Rate Analysis of HDPE pipe

Guide to use tool: i) In column C, yellow cells, put current rates of pipes. ii) These rates are FOR,NCR, Excise 8.24% included, CST at 2% against form C included, Inspection extra. As s
transportation, excise duty and CST taken at 0%. If not included put suitable % in row 5 iii) Inspection is to be paid separately to inspection agency as such not included in these rates if
otherwise then it may be added separately. iv) In row 5, green cells some percentages are given which may be reviewed and revise/update if required.
HDPE Pipes
Supply, Laying, Jointing, Field Testing, Rate of Pipe Transport Excise CST at Local Laying Testing Contractor Total Rate
Commissioning complete at site of HDPE (PE80 ation at Duty at Handling and and s Profit at
Grade Coumpound) Pipes PN-8.0 (8.0 kg/sqcm) as per & storage Jointing commissio
IS:4984 and specifications for water application, at at ning at
including all cost of material, labour required,
transportation, loading, unloading & stacking etc.
complete.

M/S kriti letter 0% 0% 0% 1% 3% 4% 10%

110mm PN8 261.19 - - - 2.61 7.84 10.45 28.21 310.29


125mm PN8 335.93 - - - 3.36 10.08 13.44 36.28 399.08
140mm PN8 420.00 - - - 4.20 12.60 16.80 45.36 498.96
160mm PN8 547.48 - - - 5.47 16.42 21.90 59.13 650.41
180mm PN8 694.14 - - - 6.94 20.82 27.77 74.97 824.64
200mm PN8 855.38 - - - 8.55 25.66 34.22 92.38 1,016.19
225mm PN8 1,078.91 - - - 10.79 32.37 43.16 116.52 1,281.75
250mm PN8 1,334.26 - - - 13.34 40.03 53.37 144.10 1,585.10
280mm PN8 1,669.80 - - - 16.70 50.09 66.79 180.34 1,983.72
315mm PN8 2,113.74 - - - 21.14 63.41 84.55 228.28 2,511.12
355mm PN8 2,676.70 - - - 26.77 80.30 107.07 289.08 3,179.92
400mm PN8 3,475.93 - - - 34.76 104.28 139.04 375.40 4,129.40
450mm PN8 4,398.75 - - - 43.99 131.96 175.95 475.07 5,225.72
500mm PN8 5,423.37 - - - 54.23 162.70 216.93 585.72 6,442.96
560mm PN8 6,795.87 - - - 67.96 203.88 271.83 733.95 8,073.49
630mm PN8 8,547.90 - - - 85.48 256.44 341.92 923.17 10,154.91
included, Inspection extra. As such
not included in these rates if

Specials Total Rate


at % of including
total cost specials

10%

31.03 341.32
39.91 438.99
49.90 548.86
65.04 715.45
82.46 907.10
101.62 1,117.81
128.17 1,409.92
158.51 1,743.61
198.37 2,182.09
251.11 2,762.24
317.99 3,497.91
412.94 4,542.35
522.57 5,748.29
644.30 7,087.26
807.35 8,880.84
1,015.49 11,170.40
Rate Analysis: MDPE Pipes
Guide to use tool: i) In column C, yellow cells, put current rates of pipes. ii) These rates are FOR,Jalgaon as such transportation added, Excise included as such 0%
added , CST not included as such added extra, iii) Inspection is to be paid separately to inspection agency as such not included in these rates if otherwise then it may
be added separately. iv) In row 4, green cells some percentages are given which may be reviewed and revise/update if required.
Service Connections: Supply, Laying, Jointing, Field Quotation of firm Excise Transporta CST Local Breakag Laying Contractor
Testing, Commissioning complete at site of MDPE applicable tion cost applicabl handling e at and s profit at
(PE 80 Grade Coumpound) Pipes PN-16 (16 kg/sqcm) e and jointing
as per ISO4427 and specifications for water storage at cost
application, including all cost of material, labour
required, transportation, loading, unloading &
stacking etc. complete.

