Professional Documents
Culture Documents
Risk Management
Risk Management
Risk Management
Risk Management
Coordinator: Students:
Boca Alexandra
Kousas Antonis
Dr. Ing. Gabriela Covatariu Chihaia Robert-Alexandru
Master ISE
- January 2018 -
Construction Phase Plan (Non – Notifiable)
This Plan format is intended for Contracts of less than 30 days duration (or less than 500 person days in total) which do not involve
significant demolition work or other high risk activities.
Complete 4 no. trial holes, in carriageway to confirm location of pipe and services, then
Excavate Eastern and Western Pits. Pits 15meters Long. Install a Linestop to achieve
isolation of the 24” water main. Undertake Night Shut, cut in Fittings and Recharge. Build
Thrust Block. Install and commission ridermain to maintain continuity of flow. Remove Old
Cast Pipe. Butt Fusion 500mm Plastic Pipe and slip line 51meters of 24” cast iron water
main to protect during tunnelling works. Complete connections, pressure test, chlorinate and
commission new pipework. Remove Rider Main and Reinstate the Pits
Take a 7” connection from the 24” Main and bring into the footpath for FLO future use.
Which of the following hazards will be significant on this Contract and will require special rules and
precautions?
Is there a risk from? Yes / No Control measures and comments
Asbestos No
Lone Working No Security Guard on site at night but Security Guard FLO/Tideway
Mass Barriers and Fences along the carriageway. Pedestrian segregation on
Risk to public/third party Yes
site. Security on site 24 hours a day.
Working occupied premises No
Working around Thames Water Live 24” main and HV Electrical Cables. PTW
Exposure to High Risk from Thames Water in place. FLO/Vision and Barhale Permit to dig in place.
Yes
Services Fireproof and Arc Resistance Overalls in place. Isolations requested Insulated
Shovels. Use Air Lance
Ladders Tied. Handrail around Excavations. All items handed down into
Working at height Yes
excavation.
Scaffolding / towers /
No
ladders
Roof work No
All CPCS trained operatives. Excavator drivers are CAT C trained. Plant sourced
from Reputable company approved on Barhale Management System. Lift Plan in
Lifting Operations Yes
place. Lift Plan briefed to all personal involved. Weight of item known. Tag Lines
as required
Manual Handling - Manual handling trained ops. Manual Handling Assessments undertaken. Split
Yes
Handling/lifting / carrying loads where possible. Use of Wheelbarrows. Use of Excavators
Hot Works Permit Systems in place. Fire Extinguishers available on site. Fire
Fire / explosion / hot work Yes
Wardens on site
Electric shock No
Permit to Dig. PTW from Thames Water in place. FLO/Vision and Barhale Permit
to dig in place. Fireproof and Arc Resistance Overalls in place. Isolations
Excavations Yes
requested Insulated Shovels. Use Air Lance. Use of CAT and Genny.
Excavations edge protected with fixed handrail system
Temporary Works source from Good Company Approved on Barhale
Temporary Works Yes Management System. Approved Temporary Works Design in Place. Experienced
operatives to install the temporary works.
Confined spaces / lofts /
No
manholes
Overhead cables No Streetlights Present
Use of High Risk Plant Yes Risk Assessed. Tool Box Talk. Authorisation t use
Is there any
environmental risk Yes / No Control measures and comments
from………….?
Noise Yes Silent generators. Ear defenders. Sound Barriers installed along the Fence Line
Dampening down during dusty activities. Dust masks. Face fit testing. Good
Dust / fumes Yes
quality plant, within EU regulations
Spill kits. Plant Nappies. Spill Drills. Permit to Pump. FLO permit to discharge for
Water pollution Yes
the Drain down of the mains
Waste disposal Yes Waste licences obtained from suppliers. Skips on site
Other
Do any anticipated products give rise to risk to health (COSHH)?
Yes
If YES provide details
Diesel.
Petrol.
Grease.
Hydraulic Oil
Line Spray
3 in 1 oil
Concrete
Chlorus
Denso Tape and Mastic
Are suitable welfare facilities already available? Yes
FLO are providing Welfare. They provided two units a 20ft and 12ft split unit. Barhale are provide the office and drying room
Permits to Work
Ref. Document
RA / MS No:
Site / Depot / Office: SWA148 Chelsea Embankment RC01
Name of Approver1(print & sign): Boca Alexandra / Kousas Antonis Date: 20/07/2017
No: Reason Author(print & sign) Date Approved(print & sign) Date
Updated of Detail, removal of
2 Robert Chihaia 10.08.17 Boca Alexandra 10.08.17
Trial holes
Updated to include Exclusion
Zone from TWUL and UKPN
3 Robert Chihaia 23.08.17 Boca Alexandra 23.08.17
Assets, Removal of welding of
Steel Members. Overall
Updated to include Support of
4 Robert Chihaia Boca Alexandra
the Water Main
Update to for construction
5 Robert Chihaia 28.11.2017 Boca Alexandra 28.11.2017
drawings
Note1: Risk Assessment & Method Statement must be approved by a Contracts Manager for activities agreed as
high risk. All other RAMS must be approved by a competent person excluding the author.
Section 1 – Task Risk Assessment
Rev
(Contract/Depot/ Chelsea Embankment
Task Risk Assessment: No. 5
Office)
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
Work Areas within Public Unauthorised personnel entering the work 4 4 16 Traffic management(TM) will be used to create a work area. The Traffic 4 1 4
Carriageway area. Management erected at present only allows for entrance to site from the
Vandalism to plant or materials. eastbound carriageway and exit back onto the eastbound carriageway
Theft of plant or materials. TM will be in accordance with Safety at Street Works & Road Works – A code of
Fatal or serious injuries to unauthorised practice.
personnel by plant movements and or The working operatives shall ensure all work equipment & materials are kept
excavations. within the fenced off work area.
All Work areas shall be surrounded by double clipped heras fence panels &
separate plant/operatives access to the work area through designated heras
pedestrian gates and designated heras plant/vehicle gates. The gates shall
remain closed & bolted when operatives are inside and locked when no
operatives inside.
Signs shall be erected stating that no unauthorised personnel shall enter the
work area.
Site Personnel will be made aware to challenge unauthorised personnel which
come in to the work area.
A site induction shall be undertaken by all employees prior to being allowed
access to the job-site.
All site personnel and all authorised visitors shall wear:
hard hat, work boots, High visibility jacket/vest
Gloves, Low impact eye protection
The MS/RA will be briefed to the operatives before works begin and the
operatives will sign same. All the work activities will then be carried out in
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
accordance with the approved MS/RA.
All Personnel shall hold a valid CSCS Card.
A Banks-Man will supervise the plant movements within the job-site at all
times & on entrance to site.
Work Vehicles delivering Collision and Crushing injuries. 3 4 12 A Banks-Man will supervise the plant movements within in the job-site at all 3 1 3
Injuries to members of the public. times.
Damage to vehicles on the public highway. Separate plant/operatives access to the work area through designated heras
Damage to Private property. pedestrian gates and designated heras plant/vehicle gates.
Road Traffic Accidents. The Banks-Man will control the directing of plant movements into/out of the job-
Collision while reversing. site to prevent collisions with pedestrians.
