Professional Documents
Culture Documents
MS-21 For Fiberglass Insulation
MS-21 For Fiberglass Insulation
Fiberglass insulation
Project Name:
Design, Construction, Completion and Maintenance of Court at Madinate Zayed, AL Dhafra
Region.
Index
1- Purpose:
2- Scope:
3- Legislation and code of practice:
4- References:
5- Definitions:
6- Resources:
6.1 Materials and their approval
6.2 Subcontractor approval
6.3 Shop drawings approval
6.4 Equipment
6.5 Human Resource
7- Role and Responsibilities
8- Safety Precautions/ Risk Assessment:
9- Detailed Construction Sequence (Methodology)
10- Inspection and Testing Plan ( ITP ):
11- Related Forms:
12- Attachments:
METHOD STATEMENT
Fiberglass insulation
1.0. PURPOSE:
The purpose of this Method Statement is to ensure that all activities related in
Fiberglass insulation and foster works are carried out sequence and serve as basic
guidance for work implementation. The aforesaid activities are in accordance with
requirements of the project specifications, approved Shop Drawings and relevant
authorities’ requirements.
Define the specific task to be performed and ensure a safe system of work
To set out the sequence of construction and work procedure
Show the procedure to ensure work complies with the specification and
drawings
Ensure works carried out without any adverse impact on environment
2.0. SCOPE:
This method statement covers the various steps involved in Fiberglass insulation
and foster works Construction at Madinat Zayed Court project.
The legislation and code of practice to be followed as per approved HSE plan of the
Project.
Fiberglass Rigid insulation and foster works for Chilled water pipes
Abu Dhabi Environment, Health and Safety Management System (OHSHAD)
CoP 2.0-PPE
CoP 3.0-Occupational Noise
CoP 4.0-First Aid & Medical Emergency Management
CoP 11.0-Safety in heat
CoP 14.0-Manual Handling and Ergonomics
CoP 17.0-Safety signage and Signals
CoP 21.0-Permit to work
CoP 22.0-Barricades of Hazards
CoP 29.0-Excavation
CoP 33.0-Working in, over or adjacent to road.
CoP 36.0-Plant and equipment
CoP 39.0-Overhead and underground services.
CoP 44.0-Traffic Management.
CoP 53.1- EHS Management during Construction
CoP 54- Waste Management
All UAE Environmental Regulation.
4.0. REFERENCES:
The following documents should also be read in conjunction with this method
statement.
METHOD STATEMENT
Fiberglass insulation
6.0. RESOURCES :
The Equipment and Tools will be used are below – Include Power tools, Hand tools,
Access equipment etc.
Survey Equipment’s
Protective clothing: Gloves, goggles, safety shoes
Electric hammer action drill machine
Spirit level
One step scaffolding
General toolbox items
Project Manager
QA/QC Engineer
Site Engineer.
HSE Engineer/officer
Foreman/Supervisor
Skilled & Unskilled Labours
First aider
a) Plan and determine the required resources for conducting the work.
b) Interface with the safety personnel to ensure that all aspects about the work
are being considered.
c) Brief all the site Foreman’s with regards to their roles and duties.
d) Complete in-charge of site supervision.
e) Ensure that operatives and works shall comply method statement, toolbox
talks and general site briefing.
f) Communicate this Method Statement to his subordinates. Provide his
subordinates with the information they need to carry out their responsibilities.
g) Ensure that the quality of works meets the requirements of the project
specifications and ITPs.
7.5. Surveyor:
a) Ensure that all surveying equipment being used are calibrated and having
valid calibration certificate.
b) Ensure that the excavation progress to the required line and level.
c) The Surveyor shall be carried out the setting out for the area location, layout,
and line, width depth including trench, underground utility services and other
dimensional requirements in accordance with the approved drawings.
d) Surveyor is responsible for carrying out all setting out and survey works
under the guidance and supervision of the Site Engineer
Please refer the detailed methodology of HSE requirements and risk identified in Risk
Assessment sheet
Safety Jackets
Safety shoes
Helmet
Hand Gloves
Safety Goggles
Ear plug
The Health, Safety and environmental Management Plan for the project has been prepared
to meet the various HSE & Traffic and Environmental management requirements as
mentioned in Contract Document and as per the established HSE & Traffic and
Environmental Management System and Procedure of M/s NIGM.
8.0.7 Environment
Noise control
Air quality
Control of Exhaust emission
Control of dust emission
Soil ground water quality
Weekly and monthly environmental inspection shall be conducted
8.0.9 Induction
All workers and staff shall attend the HSE induction before commencing
the work at site
All personnel shall adhere the PPE
All work shall attend toolbox talk held weekly
Any unsafe act or condition are to be identified and corrected immediately
and referred to respective supervisor
Any accident or incident shall be reported immediately to take preventive
measures
Training
Delivery of material
Site installation
Once the material is delivered to site and ready to install the readiness of
location is checked before fixing the frames and if any location is not finished
( plaster/paint) these items are not fixed and reported to main contractor
9.0.3 PROCEDURE
METHOD STATEMENT
Fiberglass insulation
Installation procedures
1. Straight Pipes:
Make sure the pipe surface to be insulated is clean and dry from dust, oil or grease.
Apply one coat of adhesive over the pipe surface, as per Adhesive manufacturers
Instruction.
Apply the required glue on the pipe surface to insulated.
Fix the preformed rigid section by opening snap on side enough to insert over the
pipe.
Press the section all over to achieve bonding between pipe and insulation.
Keep the overlap over the section.
Apply a light coat of adhesive on down part of overlap and fix it over the section -
take care no wrinkles are formed.
Wipe out any adhesive spill over by using a dry cotton cloth - make sure the surface
is dry off adhesive.
Fix 75 mm Aluglass Tape preferably UL Listed centric to lap and section surface of
long seam and joints between sections.
Press the tape using smooth edged plastic card (used telephone cards also found
ok) - make sure there are no wrinkles formed in the process of fixing the tape.
While fixing the next length make sure a coat of adhesive is applied on any face on
either of section of continuous joint.
Fix Aluglass tape preferably UL Listed equally centred between two sections.
2. Joints at Support:
Insert Fix the sections from either side of insert using coat of adhesive at each
faces of substrate and make sure the insulation is friction fit.
Apply Aluglass tape centric to the insert allowing equal tape lap over insulation on
both side.
Apply a tack coat of 30-36 at 60-70 sq. ft. per gal (1.5-1.7 m2/l).
Immediately imbed the selected lagging fabric into the wet coating. Smooth to avoid
wrinkles and overlap seams by at least 2 inches (5 cm).
Immediately apply a finish coat at 60-70 sq. ft. per gal. (1.5-1.7 m2/l). The dry film
thickness of this application will vary with the fabric selected.
Use clean paint brushes (suitable for water-base paints). Apply with full brush and
spread out evenly.
Materials
METHOD STATEMENT
Fiberglass insulation
The Fiberglass Rigid Rolls will be stored in a shaded in a shaded area for
Insulation materials with tarpaulin form direct sun and in accordance with
manufacturer’s recommendations.
It will be ensured that the Insulation materials do not come into contact with
sharp projections.
The insulation material will be stored in a flat level area and raised above the
ground on timber so that the lowest point of any roll is not less than 150 mm
above the ground.
The insulation material will be stacked in such a manner so that the height of
the stacked pipes does not exceed 2 metres.
Foster 30-36 stored in site Store and apply between 40°F (4°C) and 100°F
(38°C) in a dry area in its own puckets.
12.0. Attachments: