Professional Documents
Culture Documents
METHOD STATEMENT T & C General Tests
METHOD STATEMENT T & C General Tests
METHOD STATEMENT
DOCUMENT : ETA/MS/MEP/B1-REV 0
DISCIPLINE: MEP
INDEX
2 Scope
3 Reference documents
4 Responsibilities
5 Method of T & C 4
7 Manpower Requirements
10 Reference
Page No.
3
4 to 14
15
15
16
16
1. Purpose:
The Purpose of this Method statement is to describe the Testing & Commissioning methodology for villas regards
works at Al Waab city Project.
2. Scope:
This method statement is applicable for Testing & Commissining of Mechanical, Electrical and Plumbing systems
in villa type B1 of Alwaab city project.
3. Referance Document:
Testing & Commissioning Manual
*Part 1 - Testing & Commissioning specifiction submitted.
*Part 2 - Testing & Commissioning Proceduce Manual submitted.
4. Resposibilities:
4.1 The Project Managar is over all responsible for implementation of this Method statement and to ensure that
his T & C team of Engineers and Supervisors are aware of this Method statement and all resources such as
manpower, material and equipment are available to carry out the Testing & Commissioning with quality and
without any delay.
4.2 The Project Manager will co-ordinate with the T & C Engineer/T & C Supervisor/Safety Officer for safe and pro
execution to accomplish the works on time as planned and respect the quality of finished works.
4.3 T & C Engineer along with T & C Supervisor will ensure that the T & C is carried out according to the
Specifications/Drawings and this Method Statement.
4.4 QA/QC Engineer, in close interaction with T & C personnel, will ensure that the works are carried out as per
the project requirements. He is also responsible for the implementation of QA /QC related to works as detail
in the procedure and for completing Quality Document for all related works.
4.5 Safety Coordinator / Officer will ensure implemention of all safety procedures, safety measures related to th
nature of works being carried out in accordance with Project HSE Plan and finishing the works with out any dameged
and fatality.
Testing Commissining Page 3 09/12/2009
5. MEP Testing & Commissioning procedure:
Testing & commissioning shall be carried out as per the described procedures in submitted method statements.
sonnel, will ensure that the works are carried out as per
the implementation of QA /QC related to works as detailed
ELECTRICAL:
1) CONITINUITY TEST:
B)
C)
D)
Step 1:
After the completion of pre-commissioning checks, continuity test between DB and switch / socket points is to
the multimeter reading during this test should always be ZERO between phase and phase (CLOSE);between pha
nautral (OPEN), between phase and earth (OPEN) & between neutral and earth with the tolerance of 1Ω.
Step 2:
After the completion of continuity checks continuity test between DB and switch / socket, we shell proceed wit
continuity test between switch and light points, again the multimeter reading should be zero as described in ste
with the tolerance of 1Ω.
Testing Commissining page 4 09/12/2009
Step 3:
Now the continuity test between the ring circuit and power sockets is to be carried out, The multimeter reading
zero as described in step 1 with the tolerance of 1Ω.
Step 4:
All the reading are to be recorded in a standard format and submitted for final witness / approval.
OD STATEMENT
09.12.2009
scipline: MEP
ETHOD STATEMENT
Format Reference
Step 1:
Once the pre-commissioning checks are over, installation resistance test between phase and neutral wires / cable is
to started. The megger value should always be greater then 10MΩ for wires and 50MΩ for cables.
Step 2:
In the next step insulation resistance test between phase and earth wire / cables is to be done. The megger reading
in this care also should be greater then 10MΩ for wire and 50MΩ for cables.
Step 3:
The test between phase and wire / cables is to be carried out in the next stage, the megger reading acceptable are
similar reading should flow the same valve as described in step 1 to step 3.
Step 4:
All the reading should be recorded on a standard for format and submitted for final approval.
page 6 28/10/2009
page 6 28/10/2009
M & E DIVISION
D STATEMENT
8.12.2009
scipline: MEP
METHOD STATEMENT
arried out in the next stage, the megger reading acceptable are
page 6 28/10/2009
page 6 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Consult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT
3) LUX TEST:
B) Check the final connection of light fitting with ceiling roses through heat resistance flexible cable whe
applicable such as false ceiling areas.
E) Check the installation of light fixtures,make sure supports are supply installed.
STEP 1:
To perform the lux level test, select the area where level is to be checked.
STEP 2:
Switch on the lux meter, Measure the reading at four corners and the centre of illuminated area.
STEP 3:
Take the average of all recorded reading for comparison with the design lux level.
STEP 4:
Submit the reading on a standard format for final approval.