Trips and falls from height. All work vehicles coming into/out of the site shall have their orange beacons
active while manoeuvring.
All trucks/large pick-ups will have reversing alarms.
All delivery vehicles to comply with Thames Tideway Central Section - Traffic
Management Delivery Plan and Tideway Standards for Vehicles and Driver
Safety.
Where possible deliveries will be planned for the quietest periods.
No delivery trucks to ever stop on footpath during entry or exit from site.
No vehicles to drive on the footpath
Manual Handling Sprains and crushing injuries 3 3 9 Manual Handling Lifting Assessments shall be carried out as required. 3 1 3
These assessments shall consider the operatives physical ability, the weight and
shape of the object being lifted, weather conditions and trip hazards along lifting
route.
Tool Box Talks shall be carried out on manual handling regularly to raise
awareness focusing on the T.I.L.E principle (task, individual, load, environment).
Where possible all operatives will have undertaken a manual handling course.
Make use of Excavator or Crane where possible on site, all lifts to be cover by
an approved lift plan.
Mechanical lifting will be used where possible, and wheelbarrow’s/Trolley will be
used to move items as required.
Do not attempt to lift any load that seems heavy (over 25kg) or large without
asking a supervisor for a manual handling assessment to be carried out.
Use correct manual handling technique, keep back straight and bend at knees
when lifting. Share or split loads with other operatives.
Use correct gloves to protect from sharp edges that give adequate grip – if in
doubt stop and ask
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
Full PPE to be used at All times. (Hard Hat, Glasses, Orange Long Sleeve
HiVis¸ Gloves Orange Trousers, Boots and Fire Proof Overall for Operatives
Digging).
Care must be taken when lifting mass barrier bases. Make sure operatives wear
gloves and use kinetic lifting techniques. 2 operatives to lift every 1m base.
Working at heights Fatal or serious injuries to operatives and slips 3 4 12 A tidy site will be maintained with specified access/egress and walking routes to 3 1 3
and trips. be used.
Standing on Services (control measure for Keep all materials stored in designated areas off vehicle and pedestrian access
this?) routes.
Keep materials stored tidily.
Surround the excavations with a rigid barrier system.
Access and egress to be by a tied ladder.
The tools and equipment shall be handed down to the operatives working in the
excavation.
Access to be provided at both sides of services within the excavations to
prevent personal from stepping across the services.
Temporary Task lighting to be used during at night works which will be powered
by a super silent diesel generator.
A counter weight davit arm/trench supported davit arm to be position alongside
the excavation.
Excavation of Ground Damage to Private property. 4 4 16 Existing service layouts shall be obtained from the service owners. 4 1 4
Damage to existing services. A desk top survey of existing service layouts shall be carried out.
Fatal or serious crushing injuries to working All known services shall be marked out prior to any excavation commencing.
operatives. The UKPN HV cables will be supported via Ratchet Straps at 1meter intervals
Excavation Collapse. when excavating underneath. The Ratchet Straps will be connected to a
Damage to buried/surface cables. bridging beam. The Bridging Beam will rest either side of the excavation as per
Access and egress- risk of falls/slips. the developed design.
The Thames Water 24” Main will be supported via a Steel Cradle System when
excavating underneath. The Steel Cradles will be connected to a bridging beam.
The Bridging Beam will rest either side of the excavation as per the developed
design.
Areas to be cat scanned prior to permit been issued.
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
Utility drawings to be consulted prior to any excavation works taking place.
Service drawings for all services to be identified prior to any excavation works.
The records from the previously undertaken trial holes to be examined.
Permit to dig to be issued by Barhale Service Co-Ordinator.
All operatives involved with this activity shall be inducted into the permit to dig.
Ganger Operative to be trained in the use of the cable avoidance tool.
Flame retardant overalls will be worn during excavation works around potential
services.
A safe method of working around services is described within Appendix 2 of this
method statement.
No breaking with an excavator shall be carried out directly above, under or
within 500mm of the 24” Water Main as requested by Thames Water and FLO
Service Co-ordinator, only hand breaking via undermining technique is allowed
as shown in Appendix 2.8.
No breaking with an excavator shall be carried out directly above, under or
within 500mm of UKPN Cables as requested by FLO Service Co-ordinator, only
hand breaking via undermining technique is allowed as shown in Appendix 2.8
Exclusion zones to be set by FLO Service Co-ordinator/Vision Survey.
Safe Digging Practices to be followed at all times as shown in Appendix 2.8.
Toothless bucket to be used
Contact details for all utility providers to be available.
No use of forks, picks, pins or wrecking bars while digging.
Insulated hand held tools only, such as shovels to be utilised
Contact Thames Water NMC at 0800 009 3909 and Log on to PTW prior to
works commencing.
A Thames Water permit to work (PTW) will be in place.
All excavations over, under or within 500mm of a service shall be by use of
shovels.
Daily Inspections by a competent person shall be carried out on all excavations
prior to any works progressing.
Temporary works supervisor to be appointed.
Ensure no surcharge on excavation; Vehicles, muck heaps, skips etc. kept back
from edge outside angle of repose of unsupported sides.
Ensure inspected, recorded in register and corrective action if:
Fall of earth or any other support problems identified.
All excavation greater than 1.2 or less than that if poor ground encountered will be
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
support via Temporary works.
Temporary Works design to be developed and approved.
Temporary works to be installed as per supply companies guidelines.
Unloading of Delivery Wagon Trips and falls from delivery trucks which may 4 4 16 Full PPE to be worn at all times. 4 1 4
lead to fatal or serious injuries to operatives. --Helmet
--hi-viz
--safety glasses
--gloves
--safety boots (not riggers)
Fully trained competent Barhale operatives to be used on a truck where possible.
Operative attaching chains/slings on top of the load to be harnessed to a lanyard
on to a rigid object where possible.
Insist on pre-slung loads where possible. No sling use stray to be used.
All trucks/vans to have edge protection.
Sign to be erected to inform delivery drivers not to cross site/work area. The driver
will be expected to remain just inside the gate while he/she is on site. This should
prevent falls from drivers crossing the site.
Handling Excavated Material Cuts and abrasions. Trips, slips & Falls 3 3 9 Excavated materials from trial-hole to be removed from site by Barhale using a 3 1 3
licensed operator.
Disposal of all material to be in accordance with the site waste management
plan.
Waste Material to be segregated.
Gloves need to be worn at all times.
Excavated material to be stored in such a way that it does not put pressure on
excavations or block access/egress routes.
Excavated material to be stored in 20 yard skips on site prior to collect by
licenced waste carrier.
Construction Plant working on site Injuries to members of the public. 3 4 12 Only competent personnel will be allowed operate plant. 3 1 3
Collision and crushing injuries. Machine Drivers, Crane Drivers and Dumper Drivers shall be trained and
Damages to vehicles. competent and have valid CPCS cards.
Damage to private property. All operative to keep copies of their CPCS cards with them when operating
Injure to plant op plant.
Competency of plant operative to be assessed on site by Barhale Site
Management.
All excavator operatives to have Category C lifting operations.
All construction plant to be sourced from a reputable company, who have been
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
approved by Barhale Management systems.
