NGCP- DASMARINAS, CAVITE

Powercity Corporation

Today's Date: 17-Feb-2020 Monday


(vertical red line)
Project Coordinator: NELSON PUNZALAN
Start Date: 16-Oct-2019 Wednesday
[42] First Day of Week (Mon=2): 2 ###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

03 - Feb - 20

10 - Feb - 20

17 - Feb - 20

24 - Feb - 20
06 - Jan - 20

13 - Jan - 20

20 - Jan - 20

27 - Jan - 20
Days Remaining
Duration (Days)

Days Complete
% Complete

Worst Case
Workdays
WBS Tasks Start End Notes/Remarks M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F

CIVIL WORKS - Construction of 10/16/2019 12/25/2019 71 100% 61 61 10 0


1 Footings,shetlter, flooring & Genset pad.
2 Mobilization of materials for Civil Works. 10/16/2019 10/16/2019 1 100% 1 1 0 0 `
Site Clearing (including relocation of existing 10/17/2019 10/18/2019 2 100% 2 2 0 0
3 materials to new temporary stagging area).

Earth works, (excavation, tampering and gravel 10/19/2019 10/25/2019 7 100% 6 6 1 0


bedding for footing of Genset's shelter).
4
Fabrication and Installation of steel bars for 10/26/2019 11/4/2019 10 100% 8 8 2 0
5 footings and columns. 0

Concrete pouring of footings (including concrete 11/5/2019 11/14/2019 10 100% 9 9 1 0


compressive strength @ 28 days for footing).
6

Installation of anchor bolt, form works and


concrete pouring on columns (including concrete 11/15/2019 11/24/2019 10 100% 8 8 2 0
compressive strength @ 28 days for columns).
7
Stripping of form works, backfill and tampering 11/25/2019 11/27/2019 3 100% 3 3 0 0
8
Construction of genset concrete pad, spill catch 11/28/2019 12/7/2019 10 100% 9 9 1 0
9 basin & slabs for the genset house
Mobilization of materials, tools and equipment 12/8/2019 12/10/2019 3 100% 2 2 1 0
10 for fabrication and iron works.

Iron-works (including fabrication of gate, roofing, 12/11/2019 12/25/2019 15 100% 13 13 2 0


trusses genset's shelter enclosure
11
12
MECHANICAL WORKS - Installation of 12/26/2019 1/3/2020 9 100% 8 7 1 -1
13 Generator set and accessories
Delivery of 150 KVA Genset, 12/26/2019 12/27/2019 2 100% 2 2 0 0
14
Installation of Genset (including muffler
extension, exhaust pipe extension, heat resistant 12/28/2019 12/30/2019 3 100% 1 1 0 0
15 paint.)

Installation of 4" dia BI Piping for smoke stack 12/31/2019 12/31/2019 1 100% 1 1 0 0
16
17 Installation of clamp exhaust pipe 1/1/2020 1/1/2020 1 100% 1 1 0 0
18 Installation of hanger and cover 1/2/2020 1/2/2020 1 100% 1 1 0 0
19 Painting 1/3/2020 1/3/2020 1 100% 1 1 0 0
ELECTRICAL WORKS - Installation of
distribution panel, feeder and 1/3/2020 1/20/2020 18 65% 15 10 5 -5
termination.
20
21 Underground excavation for electrical piping 1/3/2020 1/9/2020 7 67% 6 4 2 -2
22 Installation of distribution panel 1/10/2020 1/13/2020 4 100% 3 3 0 0
23 Installation of terminal lugs 1/14/2020 1/16/2020 3 100% 3 3 0 0
24 Installation of terminal connector 1/17/2020 1/17/2020 1 0% 1 0 1 -1
25 Conduits 1/18/2020 1/19/2020 2 0% 1 0 1 -1
26 Cut- over 1/20/2020 1/20/2020 1 0% 1 0 1 -1
Testing and Commissioning and 2/21/2020 2/21/2020 1 0% 1 0 1 -1
27 Acceptance
28 Final testing 2/21/2020 2/21/2020 1 0% 1 0 1 -1
29
30
31
32
33
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###

