Professional Documents
Culture Documents
NGCP Dasmarinas Accomplishment
NGCP Dasmarinas Accomplishment
Powercity Corporation
03 - Feb - 20
10 - Feb - 20
17 - Feb - 20
24 - Feb - 20
06 - Jan - 20
13 - Jan - 20
20 - Jan - 20
27 - Jan - 20
Days Remaining
Duration (Days)
Days Complete
% Complete
Worst Case
Workdays
WBS Tasks Start End Notes/Remarks M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Installation of 4" dia BI Piping for smoke stack 12/31/2019 12/31/2019 1 100% 1 1 0 0
16
17 Installation of clamp exhaust pipe 1/1/2020 1/1/2020 1 100% 1 1 0 0
18 Installation of hanger and cover 1/2/2020 1/2/2020 1 100% 1 1 0 0
19 Painting 1/3/2020 1/3/2020 1 100% 1 1 0 0
ELECTRICAL WORKS - Installation of
distribution panel, feeder and 1/3/2020 1/20/2020 18 65% 15 10 5 -5
termination.
20
21 Underground excavation for electrical piping 1/3/2020 1/9/2020 7 67% 6 4 2 -2
22 Installation of distribution panel 1/10/2020 1/13/2020 4 100% 3 3 0 0
23 Installation of terminal lugs 1/14/2020 1/16/2020 3 100% 3 3 0 0
24 Installation of terminal connector 1/17/2020 1/17/2020 1 0% 1 0 1 -1
25 Conduits 1/18/2020 1/19/2020 2 0% 1 0 1 -1
26 Cut- over 1/20/2020 1/20/2020 1 0% 1 0 1 -1
Testing and Commissioning and 2/21/2020 2/21/2020 1 0% 1 0 1 -1
27 Acceptance
28 Final testing 2/21/2020 2/21/2020 1 0% 1 0 1 -1
29
30
31
32
33
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
04 - May - 20
02 - Mar - 20
09 - Mar - 20
16 - Mar - 20
23 - Mar - 20
30 - Mar - 20
24 - Feb - 20
06 - Apr - 20
13 - Apr - 20
20 - Apr - 20
27 - Apr - 20
S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S S
Burn
Plan in Workdays
Days Complete
Duration Days
16-Oct-19 CIVIL WORKS - Construction of Footings,shetlter, flooring & Genset pad. 71 61 61 71 61
19-Oct-19 Earth works, (excavation, tampering and gravel bedding for footing of Genset's 7 6 6 7 6
shelter).
26-Oct-19 Fabrication and Installation of steel bars for footings and columns. 10 8 8 10 8
28-Nov-19 Construction of genset concrete pad, spill catch basin & slabs for the genset 10 9 9 10 9
house
8-Dec-19 Mobilization of materials, tools and equipment for fabrication and iron works. 3 2 2 3 2
3-Jan-20 Painting 1 1 1 1 1
18-Jan-20 Conduits 2 1 0 2 0
Burn Up Chart
60
50
40
Total Number of Workdays
30
20
15
13
10 10 10 10 10
9 9
8 8
7
6
3 3
2 2
1
0
3 3
2 2
1
0
13
3 3
2 2
1 111
9
3 3
2 2
1 111
Duration (Days)
WBS Tasks Start End
OVERALL 99
Days Complete
% Complete
Workdays
100% 61 61
100% 8 7
65% 15 0
0% 1 0
66% 85 68