Lifting over the Thames Water 24” Main and the UKPN HV Cables should be
minimised where possible.
CPCS trained Slinger Signaller to control all lifting operations.
The use of use of Excavator for digging or breaking of concrete and tar is not
allowed within the exclusion zone for the Thames Water 24” Water Main and the
UKPN Assets as set by FLO Service Co-ordinators/Vision Survey.
All construction plant shall have working orange beacons when on-site.
All construction plant shall have working Green beacons for Seat Belt indicators.
The seatbelt will be worn at all times.
All Construction plant shall have inspections when arrival to site and daily visual
inspections in accordance with PUWER regulations which will be documented.
Any plant defects shall be reported to the site management team, any issued
rectified asap. Plant not be utilised until issues resolved.
All Construction plant shall be serviced at the correct intervals.
Any plant/ vehicle movement shall be carried out only under the control of a
banksman or traffic marshal.
Segregated routes must be established to separate plant and vehicle routes from
the pedestrians
Before walking near plant, pedestrians shall make the Banksman or driver aware
of their intentions, and do not approach until allow to do so by the driver or
banksman.
Do not enter the exclusion zone without having banksman or plant ops permission.
Traffic Marshall to control all vehicles and plant accessing and egressing from site
to manage the interaction between site plant and vehicles and public vehicles and
pedestrians.
Step irons into and out of vehicles to be maintained in good condition.
Step Irons and tracked to be cleaned if they become dirty or greasy which would
pose a trip hazard to plant op on entering and exiting plant.
Plant op to maintain 3 points of contact as they enter and exit the plant.
Plant working with Quick Hitches Crushing Injuries. 3 4 12 Full automatic with double locking facility only or Manual with double locking. No 3 1 3
Damages to UKPN services as a result of the semi-automatic quick hitches allowed.
bucket detaching from quick hitch. Always make sure quick hitch area is clear of dirt/debris.
A quick hitch register to be signed by machine driver and banksman after every
bucket/attachment change to make sure the quick hitch is attached correctly, and
at the beginning of each shift.
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
Make sure bucket is correct size for the machine.
Always follow manufacturer’s guidelines.
The quick hitch manual to be in the machine.
All excavators to be sourced from a reputable company, who have been
approved by Barhale Management systems.
Excavating around HV cables Electrocution. 4 4 16 Contact details for all utility providers to be available.
identified by UKPN and other Damage to Cables Contact details for UKPN to be available with a specific point of contact when
utilities Fires excavation around the HV Cables that UKPN have raised concerns on.
Electrocution due to close proximity of cables Isolations and or diversion of Cables to be requested in advance of the works
Loss of Supply for Utility Company. from the asset owner UKPN.
Risk of serious injury to visitors/working Explore the options to eliminate the need to excavate on the cables.
operatives due to hitting services. All available information to be source from asset owner and from previously
Explosions. works on said cables.
Flooding. Trial holes to be undertaken ahead of the main works to locate said UKPN
Fatal or serious injuries to members of the Assets, Thames Water’s 24” Main and any other services identified.
public. A safe method of working around services is described within Appendix 2 of this
method statement.
No breaking with an excavator shall be carried out directly above, under or
within 500mm of UKPN Cables as requested by FLO Service Co-ordinator, only
hand breaking via undermining technique is allowed as shown in Appendix 2.8
Exclusion zones to be set by FLO Service Co-ordinator/Vision Survey.
No breaking with an excavator shall be carried out directly above, under or
within 500mm of the 24” Water Main as requested by Thames Water and FLO
Service Co-ordinator, only hand breaking via undermining technique is allowed
as shown in Appendix 2.8.
Within 500mm of the UKPN Cables an Air Lance/Air Pick and shovels/graphs to
be used to undermine the concrete and tar of the road construction.
Existing service layouts shall be obtained from the service owners.
An assessment of the potential condition of the cables to be undertaken with
examination of the age of the cables and all available photos.
Location of the cables to be marked out in advance by FLO Service
coordinator/Vision Survey.
Area to be CAT scanned in advance of the works by Vision Survey service co-
ordinator. Permit to Break ground to be issued by Vision Survey service co-
ordinator. All operatives involved with this activity shall be inducted onto the
permit to dig.
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
Areas to be cat scanned prior to permit been issued.
Utility drawings to be consulted prior to any excavation works taking place.
Service drawings for all services to be identified prior to any excavation works.
Trial hole records from previous works to be consulted.
Previous trial excavation information to be brief to operatives as part of the
permit to break ground. The UKPN HV cables will be supported via Ratchet
Straps at 1meter intervals when excavating underneath. The Ratchet Straps will
be connected to a bridging beam. The Bridging Beam will rest either side of the
excavation as per the developed design.
The Thames Water 24” Main will be supported via a Steel Cradle System when
excavating underneath. The Steel Cradles will be connected to a bridging beam.
The Bridging Beam will rest either side of the excavation as per the developed
design.
Fire Proof Overalls to be worn by operative working to exposed and support the
UKPN cables.
Operative to wear Arc Resistant Gloves when working around the UKPN HV
Cables.
Insulated shovels/graphs to be utilised
Safe Digging practices to be followed as per Appendix of this document.
Safe Digging Practices to be followed at all times.
No skips or excavator buckets, if placing loose material into the bucket, to be
positioned within 500mm of the HV Cables.
Minimise lifting directly overhead of the UKPN HV electrical cables.
No use of forks, picks, pins or wrecking bars while digging around UPKN Cables
or at any stage.
UKPN to be informed in advance of the works, if they want to provide a UKPN
operative/supervisor to provide a watching brief.
Permit to dig to be issued by FLO to Barhale Service Co-Ordinator.
All operatives involved with this activity shall be inducted into the permit to dig.
Ganger Operative to be trained in the use of the cable avoidance tool.
Toothless bucket to be used
Insulated shovels to be utilised
Contact Thames Water NMC at 0800 009 3909 and Log on to PTW prior to
works commencing
A Thames Water permit to work (PTW) will be in place.
All excavations over, under or within 500mm of a service shall be by use of
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
shovels.
General Working Fatal or serious Injuries to Operatives. 3 4 12 Weal’s disease: Ensure issue of cards and instruction 3 1 3
Smoking/Cutting Weal’s Disease Good hygiene practices – cover cuts, wash hands before
Eating and drinking etc.
Working with COSHH substances / Serious Injuries to Site Operatives, Members of 3 4 12 COSHH data obtained, 3 1 3
materials (For concrete use please the Public and Site Visitors Personnel briefed on safe handling, storage and protection.
see further below) PPE issued as per COSHH requirements,
Eye Wash available on site,
First Aid equipment available on site and within site facilities.
First-aider available on site at all times.
Location of closest hospital briefed at site induction and maps showing locaton
of closest hospital available at First Aid stations on site. Communication
available to call emergency services.
Used Spill Kit Granules or any inert material used for spill cleaning shall be
treated as COSHH Waste.
Concrete wash out skip available on site.
COSHH waste shall be disposed of in accordance with the COSHH information.
Place COSHH waste in COSHH Waste bin.