4) EARTHING TEST:
OD STATEMENT
28.10.2009
Discipline: MEP
METHOD STATEMENT
s light fixtures are connected to the final of circuit of the distribution board.
STEP 1:
After a through visual check is conducted, set the leakage current on the instrument before the commencement o
the test.
STEP 2:
Connect the R.C.B.O. tester lead at the socket outlet of the circuit under test, press the test button of R.C.B.O. test
R.C.B.O. should trip.
STEP 3:
Similary at the terminal of any of the light fitting in the lighting circuit, connect the R.C.B.O. tester lead and perform
as mentioned in test I & II.
STEP 4:
All the measurements should be recorded on a standard format and sumitted for final approval.
STEP 1:
240VAC Single Phase Voltage calibration to check the three Phase with reference to neutral.
i.e. R Phase to neutral, Y Phase to neutral and B Phase to neutral.The values should be in the range 220-240VAC.
STEP 2:
For three Phase voltage calibration check the voltage between the three Phase. i.e.Between R-Y,Y-B and B-R.The r
shown by the multimeter to 415-440VAC.
STEP 3:
Record all the reading on a standard format and submit for find approval.
M & E DIVISION
OD STATEMENT
8.12.2009
Discipline: MEP
METHOD STATEMENT
of the circuit under test, press the test button of R.C.B.O. tester, the
he lighting circuit, connect the R.C.B.O. tester lead and perform the test
STEP 2:
Measure the ampacity of indoor unit with the help of an ameter and voltage with voltmeter. Check whether the
recorded values are in line with that shown in manufacture’s catalogue.
STEP 3:
Measure the air flow rate from the main duct within the range of 2 meters from the indoor unit. Again check
whether the recorded values are in line with that show in manufacture’s catalogue.
STEP 4:
Record all the measurements on a standard format and submit for final approval.
CHARGING:
STEP 1:
After completion of the evacuation, close the end caps and service valve.
STEP 2:
Release the already charged refrigerant to the system by opening both the services valves.
STEP 3:
Switch on the system and check the ampacity and pressure reading.
Page 5 28/10/2009
STEP 4:
Adjust the pressure by charging the refrigerant gas.
STEP 5:
Record the final reading on the standard format & submit for final approval.
Page 5 28/10/2009
M & E DIVISION
OD STATEMENT
28.10.2009
ipline: MEP
METHOD STATEMENT
Format Reference
CP M1.2
ETA Standard Format
ETA Standard Format
ETA Standard Format
ervice valve.
eading.
Page 5 28/10/2009
final approval.
Page 5 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Consult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 8.12.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT
STEP 2:
Open the shut off valve of the nitrogen cylinder with cylinder key and regulate the outlet pressure to 200 Psi.
STEP 3:
Open the manifold outlet slowly to allow entry of refrigerant gas into the system.
STEP 4:
Monitor the pressure reading in the discharge gauge, charge the system up to 150 Psi (as per manufacture’s recommend
STEP 5:
Check for any leak in all joints using liquid detergent.
STEP 6:
If any leak is found release the pressure, repair and again repeat the process.
STEP 7:
Hold the pressure for 30 min and recheck the pressure, the reading should be submitted in the standard format for final
B. EVACUATION
STEP 1:
After the pressure test is approved, release the nitrogen by opening suction & discharge service valves to release all the
from the system.
STEP 2:
Close the service valves and connect the suitable vacuum pump manifold gauge to the suction service valve.
STEP 3:
Switch on the vacuum pump, open the manifold gauge valve and suction service valve, ensure that the manifold discharg
and discharge service valve of outdoor unit is fully closed before the vacuum pump is switched on.
STEP 4:
Run the vacuum pump for 1hr continuously and keep monitoring the compound gauge of the vacuum pump.
M & E DIVISION
OD STATEMENT
8.12.2009
Discipline: MEP
METHOD STATEMENT
y opening suction & discharge service valves to release all the nitrogen
ve and suction service valve, ensure that the manifold discharge outlet
before the vacuum pump is switched on.
1. Prior to Testing & Commissioning all pre commissioning checks should be carried out.
3. Set all the dampers in the Grille outlet at full open position.
4. Take initial flow of the unit by adding up all the measured from of the design flow.
5. Compare the reading against the designed flow. Find out the percentage of the design flow.
6. Find out the index outlet (i.e. which has the very low percentage of reading) from the initial scan.
8. Then throttle the air volume at each outlet to get the design percentage of flow proportionally by using the flow hood
hood (Balometer) / anemometer.
