line.

ii) Fill the section with water, record the level of water column.
Page 8 28/10/2009
iii) After 2 hrs again record the level of water column if the levels are nearly same, the test for leakage shall be assummed as

iv) Release the water and visualy check whether the water is flowing in the right direction.

v) After successful completion of testing, submit the report on a standard format for final approval.

Page 8 28/10/2009
M & E DIVISION

OD STATEMENT
28.10.2009
Discipline: MEP
METHOD STATEMENT

mps,Heaters and Terminal Fitting are installed as per approved for the

eaters is completed as per manufactures circuit diagram.

een done as per the specialist contractor's procedures and

Page 8 28/10/2009
ls are nearly same, the test for leakage shall be assummed as successful.

Page 8 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

7. MANPOWER RQUIRMENTS:
*Skilled ductmen ,Eletrician & Plumbers shall be employed as required to carry out T & C.
*T & C Engineer/Supervisor shall Supervise the work.

8. EQUIPMENTS & TOOLS:


1) ELECTRICAL
i)Insulation Test (Megger) with variable voltage selection
ii)RCBO Tester.
iii)Multimeter.
iv)Earth tester.
v)Continuity Tester.
vii)Phase sequence meter.
vii)Lux meter.
viii)Clamp meter.

2) PLUMBING
i)Pressure gauge.
ii)Clamp meter.
iii)Thermometer.
iv)Sprit levels.

3) HVAC
i)Flow Hood Kit.
ii)Anemometer (Rotating Vane type) .
iii)Digital Thermometer.

Page 8 28/10/2009
Page 8 28/10/2009
M & E DIVISION

OD STATEMENT
28.10.2009
Discipline: MEP
METHOD STATEMENT

Page 8 28/10/2009
Page 8 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT

9. SAFETY PRECAUTIONS:

i) All work safety procedures should be followed during execution of Testing & Commissioning works.

ii) Only experienced & skilled technician shall be engaged for carrying out Testing & Commissioning of MEP system.

iii) Tools & Instruments shall be handled by authorized persons only.

iv) Usage of PPE such as safety shoes , safety helmets , safety harness , gloves , goggles , masks , earplugs etc. and any o
safety accessory as required during Commissioning works

v) Electrical power supply shall be isolated and panel switchgear shall be locked whenever carrying out work on any
rotating equipment or electrical panels.

vi) No Commissioning works shall be carried out without adequate lighting avilable.

vii) Approved project safety plan & procedures shall be followed through out the Tasting & Commissioning works.

viii) Necessary warning boards to provided as required during T & C works.

ix) Safety officer shall check & ensure that all safety pre-caution are followed.

x) Permit to work system shall be followed and the required permit shall be obtained wherever necessary.

10. REFERENCES:

i) Manufacturer's catalogs.

ii) Approved submittal.

iii) Shop drawings.

iv) Project HSE plan.

page 9 28/10/2009
page 9 28/10/2009
M & E DIVISION

OD STATEMENT
28.10.2009
Discipline: MEP
C METHOD STATEMENT

ged for carrying out Testing & Commissioning of MEP system.

safety harness , gloves , goggles , masks , earplugs etc. and any other

witchgear shall be locked whenever carrying out work on any

followed through out the Tasting & Commissioning works.

page 9 28/10/2009
page 9 28/10/2009