Introduction
Blackout means complete interruption of Power Supply. In case power plant got tripped
and grid supply not available, then it is called a Blackout.
Inform Plant head, HOD (Operation), MRSS and ESTL CCR about station trip. Action-
SIC
Ensure Station transformer upstream and downstream breaker status.
Check the fault at GRP, PP breaker relays and alarms.
Ensure DC emergency lights are “ON” in AUTO.
Check EOP (Emergency Oil Pump) and DC JOP have picked up in AUTO. Monitor the
turbine parameters.
Given Stop command for all drives and deselect AUTO/Standby from DCS.
Start EDG from AMF panel and monitor voltage build up.
Charge the EDG I/C breaker at NEDB panel board.
Charge the I/C breaker of respective USS through which USS will back charged.
Start any one AOP and select other in AUTO.
Ensure Lube oil pressure and temperature healthy.
Start the AC JOP and monitor the pressure of Alternator DE/NDE.
Monitor the speed of the turbine and observe the auto pickup of barring gear motor on
local.
Ensure the condenser Vaccum breaker open condition and observe the gland seal
pressure.
Tight close MSSV by manually.
Open the MSL steam drains.
Ensure all the HT and LT switchgear breakers are tripped condition.
SIC should be co-ordinate with GRID and MRSS for grid supply availability.
Reset all the relays and alarms at PP breaker and GRP.
Confirm GRID supply healthy from substation end.
Ensure Breaker-2 and Breaker-3 should be in open condition before extended power
supply to ESTL MRSS.
Give the clearance for extend power supply to MRSS by charging the Breaker-4.
After ensuring 220KV supply, close Breaker-3(PP Breaker at MRSS end).
Close PP Breaker at CPP end (Breaker-2).
Close the ST#1 Breaker (220KV side).
Close the ST#1 I/C Breaker at 6.6KV.
Extend the power supply for NEDB and change over the EDG.
After changeover of EDG supply, ensure the TG oil system and barring gear operation.
Extend the Power supply for critical drives and Plant lighting.
Once Aux. Power supply normalized, start the CW pumps, ACW Pumps, PAC and BFP
sequentially.
Ensure the instrument air supply pressure above 6kg/cm2.
Then Start the Boiler and Turbine as per the recommend procedures.