Jain irrigation 0% 10% 4% 1% 1% 3% 10%

Rates FOR Jalgaon,


excise included,
CST/LST extra
20 mm Dia SDR 9 22.85 - 2.29 0.91 0.23 0.02 0.69 2.70
25 mm Dia SDR 11 29.10 - 2.91 1.16 0.29 0.03 0.87 3.44
32 mm Dia SDR 11 47.95 - 4.80 1.92 0.48 0.05 1.44 5.66
40 mm Dia - - - - - - -
50 mm Dia - - - - - - -
16 mm Dia - - - - - - -
cise included as such 0%
s if otherwise then it may

Total Rate

29.68
37.80
62.29
-
-
-
Rate Analysis: Ductile Iron (DI) Pipes
Guidance for use of Tool: i) Adopt current market rate in column Consitions about excise duty, transportation, CST to be suitably accounted. ii) Rate in colomn 3 are with Nill Excise
Excise Duty Exemption certificate to be provided by the buyer along with the order / before production Central Excise Notification No. 6/2006 as amended by Central Excise Notifica
March 2007. However, if excise duty is leviable than put suitable % in cell D3.Inspection charges included. These rates are FOR NCR as such transportation taken 0% however if trans
put suitable % in cell E3. These rates are with CST zero against form C. If it is to be added then take suitable % in cell F3. Rubber gasket included in rate. if not included then add suitb
iii) Green cells may be reviewed and suitably revised/updated if needed.
Supply, Laying, Jointing Field Testing & Commissioning complete Rate of Transporta CST Excise Local Breakage Total Laying
at site as per specifications of centrifugally cast (spun) Ductile Iron Rs per tion at duty at handling at and
Pressure Pipes (S &S) ISI marked for water conforming to IS Meter and Jointing
8329/2000 with push on type EPDM 'ISI marked' rubber gasket storage at of pipes
jointing as per IS 5382 specifications. Pipe shall be outside Zinc &
coated with finishing layer of Bitumen and have factory cement hydraulic
mortar lining as per IS 8329/2000. The rates includes all cost of testing at
material, labour required, transportation, loading, unloading &
stacking etc. complete and also includes the cost of EPDM 'ISI
marked' rubber gasket

Electrosteel rate
vide letter 0.00% 0.00% 0.00% 1% 1% 2.50%
449/4-2-09
100 mm K7 832 - - - 8.32 8.32 848.64 21.22
150 mm K7 1,065 - - - 10.65 10.65 1,086.30 27.16
200 mm K7 1,540 - - - 15.40 15.40 1,570.80 39.27
250 mm K7 2,005 - - - 20.05 20.05 2,045.10 51.13
300 mm K7 2,543 - - - 25.43 25.43 2,593.86 64.85
350 mm K7 3,197 - - - 31.97 31.97 3,260.94 81.52
400 mm K7 3,833 - - - 38.33 38.33 3,909.66 97.74
450 mm K7 4,547 - - - 45.47 45.47 4,637.94 115.95
500 mm K7 5,325 - - - 53.25 53.25 5,431.50 135.79
600 mm K7 7,015 - - - 70.15 70.15 7,155.30 178.88
700 mm K7 9,622 - - - 96.22 96.22 9,814.44 245.36
750 mm K7 11,135 - - - 111.35 111.35 11,357.70 283.94
800 mm K7 12,550 - - - 125.50 125.50 12,801.00 320.03
900 mm K7 15,314 - - - 153.14 153.14 15,620.28 390.51
1000 mm K7 18,354 - - - 183.54 183.54 18,721.08 468.03

Note: Rate in colomn 3 are to be taken as per prevalent market rates.


Rate in colomn 3 are with Nill Excise duty against valid
amended by Central Excise Notification No. 6/2007 dated 1st
sportation taken 0% however if transportation is extra then
in rate. if not included then add suitble cost for rubber ring.

Contractors Total Specials Total Rate


Profit at at inclusive
of specials

10% 3%

86.99 957 28.71 986


111.35 1,225 36.74 1,262
161.01 1,771 53.13 1,824
209.62 2,306 69.18 2,375
265.87 2,925 87.74 3,012
334.25 3,677 110.30 3,787
400.74 4,408 132.24 4,540
475.39 5,229 156.88 5,386
556.73 6,124 183.72 6,308
733.42 8,068 242.03 8,310
1,005.98 11,066 331.97 11,398
1,164.16 12,806 384.17 13,190
1,312.10 14,433 432.99 14,866
1,601.08 17,612 528.36 18,140
1,918.91 21,108 633.24 21,741