9. Each time when you throttle the outlet by closing the diffuser/ grill damper, the index outlet air flow raises gradually.
Measure the index point each time.
proportionally
11. Note all reading at all out lets and keep records.
OD STATEMENT
8.12.2009
Discipline: MEP
METHOD STATEMENT
on.
ffuser/ grill damper, the index outlet air flow raises gradually.
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Consult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 8.12.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT
Depending upon the location and access to air terminals, various types of air flow measuring instruments will be utilized t
the actual air flow at terminals.Assuming adequate access provided, a direct reading balometer would be used which give
reading in volume rather than velocity, which cancels out need for effective grill areas, terminal configuration considerati
velocity corrections.
If access is restricted then a rotating vane anemometer shall be used and the velocity reading obtained would be convert
volume (velocity X free area = volume).
1. Air quantities shall be measured according to CIBSE application Guide 3/89 standard.
2. Any main branch may be chosen to start with but as normal practice and having carried out a rough balance of main an
branches, start with the most remote branch and then sub-branch.
3. Locate the terminal, which is discharging the lowest percentage of its design flow rate.This is generally the last terminal
If not, adjust the damper in the last terminal until it is working with the same percentage as the lowest one previously
4. Measure the flow from the terminal next to the index and work percentage flow as close as possible to that of the inde
Fix the damper in position.
5. Repeat the procedure for the next terminal, again comparing it with the index.
6. As the dampers a close are along the run, more air will be driven towards the downstream terminals and volume of air
discharged at the terminal index will rise. This does not affect the balancing procedure since each terminal being adjus
is related in turn with the index.
7. When all the terminals have been balanced on a sub- branch, each terminal will be running with an equal percentage
design flow rate, within the allowable tolerances.
8. The flow rates at each terminal must be measured and recorded. Once again a summation should be made to check th
check that the total is in reasonable agreement with the measured sub – branch flow.
9. Test result shall be recorded in the approved test sheets and documents.
OD STATEMENT
8.12.2009
Discipline: MEP
METHOD STATEMENT
mal practice and having carried out a rough balance of main and
ub-branch.
entage of its design flow rate.This is generally the last terminal in the run.
orking with the same percentage as the lowest one previously measured.
and documents.
AG3 – 89.2
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT
PLUMBING:
Page 5 28/10/2009
Page 5 28/10/2009
M & E DIVISION
OD STATEMENT
28.10.2009
ipline: MEP
METHOD STATEMENT
Format Reference
CP M2.1
CP M2.2
CP M2.6
Format Reference
CP M2.7
CP M2.2
CP M2.4, CP M2.5
ETA Standard Format
Page 5 28/10/2009
Page 5 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT
THE TEST REQUIREMENT:
“The water system shall be capable of withstanding an internal water pressure not less than 11/2 times the maximum pressure
installation or relevant part is designed to be subjected in operation.“ So, for water piping system that will operate at 3-bar the
will be 3 x 1.5 = 4.5bar. Pressurize the system to 11/2 times the normal maximum pressure, stop pumping and wait for 1 hour t
pressure loss is indicated whilst checking the system for visible signs of leakage.
The whole system is subjected to the test pressure by pumping after which the test continues 90 minutes without further pum
end of the pumping period the pressure is reduced to one third of the test pressure. Test is passed if the pressure does not dro
third of the test pressure over the following 90 minutes and there is no visible leakage throughout the test.
2. Release air from all the high points systematically through the system to completely fill it with water.
3. Once the system is full, raise the pressure to the test pressure and, if a plastics piping system, continue pumping for th
period.
4. If the pressure falls, check that stop valves are not letting by, then walk the system again for leaks.
5. Once the system is proven sound, have the test witnessed if necessary and obtain a signature on the test certificate.
6. After testing release the pressure. If necessary, ensure that any vents on cylinders, tanks, and pressure-vessels are ope
atmosphere before draining down and refitting vulnerableitems. If the system has to carry fluids other than water, it ma
necessary to dry out thepiping internally by passing hot air through it, (this can take some time to achieve).
7. All the readings are to the recorded on standard format and submitted for final approval.
9. Reference code:
6. After testing release the pressure. If necessary, ensure that any vents on cylinders, tanks, and pressure-vessels are ope
atmosphere before draining down and refitting vulnerableitems. If the system has to carry fluids other than water, it ma
necessary to dry out thepiping internally by passing hot air through it, (this can take some time to achieve).