COSHH waste shall be disposed of by a licensed hazardous waste contractor
Working around Contaminated Serious health injury to Site Operatives. 3 4 12 During a desk study, Borehole data and previous trial hole information to be 3 1 3
Material e.g. presence of checked to identify any sources of contamination and trial hole locations to be
Hydrocarbons away from contaminated areas where possible.
If contaminated ground is found, stop work. Barhale to undertake assessment
and control and disposal measures to be determined.
WAC Tests to be carried out on site material on site.
General Working Unable to provide first aid in unlike event of 2 3 6 First aid boxes located at site office, canteen and at First Aid Station on site. 2 1 2
Injury to Operatives. Ensure person with first aid training is on site at all times.
First aiders identified on a poster onsite.
Copies of the emergency numbers and directions to hospital attached to method
statement and displayed in the office.
Eye Wash available on site,
Location of closest hospital briefed at site induction and maps showing location
of closest hospital available at First Aid stations on site. Communication
available to call emergency services.
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
General Working, Breaking and Hearing damage to Operatives, Members of 3 4 12 All operatives and personnel to wear correct Ear Protection at all times, when 3 1 3
Excavating the Public & to Site Visitors working in the vicinity of noise making activities, i.e. suitable ear defenders
when working in the vicinity of breakers /compressors.
Noise assessments to be produced for all plant and equipment with the potential
to exceed statutory limits.
Work area shall be designated an ear protection zone and appropriate signage
to be erected when the machine breaker or hand air breaker is in use, signed
exclusion zone to be place.
Acoustic barriers shall be fitted to the heras fencing if deemed necessary.
Reduced or dampened if the welding process is within a shed or container.
Erect Sound Barriers around the Base of the PE Welding Equipment
If the above methods not practical, ensure operators wear hearing protection..
Using Ready mixed Concrete on site Cement Burns. 3 4 12 Electrical Ducts to be protected to prevent concrete falling or encasing electrical 3 1 3
Dermatitis ducts.
Electrical Cable Ducts coming in contact with Timber shutters not to be in contact with Electrical Ducts.
Concrete which may lead to flash/arc and Designs to ensure sufficient clearance around electrical ducts for future works.
consequently burns Operatives will wear goggles if splashing is likely i.e. if pokering concrete.
COSHH information for ready mixed concrete is included in the attached
Appendix.
Works will be carried out in accordance with the COSHH information.
Longer waterproof gloves will be used if there is a chance of concrete running
down the arm while working with same.
Operatives shall ensure their skin is fully covered when placing concrete. repeat
Working with Compressed Air and Serious Injury due to contact with compressed 3 3 9 Air feed valve needs to be closed prior to opening any joints in the hose. 3 1 3
Compressed Air Plant air. Whip checks shall be fitted at each joint in the hose.
Eye injuries. Under no circumstances shall the hose be bent over to stop air flow while
Cuts and abraisions changing a tool.
Noise Position air hoses so no trip hazards are created.
Injection into skin High impact eye protection to be used by operatives using hand breakers and
drills.
Visually inspect all plant and air hoses before use.
Discard Air Hoses if any issues observed with air hoses.
Noise barriers to be erected around works area.
Working under inadequate site Intruders interfering with exposing services 3 3 9 Site to be security at all times. 3 1 3
security arrangements Site Security on site at all times, Night and Day.
All gates to be closed and fully secured when Barhale are on site and night
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
security present.
All personnel to report the Tideway Security Guard on entering site.
All personnel to sign in when entering site
General Working, Breaking and Serious health Injury due to contact with dust 3 3 9 Low Impact Eye protection is mandatory. 3 1 3
Excavating. such as COPD (chronic obstructive pulmonary Cover gravel/sand piles with plastic.
disease or lung damage) Dust suppression to be used.
Eye injuries. Dampen down before all necessary tasks including general sweep of site etc.
Dust masks will be issued and worn with every activity which creates dusts.
Ensure direction of potential dust is away from general public and other workers.
If the site interacts with public then dust netting to be erected.
Eye wash solutions shall be available at the work area.
High impact eye protection to be used by operatives using hand breakers and
drills.
Ensure person with first aid training is on site at all times.
Location of closest hospital briefed at site induction and maps showing location
of closest hospital available at First Aid stations on site.
Communication available to call emergency services.
General Working, using Vibrating Hand arm vibration syndrome (damaging your 3 4 12 All operative to have undertaken personal medicals. 3 1 3
Tools on Site health) Ensure HAV assessment has been completed before each task where HAVS
Vibration white finger (VWF) Serious long term hazard has been identified or likely. This will provide you with the specific EAV
injuries could be caused to operatives if not and ELV times.
monitored. TBT to be delivered on HAVS highlighting the risks.
Section Engineer to confirm vibration value of the model of all plant which has
been identified for use on site with the potential to cause hand vibration.
Limit of vibration exposure to be set with foreman prior to works commencing.
HAVS Weekly Exposure Record.
Records need to be kept of HAVs on allocation sheets.
Use HAV gloves and goggles when breaking.
Note HAVS calculator in Appendix of this document.
Incorrect use of Hand tools Lacerations, cuts, breaks to fingers 3 4 12 Tools kept clean and clear of grease. 3 1 3
Eye damage. The correct type of tool to be selected for the job.
If incorrect tool in place then don’t substitute but wait for the correct tool.
All Tools to be used by competent operatives.
All hand tools to be sourced from a reputable company, who have been
approved by Barhale Management systems.
All hand tools shall have inspections when arrival to site and inspected prior to
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
use.
Any defects shall be reported to the site management team, any issued rectified
asap. Tools to be quarantined until issue resolved.
All hand tools shall be serviced at the correct intervals
Injury during stacking of Lacerations & cuts 2 3 6 Banks-man to control all stacking operation. 2 2 4
materials/pipes Risk of serious injuries to site operatives. Stacked as per manufacturers guidelines.
Upper Limb injures Don’t stack materials near fencing.
Back Problems Strapped together until needed for use.
Pipe falling
Risk of crushing
Activities giving rise to Flying Lacerations & cuts 4 4 16 Wear goggles during cutting operations. Wear safety glasses at all other times. 4 1 4
Debris such as breaking road Risk of serious injury to members of the public. Place material to the side of the exaction.
surface Eye damage. Do not throw material.
Top man to move material away from the side of the excavation.
Debris netting to be installed on the perimeter fencing.
Clean, tidy site to be maintained.
Placing Diesel in Plant (re-fuelling) Dermatitis 3 3 9 Plant nappies to be used under all operating plant. 3 1 3
Potential fire risk leading to a risk of Burns. Funnels to be used while filling plant.
Damage to the environment Diesel to be stored in metal jerry cans which will be stored in a lockable fuel
storage area.
Automatic pumps in large plant such as excavators to be used.
Person undertaking refuelling to have arms and legs covered with the correct
PPE.
A designated person to be responsible for the diesel filling of plant.
Spill kits to be located on-site at all times.
Information with regards “Emergency Spill Response” to be available with spill kit.
All operatives to be trained in the use of a spill kit.
COSHH information for diesel to be included in Appendix of this document.
Water fittings not to be stored in close proximity to diesel storage areas.
Tool Box talks shall be given to operatives to raise awareness of environmental
issues.
For small plant such a 3kva generators and petrol saws etc., to be allowed cool
down before refuel.