04 - May - 20
02 - Mar - 20

09 - Mar - 20

16 - Mar - 20

23 - Mar - 20

30 - Mar - 20
24 - Feb - 20

06 - Apr - 20

13 - Apr - 20

20 - Apr - 20

27 - Apr - 20
S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S SM TWT F S S
Burn

Actual Worked Days


Total Planned Days
Date Task

Plan in Workdays

Days Complete
Duration Days
16-Oct-19 CIVIL WORKS - Construction of Footings,shetlter, flooring & Genset pad. 71 61 61 71 61

16-Oct-19 Mobilization of materials for Civil Works. 1 1 1 1 1

17-Oct-19 Site Clearing (including relocation of existing materials to new temporary 2 2 2 2 2


stagging area).

19-Oct-19 Earth works, (excavation, tampering and gravel bedding for footing of Genset's 7 6 6 7 6
shelter).

26-Oct-19 Fabrication and Installation of steel bars for footings and columns. 10 8 8 10 8

Concrete pouring of footings (including concrete compressive strength @ 28


5-Nov-19 10 9 9 10 9
days for footing).

Installation of anchor bolt, form works and concrete pouring on columns


15-Nov-19 10 8 8 10 8
(including concrete compressive strength @ 28 days for columns).

25-Nov-19 Stripping of form works, backfill and tampering 3 3 3 3 3

28-Nov-19 Construction of genset concrete pad, spill catch basin & slabs for the genset 10 9 9 10 9
house

8-Dec-19 Mobilization of materials, tools and equipment for fabrication and iron works. 3 2 2 3 2

Iron-works (including fabrication of gate, roofing, trusses genset's shelter


11-Dec-19 15 13 13 15 13
enclosure

26-Dec-19 MECHANICAL WORKS - Installation of Generator set and accessories 9 8 7 9 7

26-Dec-19 Delivery of 150 KVA Genset, 2 2 2 2 2

Installation of Genset (including muffler extension, exhaust pipe extension, heat


28-Dec-19 3 1 1 3 1
resistant paint.)

31-Dec-19 Installation of 4" dia BI Piping for smoke stack 1 1 1 1 1


1-Jan-20 Installation of clamp exhaust pipe 1 1 1 1 1

2-Jan-20 Installation of hanger and cover 1 1 1 1 1

3-Jan-20 Painting 1 1 1 1 1

ELECTRICAL WORKS - Installation of distribution panel, feeder and


3-Jan-20 18 15 10 18 10
termination.

3-Jan-20 Underground excavation for electrical piping 7 6 4 7 4

10-Jan-20 Installation of distribution panel 4 3 3 4 3

14-Jan-20 Installation of terminal lugs 3 3 3 3 3

17-Jan-20 Installation of terminal connector 1 1 0 1 0

18-Jan-20 Conduits 2 1 0 2 0

21-Feb-20 Testing and Commissioning and Acceptance 1 1 0 1 0


21-Feb-20 Final testing 1 1 0 1 0
Burn Up Chart

Burn Up Chart
60

50

40
Total Number of Workdays

30

20

15

13

10 10 10 10 10
9 9
8 8
7
6

3 3
2 2
1
0

Tota l Pla nned Days Actua l Worked Days


9 9
8 8
7
6

3 3
2 2
1
0

Tota l Pla nned Days Actua l Worked Days


15

13

3 3
2 2
1 111
9

3 3
2 2
1 111
Duration (Days)
WBS Tasks Start End

CIVIL WORKS - Construction of Footings,shetlter, 10/16/2019 12/25/2019 71


1 flooring & Genset pad.
MECHANICAL WORKS - Installation of Generator 12/26/2019 1/3/2020 9
2 set and accessories
ELECTRICAL WORKS - Installation of distribution 1/3/2020 1/20/2020 18
3 panel, feeder and termination.

Testing and Commissioning and Acceptance 2/21/2020 2/21/2020 1


4

OVERALL 99
Days Complete
% Complete

Workdays
100% 61 61

100% 8 7

65% 15 0

0% 1 0

66% 85 68