7. All the readings are to the recorded on standard format and submitted for final approval.
9. Reference code:
Page 8 28/10/2009
M & E DIVISION
OD STATEMENT
28.10.2009
Discipline: MEP
METHOD STATEMENT
ater pressure not less than 11/2 times the maximum pressure to which the
on.“ So, for water piping system that will operate at 3-bar the test pressure
ormal maximum pressure, stop pumping and wait for 1 hour to see if any
ns of leakage.
fter which the test continues 90 minutes without further pumping; at the
f the test pressure. Test is passed if the pressure does not drop below one
is no visible leakage throughout the test.
ping under test, continuously visually checking for leaks and by listening
ssure and, if a plastics piping system, continue pumping for the specified
ods including socket and spigot, push-fit and mechanical fittings. The forces
o, in addition to the above procedures, the following items are also
Page 8 28/10/2009
Page 8 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT
PRE COMMISSIONING CHECK FOR DOMESTIC WATER SYSTEM:
i) Check whether domestic water system i.e. Pipes,Valves,Pumps,Heaters and Terminal Fitting are installed as per approve
shop drawings.
iii) Check whether all installtion works have been carried out.
vii) Check whether all power and control wiring for pumps & heaters is completed as per manufactures circuit diagram.
ix) Check whether all domestic water system has been cleaned of dust and debris.
i) Check whether the drainage system i.e. Pipes,Cleanouts etc,. Are installed as per the approved shop drawings.
ii) Check whether all cleanouts are fitted, undamaged and accessible.
iv) Check whether all sanitarywares are set and sealed properly.
v) Check whether drainage system flushing and cleaning has been done as per the specialist contractor's procedures and
recommendations prior to start up of commissions.
ii) Fill the section with water, record the level of water column.
Page 8 28/10/2009
iii) After 2 hrs again record the level of water column if the levels are nearly same, the test for leakage shall be assummed as
iv) Release the water and visualy check whether the water is flowing in the right direction.
v) After successful completion of testing, submit the report on a standard format for final approval.
Page 8 28/10/2009
M & E DIVISION
OD STATEMENT
28.10.2009
Discipline: MEP
METHOD STATEMENT
mps,Heaters and Terminal Fitting are installed as per approved for the
Page 8 28/10/2009
ls are nearly same, the test for leakage shall be assummed as successful.
Page 8 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT
7. MANPOWER RQUIRMENTS:
*Skilled ductmen ,Eletrician & Plumbers shall be employed as required to carry out T & C.
*T & C Engineer/Supervisor shall Supervise the work.
2) PLUMBING
i)Pressure gauge.
ii)Clamp meter.
iii)Thermometer.
iv)Sprit levels.
3) HVAC
i)Flow Hood Kit.
ii)Anemometer (Rotating Vane type) .
iii)Digital Thermometer.
Page 8 28/10/2009
Page 8 28/10/2009
M & E DIVISION
OD STATEMENT
28.10.2009
Discipline: MEP
METHOD STATEMENT
Page 8 28/10/2009
Page 8 28/10/2009
Client : M/s AL WAAB CITY
Project : Project Manager : M/s Cansult Ltd.
Supervising Consultant : M/s ECG
Project : Q001/007.2 &007.3 Main Contractor : Arabtec Construction Co.
MEP Contractor :ETA Engg. & Contracting.
METHOD STATEMENT
Rev.: 00 Date 28.10.2009
Method Statement No.: ETA/MS/MEP/B1-REV 0
Discipline: MEP
TITLE : MEP T & C METHOD STATEMENT
9. SAFETY PRECAUTIONS:
i) All work safety procedures should be followed during execution of Testing & Commissioning works.
ii) Only experienced & skilled technician shall be engaged for carrying out Testing & Commissioning of MEP system.
iv) Usage of PPE such as safety shoes , safety helmets , safety harness , gloves , goggles , masks , earplugs etc. and any o
safety accessory as required during Commissioning works
v) Electrical power supply shall be isolated and panel switchgear shall be locked whenever carrying out work on any
rotating equipment or electrical panels.
vi) No Commissioning works shall be carried out without adequate lighting avilable.
vii) Approved project safety plan & procedures shall be followed through out the Tasting & Commissioning works.
ix) Safety officer shall check & ensure that all safety pre-caution are followed.
x) Permit to work system shall be followed and the required permit shall be obtained wherever necessary.
10. REFERENCES:
i) Manufacturer's catalogs.
page 9 28/10/2009
page 9 28/10/2009
M & E DIVISION
OD STATEMENT
28.10.2009
Discipline: MEP
C METHOD STATEMENT
safety harness , gloves , goggles , masks , earplugs etc. and any other
page 9 28/10/2009
page 9 28/10/2009