Access and Egress Risk of serious injury to visitors/working 4 4 16 Ladders: Max lift height 9m (not a consideration here as trench is Maximum of 4 m 4 1 4
operatives due to falls from heights. deep) condition regularly checked; angle 1:4; secured; project 1.5m above top
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
edge.
Don’t stand on Services to Enter and Exit the Excavation.
Ladders to be inspected prior to use and recorded on a weekly basis. All ladders to
have ladder tags.
Ensure platform at access/egress point is kept clean at all times to prevent falls.
Ensure steps of ladder are kept clean at all times and that there is enough toe
depth, even at clashes with trench shoring brace.
Ensure that nothing is stored at the access/egress point.
Tie ladders at two spots near the top.
Night Time/Dusk Working Risk of serious injury to visitors / working 4 4 16 Always have a back up generator which is full of fuel encase main power source 4 1 4
operatives due to injuries caused by bad fails during night works.
lighting. Ensure that there is a ready supply of spare bulbs.
Ensure each gang has a good torch with batteries.
For works carried out at night or in the evening when it is dark, tower lights or task
lighting must be used to keep good visibility within the works areas
All noisy works must conform with those set out in the S61
Ensure all trip hazards and obstruction are removed
All involved to be aware on the relevant Supervisors, First Aiders and fire Wardens
and understand the procedures for escalating any incidents or occurrences.
Operatives to ensure they keep warm during Cold weather conditions – Adequate
PPE to be issued, (Hard Hat, Glasses, Orange Long Sleeve HiVis Jackets¸
Gloves Orange Trousers, Boots and Fire Proof Overall for Operatives Digging).
Lifting operations including: Risk of serious injury to visitors/working 4 4 16 Lifting equipment (max load); certificated and checked. 4 1 4
Heavy Loads and Incorrect slinging operatives/members of the public due to lifting Approved lifting plan will be developed for excavators and crane and must be
incorrectly. briefed to all involved before any lifting takes place.
Crushing Injuries Minimise lifting directly overhead of the existing services.
Falling Opjects Bridging beams to be lifted into position prior to fully exposing the Thames
Water main and the HV Cables
Adequate access around pits during lifting.
Qualified CPCS certified Slinger Signaller to control all lifts.
Qualified CPCS certified Lift Supervisor to control all more complex lifts.
Exclusion zone erected around lift locations.
Slinger to communicate to personal within pit that a load is about to be lifted into
the pit.
Tag lines will be used when lifting loads above ground.
No over sailing of perimeter fencing allowed.
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
No items to be lifted over personal
Lifting equipment to be certified and visually checked before use.
Crane/excavator 7 day inspection as per Barhale Mobile Plant procedure &
certificates in date.
Select Crane will also be inspected by crane op on a daily basis as per Select
policy
Lifting accessories in date and registered. Colour tagging system to be used.
Weekly lifting equipment inspections completed and recorded as per Loler and
Puwer requirements.
Good communication between Slinger/Signaller and Crane/Excavator Operative
Tag lines to be used to control movement of larger items.
Use of kettle skip Serious injury to fingers or operatives 4 3 12 Ensure skip is landed properly on the ground before approaching. 4 1 4
Excavator to be isolated.
Operative to undo restraints on the skip handle and stand clear of area.
Skip to be tipped by the excavator.
Skip to be landed and stationary before operative approaches to redo handle
restraints.
Skip base and sides to be checked and any materials stuck to the sides to be
removed.
Skip regularly inspected weekly as per LOLER regulations and daily prior to
use.
Kettle Skips to be sourced from BCS or from a reputable company, who have
been approved by Barhale Management systems.
Kettle Skip is to be a Self-Tipping Kettle Skip.
Excavating alongside Water Main Flooding 3 3 9 A discharge license to be agreed with Thames Water for the nearest sewer for 2 1 2
Drowning clean water, chlorinated water & trench pump out.
Destruction of Property Water Main Leak Contingency Plans to be in position.
Trial of Water Main Leak Contingency Plans to be undertaken.
Pumps to be located on site.
A permit to pump to be signed off.
A 2” electric submersible pump to be kept on-site at all times.
Procedure if Water Mains Leaks to be displayed on site.
Thames Water to be notified immediately if any leaks observed.
Stock of sand bags to be available.
Slump to be located within excavation or box placed underneath cut pipe to
allow water to be pumped out.
Initial1 Residual1
Activity Hazards Control measures
S L R S L R
Third Parties Accident 3 3 9 All personnel entering the site to sign in with security guard. 3 1 3
Injury to Operatives All personnel to report to Site Office.
Slips Trips and Falls All personnel to be Brief by Barhale on Barhale activities
FLO to advise Barhale off all third parties/visitors in advance of third parties
entering the site.
All Third Parties operatives to work to their own approved RAMS.
Guidance on Scoring of H, S & E Risks/Aspects
1
Site / Depot / Office specific initial risks should be based on corporate residual risks presented in the company health & safety risk registers
(see 621-01). In evaluating site-specific residual risks, scores should only change if controls additional to company controls are implemented
locally.
Environmental risks/aspects
1
Site / Depot / Office specific initial risks should be based on corporate residual risks presented in the company environmental risk registers
(see 621-02) In evaluating site-specific residual risks, scores should only change if controls additional to company controls are implemented
locally.
Note:
First review date will be undertaken on the first day of the activity with subsequent review dates on a weekly basis or following changes to
working methods/conditions resulting in additional risk realisation and control measures.
Section 2 - Method Statement
1.0 References
Health & Safety Plan
Quality Assurance Plan
All work will be carried out in accordance with the Health & Safety at Work Act 1974, and Barhale Health &
Safety Plan (MAN/HSP) and Environmental Plan
BS EN ISO 5349-1 Mechanical Vibration.
HSG47 - Avoiding danger from Underground Services
Mandatory Code of Practice for Site Set up and Maintenance of corporate image
Copies of the relevant documents are retained on-site for inspection. Any queries relating to the design
documents or drawings must be directed to the issuing party for further clarification
Site drawings
Utility drawings
Construction Phase Plan 4000-FLOJV-TTCEN-210-ZA-PQ-100003
Contract Emergency Response Plan 4000-FLO-TTCEN-090-ZA-PQ-100001
Service protection procedure 4610-FLOJV-TTCEN-150-ZA-HI-100034
Safety when working in excavations procedure 4610-FLOJV-TTCEN-150-ZA-HI-100032
Control of Hot works procedure 4610-FLoJV-TTCEN-150-ZA-HI-100030
Reline 51m of 24” cast iron water main to protect during tunnelling works.
Install ridermain to maintain continuity of flow.
Notes:
TWUL is to confirm final location of excavation pits based on Damage assessment phase 3.
24” water main mitigation design can be found in appendix 2.13. However, changes on the
design have been agreed with TWUL and captured in the commissioning plan appendix 2.13.
A separate Work Package Plan will be produced to detail the methodology of protecting/
supporting the UKPN assets located in close proximity of the 24” water main.
A Thames Water Permit to Work (PTW) with a London Water Control Centre (LWCC) log on number will also be needed
before Barhale can commence excavation works around the live Thames Water mains.
