Professional Documents
Culture Documents
MS Project
MS Project
10 Project Information
One would be able to get MS-Project to schedule from a specified project end date
It is advisable to introduce all project constrains at the very end of your planning session.
Task : Remove the constrain for 2-4 and specify project end date as 12/01/2009 and schedule from Project Finish Date.
What is the project Start Date now
Use the undo button to get it back to schedule from the Project start date.
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 7
Introduction To MS Project 2007 Professional
11 Assigning Resources to Activities
Check : TOOLS / OPTIONS / GENERAL
Define Rate Works on Working Hours Max Units
Peter 100 T/S 8-5
Harry 100 T/S 8-5
Martin 100 T/S 8-5
Bob 200 T/S 8-5
Chris 100 t/s 8-5
cat 5 network wire 5000 per 100m
sk-lab 40 T/S 8-5 400%
unsk-lab 20 T/S 8-5 800%
Cost
Max Units
Base Calendar
Available From
Available To
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 8
Introduction To MS Project 2007 Professional
13 Descriptions Material
Cost
Material Label
Field
Max Units
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 9
Introduction To MS Project 2007 Professional
Accrue at
Field
Base Calendar
. Custom
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 10
Introduction To MS Project 2007 Professional
15 Assign 1-2 Peter
1-4 Chris
2-4 Peter 200 m of cat 5
2-3 Bob 200 m of cat 5
3-5 Bob
2-5 Harry 300 m of cat 5
4-5 Peter
5-7 Peter
7-9 Peter
5-6 Sk Lab 100%
6-9 Harry
5-8 Martin
8-9 Martin
4-5 Peter
5-7 Peter
7-9 Peter
5-6 Harry
6-9 Harry
5-8 Bob
8-9 Bob
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 11
Introduction To MS Project 2007 Professional
18
Introduce
constrain As
Late As
Possible to
Phase 1 and
Phase 2
Activities
Do you see
any change in
project
duration ?
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 12
Introduction To MS Project 2007 Professional
OR
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 13
Introduction To MS Project 2007 Professional
20 Making Changes to the project : Change -- ONE
Project Cost
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 14
Introduction To MS Project 2007 Professional
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 15
Introduction To MS Project 2007 Professional
Remember to have your tracking table and also move the cursor to the activity you want to update
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 16
Introduction To MS Project 2007 Professional
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 17
Introduction To MS Project 2007 Professional
26 Setting Baselines : Manipulation of baselines / others start finish dates : What if sessions
© Indunil Seneviratne B.Sc (QS), M.Sc(Const. Mgmt), AIQSSL Program : M.Sc / PG-Dip in Project Management :2008 Page : 18