BONIFACIO LANDMARK REALTY DEVELOPMENT CORP.

CHANG

CO No:
Project: 6th AVENUE
Date:
Location: 6th Avenue, Veritown, Fort Bonifacio Global City PO No.:
Contractor:
MONTEVISTA CONSTRUCTION CORP.

Cost Breakdown (attach additional papers, if necessary)


Unit Unit Rate Omissions
Description of work
(Php) Qty Amount (Php)

1 lot

DEMOLITION OF EXISTING STRUCTURE

(OLD BGCR SHOWROOM) Deductive


TOTAL

REASON FOR CHANGE INITIATED BY Justifications:


Bid vs. Const. Var. X Owner

X Site Conditions Project Manager Per actual site condition. Location of Cluster M has an existing

Design Change Consultant demolished.

Budget Transfer Contractor

Code Compliance Building Official

Others: Others

RECOMMENDED BY:

PREPARED / CHECKED BY: RECOMMENDING APPROVAL:

Fennelyn T. Jusayan Date Peter N. Moralde


Asst. Manager Vice President
Federal Land Inc. Federal Land Inc.
ACCEPTED BY: APPROVED BY:

MONTEVISTA CONSTRUCTION CORP. FEDERAL LAND INC.

Jose C. Talusan Jr
Nila M. Rivera First Vice President
Montevista Construction Corp.

ALFRED V. TY
President
CHANGE ORDER

MCC-001
23-Sep-15

additional papers, if necessary)


Additions
Qty Amount (Php)

300,000.00

X Additive
300,000.00

site condition. Location of Cluster M has an existing structure that needs to be

demolished.

MMENDED BY:

RECOMMENDING APPROVAL:

Date
APPROVED BY:

FEDERAL LAND INC.

Antonio T. Tan
Exec. Vice President

ALFRED V. TY
President