Existing services
The Vision Survey Service Co-ordinator shall obtain layouts of all the existing services and carry out a desk top
survey to determine which services are present in each of the work areas.
All existing trial holes information to be analysed
The Vision Survey Service Co-ordinator and the BARHALE engineer shall carry out a visual inspection of any
work area, which shall include any existing lamp columns and street furniture that would require power or
comms and existing trench scare that may be present and carry out a cable avoidance tool (CAT) scan prior to
any excavation commencing. All known services shall be marked out so that each mark extends out of the
excavation area by 1 metre on either side.
The Vision Survey Service Co-ordinator shall issue a permit to dig to the Barhale supervisor prior to any
excavation commencing. All operatives involved in the activity shall be briefed into the contents of the permit.
A CAT shall be available on site at all times during this activity. There shall be at least one operative in each
gang trained in use of the CAT.
Thames Water shall issue and Licence to Operate. When holes are being excavated over any of the water
mains the site supervisor (foreman) shall inform the (Network management centre) NMC that the excavation
has commenced and ended at the beginning and end of every working day, quoting the relevant Thames Water
log on number. Contact NMC on 0800 009 3909 and log onto the permit to work (PTW) by quoting the number
of the permit. Permit number to be provided by Thames Water.
Skills and Training requirements
All operatives will have undertaken the Tideway Induction prior to commencing on site.
All personnel and visitors shall be given a site induction prior to being allowed access to any part of the site.
All personnel shall hold a valid Construction Skill Certification Scheme (CSCS) card and shall be competent to
carry out any task asked of them.
Construction plant shall only be operated by the personnel competent to do so and holding a valid Construction
Plant Certification Scheme (CPCS) card.
A member of each gang shall hold a valid New Roads and Street Works Act (NRSWA) card.
A member of each gang shall have undertaken a CAT Detector course.
All Work activities shall be carried out in accordance with the risk specific risk assessment and method
statement. All personnel involved with specific task shall be inducted into the risk assessment a method
statement and shall sign to state that they have read and understood the risk assessment and method
statement.
The floor saw blade shall only be changed by competent personnel.
All operatives working with water main fittings will have a EUSR hygiene card.
All Barhale Construction plc operatives to have a Thames Water Safety Passport.
Waste management
Waste management shall be in accordance with the Health and Safety Environmental Management Plan.
All excavated material shall be removed from the site and transported by grab truck, by licenced waste carriers
to the designated site where it will be recycled for further use as trench fill. This trench fill will be brought back
in to use on the scheme and to be used to backfill the excavated trenches.
All excavated material to be stored in a 20yard skip on site prior to removal from site.
All COSHH materials shall be treated as special waste and shall be of in accordance with the COSHH
information sheet.
Canteen waste shall also be segregated and placed in covered skips and removed from site and transported to
a licensed disposal facility for disposal.
Manual handling
All personnel to have undertaken manual handling training.
TBT to be delivered with regards manual handling.
Manual handling assessments for the lifting of items of plant, pieces of tarmac, trench shoring, small tools,
small pipe fittings and Heras fencing panels shall be carried out by the supervisor prior to any work
commencing.
The supervisor shall assess the physical ability of the operative, weight and shape of the item, any changes in
the lever or direction and the weather condition at the time of the manual handling activity. Operatives shall also
ensure that the route is clean of obstructions and trip hazards prior to the manual handling activity.
Operatives shall be given tool box talks to raise awareness regarding manual handling.
MASS barrier bare units shall be transported on a flat bed trolley from the stocking area to the work area by
BARHALE.
MASS barrier base units shall be place onto the trolley using the proprietary lifting bars by BARHALE.
Mechanical lifting will be used where possible, and wheelbarrow’s/Trolley will be used to move items as
required.
Do not attempt to lift any load that seems heavy (over 25kg or your own personal lift if less than 25kgs) or large
without asking a supervisor for a manual handling assessment to be carried out.
Use correct manual handling technique, keep back straight and bend at knees when lifting. Share or split loads
with other operatives.
Use correct gloves to protect from sharp edges.
Fuels
Fuel for plant shall be kept off site and delivered when needed to a double bunded metal tank. If fuel is stored
on site it shall be stored in designated containers, identified as either petrol or diesel, in quantities not greater
than 5 liters in a bunded gas cage.
A designate competent person who has undergone an environmental course shall be responsible for fuelling
the items of plant. The diesel will be transported around site with a bunded wheelie bin bowser. Operators shall
use a proprietary funnel for refuelling to reduce risk of spills. Spill Kit to be available.
COSHH information for diesel etc. is included in appendix 2 of this document. All work shall be carried out in
accordance with the COSHH information.
A spill kit shall be kept at each work area when plant is being used. All personnel carrying out this activity shall
be instructed on how to use a spill kit. Any used granules shall be treated as hazardous waste and disposed of
in accordance with the COSHH information.
Diesel to be stored in metal jerry cans which will be stored in a lockable fuel storage area.
Information with regards “Emergency Spill Response” to be available with spill kit.
Mobile Phones
Use of Mobile Phones only allowed within the safe areas only (close to pedestrian gates away from works
interface) and be aware of surroundings and activities being conducted in the vicinity.
COSHH
The following COSHH substances are anticipated to be used in the works outlined by this Method Statement.
PPE
Personal protective equipment for these works will be a minimum of:
Tideway high visibility vest / t-shirt / jacket
Tideway high visibility trousers
Hard hat
Steel toe cap safety footwear with midsole protection (not rigger boots)
Task specific eyewear (low impact glasses as a minimum)
Task specific gloves (low impact gloves as a minimum)
Ear defenders
High impact goggles.
Protective gloves
Fire retardant overalls - Hand digging
For identification purposes, at all times FLO employees will be wearing Tideway branded Orange High Visibility Clothing
with hard hat as follows;
QUALITY
24” water main works will be carried out as per ITP: 4300-FLOJV-CHEEF-260-UZ-PQ-100007
Methodology
1. Mobilise to site
- Set up compounds, welfare etc..
2. Excavate trial holes as per FLO Drawing “Produced by FLOJV Utilities Team 27/07/2017
3. Linestop pit
- Excavate for installation of linestop at location 81m west of west pit
- Install under pressure tee, pressure test and pour concrete thrust block around tee.
- Allow thrust block to cure, as per design
4. Excavate east launch pit and west reception pit
5. Isolate main using Thames water valve at east end and install linestop at west end ( 10 hour shut)
6. Cut out old cast iron pipe in both launch and reception pits and install new pipework configuration
- Re-connect to existing cast iron pipe
- Thames water to re-charge main by opening valve at east end and removing linestop at west
end.
7. Construct and pour thrust blocks in launch and reception pits and allow to cure. ( quick setting
concrete), as per design.
8. Construct 250mm rider main
- Test rider main (test to be witnessed by Thames Water), chlorinate and commission rider main
9. Switch flows from 24” to rider main by closing newly installed valves in launch and reception pits.
10. Allow for providing that there is no connection from the 24”, can done via CCTV Survey, RAMS for
CCTV survey will be provided by Subcontract at a later date.
11. Slipline section of 24” cast iron pipe between launch and reception pit
- Test, chlorinate and commission sliplined section of main.
12. Divert flows back to 24” main and isolate rider main by closing 250mm valves.
- Decommission and remove rider main
13. Backfill all excavations
14. Excavate for 7” supply to FLO site
- Install UPT with 200mm outlet
- Drill UPT and isolate with 200mm gate valve
- Extend pipework into footway and construct chamber for access by FLO.
- Reinstate excavation
15. Demobilise
Buried services
High Voltage (HV) Cables – UKPN Assets
Thames Water 24” Main
Excavation around Live Services
Working in a deep excavation
Lifting Operations
Slips Trips and falls
Falling from Height
Deliveries and other plant movement
Flooding
NOTE – This RAMS is to be read in conjunction with “RAMS for working around UKPN Assets in
Chelsea Embankment”
Method Responsibilit
y
Site
Setting Out Supervisor
Works Supervisor / Site Engineer to mark out the plan area of all the required excavations.
The width and positioning of the excavation will be determined by the location of the 24”
water main and the additional services within the area. Where possible the excavation will
be positioned to minimise the interaction with other services.
Once the Excavation has been sprayed out and the permit issued the outline of the
excavation will be saw cut.
The existing road surface shall be cut using a floor saw. (During any sawing activity the
work area shall be designated an ear and eye protection area and all personnel entering
the work area shall wear ear protection and high impact eye protection. If any personnel
wish to enter the work are not wearing ear protection and only wearing low impact eye
protection then the sawing shall stop.)
Utilising the information obtained from the trial holes the plinth for the bridging beams will
be cast.
The plinth will be a 1m x 1m x 200mm high concrete pad. There will be A393 Mesh
installed on the top and bottom of the pad. The concrete utilised will be C25/30 concrete.
A timber shutter will be built to accommodate the plinth.
The Bridging Beam will be a Universal Column – 305 x 158.
The UC305x158 will be procured in 2 number 5meters and 1 number 7meter lengths.
The required bolt bolts will be marked out on the UC305 x 158 and on the Flange and Web
Plates.
The bolt bolts will be drilled with a Mag Drill on site.
The bolts to be utilised to connect the flange and web plates will be M20 HSFG Bolts.
The Web Plates to be utilised will be 2 Number 220mm x 260mm x 10mm thick at both
sides of the web at each splice location. 3 Number bolts will be used on both sides of the
splice (6 bolts in total)
The Flange Plates to be utilised will be 2 Number 1000mm x 225mm x 25mm thick top and
bottom at each splice location. There will be 14 number bolts installed in two rows
therefore 28bolts in total. The first bolt will be positioned 40mm from the end with a spacing
of 70mm between bolts
The UC elements will be positioned on the precast plinths and supported on 8” x 8” timber
or similar, while the flange and web plates installed and bolted together.
Excavation by hand dig within 500mm of the 24” Water Main and within 500mm of the
UKPN Assets. No Excavator can be used, excavator can only be utilised to shovel into the
bucket of the excavator and for lifting operations as per the approved lift plan within the
encroachment limits.
Existing road surface construction shall be removed using a combination of hydraulic
pecker on the excavator outside the encroachment limits as sprayed by the FLO Service
Co-ordinator/Vision Survey and hand operated breaker and compressor. Excavated
materials to be kept in separate muck away heaps where possible.
All excavation works to be adequately protected from access by unauthorised personnel.
Compound fencing to be kept closed when not in use. 24hour FLO/Tideway security on
site at all times.
Starting from the area where the trial holes were completed previously using careful hand
excavation all services in the top 1.2m of the excavation will be exposed. There will be the
24” water main and the electrical ducts within this level.
The electrical ducts will be supported at per “RAMS for working around UKPN Assets in
Chelsea Embankment”
The 24” Water Main will be supported at the existing Spigot Socket Joints. We believe the
spigot socket joints are located at 3.6meters intervals and not 3meters as originally
believed.
The 24” Water Main will be supported with the use of a Steel Cradle system supported
from the bridging beam.
Operatives working to exposing and support both the Water Main and the electrical cables
will wear fire proof overalls.
When the excavation has been lowered to a depth of 1.2meters the area surround the
spigot socket collars will be excavated locally.
The Hanger System will be made from PFC 125 x 65 sections.
The channel sections will be delivered to site with the required end plates already welded
in position.
Once the area underneath the pipe has been excavation locally the hanger system will be
installed and bolted together.
The bolts used to join the hanger system are M12 Bolts and M8.8 grade.
Outside the encroachment limits a slip trench shall be excavated by hand to a depth of
300mm along the length the excavation. If no services are found then the excavator shall
excavate to the depth of the slip trench only, in the area where the slip trench was
completed outside the encroachment limits. Toothless bucket will be used. This shall be
repeated until either the excavation reaches full depth or a service is uncovered. If a
service is uncovered then the service shall be fully exposed by hand excavation only.
Prior to the works around the UKPN High Voltage Cables, UKPN will be contacted to allow
them if they want to provide a UKPN operative/supervisor to provide a watching brief while
we work around the UKPN HV Cables.
When the excavation reaches the encroachment line of any service the concrete
road construction shall be undermined by using Air Lance/Soil Picks and insulated
shovels or insulated grafts and then broken out using the hand held breaker once
the concrete has been undermined.
A length of timber will be placed underneath the undermined concrete prior to the concrete
been broken out to act as a barrier between the hand held breaker and a potential service.
Under no circumstances shall forks, picks, bars or any other sharp ended tools be used.
If there is additional concrete or any other unforeseen item present within the excavation
then the breaking activity shall cease and be assessed by the works supervisor to
determine whether the concrete can be removed safely.
All services crossing the pit will be supported using suitable sized timber & ratchet straps
or i-beams.
All ladders must be tied at sides and extend above ground level by 1000mm minimum.
Access will be provided to both sides of the excavation to prevent operatives climbing
across the both the Thames Water 24” Main and UKPN electrical ducts.
Surplus material to be deposited in a dumper & removed to the agreed storage location, for
removal from site as required by grabs truck.
Roads, footpaths and working areas to be kept clean and clear of debris, which can cause
a trip hazard, particularly in the vicinity of the open excavations.
All services encountered shall be carefully excavated around by hand and supported
where necessary.
Careful excavation will be used to carry out the entire excavation as per safe digging
proceess below which is sketched out in the attached appendix:
- After services are identified & marked on the ground the supervisor will decide the best
place to start excavation (greater than 500mm from known services).
- The tarmac will be cut in this area and broken and removed using the pecker on the
excavator if outside the encroachment limits, if within the encroachment limits then the tar
will be broken by hand held breakers.
- The 200mm deep reinforced concrete slab will be removed from beneath same using
spotted machine breaker to reduce HAVS when outside the encroachment limits.
- The pit will be dug from a face from this initial point in both directions always from this safe
face which has no services in same.
It is anticipated that Trench shoring will not be needed in the top metre of dig but shoring
will be needed when we need to go lower - shoring will consist of a MGF tank brace and
sheet piles & cross boarding as per Appendix 2.6. All temporary works designs have been
developed by a competent designer and the design will be approved by FLO prior to use.
The excavator with a toothless bucket will only be used to dig when it is safe to do so. A
timber template made from 9” x 3” timber will be inserted around the pits as a guide for the
sheet piles. It can also be used for attaching edge protection on to same.
The 4 corner sheet piles will be inserted first. These will be held in place using a timber
cross strut at each corner to prevent them from falling over.
The parts of the Top frame will be lowered into excavation in pieces and assembled
together then cross struts inserted to hold bottom of corner sheet piles.
The Top frame legs will be hung using chains from the trench sheets.
The sheet piles will then be inserted on all faces as per the temporary works design.
The material from bottom of piles will be hand dug with spades. The ground ahead of the
sheet will be hand dug and the sheet dropped into position, the soil in front of the sheet will
be reinstated to provide the necessary toe and timber wedges will be used to tighten
sheets behind the frame. The central material will them be excavated.
The excavated material underneath the services will be excavated into a self tipping kettle
skip when it is not possible for the excavators bucket to be lowered into the excavation.
The excavation will be carried out to a depth of approximately 2.2m and the first 4meters
on the west side of the Linestop/Isolation Pit will be dug to approx 3.5m deep.
There will be two number excavation 1meter deep perpendicular to the water main at the
Reception Pit (Eastern Pit) which will act as the “key” for the reinorced concrete base.
The installation of the 2nd frame from top will be as per the top frame and this frame will be
hung from the top frame etc.
The second frame will be inserted underneath the water main.
Above and below the Thames Water 24” main and the UKPN electrcial ducts, the soil will
be crossboarded with either 9” x 2” or 9” x 3” timbers.
Tighten to 100% estimated torque. All flanged joints shall be tightened to the required
torque as per manufactures guidance using a hand torgue spanner.
All spanners to be kept in a sperilised bucket containing chlorus solution.
All flanged joints to be visually and physically checked at the time of installation and prior
to testing.
Support the pipes on timbers as requires ensuring the ends of fittings are not touching the
ground.
After assembling the joint fully, examine to ensure assemble correctly.
Pressure Test
All personnel to be advised that testing is taking place, to be brief at Daily Briefing and
signage to be erected.
All joints to be visually and physically checked at the time of installation and prior to testing.
All pressure test apparatus to be procured from chosen supplier. Barhale Personnel are
familiar and competent with this equipment. The equipment is all coming from the same
supplier, thus reducing risk of components not been compatible.
Water will be sourced from an installed hydrant on the new connect pipework/ hydrant on
the rider main.
Install test plate at one end on hydrant T-piece. Lay out 2” fire hose along the top of the
ground from test plate to agreed Thames Water discharge point at sewer manhole.
Connect pipe to hydrant (fill point) and fill entire length with water.
Attach pump equipment.
Open air release valve at high point of main.
Pump the water in and observe pressure gauge increase. Close air valve when water
starts emerging from same.
The pipeline is to be pressurised again & inspected by FLO and Barhale during the
allocated TW period to observe any leaks or failures.
Upon a successful test, TW will issue the relevant paperwork.
Rider Main
The plastic pipework, associated ductile iron fittings, pressure testing and chlorinating will
be undertaken as described above.
The Plastic Pipework to be utilised for the rider main will be 250mm, SDR 17 Blue Plastic
Pipe.
The rider-main will be installed on the footpath as there will not be sufficient room on the
Carriageway due to the width of the western excavation. Please see the below image
which shows an outline of the position of the rider main.
The plastic pipework will be supported on timbers.
The plastic pipework element of the rider main will be wrapped in Hessian Material to
protect from frost. The pipework will be wrapped in advance of the cold weather.
Pedestrian Barriers will be erected to form a segregation between the general works area
and the rider main.
Training
All personnel shall hold a valid Construction Skills Certification Scheme (CSCS) card and shall be competent to
carry out any task asked of them.
All operatives to have attended Tideway Induction.
Construction plant shall only be operated by personnel competent to do so and holding a valid Construction
Plant Certification Scheme (CPCS) card.
At least one person in each gang shall hold a valid New Roads and Street Works Act (NRSWA) card.
All pipefitters to have a EUSR hygiene card and Control Point Training.
All Barhale operatives to have a Thames Water safety passport.
6.0 Plant and Equipment
Materials
Item Specification Quantity
Self Compacting Surround 10mm shingle TBC
Backfill Primary Type 1 TBC
Backfill Sand TBC
Backfill Marker Tape TBC
Concrete CBM 3 TBC
Bituminous Material To be replaced as existing TCB
Contact Details
FLO Contacts
Hein Prinsloo Project Manager 07789 504429
Michael Walsh Construction Manager 07734 312647
Alejandro Corral Agent 07808 101842
Ross Green Site Engineer 07595200954
Alan Hughes HESQ 07342026286
Chris Glass Senior Quality Engineer 07796696037
Eilidh Johnson Environmental Advisor 07392120158
Alex Lindsay General Foreman 07387233790
Tideway
Jonathan Keyworth Project Manager 07594887050
Garry Frew Site manager 07712230994
BARHALE Contacts
Site Manager Jimmy Gill 07903944753
Emergency Services Phone number
Police / Ambulance / Fire Brigade / Coastguard 999 / 112 / 911
Local Police Non-emergency 101
Environment Agency Environmental incident 0800 807060
Anti-Terrorist Hotline Terrorist activity 0800 789321
Thames Water Effect on assets 0800 714614
National Grid Gas Effect on assets 0800 111999
UK Power Networks Effect on assets 0800 7838838
London Underground Effect on assets 0343 2221234
Port of London Authority Effect on river 07711 640055
environment
Westminster City Council Incident within 0207 6412388
constituency
City of London Incident within constituency 0207 6063030
FLO Site Incident Controller (SIC) 07931 877404
7.0 Appendices (list & attach all applicable assessments i.e. HAVS, Manual Handling,
COSHH, Noise, lifting plans etc)
The following COSHH substances are anticipated to be used in the works outlined by this Method Statement.
Prior to commencing the activities covered in this safe system of work document all personnel are to sign
below to confirm that a clear briefing explaining the job has been given and is understood:
Example:
FL22 (small breaker) = 18 mins trigger time per day (Exposure Action values)
German Jigger (big breaker)= 6 mins trigger time per day (Exposure Action values)
Rammer = 61mins trigger time per day(Exposure Action values)
Air powered disc cutter = 36mins trigger time per day(Exposure Action values)
Floor saw = 170mins trigger time per day(Exposure Action values)
Air Powered Drill= 150mins trigger time per day(Exposure Action values)
BAR/RAIL/F/058
Hand Arm Vibration Assessment Form
Individuals Name
Site Name
Contract No
Ai(8)=a w?t/8
Where a h,w is the vibration magnitude for the tool in m/s 2 and t is the length of time the tool is used in hours.
Daily vibration dose is calculated using the following formulae:
Where A1 (8), A2 (8) and A3 (8) are the partial exposure values for each vibration source.
Address: Charing Cross Hospital, Fulham Palace Rd, London W6 8RF, Phone: 020
3311 1234
Appendix 2.8: Safe Digging Process
Appendix 2.7: Barhale Safe Zones around Plant
Appendix 2.8 – Safely Mount and Dismount Your Machine Poster
Appendix 2.9 – Take 5 Poster